ML24043A095
Letter Sequence Meeting | |
---|---|
Initiation
Administration
Questions
Answers
Results
Other: L-23-005, Independent Spent Fuel Storage Installation License Renewal Application, Revision 1 (Cac/Epid No. 001028/L-2022-RNW-0007), ML19276D398, ML20014E677, ML20049A082, ML20065N277, ML20065N278, ML20065N280, ML20065N281, ML20065N285, ML20071F156, ML20076D696, ML20094G482, ML20099A180, ML20104C015, ML20104C016, ML20104C018, ML20104C019, ML20105A135, ML20105A136, ML20105A137, ML20105A138, ML20105A139, ML20105A173, ML20111A240, ML20115E377, ML20121A272, ML20136A049, ML20136A050, ML20136A051, ML20150A300, ML20150A335, ML20150A421, ML20155K741, ML20155K742, ML20155K743, ML20155K744, ML20160A040, ML20161A088, ML20163A702, ML20163A703, ML20163A704, ML20181A211, ML20181A212, ML20192A328, ML20192A329, ML20212L768, ML20212L769, ML20212L878, ML20223A036, ML20224A287... further results | |
MONTHYEARML20115E3782019-10-0303 October 2019
[Table View]Independent Spent Fuel Storage Installation Exemption Safety Evaluation Report Project stage: Approval ML19276D3982019-10-0303 October 2019 Exemption Request to Load and Store Spent Fuel in HI-STORM FW Spent Fuel Casks Utilizing Amendment 1, Revision 1 to CoC No. 1032 Project stage: Other ML20014E6772020-01-0909 January 2020 Fws List of Threatened and Endangered Species That May Occur with Respect to the McGuire Exemption Request Project stage: Other ML20015A3142020-01-14014 January 2020 Package: Exemption Request McGuire Nuclear Facility Project stage: Request ML20049A0822020-01-31031 January 2020 Holtec International - HI-STORM 100 Storage CoC Renewal Application Project stage: Other ML20049A0812020-01-31031 January 2020 Holtec International - HI-STORM 100 Storage CoC Renewal Application Project stage: Request ML20055F3372020-02-20020 February 2020 Conversation Record - Clarification Call (02/20/2020) on RAI 1 for CoC 1040 Umax Amendment 4 Project stage: RAI ML20064F6162020-02-29029 February 2020 January 15, 2020, Summary of Meeting with Holtec International, Inc., to Discuss the Upcoming Submittal of the Application for Renewal of the Storage Certificate of Compliance No. 1014 for the HI-Storm 100 Cask System Project stage: Meeting ML20063M0152020-03-0303 March 2020 HI-STORM 100 Renewal Presubmittal Meeting (Holtec Slides, 1-15-20) Project stage: Meeting ML20064E6222020-03-0303 March 2020 U.S. Nuclear Regulatory Commission Approval of NAC International Request for Withholding Information from Public Disclosure for Coc 1025 Renewal (CAC No. 001028) Project stage: Withholding Request Acceptance ML20065J4272020-03-0505 March 2020 Submittal of Renewal Application for the TN-32 Dry Storage Cask - CoC 1021 Project stage: Request ML20071F1562020-03-0505 March 2020 Interim Storage Partners, LLC - Affidavit Project stage: Other ML20071F1532020-03-0505 March 2020 Interim Storage Partners, LLC - Supplemental Information in Support of Nrc'S Environmental Review Project stage: Supplement ML20071J0552020-03-0505 March 2020 Notice of Cancelled Meeting with the U.S. Department of Energy, Idaho Operations Office to Discuss the Upcoming Submittal of the Application for Renewal of the Idaho Spent Fuel Facility License (SNM-2512) Project stage: Meeting ML20065K2162020-03-0505 March 2020 Notice of Meeting with U.S. Department of Energy, Idaho Operations Office to Discuss the Upcoming Submittal of the Application for Renewal of the Idaho Spent Fuel Facility License (SNM-2512) Project stage: Meeting ML20065L3442020-03-0606 March 2020 Amendment No. 15 to Certificate of Compliance No. 1014 for the Hi-Storm 100 Multipurpose Canister Storage System - Request for Additional Information