Letter Sequence Other |
|---|
CAC:001028, SR 3.5.1.2 Notation (Approved, Closed) EPID:L-2020-RNW-0007, Holtec International - HI-STORM 100 Storage CoC Renewal Application (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, ... further results|Supplement]]
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, ... further results|Meeting]]
Results
- Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, ... further results|Approval]]
Other: L-18-006, ISFSI - Site-Specific License Renewal Application, Revision 0, July 2018, L-23-005, Independent Spent Fuel Storage Installation License Renewal Application, Revision 1 (Cac/Epid No. 001028/L-2022-RNW-0007), ML17311A450, ML18018A018, ML18022A077, ML18022A078, ML18022A079, ML18087A056, ML18087A057, ML18087A058, ML18087A059, ML18087A060, ML18087A061, ML18087A062, ML18100A185, ML18100A188, ML18100A190, ML18100A191, ML18100A193, ML18101A024, ML18108A052, ML18131A047, ML18131A048, ML18141A561, ML18141A562, ML18141A563, ML18141A564, ML18141A565, ML18141A567, ML18179A258, ML18179A260, ML18179A266, ML18201A455, ML18205A179, ML18222A351, ML18228A530, ML18228A531, ML18228A532, ML18228A533, ML18234A012, ML18248A121, ML18255A093, ML18255A094, ML18255A096, ML18255A097, ML18255A098, ML18255A101, ML18255A102, ML18324A577, ML18324A594... further results
|
MONTHYEARML19255E7911997-05-31031 May 1997 Enclosure 1 - Ecological Assessment of the Low Level Waste Depository, Andrews County, Tx Project stage: Other ML19255E7952004-10-25025 October 2004 Enclosure 2 - Habitat Characterization and Rare Species Survey for the Proposed Low Level Waste Repository, Andrews County, Tx Project stage: Other ML19255E7982007-03-16016 March 2007 Enclosure 3 - Supplemental Survey to Ecological Assessment of the Low Level Waste Depository, Andrews County, Texas Project stage: Supplement ML19337B5182007-03-16016 March 2007 Enclosure 10 - Applicable Sections of LLRW License Project stage: Other ML19217A2112007-04-30030 April 2007 Enclosure 1 - Report on Mapping of a Trench Through Pedogenic Calcrete (Caliche) Across a Drainage and Possible Lineament, Waste Control Specialists Disposal Site, Andrews County, Tx (Public) Project stage: Other ML19255E8002008-07-0303 July 2008 Enclosure 4 - Environmental Assessment Report Prepared for Application for Renewal of Radioactive Material License R04971 Waste Control Specialists LLC Andrews County, Texas Project stage: Request ML19217A2142008-07-28028 July 2008 Enclosure 4 - Report on Activities to Satisfy Byproduct RML Conditions 41A, 41C, and 43, July 2008 (Public) Project stage: Other ML19217A2132011-02-22022 February 2011 Enclosure 3 - Oag Water Levels: Empirical and Modeled Relationships Between Precipitation and Infiltration, 2011 (Public) Project stage: Other ML18100A1882013-04-11011 April 2013 Enclosure 7 - Procedure 12751-MNGP-QP-9.201, Revision 0, Visual Weld Examination Project stage: Other ML18100A1852013-04-11011 April 2013 Enclosure 6 - Procedure 12751-MNGP-OPS-01, Revision 0, Spent Fuel Cask Welding: 61BT/BTH NUHOMS Canisters Project stage: Other ML18100A1912014-01-30030 January 2014 Enclosure 9 - Structural Integrity Associates, Inc. Report 130415.402, Revision 0, Review of Trivis Inc. Welding Procedures Used for Field Welds on the Transnuclear NUHOMS 61BTH Type 1 & 2 Transportable Canister for BWR Fuel Project stage: Other ML18100A1902014-05-22022 May 2014 Enclosure 8 - Structural Integrity Associates, Inc. Report 130415.403, Revision 2, Assessment of Monticello Spent Fuel Canister Closure Plate Welds Based on Welding Video Records Project stage: Other ML18011A1582017-12-22022 December 2017 International HI-STORE Cis (Consolidated Interim Storage Facility) License Application Responses to Safeguards Related Requests for Supplemental Information Project stage: Supplement ML17249A1572018-01-11011 January 2018, 16 January 2018 Package: Vermont Yankee Nuclear Power Station ISFSI Environmental Assessment and Finding of No Significant Impact Related to Issuance of Exemption to Allow a New Loading Pattern and Loading Fuel Cooled for at Least 2 Years Project stage: Request ML18022A1512018-01-16016 January 2018 Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay