ML18094B083

From kanterella
Jump to navigation Jump to search

Enclosurequest for Additional Information (Letter to P. Duke RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for Salem and Hope Creek, and Peach Bottom ISFSIs Docket Nos. 72-48 and 72-29)
ML18094B083
Person / Time
Site: Peach Bottom, Salem, Hope Creek  Constellation icon.png
Issue date: 04/05/2018
From: Pamela Longmire
Spent Fuel Licensing Branch
To: Duke P
Public Service Enterprise Group
Longmire P
Shared Package
ML18094B082 List:
References
CAC 001028, EPID L-2017-FPR-0033, EPID L-2017-FPR-0052
Download: ML18094B083 (1)


Text

REQUEST FOR ADDITIONAL INFORMATION REGARDING PSEG NUCLEAR LLCS DECOMMISSIONING FUNDING PLAN UPDATE FOR HOPE CREEK GENERATING STATION, SALEM GENERATING STATION, UNITS 1 AND 2 AND PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS DOCKET NOS. 72-48 AND 72-29 Regulatory Requirement Pursuant to Title 10 of the Code of Federal Regulations (CFR) 72.30(c), at the time of license renewal and at intervals not to exceed 3 years, the decommissioning funding plan (DFP) required to be submitted by 10 CFR 72.30(b) must be resubmitted with adjustments as necessary to account for changes in costs and the extent of contamination. The DFP must update the information submitted with the original or prior approved plan. In addition, the DFP must also specifically consider the effect of the following events on decommissioning costs, as required by 10 CFR 72.30(c)(1)-(4): (1) spills of radioactive material producing additional residual radioactivity in onsite subsurface material, (2) facility modifications, (3) changes in authorized possession limits, and (4) actual remediation costs that exceed the previous cost estimate.

Background

By letter dated December 17, 2015, PSEG Nuclear LLC (PSEG) submitted, for U.S. Nuclear Regulatory Commission (NRC) staff review and approval, decommissioning funding plan updates (DFP Updates) for the independent spent fuel storage installations at Hope Creek Generating Station, Salem Generating Station, Units 1 and 2 and Peach Bottom Atomic Power Station, Units 2 and 3 (Agencywide Documents Access and Management System Accession No. ML15351A336). The NRC staff reviewed PSEGs DFP updates for each independent spent fuel storage installation (ISFSI) and believes PSEGs submittal was not sufficient to meet the intent of the requirement in 72.30(c). Specifically, the DFP updates do not provide sufficient information to allow the NRC to determine that the events listed in 10 CFR 72.30(c)(1)-(4) have been specifically considered.

RAI 1

For each ISFSI, provide a revised DFP that includes the effect on decommissioning costs of each of the events listed in 10 CFR 72.30(c)(1)-(4): (1) spills of radioactive material producing additional residual radioactivity in onsite subsurface material, (2) facility modifications, (3) changes in authorized possession limits, and (4) actual remediation costs that exceed the previous cost estimate.