If a criteria is reached according to NUREG-1022 then a Licensee to the NRC must submit a Licensee Event Report to explain what happened.
Reporting Criteria
Writing LERs
Explain exactly what happened during the entire event or condition, including how systems, components, and operating personnel performed. Do not cover specific hardware problems in excessive detail. Describe unique characteristics of a plant as well as other characteristics that influenced the event (favorably or unfavorably).
- Avoid using plant-unique terms and abbreviations, or, as a minimum, clearly define them.
- The audience for LERs is large and does not necessarily know the details of each plant.
- Include the root causes, the plant status before the event, and the sequence of occurrences.
- Describe the event from the perspective of the Operator (i.e., what the operator saw, did, perceived, understood, or misunderstood).
- If several systems actuate during an event, describe all aspects of the complete event, including all actuations sequentially, and those aspects that by themselves would not be reportable.
- For example, if a single component failure (generally not reportable) occurs following a reactor scram (reportable), describe the component failure in the narrative of the LER for the reactor scram.
- It is necessary to discuss the performance and status of equipment.
- Paraphrase pertinent sections of the latest submitted Safety analysis report (SAR) rather than referencing them because not all organizations or individuals have access to SARs.
- Extensive cross-referencing would be time consuming considering the large number of LERs and reviewers that read each LER.
- Ensure that each component's safety-significant effect on the event or condition is clearly and completely described.
- Do not use statements such as "this event is not significant with respect to the health and safety of the public" without explaining the basis for the conclusion.
Specific information that should be included, as appropriate, is described in paragraphs 50.73(b).
Submissions of LERs
Section 50.73(d) of the NUREG-1022 states that submmissions must be done with Form NRC 366 as described by section 50.4. Submissions are to be done within 60 days of the event. If that happens to be a weekend or a holiday then it must be the next working day. If a Licensee knows that a report will be late or needs an additional day or so to complete the report, the situation should be discussed with the appropriate NRC regional office. See Section 2.5 for further discussion of discovery date.
LER Forwarding Letter and Cancellations
The cover letter forwarding an LER to the NRC should be signed by a responsible official. There is no prescribed format for the letter. The date the letter is issued and the report date should be the same. Licensees are encouraged to include the NRC resident inspector and the Institute of Nuclear Power Operations (INPO) in their distribution. Multiple LERs can be forwarded by one forwarding letter. Cancellations of LERs submitted should be made by letter. The letter should state that the LER is being canceled (i.e., formally withdrawn). The bases for the cancellation should be explained so that the staff can understand and review the reasons supporting the determination. The notice of cancellation will be filed and stored with the LER and acknowledgement made in various automated data systems. The LER will be removed from the LER data base.
Voluntary LERs
Indicate information-type LERS (i.e., Voluntary LERs) by checking the "Other" block in Item 11 of the LER form and type "Voluntary Report" in the space immediately below the block. Also give a sequential LER number to the voluntary report as noted in Section 5.2.4(5). Because not all requirements of 50.73(b), "Contents," may pertain to some voluntary reports, licensees should develop the content of such reports to best present the information associated with the situation being reported. See Section 2.7 for additional discussion of Voluntary LERs.
