Letter Sequence Acceptance Review |
---|
EPID:L-2018-RNW-0030, International, Submittal of Responses to NRC RAIs on the Renewal of the HI-STAR 100 Storage CoC (Approved, Closed) |
Results
Other: ML18362A303, ML19094A740, ML20010D564, ML20323A043, ML20329A323, ML20351A371, ML20352A045, ML21168A352, ML21168A353, ML21168A354, ML21168A355, ML21168A356, ML21168A357, ML21168A358, ML21168A359, ML21168A360, ML21168A361, ML21168A362, ML21168A363, ML21168A364
|
MONTHYEARML18362A3032018-12-28028 December 2018 E-Mail from K. Banovac to K. Manzione Acknowledgement of NRC Receipt of HI-STAR 100 CoC Renewal Application Project stage: Other ML19086A1352019-03-26026 March 2019 E-Mail from K. Banovac to K. Manzione Starting Acceptance Review of HI-STAR 100 CoC Renewal Application Project stage: Acceptance Review ML19094A7402019-04-0303 April 2019 4/3/19, E-Mail from K. Banovac/Nrc to K. Manzione/Holtec Holtec Letter 5014860 - Question About Proprietary Information - Follow-up Information Project stage: Other ML19317D5782019-11-0606 November 2019 HI-STAR 100 CoC Renewal Acceptance Letter Project stage: Acceptance Review ML20010D5642020-01-10010 January 2020 Proprietary Determination Letter for HI-STAR 100 CoC Renewal Submittals Project stage: Other ML20071D9942020-03-11011 March 2020 Submittal of HI-STAR 100 Updated FSAR, Revision 4 Project stage: Request ML20104A0402020-04-10010 April 2020 Request for Additional Information for HI-STAR 100 CoC Renewal Application Project stage: RAI ML20153A7682020-06-0101 June 2020, 11 June 2020 International, Submittal of Responses to NRC RAIs on the Renewal of the HI-STAR 100 Storage CoC Project stage: Request ML20267A3452020-09-30030 September 2020 Request for Clarification of Response to RAI for HI-STAR 100 CoC Renewal Application Project stage: RAI ML20318A3212020-11-13013 November 2020 Submittal of Clarification RAI Responses on HI-STAR 100 License Renewal Project stage: Request ML20323A0432020-11-17017 November 2020 NRC 699 (11-10-20 Call W Holtec, Signed) Project stage: Other ML20329A3232020-11-24024 November 2020 International, Clarification RAI Responses on HI-STAR 100 License Renewal Updated Project stage: Other ML20351A3712020-12-16016 December 2020 Proprietary Determination Letter for HI-STAR 100 11-13-2020 Submittal Project stage: Other ML20352A0452020-12-16016 December 2020 NRC 699 (12-3-2020 Call W Holtec on HI-STAR 100, Signed) Project stage: Other ML21168A3512021-06-28028 June 2021, 9 September 2021 Rulemaking for the Renewal of CoC No. 1008, HI-STAR 100 Cask System Project stage: Request ML21168A3522021-06-28028 June 2021 User Need Memo for Renewal of CoC No. 1008 (HI-STAR 100) Project stage: Other ML21168A3532021-09-0909 September 2021 Proposed CoC No. 1008, Renewed Amendment No. 0 Project stage: Other ML21168A3542021-09-0909 September 2021 Proposed Technical Specifications (Appendix a) for CoC No. 1008, Renewed Amendment No. 0 Project stage: Other ML21168A3552021-09-0909 September 2021 Proposed Technical Specifications (Appendix B) for CoC No. 1008, Renewed Amendment No. 0 Project stage: Other ML21168A3562021-09-0909 September 2021 Proposed CoC No. 1008, Renewed Amendment No. 1 Project stage: Other ML21168A3572021-09-0909 September 2021 Proposed Technical Specifications (Appendix a) for CoC No. 1008, Renewed Amendment No. 1 Project stage: Other ML21168A3582021-09-0909 September 2021 Proposed Technical Specifications (Appendix B) for CoC No. 1008, Renewed Amendment No. 1 Project stage: Other ML21168A3592021-09-0909 September 2021 Proposed CoC No. 1008, Renewed Amendment No. 2 Project stage: Other ML21168A3602021-09-0909 September 2021 Proposed Technical Specifications (Appendix a) for CoC No. 1008, Renewed Amendment No. 2 Project stage: Other ML21168A3612021-09-0909 September 2021 Proposed Technical Specifications (Appendix B) for CoC No. 1008, Renewed Amendment No. 2 Project stage: Other ML21168A3622021-09-0909 September 2021 Proposed CoC No. 1008, Renewed Amendment No. 3 Project stage: Other ML21168A3632021-09-0909 September 2021 Proposed Technical Specifications (Appendix a) for CoC No. 1008, Renewed Amendment No. 3 Project stage: Other ML21168A3642021-09-0909 September 2021 Proposed Technical Specifications (Appendix B) for CoC No. 1008, Renewed Amendment No. 3 Project stage: Other ML21168A3652021-09-0909 September 2021 Preliminary Safety Evaluation Report for Renewed CoC No. 1008, Amendment Nos. 0, 1, 2, and 3 Project stage: Approval 2020-11-24
