Letter to P. Simpson Request for Additional Information Regarding Zionsolutions, LLCs Decommissioning Funding Plan Update for Zion Independent Spent Fuel Storage Installation
ML18067A187
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 03/09/2018
From: Pamela Longmire
Spent Fuel Licensing Branch
To: Simpson P
Exelon Generation Co
Longmire P
Shared Package
ML18067A186 List:
References
CAC 001028, EPID L-2017-FPR-0075
Download: ML18067A187 (3)


Text

March 9, 2018 Mr. Patrick Simpson Licensing Manager Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION REGARDING ZIONSOLUTIONS, LLCS DECOMMISSIONING FUNDING PLAN UPDATE FOR ZION INDEPENDENT SPENT FUEL STORAGE INSTALLATION

Dear Mr. Simpson:

By letter dated March 30, 2017, ZionSolutions LLC (ZS) submitted, for U.S. Nuclear Regulatory Commission (NRC) staff review and approval, a decommissioning funding plan update (DFP Update) for the independent spent fuel storage installation at Zion (Agencywide Documents Access and Management System Accession No. ML17094A735). The NRC staff reviewed ZSs DFP update and believes ZSs submittal was not sufficient to meet the intent of the requirement in Title 10 of the Code of Federal Regulations (10 CFR) 72.30(c). Specifically, the DFP updates do not provide sufficient information to allow the NRC to determine that the events listed in 10 CFR 72.30(c)(1)-(4) have been considered.

The NRC staff need the information identified in the enclosure to this letter. We request that you provide this information within forty-five (45) working day of the date of this letter. Inform us at your earliest convenience, but no later than 2 weeks prior to the due date, if you are not able to provide the information by that date. To assist us in re-scheduling your review, you should include a new proposed submittal date and the reasons for the delay. Discussion of the request for additional information (RAI) and RAI response date occurred January 31, 2018, by e-mail exchange with Mr. van Noordennen.

The staff is available to clarify these questions, and if necessary to meet and discuss your proposed responses. If you have any questions regarding this matter, please contact me by e-mail at pamela.longmire@nrc.gov.

Sincerely,

/RA/

Pamela Longmire, Ph.D.

Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 72-1037 CAC No.: 001028 EPID No.: L-2017-FPR-0075

Enclosure:

Request for Additional Information

REQUEST FOR ADDITIONAL INFORMATION REGARDING ZIONSOLUTIONS, LLCS DECOMMISSIONING FUNDING PLAN UPDATE FOR ZION INDEPENDENT SPENT FUEL STORAGE INSTALLATION, DOCUMENT DATE: March 9, 2018 DISTRIBUTION:

SFM R/F JMcKirgan ABowers BWatson SHarwell KLois MHenderson JHickman ADAMS Package No.: ML18067A186 Letter: ML18067A187

Enclosure:

ML18067A188 C = COVER E = COVER & ENCLOSURE N = NO COPY OFC NMSS/DSFM NMSS/DSFM NMSS/DSFM NAME PLongmire WWheatley JMcKirgan DATE 3/5/18 3/8/18 3/9/18 OFFICIAL RECORD COPY