ML20246G482

From kanterella
Jump to navigation Jump to search

Acceptance Review Completed for CoC 1027 (TN-68) Renewal
ML20246G482
Person / Time
Site: 07201027
Issue date: 09/02/2020
From: Christian Jacobs
Storage and Transportation Licensing Branch
To: Narayanan P
TN Americas LLC
CJJacobs NMSS/DFM/STL 415.6825
References
CAC 001028, EPID L-2020-RNW-0014
Download: ML20246G482 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 2, 2020 Mr. Prakash Narayanan Chief Technical Officer TN Americas LLC 7160 Riverwood Drive, Suite 200 Columbia, MD 21046

SUBJECT:

ACCEPTANCE REVIEW COMPLETED FOR TN AMERICAS LLC RENEWAL APPLICATION FOR THE TN-68 DRY STORAGE CASK SYSTEM, CERTIFICATE OF COMPLIANCE NO. 1027 (DOCKET NO. 72-1027, CAC NO.

001028, EPID: L-2020-RNW-0014)

Dear Mr. Narayanan:

By letter dated April 9, 2020, and supplemented on July 29, 2020, TN Americas LLC (TN) submitted a renewal application to the U.S. Nuclear Regulatory Commission (NRC) for the TN-68 dry storage cask system, Certificate of Compliance (CoC) No. 1027, pursuant to the requirements of Part 72 of Title 10 of the Code of Federal Regulations.

The staff has reviewed TNs renewal application and has determined the application contains sufficient technical information in scope and depth to begin a detailed technical review. This letter acknowledges acceptance of your application.

We have established a schedule for the review and estimated that the staff may need approximately 1500 hours0.0174 days <br />0.417 hours <br />0.00248 weeks <br />5.7075e-4 months <br /> to complete its review. The schedule allows for the staff to complete its technical review by the end of November 2020 and issue a request for additional information (RAI) in December 2020. If TN provides sufficient responses to the RAI by February 2021, and a second RAI is not needed, the CoC would be submitted to Rulemaking in July 2021.

Rulemaking is estimated to take 6 months, and if there are no significant adverse comments received during the comment period, the CoC will become effective in January 2022. In general, no additional changes to the application should be submitted except for changes resulting from your response to a RAI.

P. Narayanan Please reference Docket No. 72-1027, CAC No. 001028 and EPID: L-2020-RNW-0014 in future correspondence related to the acceptance review for this licensing action. If you have any questions, please contact me at (301) 415-6825.

Sincerely, Christian Jacobs, Senior Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 72-1027 CAC No.: 001028 EPID: L-2020-RNW-0014

P. Narayanan

SUBJECT:

ACCEPTANCE REVIEW COMPLETED FOR TN AMERICAS LLC RENEWAL APPLICATION FOR THE TN-68 DRY STORAGE CASK SYSTEM, CERTIFICATE OF COMPLIANCE NO. 1027 (DOCKET NO. 72-1027, CAC NO.

001028, EPID: L-2020-RNW-0014 DOCUMENT DATE: September 2, 2020 DISTRIBUTION:

DFM r/f AKock, DFM ADAMS Accession Number: ML20246G482 *via email OFFICE: DFM *DFM *DFM NAME: CJacobs WWheatley JMcKirgan DATE: 09/02/2020 09/01/2020 09/02/2020 OFFICIAL RECORD COPY