Acceptance of Maine Yankee Request for Exemption from Certain Requirements of Title 10 of the Code of Federal Regulations Section 72.212 and 72.214
ML24162A273
Person / Time
Site: Maine Yankee, 07201015
Issue date: 06/04/2024
From: Kristina Banovac
Storage and Transportation Licensing Branch
To: Laing D
Maine Yankee Atomic Power Co
References
CAC 001028, EPID L-2024-LLE-0015
Download: ML24162A273 (1)


Text

From:

Kristina Banovac To:

Daniel Laing Cc:

Stan Day; Yoira Diaz Sanabria

Subject:

Acceptance of Maine Yankee Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for the Maine Yankee Independent Spent Fuel Storage Installation - CAC/EPID 001028/L-2024-LLE-0015 Date:

Tuesday, June 4, 2024 4:31:00 PM

Dear Daniel Laing:

By letter dated March 28, 2024 (Agencywide Documents Access and Management System

[ADAMS] Accession No. ML24094A060), you submitted a request for exemption from certain requirements of Title 10 of the Code of Federal Regulations (10 CFR) Section 72.212, Conditions of general license issued under § 72.210, and 10 CFR 72.214, List of approved spent fuel storage casks, for the Maine Yankee Independent Spent Fuel Storage Installation. The U.S. Nuclear Regulatory Commission (NRC) staff acknowledged receipt of your application by email dated April 22, 2024 (ML24120A048).

The NRC staff completed an acceptance review of your submittal and have identified no administrative omissions or deficiencies that would prevent us from proceeding with a detailed review. Your submittal has been assigned Cost Activity Code/Enterprise Project Identification Numbers 001028/L-2024-LLE-0015. Please reference these numbers and Docket Nos.50-039, 72-30, 72-1015 in any future correspondence associated with this request.

Please note that the NRC staffs detailed review of your submittal may identify issues that could require that you provide additional information. Based on our preliminary evaluation and projection of current review schedules, we anticipate completing our review in March 2025. This schedule includes the issuance, if needed, of a request for additional information (RAI) in September 2024, and receiving your response to the RAI 30 days after its issuance. Please note that these dates could change depending on the findings of our detailed review, urgent assignments, or other factors, such as whether your responses to the RAI are or are not adequate. The NRC staff estimates that completing the review of your submittal will require approximately 70 staff hours. We will promptly communicate significant schedule and/or cost changes.

In accordance with 10 CFR 2.390, Public inspections, exemptions, requests for withholding, a copy of this email will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records component of the NRCs ADAMS. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. The PDR is open by appointment. To make an appointment to visit the PDR, please send an email to PDR.Resource@nrc.gov or call 1 800 397-4209 or 301-415-4737, between 8:00 a.m. and 4:00 p.m. eastern time (ET),

Monday through Friday, except Federal holidays.

If you have any questions regarding this communication, please contact me at (301) 415-7116, or via email to Kristina.Banovac@nrc.gov.

Sincerely,

Kristina Banovac, Project Manager Storage and Transportation Licensing Branch

Division of Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission

Docket Nos.: 50-039, 72-30, 72-1015 CAC No.: 001028 EPID No.: L-2024-LLE-0015