Licensee Event Report

From kanterella
Jump to navigation Jump to search

If a criteria is reached according to NUREG-1022 then a Licensee to the NRC must submit a Licensee Event Report to explain what happened.

Reporting Criteria

Writing LERs

Explain exactly what happened during the entire event or condition, including how systems, components, and operating personnel performed. Do not cover specific hardware problems in excessive detail. Describe unique characteristics of a plant as well as other characteristics that influenced the event (favorably or unfavorably).

  • Avoid using plant-unique terms and abbreviations, or, as a minimum, clearly define them.
    • The audience for LERs is large and does not necessarily know the details of each plant.
  • Include the root causes, the plant status before the event, and the sequence of occurrences.
  • Describe the event from the perspective of the Operator (i.e., what the operator saw, did, perceived, understood, or misunderstood).
  • If several systems actuate during an event, describe all aspects of the complete event, including all actuations sequentially, and those aspects that by themselves would not be reportable.
    • For example, if a single component failure (generally not reportable) occurs following a reactor scram (reportable), describe the component failure in the narrative of the LER for the reactor scram.
  • It is necessary to discuss the performance and status of equipment.
  • Paraphrase pertinent sections of the latest submitted Safety analysis report (SAR) rather than referencing them because not all organizations or individuals have access to SARs.
  • Extensive cross-referencing would be time consuming considering the large number of LERs and reviewers that read each LER.
  • Ensure that each component's safety-significant effect on the event or condition is clearly and completely described.
  • Do not use statements such as "this event is not significant with respect to the health and safety of the public" without explaining the basis for the conclusion.

Specific information that should be included, as appropriate, is described in paragraphs 50.73(b).

Submissions of LERs

Section 50.73(d) of the NUREG-1022 states that submmissions must be done with Form NRC 366 as described by section 50.4. Submissions are to be done within 60 days of the event. If that happens to be a weekend or a holiday then it must be the next working day. If a Licensee knows that a report will be late or needs an additional day or so to complete the report, the situation should be discussed with the appropriate NRC regional office. See Section 2.5 for further discussion of discovery date.


LER Forwarding Letter and Cancellations

The cover letter forwarding an LER to the NRC should be signed by a responsible official. There is no prescribed format for the letter. The date the letter is issued and the report date should be the same. Licensees are encouraged to include the NRC resident inspector and the Institute of Nuclear Power Operations (INPO) in their distribution. Multiple LERs can be forwarded by one forwarding letter. Cancellations of LERs submitted should be made by letter. The letter should state that the LER is being canceled (i.e., formally withdrawn). The bases for the cancellation should be explained so that the staff can understand and review the reasons supporting the determination. The notice of cancellation will be filed and stored with the LER and acknowledgement made in various automated data systems. The LER will be removed from the LER data base.


Voluntary LERs

Indicate information-type LERS (i.e., Voluntary LERs) by checking the "Other" block in Item 11 of the LER form and type "Voluntary Report" in the space immediately below the block. Also give a sequential LER number to the voluntary report as noted in Section 5.2.4(5). Because not all requirements of 50.73(b), "Contents," may pertain to some voluntary reports, licensees should develop the content of such reports to best present the information associated with the situation being reported. See Section 2.7 for additional discussion of Voluntary LERs.