Independent Spent Fuel Storage Installation License Project stage: Meeting ML18022A1522018-01-16016 January 2018 Enclosure 1: Meeting Attendees (Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay ISFSI License) Project stage: Meeting ML18022A1532018-01-16016 January 2018 Enclosure 2: Agenda (Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay ISFSI License) Project stage: Meeting ML18022A1542018-01-16016 January 2018 Enclosure 3: Handout-PG&E Presentation on Humboldt Bay ISFSI LRA (Memo to A. Hsia Summary of December 12, 2017, Meeting) Project stage: Meeting ML17249A1592018-01-16016 January 2018 Letter to C. C. Chappell Vermont Yankee Nuclear Power Station ISFSI Environmental Assessment and Finding of No Significant Impact Related to Issuance of Exemption to Allow a New Loading Pattern and Loading Fuel Cooled for at Least 2 Years Project stage: Approval ML18018A0182018-01-17017 January 2018 Letter to K. Manzione Application for Holtec International HI-STORM Umax Multipurpose Canister Storage System License Amendment Request No. 3 to Certificate of Compliance No. 1040 - Accepted for Review Project stage: Other ML18018A0192018-01-17017 January 2018 Enclosurequest for Additional Information (Ltr to K. Manzione Application for Holtec International HI-STORM Umax Multipurpose Canister Storage System License Amendment Request No. 3 to Certificate of Compliance No. 1040-Accepted for Review) Project stage: RAI ML18022A6122018-01-19019 January 2018 Letter to K. Manzione Amendment No. 4 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System-Request for Additional Information Project stage: RAI ML18018B2972018-01-19019 January 2018 Federal Registered Notice: Correction of Certificate of Compliance No. 1004, Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 Project stage: Request ML18022A0772018-01-22022 January 2018 Letter to J. Bondre Correction to Tn Americas LLC Technical Specifications for Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 to Standardized NUHOMS Certificate of Compliance No. 1004 for Spent Fuel Storage Casks Project stage: Other ML18022A0782018-01-22022 January 2018 Enclosure 1: Revised Title for Figure 1-5 Corrected Technical Specifications for Certificate of Compliance No. 1004 Renewed Amendment No. 11, Revision 1 Enclosure 1 Project stage: Other ML18022A0762018-01-22022 January 2018 Package: Correction to Title of Figure 1-15 in Technical Specifications for Certificate of Compliance 1004 Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 Project stage: Request ML18022A0792018-01-22022 January 2018 Enclosure 2: Revised Title for Figure 1-5 Corrected Technical Specifications for Certificate of Compliance No. 1004 Renewed Amendment No. 13, Revision 1 Project stage: Other ML18024A2732018-01-24024 January 2018 Letter to D. G. Stoddard U.S. NRC Approval of Virginia Electric and Power Company Request for Withholding Information from Public Disclosure for North Anna Power Station ISFSI (Cac/Epid Nos. 001028/L-2017-RNW-0010 and 000993/L-2017-LNE-0008 Project stage: Withholding Request Acceptance ML17311A4502018-01-31031 January 2018 ISFSI License Renewal Final Environmental Assessment Project stage: Other ML18031A4572018-01-31031 January 2018 Submittal Date for Response to NRCs Requests for Additional Information (Rais) for License Amendment Request 1032-4 to HI-STORM FW CoC No. 1032 (CAC No. 001028) Project stage: Request ML18036A2222018-02-0101 February 2018 International - Transmittal of HI-STORM Umax License Amendment Request No. 3 - Administrative RAI Response Project stage: Request ML17298A1342018-02-0202 February 2018 Letter to C. C. Chappell Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Issuance of Exemption (CAC No.: 001028, Docket Nos. 50-271, 72-59, and 72-1014; EPID L-2017-LLE-0005) Project stage: Approval ML17298A1352018-02-0202 February 2018 Safety Evaluation Report (Letter to C. C. Chappell Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Issuance of Exemption (CAC No.: 001028, Docket Nos. 50-271, 72-59, and 72-1014; EPID L-2017-LLE-0005) Project stage: Approval ML18031A2242018-02-0606 February 2018 Enclosure 1: Preamble-SNM-2507 License Renewal