Acceptance of Constellation License Amendment Request - Deletion of Decommissioning License Conditions for Zion
ML25119A316
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 04/28/2025
From: Kristina Banovac
Storage and Transportation Licensing Branch
To: Steinman R
Constellation Energy Generation
References
EPID L-2025-LLA-0048., CAC 001028
Download: ML25119A316 (1)


Text

From:

Kristina Banovac To:

Rebecca.Steinman@constellation.com Cc:

Seawright, Brian A: (Constellation Nuclear); Yoira Diaz Sanabria

Subject:

Acceptance of Constellation License Amendment Request - Deletion of Facility Operating License Conditions Related to Decommissioning Trust Provisions and License Termination Plan for Zion Nuclear Power Station -

CAC/EPID 001028/ L-2025-LLA-0048 Date:

Monday, April 28, 2025 1:50:00 PM

Dear Rebecca Steinman:

By letter dated March 7, 2025 (Agencywide Documents Access and Management System

[ADAMS] Accession No. ML25066A171), Constellation Energy Generation, LLC (CEG) submitted, for NRC review and approval, a license amendment request for Facility Operating License (FOL) Nos. DPR-39 and DPR-48 for Zion Nuclear Power Station (Zion),

Units 1 and 2. Specifically, the amendment request proposes to delete from the FOLs certain license conditions relating to the terms and conditions of decommissioning trust agreements and, instead, conform to the 10 CFR 50.75(h) regulations, and delete license conditions relating to the License Termination Plan.

The NRC staff completed an acceptance review of your submittal and have identified no administrative omissions or deficiencies that would prevent us from proceeding with a detailed review. Your submittal has been assigned Cost Activity Code/Enterprise Project Identification Numbers 001028/ L-2025-LLA-0048. Please reference these numbers and Docket Nos. 50-295, 50-304 and 72-1037 in any future correspondence associated with this request.

Please note that the NRC staffs detailed review of your submittal may identify issues that could require you to provide additional information. Based on our preliminary evaluation and projection of current review schedules, we anticipate completing our review in January 2026. This schedule includes the issuance, if needed, of a request for additional information (RAI) in September 2025, and receiving your response to the RAI 30 days after its issuance. Please note that these dates could change depending on the findings of our detailed review, urgent assignments, or other factors, such as whether your responses to the RAI are adequate. The NRC staff estimates that completing the review of your submittal will require approximately 120 staff hours. We will promptly communicate significant schedule and/or cost changes.

In accordance with 10 CFR 2.390, Public inspections, exemptions, requests for withholding, a copy of this email will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records component of the NRCs ADAMS. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. The PDR is open by appointment. To make an appointment to visit the PDR, please send an email to PDR.Resource@nrc.gov or call 1800397-4209 or 301-415-4737, between 8:00 a.m. and 4:00 p.m. eastern time (ET),

Monday through Friday, except Federal holidays.

If you have any questions regarding this communication, please contact me at (301) 415-7116, or via email to Kristina.Banovac@nrc.gov.

Sincerely,

Kristina L. Banovac, Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards

Docket Nos.: 50-295, 50-304 and 72-1037 CAC No.: 001028 EPID No.: L-2025-LLA-0048