How To Find LERs

See also

LER list

by site

1 year

Site#CompanyEvent lists
Almaraz 0 Iberdrola [Almaraz events] [RSS]
Arkansas Nuclear 0 Entergy [Arkansas Nuclear events] [RSS]
Asco 0 Endesa [Asco events] [RSS]
Beaver Valley 0 Vistra [Beaver Valley events] [RSS]
Belleville 0 Électricité de France [Belleville events] [RSS]
Big Rock Point 0 Consumers Energy [Big Rock Point events] [RSS]
Blayais 0 Électricité de France [Blayais events] [RSS]
Braidwood 0 Constellation [Braidwood events] [RSS]
Browns Ferry 0 Tennessee Valley Authority [Browns Ferry events] [RSS]
Brunswick 0 Duke Energy [Brunswick events] [RSS]
Byron 0 Constellation [Byron events] [RSS]
Callaway 0 Ameren [Callaway events] [RSS]
Calvert Cliffs 0 Constellation [Calvert Cliffs events] [RSS]
Catawba 0 Duke Energy [Catawba events] [RSS]
Chernobyl 0 [Chernobyl events] [RSS]
Clinch River 0 [Clinch River events] [RSS]
Clinton 0 Constellation [Clinton events] [RSS]
Cofrentes 0 Iberdrola [Cofrentes events] [RSS]
Columbia 0 Energy Northwest [Columbia events] [RSS]
Comanche Peak 0 Luminant [Comanche Peak events] [RSS]
Cook 0 American Electric Power [Cook events] [RSS]
Cooper 0 Entergy [Cooper events] [RSS]
Crane 0 Constellation [Crane events] [RSS]
Crystal River 0 Duke Energy [Crystal River events] [RSS]
Dampierre 0 Électricité de France [Dampierre events] [RSS]
Davis Besse 0 Cleveland Electric [Davis Besse events] [RSS]
Diablo Canyon 0 Pacific Gas & Electric [Diablo Canyon events] [RSS]
Dresden 0 Constellation [Dresden events] [RSS]
Duane Arnold 0 NextEra Energy [Duane Arnold events] [RSS]
Dungeness 0 EDF Energy [Dungeness events] [RSS]
Elk River 0 [Elk River events] [RSS]
Farley 0 Southern Nuclear [Farley events] [RSS]
Fermi 0 DTE Energy [Fermi events] [RSS]
FitzPatrick 0 Constellation [FitzPatrick events] [RSS]
Flamanville 0 Électricité de France [Flamanville events] [RSS]
Fort Calhoun 0 Omaha Public Power District [Fort Calhoun events] [RSS]
Fort Saint Vrain 0 Xcel Energy [Fort Saint Vrain events] [RSS]
Fukushima Dai-Ichi 0 TEPCO [Fukushima Dai-Ichi events] [RSS]
Ginna 0 Constellation [Ginna events] [RSS]
Grand Gulf 0 Entergy [Grand Gulf events] [RSS]
Haddam Neck 0 Connecticut Yankee Atomic Power Co [Haddam Neck events] [RSS]
Hallam 0 [Hallam events] [RSS]
Harris 0 Duke Energy [Harris events] [RSS]
Hartlepool 0 EDF Energy [Hartlepool events] [RSS]
Hatch 0 Southern Nuclear [Hatch events] [RSS]
Heysham 0 EDF Energy [Heysham events] [RSS]
Hinkley Point 0 EDF Energy [Hinkley Point events] [RSS]
Hope Creek 0 PSEG [Hope Creek events] [RSS]
Humboldt Bay 0 Pacific Gas and Electric [Humboldt Bay events] [RSS]
Hunterston 0 EDF Energy [Hunterston events] [RSS]
Indian Point 0 Entergy [Indian Point events] [RSS]
Jose Cabrera 0 Enresa [Jose Cabrera events] [RSS]
Kemmerer 0 TerraPower [Kemmerer events] [RSS]
Kewaunee 0 Dominion [Kewaunee events] [RSS]
Khmelnytskyi 0 Energoatom [Khmelnytskyi events] [RSS]
La Crosse 0 Dairyland Power Cooperative [La Crosse events] [RSS]
LaSalle 0 Constellation [LaSalle events] [RSS]
Lee 0 Duke Energy [Lee events] [RSS]
Limerick 0 Constellation [Limerick events] [RSS]
Maine Yankee 0 Maine Yankee [Maine Yankee events] [RSS]
McGuire 0 Duke Energy [McGuire events] [RSS]
Millstone 0 Dominion [Millstone events] [RSS]
Monticello 0 Xcel Energy [Monticello events] [RSS]
Nine Mile Point 0 Constellation [Nine Mile Point events] [RSS]
Nogent 0 Électricité de France [Nogent events] [RSS]
North Anna 0 Dominion [North Anna events] [RSS]
Oconee 0 Duke Energy [Oconee events] [RSS]
Olkiluoto 0 Teollisuuden Voima [Olkiluoto events] [RSS]
Oyster Creek 0 Holtec [Oyster Creek events] [RSS]
Palisades 0 Entergy [Palisades events] [RSS]
Palo Verde 0 Arizona Public Service [Palo Verde events] [RSS]
Parr 0 [Parr events] [RSS]
Peach Bottom 0 Constellation [Peach Bottom events] [RSS]
Perry 0 FirstEnergy [Perry events] [RSS]
Pilgrim 0 Holtec [Pilgrim events] [RSS]
Point Beach 0 NextEra Energy [Point Beach events] [RSS]