Order (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation) Project stage: Approval ML18031A2272018-02-0606 February 2018 Enclosurenewed License SNM-2507 Technical Specifications (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18031A2222018-02-0606 February 2018 Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation (Cac/Epid Nos. 001028/L-2017-RNW-0010 and 000993/L-2017-LNE-0008) Project stage: Approval ML18031A2282018-02-0606 February 2018 Enclosure 2: Safety Evaluation Report (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18031A2252018-02-0606 February 2018 Enclosurenewed License SNM-2507 (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation) Project stage: Approval ML18031A2312018-02-0808 February 2018 Federal Register Notice - Notice of Issuance for License Renewal (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18053A2342018-02-15015 February 2018 Enclosure 6: Proposed Amendment 1, Revision 0 Changes to the NUHOMS Eos System Updated Final Safety Analysis Report, Chapters 1 to 14 Project stage: Request ML18053A2222018-02-15015 February 2018 Application for Amendment 1 to the NUHOMS Eos System, Revision O (Docket No. 72-1042) Project stage: Request ML18053A2332018-02-15015 February 2018 Enclosure 4: CoC 1042 Amendment 1 Proposed Technical Specifications, Revision 0 Project stage: Request ML18058A0572018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.S Decommissioning Funding Plan Update) Project stage: RAI ML18058A6072018-02-23023 February 2018 HI-2177565, Rev 0, Holtec International & Eddy Lea Energy Alliance (Elea) Cis Facility - Decommissioning Cost Estimate and Funding Plan Project stage: Request ML18058A6082018-02-23023 February 2018 HI-2177593, Rev 0, Holtec International & Eddy Lea Energy Alliance (Elea) Underground CISF - Financial Assurance & Project Life Cycle Cost Estimates Project stage: Request ML18058A0562018-02-23023 February 2018 Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.S Decommissioning Funding Plan Update Project stage: RAI ML18058A0232018-02-23023 February 2018 Letter to G. Van Noordennen Request for Additional Information Regarding Zionsolutions, LLCs Decommissioning Funding Plan Update for Zion Independent Spent Fuel Storage Installation Project stage: RAI ML18057A2172018-02-23023 February 2018 Letter to A. Zaremba Request for Additional Information for Review of Duke Energys Decommissioning Funding Plan Update Project stage: RAI ML18058A0242018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to G. Van Noordennen Request for Additional Information Regarding Zionsolutions, LLCs Decommissioning Funding Plan Update for Zion Independent Spent Fuel Storage Installation) Project stage: RAI ML18057A2182018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to A. Zaremba Request for Additional Information for Review of Duke Energys Decommissioning Funding Plan Update) Project stage: RAI 2018-01-11
[Table View] |
Text
NRC FORM 651 (3-1999) 10 CFR 72 U.S. NUCLEAR REGULATORY COMMISSION CERTIFICATE OF COMPLIANCE FOR SPENT FUEL STORAGE CASKS Page 1
of 4
The U.S. Nuclear Regulatory Commission is issuing this Certificate of Compliance pursuant to Title 10 of the Code of Federal Regulations, Part 72, "Licensing Requirements for Independent Storage of Spent Nuclear Fuel, High-Level Radioactive Waste, and Reactor-Related Greater than Class C Waste" (10 CFR Part 72). This certificate is issued in accordance with 10 CFR 72.238, certifying that the storage design and contents described below meet the applicable safety standards set forth in 10 CFR Part 72, Subpart L, and on the basis of the Final Safety Analysis Report (FSAR) of the cask design. This certificate is conditional upon fulfilling the requirements of 10 CFR Part 72, as applicable, and the conditions specified below.
Certificate No.
Effective Date Expiration Date Docket No.
Amendment No.
Amendment Effective Date Package Identification No.
1014 05/31/2000 05/31/2020 72-1014 0
USA/72-1014 Renewed Effective Date 08/02/2023 Renewed Expiration Date 05/31/2060 Revision No.
0 Revision Effective Date N/A Issued To: (Name/Address)
Holtec International Holtec Technology Campus One Holtec Blvd.
