ML18067A148

From kanterella
Jump to navigation Jump to search
Enclosurequest for Additional Information (Letter to P. R. Simpson Request for Additional Information Regarding Exelon Generating Company, Llc'S Decommissioning Funding Plan Update for Independent Spent Fuel Storage Installation)
ML18067A148
Person / Time
Site: Calvert Cliffs, Dresden, Peach Bottom, Salem, Oyster Creek, Byron, Braidwood, Limerick, Ginna, Quad Cities, LaSalle, 07201036  Constellation icon.png
Issue date: 03/08/2018
From: Pamela Longmire
Spent Fuel Licensing Branch
To: Simpson P
Exelon Generation Co
Longmire P
Shared Package
ML18067A147 List:
References
CAC 001028
Download: ML18067A148 (1)


Text

REQUEST FOR ADDITIONAL INFORMATION REGARDING EXELON GENERATING COMPANY, LLCS DECOMMISSIONING FUNDING PLAN UPDATE FOR CALVERT CLIFFS NUCLEAR POWER PLANT, NINE MILE POINT NUCLEAR STATION, R.E. GINNA NUCLEAR POWER PLANT, BRAIDWOOD STATION, BYRON STATION, DRESDEN NUCLEAR POWER STATION, LASALLE COUNTY STATION, LIMERICK GENERATING STATION, OYSTER CREEK NUCLEAR GENERATING STATION, PEACH BOTTOM ATOMIC POWER STATION, QUAD CITIES NUCLEAR POWER STATION, AND SALEM GENERATING STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS DOCKET NOS. 72-08, 72-1036, 72-67, 72-73, 72-68, 72-37, 72-70, 72-65, 72-15, 72-29, 72-53 AND 72-48 Regulatory Requirement Pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 72.30(c), at the time of license renewal and at intervals not to exceed 3 years, the decommissioning funding plan (DFP) required to be submitted by 10 CFR 72.30(b) must be resubmitted with adjustments as necessary to account for changes in costs and the extent of contamination. The DFP must update the information submitted with the original or prior approved plan. In addition, the DFP must also specifically consider the effect of the following events on decommissioning costs, as required by 10 CFR 72.30(c)(1)-(4): (1) spills of radioactive material producing additional residual radioactivity in onsite subsurface material, (2) facility modifications, (3) changes in authorized possession limits, and (4) actual remediation costs that exceed the previous cost estimate.

Background

By letter dated March 31, 2015, Exelon Generation Company submitted, for U.S. Nuclear Regulatory Commission (NRC) staff review and approval, a decommissioning funding plan update (DFP Update) for the independent spent fuel storage installations at Calvert Cliffs Nuclear Power Plant, Nine Mile Point Nuclear Station, R.E. Ginna Nuclear Power Plant, Braidwood Station, Byron Station, Dresden Nuclear Power Station, LaSalle County Station, Limerick Generating Station, Oyster Creek Nuclear Generating Station, Peach Bottom Atomic Power Station, Quad Cities Nuclear Power Station, and Salem Generating Station (Agencywide Documents Access and Management System Accession No. ML15090A537). The NRC staff reviewed EGCs DFP update for each ISFSI and believes EGCs submittal was not sufficient to meet the intent of the requirement in 10 CFR 72.30(c). The DFP updates do not provide sufficient information to allow the NRC to determine that the events listed in 10 CFR 72.30(c)(1)-

(4) have been specifically considered.

RAI 1

For each ISFSI, provide a revised DFP that includes information on the occurrence, and the effect on decommissioning costs, of each of the events listed in 10 CFR 72.30(c)(1)-(4): (1) spills of radioactive material producing additional residual radioactivity in onsite subsurface material, (2) facility modifications, (3) changes in authorized possession limits, and (4) actual remediation costs that exceed the previous cost estimate.