Prairie Island 0 Xcel Energy [Prairie Island events] [RSS]
Quad Cities 0 Constellation [Quad Cities events] [RSS]
Rancho Seco 0 Sacramento Municipal Utility District [Rancho Seco events] [RSS]
River Bend 0 Entergy [River Bend events] [RSS]
Rivne 0 Energoatom [Rivne events] [RSS]
Robinson 0 Duke Energy [Robinson events] [RSS]
Saint Lucie 0 NextEra Energy [Saint Lucie events] [RSS]
Salem 0 PSEG [Salem events] [RSS]
San Onofre 0 Southern California Edison [San Onofre events] [RSS]
Santa Maria De Garona 0 Nuclenor [Santa Maria De Garona events] [RSS]
Saxton 0 GPU Nuclear [Saxton events] [RSS]
Seabrook 0 NextEra Energy [Seabrook events] [RSS]
Sequoyah 0 Tennessee Valley Authority [Sequoyah events] [RSS]
Shippingport 0 [Shippingport events] [RSS]
Shoreham 0 Long Island Lighting Company [Shoreham events] [RSS]
Sizewell 0 EDF Energy [Sizewell events] [RSS]
South Texas 0 STP Nuclear Operating Company [South Texas events] [RSS]
South Ukraine 0 Energoatom [South Ukraine events] [RSS]
Summer 0 South Carolina Electric & Gas Company [Summer events] [RSS]
Sundesert 0 San Diego Gas & Electric Compnay [Sundesert events] [RSS]
Surry 0 Dominion [Surry events] [RSS]
Susquehanna 0 Talen Energy [Susquehanna events] [RSS]
Taishan 0 China Guangdong Nuclear Power Group [Taishan events] [RSS]
Trillo 0 Iberdrola [Trillo events] [RSS]
Trojan 0 Portland General Electric [Trojan events] [RSS]
Turkey Point 0 NextEra Energy [Turkey Point events] [RSS]
Vandellos 0 Endesa [Vandellos events] [RSS]
Vermont Yankee 0 NorthStar Vermont Yankee [Vermont Yankee events] [RSS]
Victoria 0 Exelon [Victoria events] [RSS]
Vogtle 0 Southern Nuclear [Vogtle events] [RSS]
Waterford 0 Entergy [Waterford events] [RSS]
Watts Bar 0 Tennessee Valley Authority [Watts Bar events] [RSS]
Wolf Creek 0 Wolf Creek Nuclear Operating Corporation [Wolf Creek events] [RSS]
Yankee Rowe 0 [Yankee Rowe events] [RSS]
Zaporizhzhia 0 Enerhodar [Zaporizhzhia events] [RSS]
Zion 0 ZionSolutions [Zion events] [RSS]
 SiteStart dateReporting criterionSystemTopic
05000263/LER-2025-003, Condition Prohibited by Technical Specifications for Not Implementing Setpoint Change of Primary Containment Isolation ValveMonticello18 June 203610 CFR 50.73(a)(2)(i)(B), Prohibited by Technical SpecificationsPrimary containment
05000373/LER-2025-001, Automatic Scram on Turbine Control Valves Fast Closure on Generator LockoutLaSalle31 December 202510 CFR 50.73(a)(2)(iv)(A), System ActuationReactor Protection System
Emergency Core Cooling System
Control Rod
Temporary Modification
05000400/LER-2025-002, Incorrect Current Value Used During Power Range Nuclear Instrument CalibrationHarris29 December 202510 CFR 50.73(a)(2)(i)(B), Prohibited by Technical SpecificationsFeedwater
05000445/LER-2025-002, Pressure Transmitter Inoperable for a Duration Prohibited by TSComanche Peak29 December 2025Reactor Coolant SystemTime of Discovery
Anticipated operational occurrence
Past operability
05000237/LER-2025-002, Valid Reactor Protection System Actuation While ShutdownDresden26 December 202510 CFR 50.73(a)(2)(iv)(A), System ActuationReactor Protection System
Control Rod
Scram Discharge Volume
05000334/LER-2025-001, Condition Prohibited by Technical Specifications and Event or Condition That Could Have Prevented Fulfillment of a Safety FunctionBeaver Valley23 December 202510 CFR 50.73(a)(2)(v), Loss of Safety Function
10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
Unanalyzed Condition
Time of Discovery
Past operability
Large early release frequency
Through-Wall Leak
05000382/LER-2025-004, Station Air Leak in Control Room Envelope Results in a Condition That Could Have Prevented Fulfilment of a Safety FunctionWaterford23 December 202510 CFR 50.73(a)(2)(v), Loss of Safety FunctionControl Room EnvelopeStress corrosion cracking
05000321/LER-2025-002, Reactor Protection System Instrumentation for Turbine Control Valve Fast Closure InoperableHatch19 December 202510 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor
10 CFR 50.73(a)(2)(vii), Common Cause Inoperability
10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
10 CFR 50.73(a)(2)
Reactor Protection System
Electrohydraulic Control
Past operability
05000338/LER-2025-002, Automatic Reactor Trip Due to PRNI High Negative RateNorth Anna17 December 202510 CFR 50.73(a)(2)(iv)(A), System ActuationReactor Protection System
Auxiliary Feedwater
Control Rod
Negative Flux Rate Trip
05000482/LER-2025-003, Loss of Voltage on ESF Bus Results in Automatic Actuation of Emergency Diesel GeneratorWolf Creek17 December 202510 CFR 50.73(a)(2)(iv)(A), System ActuationEmergency Diesel Generator
Main Transformer
05000482/LER-2025-002, Loss of Both Trains of Control Room Air Conditioning Causes Condition That Could Have Prevented Fulfillment of a Safety FunctionWolf Creek17 December 202510 CFR 50.73(a)(2)(v), Loss of Safety FunctionControl Room Emergency Ventilation
05000482/LER-2025-001, Improperly Breached Control Building Doors Cause a Condition Prohibited by Technical SpecificationsWolf Creek17 December 202510 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
05000461/LER-2025-003, Scram Turbine Hydraulic Oil LeakClinton16 December 202510 CFR 50.73(a)(2)(iv)(A), System ActuationFeedwater
Reactor Protection System
Main Condenser
Electro-Hydraulic Control
Safe Shutdown
05000388/LER-2025-001, Event Involving the Trip of the Unit 2 Main Generator and Subsequent Automatic Reactor ScramSusquehanna16 December 202510 CFR 50.73(a)(2)(iv)(A), System Actuation
10 CFR 50.73(a)(2)
Reactor Protection System
Main Condenser
Arc flash
05000395/LER-2025-004, (Vcsns), Actuation of the Reactor Protection and Emergency Feedwater SystemsSummer12 December 202510 CFR 50.73(a)(2)(iv)(A), System ActuationSteam Generator
Feedwater
Emergency Feedwater System
05000370/LER-2025-002, Reactor Trip, Auxiliary Feedwater Actuation, and Refueling Water Storage Tank Inoperability Due to Relief Valve LeakMcguire9 December 2025Steam Generator
Reactor Coolant System
Auxiliary Feedwater
Boric Acid
Downpower
05000458/LER-2025-007, Division 1 Balance of Plant Isolation Results in Manual Reactor TripRiver Bend8 December 202510 CFR 50.73(a)(2)(iv)(A), System ActuationFeedwater
Service water
Reactor Protection System
Main Turbine
05000280/LER-2025-002, Fault on Transformer Feeder Cable Caused Automatic Start of Emergency Diesel GeneratorSurry8 December 2025Emergency Diesel GeneratorReserve Station Service Transformer
05000461/LER-2025-002, Automatic Scram on High Reactor Water LevelClinton5 December 2025Feedwater
Reactor Protection System
Safe Shutdown
05000370/LER-2025-001-01, Condition Prohibited by Technical Specifications Due to Emergency Diesel Ventilation Damper MalfunctionMcguire4 December 2025Auxiliary FeedwaterFLEX
Loss of Offsite Power
Offsite Circuit
05000456/LER-2025-002, Liquid Penetrant Indication in Control Rod Drive Mechanism Nozzle Seal Weld Repair Due to Subsurface Weld Defects Opening from Thermal and Pressure Stresses During OperationBraidwood4 December 2025Control RodLiquid penetrant
Pressure Boundary Leakage
Through-Wall Leakage
Seal weld
05000400/LER-2025-001, Fuel Assembly Incorrectly Placed in Spent Fuel Pool BHarris2 December 202510 CFR 50.73(a)(2)(i)(B), Prohibited by Technical SpecificationsUnanalyzed Condition
05000445/LER-2025-001, (Cpnpp), Manual Reactor Trip from a Loss of Both Main Feedwater Pump Due to a Failure to Reset a Signal FaultComanche Peak24 November 202510 CFR 50.73(a)(2)(iv)(A), System ActuationSteam Generator
Feedwater
Reactor Protection System
Auxiliary Feedwater
Temporary Modification
Overspeed trip
Overspeed
05000318/LER-2025-002, Condition Prohibited by Technical Specifications Due to Condition 3.7.12.A Required Restoration Time ExceededCalvert Cliffs21 November 2025Steam Generator
Main Turbine
