Letter to D. Tallman Request for Additional Information Regarding Sacramento Municipal Utility District'S Decommissioning Funding Plan Update for Rancho Seco Independent Spent Fuel Storage Installation
ML18094A261
Person / Time
Site: 07200011
Issue date: 04/03/2018
From: Pamela Longmire
Spent Fuel Licensing Branch
To: Tallman D
Sacramento Municipal Utility District (SMUD)
Longmire P
Shared Package
ML18094A264 List:
References
CAC 001028, EPID L-2017-FPR-0059
Download: ML18094A261 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 3, 2018 Mr. Dan Tallman Manager, Rancho Seco Assets Sacramento Municipal Utility District Rancho Seco Nuclear Generating Station 14440 Twin Cities Road Herald, CA 95638-9799

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION REGARDING SACRAMENTO MUNICIPAL UTILITY DISTRICTS DECOMMISSIONING FUNDING PLAN UPDATE FOR RANCHO SECO INDEPENDENT SPENT FUEL STORAGE INSTALLATION

Dear Mr. Tallman:

By letter dated April 7, 2016, Sacramento Municipal Utility District (SMUD) submitted for U.S.

Nuclear Regulatory Commission (NRC) staff review and approval, a decommissioning funding plan update (DFP Update) for the independent spent fuel storage installation (ISFSI) at Rancho Seco Nuclear Generating Station (Agencywide Documents Access and Management System Accession No. ML16106A109). The NRC staff reviewed SMUDs DFP update for the ISFSI and believes SMUDs submittal was not sufficient to meet the intent of the requirement in Title 10 of the Code of Federal Regulations (10 CFR) 72.30(c). The DFP update does not provide sufficient information to allow the NRC to determine that the events listed in 10 CFR 72.30(c)(1)-(4) have been specifically considered.

The NRC staff need the information identified in the enclosure to this letter. We request that you provide this information within forty-five (45) working day of the date of this letter. Inform us at your earliest convenience, but no later than 2 weeks prior to the due date, if you are not able to provide the information by that date. To assist us in re-scheduling your review, you should include a new proposed submittal date and the reasons for the delay. Discussion of the request for additional information (RAI) and RAI response date occurred March 27, 2018.

D. Tallman The staff is available to clarify these questions, and if necessary to meet and discuss your proposed responses. If you have any questions regarding this matter, please contact me by e-mail at pamela.longmire@nrc.gov.

Sincerely,

/RA John McKirgan Acting for/

Pamela Longmire, Ph.D.

Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 72-11 CAC No.: 001028 EPID No.: L-2017-FPR-0059

Enclosure:

Request for Additional Information

D. Tallman 3 REQUEST FOR ADDITIONAL INFORMATION REGARDING SACRAMENTO MUNICIPAL UTILITY DISTRICTS DECOMMISSIONING FUNDING PLAN UPDATE FOR RANCHO SECO INDEPENDENT SPENT FUEL STORAGE INSTALLATION, DOCUMENT DATE: April 3, 2018 DISTRIBUTION:

SFM R/F JMcKirgan ABowers SHarwell KLois MHenderson BWatson Letter: G:\SFST\72.30 Decommissioning Funding Plans\RAIs\Rancho Seco\Rancho Seco-RAI.docx

Enclosure:

G:\SFST\72.30 Decommissioning Funding Plans\RAIs\Rancho Seco\Rancho Seco-Enclosure.docx ADAMS Package No.: ML18094A264 Letter: ML18094A262 Encl.: ML18094A261 C = COVER E = COVER & ENCLOSURE N = NO COPY OFC NMSS/DSFM NMSS/DSFM NMSS/DSFM NAME PLongmire WWheatley JMcKirgan DATE 3/27/18 3/28 /18 4/03/18 OFFICIAL RECORD COPY