Camden, NJ 08104 Safety Analysis Report Title Holtec International Inc., Final Safety Analysis Report for the HI-STORM 100 Cask System Docket No. 72-1014 CONDITIONS This certificate is conditioned upon fulfilling the requirements of 10 CFR Part 72, as applicable, the attached Appendix A (Technical Specifications) and Appendix B (Approved Contents and Design Features), and the conditions specified below:
- 1. CASK
- a. Model No.: HI-STORM 100 Cask System The HI-STORM 100 Cask System (the cask) consists of the following components: (1) interchangeable multi-purpose canisters (MPCs), which contain the fuel; (2) a storage overpack (HI-STORM 100), which contains the MPC during storage; and (3) a transfer cask (HI-TRAC),
which contains the MPC during loading, unloading and transfer operations. The cask stores up to 24 pressurized water reactor (PWR) fuel assemblies or 68 boiling water reactor (BWR) fuel assemblies.
- b. Description The HI-STORM 100 Cask System is certified as described in the Topical Safety Analysis Report (SAR) and in NRCs Safety Evaluation Report (SER) accompanying the Certificate of Compliance.
The cask comprises three discrete components: the MPCs, the HI-TRAC transfer cask, and the HI-STORM 100 storage overpack.
NRC FORM 651A (3-1999) 10 CFR 72 U.S. NUCLEAR REGULATORY COMMISSION CERTIFICATE OF COMPLIANCE FOR SPENT FUEL STORAGE CASKS Supplemental Sheet Certificate No.
1014 Amendment No.
0 Renewed Yes Page 2
of 4
- 1. b. Description (continued)
The MPC is the confinement system for the stored fuel. It is a welded, cylindrical canister with a honeycombed fuel basket, a baseplate, a lid, a closure ring, and the canister shell. It is made entirely of stainless steel except for the neutron absorbers and aluminum heat conduction elements. The canister shell, baseplate, lid, vent and drain port cover plates, and closure ring are the main confinement boundary components. The honeycombed basket, which is equipped with Boral neutron absorbers, provides criticality control.
There are three types of MPCs: the MPC-24, the MPC-68, and the MPC-68F. The MPC-24 holds up to 24 PWR fuel assemblies that must be intact. The MPC-68 holds up to 68 BWR fuel assemblies that may be intact or damaged (i.e., with known or suspected cladding defects greater than hairline cracks or pinholes). The MPC-68F holds up to 68 BWR fuel assemblies that may be intact, damaged, or in the form of fuel debris (i.e., with known or suspected defects such as ruptured fuel rods, severed fuel rods, and loose fuel pellets). All three MPCs have the same external dimensions.
The HI-TRAC transfer cask provides shielding and structural protection of the MPC during loading, unloading, and movement of the MPC from the spent fuel pool to the storage overpack. The transfer cask is a multi-walled (carbon steel/lead/carbon steel) cylindrical vessel with a water jacket attached to the exterior. Two types of HI-TRAC transfer casks are available: the 125-ton HI-TRAC and the 100-ton HI-TRAC. The weight designation is the maximum weight of a loaded transfer cask during any loading, unloading or transfer operation. Both transfer cask types have identical cavity diameters. The 125-ton HI-TRAC transfer cask has thicker lead and water shielding and larger outer dimensions than the 100-ton HI-TRAC transfer cask.
The HI-STORM 100 storage overpack provides shielding and structural protection of the MPC during storage. The overpack is a heavy-walled, steel and concrete, cylindrical vessel. Its side wall consists of plain concrete that is enclosed between inner and outer carbon steel shells. The overpack has four air inlets at the bottom and four air outlets at the top to allow air to circulate naturally through the cavity to cool the MPC inside. The inner shell has channels attached to its interior surface to guide the MPC during insertion and removal, provide a flexible medium to absorb impact loads, and allow cooling air to circulate through the overpack. A loaded MPC is stored within the HI-STORM 100 storage overpack in a vertical orientation.
- 2.
OPERATING PROCEDURES Written operating procedures shall be prepared for cask handling, loading, movement, surveillance, and maintenance. The users site-specific written operating procedures shall be consistent with the technical basis described in Chapter 8 of the SAR.
NRC FORM 651A (3-1999) 10 CFR 72 U.S. NUCLEAR REGULATORY COMMISSION CERTIFICATE OF COMPLIANCE FOR SPENT FUEL STORAGE CASKS Supplemental Sheet Certificate No.
1014 Amendment No.
0 Renewed Yes Page 3
of 4
- 3.
ACCEPTANCE TESTS AND MAINTENANCE PROGRAM Written cask acceptance tests and maintenance program shall be prepared consistent with the technical basis described in Chapter 9 of the SAR.
- 4.