05000313/LER-2025-001, Automatic Reactor Trip Due to Fault on the B Main Phase TransformerArkansas Nuclear20 November 202510 CFR 50.73(a)(2)(iv)(A), System ActuationSteam Generator
Feedwater
Reactor Protection System
Control Rod
Arc flash
Coast down
05000317/LER-2025-001-01, Control Room Loss of Ventilation Due to Smoke Detector Failure Causing Common Supply Damper to ShutCalvert Cliffs19 November 2025HVAC
Control Room Emergency Ventilation
Control Room Envelope
Manual Operator Action
05000446/LER-2025-003, Failure of Turbine Electrohydraulic Control System Results in Manual Trip of Unit 2 and Actuation of the Auxiliary Feedwater SystemComanche Peak13 November 202510 CFR 50.73(a)(2)(iv)(A), System ActuationSteam Generator
Auxiliary Feedwater
Main Turbine
Electrohydraulic Control
Main Steam
05000387/LER-2025-001-01, (SSES) Unit 1, Manual Reactor Scram Following Loss of Cooling to Main TransformerSusquehanna13 November 202510 CFR 50.73(a)(2)(iv)(A), System ActuationFeedwater
High Pressure Coolant Injection
Reactor Protection System
Main Transformer
Main Turbine
Emergency Core Cooling System
Main Steam Line
Safety Relief Valve
Main Condenser
Main Turbine Bypass System
05000277/LER-2025-003, Invalid Actuation Due to Transformer TripPeach Bottom13 November 202510 CFR 50.73(a)(2)(iv)(A), System ActuationService water
Primary Containment Isolation System
Reactor Water Cleanup
Coast down
05000461/LER-2025-001, MSIV B21-F022D Limit Switch Failed TestingClinton12 November 2025Reactor Protection System
Main Steam Line
Main Steam
Operability Determination
05000366/LER-2025-003, Manual Reactor Scram Due to Trip of Both Reactor Recirculation PumpsHatch11 November 202510 CFR 50.73(a)(2)(iv)(A), System ActuationReactor Protection System
Reactor Recirculation Pump
05000306/LER-2024-002-01, Reactor Trip and auto-start Actuation of Auxiliary Feedwater Due to High Negative Neutron Flux Rate TripPrairie Island10 November 202510 CFR 50.73(a)(2)(iv)(A), System ActuationSteam Generator
Reactor Protection System
Auxiliary Feedwater
Control Rod
Main Steam
05000318/LER-2024-001-02, Submittal of Manual Reactor Trip Due to 22 Steam Generator Feed Pump TripCalvert Cliffs7 November 202510 CFR 50.73(a)(2)(iv)(A), System ActuationSteam Generator
Feedwater
Reactor Protection System
Auxiliary Feedwater
Main Condenser
05000254/LER-2025-006, High Pressure Coolant Injection Inoperable Due to Turbine Inlet Valve Failure to OpenQuad Cities4 November 202510 CFR 50.73(a)(2)(v), Loss of Safety FunctionHigh Pressure Coolant Injection
Reactor Core Isolation Cooling
Core Spray
Automatic Depressurization System
Low Pressure Coolant Injection
05000370/LER-2025-001, Condition Prohibited by Technical Specifications Due to Emergency Diesel Ventilation Damper MalfunctionMcguire3 November 202510 CFR 50.73(a)(2)(v), Loss of Safety Function
10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
Auxiliary FeedwaterFLEX
Loss of Offsite Power
Offsite Circuit
05000414/LER-2025-004, Through Wall Leak in Letdown PipingCatawba3 November 202510 CFR 50.73(a)(1), Submit an LER
10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded
Steam Generator
Reactor Coolant System
Feedwater
Emergency Core Cooling System
Main Steam
Boric Acid
Time of Discovery
Pressure Boundary Leakage
Through Wall Leak
Operational leakage
05000387/LER-2025-002, Both Sub-Systems of the Control Room Emergency Outside Air Supply System Impacted by Concurrent, Unrelated Equipment Issues in the Control Structure Heating, Ventilation & AirSusquehanna3 November 202510 CFR 50.73(a)(2)(v), Loss of Safety FunctionHVACControl Room Habitability
05000416/LER-2025-005, Loss of Secondary Containment Due to Unsecured Roof HatchGrand Gulf3 November 202510 CFR 50.73(a)(2)(v), Loss of Safety FunctionSecondary containment
05000318/LER-2025-001-01, Loss of Site Transformer U-4000-12Calvert Cliffs30 October 2025Emergency Diesel Generator