How To Find LERs
See also
LER list
by site
1 year
| | Site | Start date | Reporting criterion | System | Topic |
|---|
| 05000263/LER-2025-003, Condition Prohibited by Technical Specifications for Not Implementing Setpoint Change of Primary Containment Isolation Valve | Monticello | 18 June 2036 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | Primary containment | |
| 05000373/LER-2025-001, Automatic Scram on Turbine Control Valves Fast Closure on Generator Lockout | LaSalle | 31 December 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | Reactor Protection System Emergency Core Cooling System Control Rod | Temporary Modification |
| 05000400/LER-2025-002, Incorrect Current Value Used During Power Range Nuclear Instrument Calibration | Harris | 29 December 2025 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | Feedwater | |
| 05000445/LER-2025-002, Pressure Transmitter Inoperable for a Duration Prohibited by TS | Comanche Peak | 29 December 2025 | | Reactor Coolant System | Time of Discovery Anticipated operational occurrence Past operability |
| 05000237/LER-2025-002, Valid Reactor Protection System Actuation While Shutdown | Dresden | 26 December 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | Reactor Protection System Control Rod | Scram Discharge Volume |
| 05000334/LER-2025-001, Condition Prohibited by Technical Specifications and Event or Condition That Could Have Prevented Fulfillment of a Safety Function | Beaver Valley | 23 December 2025 | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | Unanalyzed Condition Time of Discovery Past operability Large early release frequency Through-Wall Leak |
| 05000382/LER-2025-004, Station Air Leak in Control Room Envelope Results in a Condition That Could Have Prevented Fulfilment of a Safety Function | Waterford | 23 December 2025 | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | Control Room Envelope | Stress corrosion cracking |
| 05000321/LER-2025-002, Reactor Protection System Instrumentation for Turbine Control Valve Fast Closure Inoperable | Hatch | 19 December 2025 | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2) | Reactor Protection System Electrohydraulic Control | Past operability |
| 05000338/LER-2025-002, Automatic Reactor Trip Due to PRNI High Negative Rate | North Anna | 17 December 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | Reactor Protection System Auxiliary Feedwater Control Rod | Negative Flux Rate Trip |
| 05000482/LER-2025-003, Loss of Voltage on ESF Bus Results in Automatic Actuation of Emergency Diesel Generator | Wolf Creek | 17 December 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | Emergency Diesel Generator Main Transformer | |
| 05000482/LER-2025-002, Loss of Both Trains of Control Room Air Conditioning Causes Condition That Could Have Prevented Fulfillment of a Safety Function | Wolf Creek | 17 December 2025 | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | Control Room Emergency Ventilation | |
| 05000482/LER-2025-001, Improperly Breached Control Building Doors Cause a Condition Prohibited by Technical Specifications | Wolf Creek | 17 December 2025 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | |
| 05000461/LER-2025-003, Scram Turbine Hydraulic Oil Leak | Clinton | 16 December 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | Feedwater Reactor Protection System Main Condenser Electro-Hydraulic Control | Safe Shutdown |
| 05000388/LER-2025-001, Event Involving the Trip of the Unit 2 Main Generator and Subsequent Automatic Reactor Scram | Susquehanna | 16 December 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2) | Reactor Protection System Main Condenser | Arc flash |
| 05000395/LER-2025-004, (Vcsns), Actuation of the Reactor Protection and Emergency Feedwater Systems | Summer | 12 December 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | Steam Generator Feedwater Emergency Feedwater System | |
| 05000370/LER-2025-002, Reactor Trip, Auxiliary Feedwater Actuation, and Refueling Water Storage Tank Inoperability Due to Relief Valve Leak | Mcguire | 9 December 2025 | | Steam Generator Reactor Coolant System Auxiliary Feedwater | Boric Acid Downpower |
| 05000458/LER-2025-007, Division 1 Balance of Plant Isolation Results in Manual Reactor Trip | River Bend | 8 December 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | Feedwater Service water Reactor Protection System Main Turbine | |
