Letter to J. Shaw Request for Additional Information Regarding Nebraska Public Power Districts Decommissioning Funding Plan Update for Cooper Nuclear Station Independent Spent Fuel Storage Installation
ML18060A026
Person / Time
Site: Cooper Entergy icon.png
Issue date: 02/28/2018
From: Pamela Longmire
Spent Fuel Licensing Branch
To: Shaw J
Nebraska Public Power District (NPPD)
Longmire P
Shared Package
ML18060A025 List:
References
CAC 001028, EPID L-2017-FPR-0018
Download: ML18060A026 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 28, 2018 Mr. Jim Shaw Licensing Manager Nebraska Public Power District P.O. Box 98 Brownville, NE 68321-0098

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION REGARDING NEBRASKA PUBLIC POWER DISTRICTS DECOMMISSIONING FUNDING PLAN UPDATE FOR COOPER NUCLEAR STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATION

Dear Mr. Shaw:

By letter dated December 17, 2015, Nebraska Public Power District (NPPD) submitted, for U.S.

Nuclear Regulatory Commission (NRC) staff review and approval, a decommissioning funding plan update (DFP Update) for the independent spent fuel storage installation (ISFSI) at Cooper Nuclear Station (Cooper) (Agencywide Documents Access and Management System Accession No. ML16014A382). The NRC staff reviewed NPPDs DFP update and believes NPPDs submittal was not sufficient to meet the intent of the requirement in Title 10 of the Code of Federal Regulations (10 CFR) 72.30(c). The DFP update does not provide sufficient information to allow the NRC to determine that the events listed in 10 CFR 72.30(c)(1)-(4) have been specifically considered.

The NRC staff need the information identified in the enclosure to this letter. We request that you provide this information within forty-five (45) working day of the date of this letter. Inform us at your earliest convenience, but no later than 2 weeks prior to the due date, if you are not able to provide the information by that date. To assist us in re-scheduling your review, you should include a new proposed submittal date and the reasons for the delay. Discussion of the request for additional information (RAI) and RAI response date occurred February 1, 2018.

The staff is available to clarify these questions, and if necessary to meet and discuss your proposed responses. If you have any questions regarding this matter, please contact me by e-mail at pamela.longmire@nrc.gov.

Sincerely,

/RA/

Pamela Longmire, Ph.D.

Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 72-66 CAC No.: 001028 EPID No.: L-2017-FPR-0018

Enclosure:

Request for Additional Information

REQUEST FOR ADDITIONAL INFORMATION REGARDING NEBRASKA PUBLIC POWER DISTRICTS DECOMMISSIONING FUNDING PLAN UPDATE FOR COOPER NUCLEAR STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATION, DOCUMENT DATE FEBRUARY 28, 2018 DISTRIBUTION:

SFM R/F McKirgan ABowers SHarwell KLois MHenderson RidsNRRPMCooperResource G:/SFST/72.30 Decommissioning Funding Plans/RAIs/Nebraska PPD/Cooper-RAI.docx G:/SFST/72.30 Decommissioning Funding Plans/RAIs/ Nebraska PPD/Cooper-Enclosure.docx ADAMS Package No.: ML18060A025 Ltr: ML18060A026 Encl: ML18060A027 C = COVER E = COVER & ENCLOSURE N = NO COPY OFC NMSS/DSFM NMSS/DSFM NMSS/DSFM NAME PLongmire WWheatley JMcKirgan DATE 2/1/18 2/13/18 2/28/18 OFFICIAL RECORD COPY