05000315/LER-2025-002, Supplemental Diesel Generators (DG) Unavailable Resulting in Emergency DGs Inoperable Greater than Allowed by TSCook29 October 202510 CFR 50.73(a)(2)(i)(B), Prohibited by Technical SpecificationsEmergency Diesel GeneratorProbabilistic Risk Assessment
Large early release frequency
05000260/LER-2025-003-01, Primary Containment Isolation and Manual Reactor Trip Due to Dual Recirculation Pump TripsBrowns Ferry27 October 202510 CFR 50.73(a)(2)(iv)(A), System ActuationReactor Protection System
Primary Containment Isolation System
Primary containment
05000282/LER-2025-003, Nuclear Instrumentation Over-Temperature Delta Temperature Function Inoperable Due to Defective PotentiometersPrairie Island23 October 202510 CFR 50.73(a)(2)(i)(B), Prohibited by Technical SpecificationsReactor Protection SystemPast operability
05000237/LER-2024-001-01, Containment Cooling Service Water Valve Failure Resulted in a Condition Prohibited by Technical Specifications and Loss of Safety FunctionDresden23 October 202510 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat
10 CFR 50.73(a)(2)(v), Loss of Safety Function
10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
Service water
Low Pressure Coolant Injection
Past operability
Overtravel
Fuel cladding
05000249/LER-2024-002-02, Low Pressure Coolant Injection Pump Suction Relief Valve Inoperable as a Primary Containment Isolation Valve Resulted in a Condition Prohibited by Technical SpecificationsDresden23 October 2025Primary containment
Low Pressure Coolant Injection
05000251/LER-2025-005, A Main Steam Isolation Valve Failed to Fully Close Resulting in Loss of Safety FunctionTurkey Point22 October 202510 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual HeatMain Steam Isolation Valve
05000327/LER-2025-001-01, Manual Reactor Trip Due to Reboot of the Distributed Control System and Lowering Steam Generator LevelsSequoyah22 October 202510 CFR 50.73(b)(3)(iv)(A)Steam Generator
Reactor Protection System
Auxiliary Feedwater
05000296/LER-2025-002, Reactor Core Isolation Cooling Inoperable Due to Failed Ramp Generating Signal ConverterBrowns Ferry20 October 202510 CFR 50.73(a)(2)(i)(B), Prohibited by Technical SpecificationsHigh Pressure Coolant Injection
Reactor Core Isolation Cooling
05000458/LER-2025-002-01, For River Bend Station, Unit 1, Unidentified Drywell Leakage Increase Results in ShutdownRiver Bend20 October 202510 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded
10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown
Reactor Coolant System
Feedwater
Residual Heat Removal
Unanalyzed Condition
Stress corrosion cracking
Pressure Boundary Leakage
Unidentified leakage
05000458/LER-2025-005, For River Bend Station, Unit 1, Containment Unit Coolers Inoperable Due to Compensatory MeasuresRiver Bend20 October 202510 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition
10 CFR 50.73(a)(2)(v), Loss of Safety Function
10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
Primary containmentUnanalyzed Condition
Loss of Offsite Power
Operability Determination
05000458/LER-2025-006, For River Bend Station, Potential Loss of Safety Function of Control Building Chillers Due to a Valve MispositionedRiver Bend20 October 202510 CFR 50.73(a)(2)(iv)(A), System Actuation
10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition
10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor
10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat
10 CFR 50.73(a)(2)(v), Loss of Safety Function
10 CFR 50.73(a)(2)(vii), Common Cause Inoperability
10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
10 CFR 50.73(a)(2)(i)
10 CFR 50.73(a)(2)(x)
10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded
10 CFR 50.73(a)(2)(iii)
10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown
10 CFR 50.73(a)(2)(ix)(A), Prevented Safety Function in Multiple System
10 CFR 50.73(a)(2)(viii)(A)
10 CFR 50.73(a)(2)(viii)(B)
Safe Shutdown
... further results