| 05000280/LER-2025-002, Fault on Transformer Feeder Cable Caused Automatic Start of Emergency Diesel Generator | Surry | 8 December 2025 | | Emergency Diesel Generator | Reserve Station Service Transformer |
| 05000461/LER-2025-002, Automatic Scram on High Reactor Water Level | Clinton | 5 December 2025 | | Feedwater Reactor Protection System | Safe Shutdown |
| 05000370/LER-2025-001-01, Condition Prohibited by Technical Specifications Due to Emergency Diesel Ventilation Damper Malfunction | Mcguire | 4 December 2025 | | Auxiliary Feedwater | FLEX Loss of Offsite Power Offsite Circuit |
| 05000456/LER-2025-002, Liquid Penetrant Indication in Control Rod Drive Mechanism Nozzle Seal Weld Repair Due to Subsurface Weld Defects Opening from Thermal and Pressure Stresses During Operation | Braidwood | 4 December 2025 | | Control Rod | Liquid penetrant Pressure Boundary Leakage Through-Wall Leakage Seal weld |
| 05000400/LER-2025-001, Fuel Assembly Incorrectly Placed in Spent Fuel Pool B | Harris | 2 December 2025 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | Unanalyzed Condition |
| 05000445/LER-2025-001, (Cpnpp), Manual Reactor Trip from a Loss of Both Main Feedwater Pump Due to a Failure to Reset a Signal Fault | Comanche Peak | 24 November 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | Steam Generator Feedwater Reactor Protection System Auxiliary Feedwater | Temporary Modification Overspeed trip Overspeed |
| 05000318/LER-2025-002, Condition Prohibited by Technical Specifications Due to Condition 3.7.12.A Required Restoration Time Exceeded | Calvert Cliffs | 21 November 2025 | | Steam Generator Main Turbine | |
| 05000313/LER-2025-001, Automatic Reactor Trip Due to Fault on the B Main Phase Transformer | Arkansas Nuclear | 20 November 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | Steam Generator Feedwater Reactor Protection System Control Rod | Arc flash Coast down |
| 05000317/LER-2025-001-01, Control Room Loss of Ventilation Due to Smoke Detector Failure Causing Common Supply Damper to Shut | Calvert Cliffs | 19 November 2025 | | HVAC Control Room Emergency Ventilation Control Room Envelope | Manual Operator Action |
| 05000446/LER-2025-003, Failure of Turbine Electrohydraulic Control System Results in Manual Trip of Unit 2 and Actuation of the Auxiliary Feedwater System | Comanche Peak | 13 November 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | Steam Generator Auxiliary Feedwater Main Turbine Electrohydraulic Control Main Steam | |
| 05000387/LER-2025-001-01, (SSES) Unit 1, Manual Reactor Scram Following Loss of Cooling to Main Transformer | Susquehanna | 13 November 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | Feedwater High Pressure Coolant Injection Reactor Protection System Main Transformer Main Turbine Emergency Core Cooling System Main Steam Line Safety Relief Valve Main Condenser Main Turbine Bypass System | |
| 05000277/LER-2025-003, Invalid Actuation Due to Transformer Trip | Peach Bottom | 13 November 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | Service water Primary Containment Isolation System Reactor Water Cleanup | Coast down |
| 05000461/LER-2025-001, MSIV B21-F022D Limit Switch Failed Testing | Clinton | 12 November 2025 | | Reactor Protection System Main Steam Line Main Steam | Operability Determination |
| 05000366/LER-2025-003, Manual Reactor Scram Due to Trip of Both Reactor Recirculation Pumps | Hatch | 11 November 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | Reactor Protection System Reactor Recirculation Pump | |
| 05000306/LER-2024-002-01, Reactor Trip and auto-start Actuation of Auxiliary Feedwater Due to High Negative Neutron Flux Rate Trip | Prairie Island | 10 November 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | Steam Generator Reactor Protection System Auxiliary Feedwater Control Rod Main Steam | |
| 05000318/LER-2024-001-02, Submittal of Manual Reactor Trip Due to 22 Steam Generator Feed Pump Trip | Calvert Cliffs | 7 November 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | Steam Generator Feedwater Reactor Protection System Auxiliary Feedwater Main Condenser | |
| 05000254/LER-2025-006, High Pressure Coolant Injection Inoperable Due to Turbine Inlet Valve Failure to Open | Quad Cities | 4 November 2025 | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | High Pressure Coolant Injection Reactor Core Isolation Cooling Core Spray Automatic Depressurization System Low Pressure Coolant Injection | |