[Table View] |
|
---|
Category:Letter
MONTHYEARML22257A1072022-09-0707 September 2022 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report ML22063B1362022-03-0404 March 2022 International - Submittal of Updated FSAR for Renewed CoC ML21316A2062021-11-16016 November 2021 Transmittal Letter, Issuance of Renewed CoC No. 1008, HI-STAR 100 Cask System ML21301A1662021-10-28028 October 2021 Inspection, NRC Inspection Report 07201014/2021201 ML21295A3502021-10-22022 October 2021 Submittal of Revision 5 of the Final Safety Analysis Report (FSAR) for the HI-STAR 100 Dry Spent Fuel Storage System ML21194A4042021-07-13013 July 2021 Internationa - Extreme Environmental Phenomena During Short Term Operations within 10CFR72 Jurisdiction - Update ML21175A0462021-06-23023 June 2021 International, Submittal of Position Paper DS-481, Consideration of Transient Loadings During Short Term Operations ML21132A2982021-05-12012 May 2021 International - Extreme Environmental Phenomena During Short Term Operations within 10CFR72 Jurisdiction ML20351A3712020-12-16016 December 2020 Proprietary Determination Letter for HI-STAR 100 11-13-2020 Submittal ML20329A3222020-11-24024 November 2020 International, Submittal of Clarification RAI Responses on HI-STAR 100 License Renewal - Updated Attachment ML20318A3222020-11-13013 November 2020 Submittal of Clarification RAI Responses on HI-STAR 100 License Renewal ML20267A3452020-09-30030 September 2020 Request for Clarification of Response to RAI for HI-STAR 100 CoC Renewal Application ML20163A7142020-06-11011 June 2020 International Submittal of Responses to NRC RAIs on the Renewal of the HI-STAR 100 Storage CoC ML20153A7692020-06-0101 June 2020 International, Submittal of Responses to NRC RAIs on the Renewal of the HI-STAR 100 Storage CoC ML20104A0402020-04-10010 April 2020 Request for Additional Information for HI-STAR 100 CoC Renewal Application ML20071D9942020-03-11011 March 2020 Submittal of HI-STAR 100 Updated FSAR, Revision 4 ML20010D5642020-01-10010 January 2020 Proprietary Determination Letter for HI-STAR 100 CoC Renewal Submittals ML19317D5782019-11-0606 November 2019 HI-STAR 100 CoC Renewal Acceptance Letter ML19270D3602019-09-27027 September 2019 Amendment No. 3 to Certificate of Compliance No. 1008 for the HI-STAR 100 Storage System SVPLTR 19-0049, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2019-09-10010 September 2019 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report ML18298A0572018-10-23023 October 2018 Letter to K. Manzione Holtec International Certificate of Compliance Nos. 1008, 1014, 1032, and 1040 - Request for Withholding Information from Public Disclosure SVPLTR 18-0025, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2018-08-15015 August 2018 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report ML18192A1572018-07-10010 July 2018 Letter to K. Manzione Holtec International Certificate of Compliance No. 1008 - Request for Withholding Information from Public Disclosure ML18192A6312018-07-10010 July 2018 Letter to K. Manzione Holtec International Certificate of Compliance No. 1008 - Request for Withholding Information from Public Disclosure ML18192B0262018-07-10010 July 2018 Letter to K. Manzione Holtec International Certificate of Compliance No. 1008 - Request for Withholding Information from Public Disclosure ML16251A0762016-09-0101 September 2016 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report ML13228A3992013-08-12012 August 2013 Letter to Holders of Independent Spent Fuel Storage Installation (ISFSI) Licenses Re Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit - Rin 3150-AI64 (NRC-2009-0163) EA-02-109 NL-04-2181, Joseph M. Farley Nuclear Plant, Request for Exemption from 10 CFR 72.124(c) - Criticality Monitors2005-01-19019 January 2005 Joseph M. Farley Nuclear Plant, Request for Exemption from 10 CFR 72.124(c) - Criticality Monitors RS-02-002, Registration of Use of Cask to Store Spent Fuel2002-01-28028 January 2002 Registration of Use of Cask to Store Spent Fuel ML0605903291999-10-21021 October 1999 Correction of Distribution Error on Holtec Hl-STAR 100 Certificate of Compliance 1008 ML0605903151999-10-13013 October 1999 Issuance of Page Changes to Certificate of Compliance for the Holtec HI-STAR 100 Cask System 2022-09-07
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 6, 2019 Ms. Kimberly Manzione Licensing Manager Holtec International Holtec Technology Campus One Holtec Boulevard Camden, NJ 08104
SUBJECT:
APPLICATION FOR RENEWAL OF THE CERTIFICATE OF COMPLIANCE NO.
1008 FOR THE HI-STAR 100 STORAGE CASK SYSTEM - ACCEPTED FOR REVIEW (CAC/EPID NOS. 001028/L-2018-RNW-0030)
Dear Ms. Manzione:
By letter dated December 7, 2018, Holtec International (Holtec) submitted to the U.S. Nuclear Regulatory Commission (NRC) an application for renewal of the Certificate of Compliance (CoC) No. 1008 for the HI-STAR 100 Storage Cask System (Agencywide Documents Access and Management System [ADAMS] Accession No. ML18345A178). The submittal of the CoC renewal application was timely per the requirements of Title 10 of the Code of Federal Regulations 72.240(b). In the application, Holtec requested to renew the CoC for an additional 40 years. The NRC staff performed an acceptance review of the application.
By letter dated May 14, 2019, the NRC staff requested Holtec submit supplemental information to enable the NRC staff to begin a detailed review of the license renewal application (ADAMS Accession No. ML19135A106). By letters dated June 28, 2019, and October 10, 2019, Holtec submitted responses to the NRC request for supplemental information (RSI) (ADAMS Accession Nos. ML19184A232 and ML19288A089). The NRC staff has reviewed Holtecs RSI responses and has determined the application, supplemented by the RSI responses, now contains sufficient technical information in scope and depth to begin a detailed technical review.
In the RSI, the NRC staff asked whether hardening of the concrete pad (as it continues to cure with time) will cause cask decelerations that exceed the loads analyzed in the tip-over event in the HI-STAR 100 final safety analysis report (FSAR). The NRC staff recognizes that the majority of concrete hardening occurs within the first 10 years of service life, as Holtec noted in its RSI response. The NRC staff is conducting a generic assessment to evaluate the effects of concrete hardening that occurs within the first 10 years of service life compared to a 28-day concrete strength that may be used in some design-basis tip-over analyses, including those in the HI-STAR 100 FSAR. Therefore, the NRC staff will not include concrete hardening in its review of the CoC renewal.
This letter acknowledges acceptance of your application. We have established a schedule for the review. The schedule allows for the staff to complete its technical review and issue a request for additional information (RAI) in April 2020. If Holtec provides a sufficient response to the RAI in July 2020, and a second RAI is not needed, the CoC would be submitted to Rulemaking in January 2021. Rulemaking is estimated to take 6 months, and if there are no
K. Manzione 2 significant adverse comments received during the comment period, the CoC will become effective in July 2021. In general, no additional changes to the application should be submitted except for changes resulting from your response to a RAI.
Please reference Docket No. 72-1008 and CAC/EPID Nos. 001028/L-2018-RNW-0030 in future correspondence related to this request. If you have any questions regarding this matter, please contact me at 301-415-7116 or Kristina.Banovac@nrc.gov.