QUALITY ASSURANCE Activities in the areas of design, purchase, fabrication, assembly, inspection, testing, operation, maintenance, repair, modification of structures, systems and components, and decommissioning that are important to safety shall be conducted in accordance with a Commission-approved quality assurance program which satisfies the applicable requirements of 10 CFR Part 72, Subpart G, and which is established, maintained, and executed with regard to the cask system.
- 5.
HEAVY LOADS REQUIREMENTS Each lift of an MPC, a HI-TRAC transfer cask, or a HI-STORM 100 overpack must be made in accordance to the existing heavy loads requirements and procedures of the licensed facility at which the lift is made. A plant-specific safety review (under 10 CFR 50.59 or 10 CFR 72.48, if applicable) is required to show operational compliance with existing plant-specific heavy loads requirements. Lifting operations outside of structures governed by 10 CFR Part 50 must be in accordance with Section 3.5 of Appendix B to this certificate.
- 6.
APPROVED CONTENTS Contents of the HI-STORM 100 Cask System must meet the fuel specifications given in Appendix B to this certificate.
- 7.
DESIGN FEATURES Features or characteristics for the site, cask, or ancillary equipment must be in accordance with Appendix B to this certificate.
- 8.
CHANGES TO THE CERTIFICATE OF COMPLIANCE The holder of this certificate who desires to make changes to the certificate, which includes Appendix A (Technical Specifications) and Appendix B (Approved Contents and Design Features),
shall submit an application for amendment of the certificate.
- 9.
FSAR UPDATE FOR RENEWED CoC The CoC holder shall submit an updated FSAR to the Commission, in accordance with 10 CFR 72.4, within 90 days after the effective date of the renewal. The updated FSAR shall reflect the changes resulting from the review and approval of the renewal of the CoC, including the HI-STORM 100 FSAR supplement, as documented in Appendix D of the HI-STORM 100 CoC renewal application, Revision 1, dated April 23, 2021 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML21113A203). The CoC holder shall continue to update the FSAR pursuant to the requirements of 10 CFR 72.248.
NRC FORM 651A (3-1999) 10 CFR 72 U.S. NUCLEAR REGULATORY COMMISSION CERTIFICATE OF COMPLIANCE FOR SPENT FUEL STORAGE CASKS Supplemental Sheet Certificate No.
1014 Amendment No.
0 Renewed Yes Page 4
of 4
- 10.
10 CFR 72.212 EVALUATIONS FOR CoC USE DURING THE PERIOD OF EXTENDED OPERATION Any general licensee that initiates spent fuel dry storage operations with the HI-STORM 100 Cask System after the effective date of the renewal of the CoC and any general licensee operating a HI-STORM 100 Cask System as of the effective date of the renewal of the CoC, including those that put additional storage systems into service after that date, shall:
- a. As part of the evaluations required by 10 CFR 72.212(b)(5), include the evaluations related to the terms, conditions, and specifications of this CoC amendment as modified (i.e., changed or added) as a result of the renewal of the CoC.
- b. As part of the document review required by 10 CFR 72.212(b)(6), include a review of the FSAR changes resulting from the renewal of the CoC and the NRC Safety Evaluation Report related to the renewal of the CoC.
- c. Ensure that the evaluations required by 10 CFR 72.212(b)(7) and determinations required by 10 CFR 72.212(b)(8) capture the evaluations and review described in (a.) and (b.) of this CoC condition.
- d. Complete this condition prior to entering the period of extended operation or no later than 365 days after the effective date of the renewal of the CoC, whichever is later.
- 11.
AMENDMENTS AND REVISIONS FOR RENEWED CoC All future amendments and revisions to this CoC shall include evaluations of the impacts to aging management activities (i.e., time-limited aging analyses and aging management programs) to ensure they remain adequate for any changes to structures, systems, and components within the scope of renewal.
- 12.
AUTHORIZATION The HI-STORM 100 Cask System, which is authorized by this certificate, is hereby approved for use under the general license issued pursuant to 10 CFR 72.210, subject to the conditions specified by 10 CFR 72.212, and the attached Appendix A and Appendix B.
FOR THE U. S. NUCLEAR REGULATORY COMMISSION Yoira K. Diaz-Sanabria, Chief Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Dated: June 29, 2023 Attachments:
- 1. Appendix A
- 2. Appendix B Yoira K. Diaz-Sanabria Digitally signed by Yoira K. Diaz-Sanabria Date: 2023.06.29 08:05:27 -04'00'