| 05000370/LER-2025-001, Condition Prohibited by Technical Specifications Due to Emergency Diesel Ventilation Damper Malfunction | Mcguire | 3 November 2025 | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | Auxiliary Feedwater | FLEX Loss of Offsite Power Offsite Circuit |
| 05000414/LER-2025-004, Through Wall Leak in Letdown Piping | Catawba | 3 November 2025 | 10 CFR 50.73(a)(1), Submit an LER 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded | Steam Generator Reactor Coolant System Feedwater Emergency Core Cooling System Main Steam | Boric Acid Time of Discovery Pressure Boundary Leakage Through Wall Leak Operational leakage |
| 05000387/LER-2025-002, Both Sub-Systems of the Control Room Emergency Outside Air Supply System Impacted by Concurrent, Unrelated Equipment Issues in the Control Structure Heating, Ventilation & Air | Susquehanna | 3 November 2025 | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | HVAC | Control Room Habitability |
| 05000416/LER-2025-005, Loss of Secondary Containment Due to Unsecured Roof Hatch | Grand Gulf | 3 November 2025 | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | Secondary containment | |
| 05000318/LER-2025-001-01, Loss of Site Transformer U-4000-12 | Calvert Cliffs | 30 October 2025 | | Emergency Diesel Generator | |
| 05000315/LER-2025-002, Supplemental Diesel Generators (DG) Unavailable Resulting in Emergency DGs Inoperable Greater than Allowed by TS | Cook | 29 October 2025 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | Emergency Diesel Generator | Probabilistic Risk Assessment Large early release frequency |
| 05000260/LER-2025-003-01, Primary Containment Isolation and Manual Reactor Trip Due to Dual Recirculation Pump Trips | Browns Ferry | 27 October 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | Reactor Protection System Primary Containment Isolation System Primary containment | |
| 05000282/LER-2025-003, Nuclear Instrumentation Over-Temperature Delta Temperature Function Inoperable Due to Defective Potentiometers | Prairie Island | 23 October 2025 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | Reactor Protection System | Past operability |
| 05000237/LER-2024-001-01, Containment Cooling Service Water Valve Failure Resulted in a Condition Prohibited by Technical Specifications and Loss of Safety Function | Dresden | 23 October 2025 | 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | Service water Low Pressure Coolant Injection | Past operability Overtravel Fuel cladding |
| 05000249/LER-2024-002-02, Low Pressure Coolant Injection Pump Suction Relief Valve Inoperable as a Primary Containment Isolation Valve Resulted in a Condition Prohibited by Technical Specifications | Dresden | 23 October 2025 | | Primary containment Low Pressure Coolant Injection | |
| 05000251/LER-2025-005, A Main Steam Isolation Valve Failed to Fully Close Resulting in Loss of Safety Function | Turkey Point | 22 October 2025 | 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat | Main Steam Isolation Valve | |
| 05000327/LER-2025-001-01, Manual Reactor Trip Due to Reboot of the Distributed Control System and Lowering Steam Generator Levels | Sequoyah | 22 October 2025 | 10 CFR 50.73(b)(3)(iv)(A) | Steam Generator Reactor Protection System Auxiliary Feedwater | |
| 05000296/LER-2025-002, Reactor Core Isolation Cooling Inoperable Due to Failed Ramp Generating Signal Converter | Browns Ferry | 20 October 2025 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | High Pressure Coolant Injection Reactor Core Isolation Cooling | |
| 05000458/LER-2025-002-01, For River Bend Station, Unit 1, Unidentified Drywell Leakage Increase Results in Shutdown | River Bend | 20 October 2025 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | Reactor Coolant System Feedwater Residual Heat Removal | Unanalyzed Condition Stress corrosion cracking Pressure Boundary Leakage Unidentified leakage |
| 05000458/LER-2025-005, For River Bend Station, Unit 1, Containment Unit Coolers Inoperable Due to Compensatory Measures | River Bend | 20 October 2025 | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | Primary containment | Unanalyzed Condition Loss of Offsite Power Operability Determination |
| 05000458/LER-2025-006, For River Bend Station, Potential Loss of Safety Function of Control Building Chillers Due to a Valve Mispositioned | River Bend | 20 October 2025 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown 10 CFR 50.73(a)(2)(ix)(A), Prevented Safety Function in Multiple System 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) | | Safe Shutdown |