Project stage: RAI ML20066K5782020-03-0606 March 2020 Acceptance Review of Request for Amendment No. 7 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System Project stage: Acceptance Review ML20065N2772020-03-0909 March 2020 ISFSI Renewal Cover Letter Project stage: Other ML20065N2812020-03-0909 March 2020 ISFSI Preamble-License Renewal Order Project stage: Other ML20065N2852020-03-0909 March 2020 ISFSI Renewed Technical Specifications Project stage: Other ML20071D9942020-03-11011 March 2020 Submittal of HI-STAR 100 Updated FSAR, Revision 4 Project stage: Request ML20076D6962020-03-11011 March 2020 Interim Storage Partners, LLC - Submittal of Clarifications to Support Nrc'S Continued Review of the Safety Case for the WCS CISF Project stage: Other ML20065N2782020-03-11011 March 2020 ISFSI FRN Notice of Issuance for License Renewal Project stage: Other ML20104C0202020-03-30030 March 2020 International - HI-STORM Umax Amendment 4 Responses to Requests for Additional Information - Supplemental Information Project stage: Supplement ML20104C0182020-03-30030 March 2020 International - HI-STORM Umax Amendment 4 FSAR - Changed Pages Project stage: Other ML20104C0192020-03-30030 March 2020 International - Affidavit for Kimberly Manzione Project stage: Other ML20104C0162020-03-30030 March 2020 International - Proposed HI-STORM Umax CoC Amendment 4 Appendix a - Changed Pages Project stage: Other ML20104C0152020-03-30030 March 2020 International - Amendment No. 4 to the HI-STORM Umax Canister Storage System Project stage: Other ML20104C0482020-03-31031 March 2020 International - HI-STORM Umax Amendment 3 Responses to Requests for Additional Information Project stage: Response to RAI ML20101P3992020-03-31031 March 2020 Interim Storage Partners, LLC - Submittal of Draft Responses for Several Rals and Associated Document Markups from First Request for Additional Information, Parts 1, 2 and Clarifications Project stage: Draft Request ML20091L0642020-03-31031 March 2020 Enclosure 1 - Request for Additional Information - Non-Proprietary Project stage: RAI ML20065N2802020-03-31031 March 2020 ISFSI License Renewal SER Project stage: Other ML20091L0632020-03-31031 March 2020 Transmittal Letter - CoC 1042 Amendment Number 2 Request for Additional Information Project stage: RAI ML20105A1352020-03-31031 March 2020 Enclosure 1 - Affidavits Project stage: Other ML20099A1802020-04-0606 April 2020 Application for Renewal of the Certificate of Compliance No. 1014 for the Hi-Storm 100 Storage Cask System Accepted for Review (Cac/Epid Nos. 001028/L-2020-RNW-0007) Project stage: Other ML20105A1732020-04-0606 April 2020 Interim Storage Partners, LLC - Affidavits Project stage: Other ML20105A1722020-04-0707 April 2020 Interim Storage Partners, LLC - Submittal of Supplemental Information in Support of RAI, Part 3 Project stage: Supplement ML20105A1362020-04-0707 April 2020 Enclosure 3 - RAIs and Responses Project stage: Other ML20105A1382020-04-0707 April 2020 Enclosure 7 - SAR Changed Pages Project stage: Other ML20105A1372020-04-0707 April 2020 Enclosure 5 - La Changed Pages Project stage: Other ML20105A1392020-04-0707 April 2020 Enclosure 8 - Referenced Documents Project stage: Other ML20105A1342020-04-0707 April 2020 Submission of ISP Responses for RAIs and Associated Document Markups from First Request for Additional Information, Parts 2, 3, and 4 Project stage: Request ML20100F2952020-04-0909 April 2020 Tn Americas LLC - Submittal of Renewal Application for the TN-68 Dry Storage Cask - CoC 1027 Project stage: Request ML20104A0402020-04-10010 April 2020 Request for Additional Information for HI-STAR 100 CoC Renewal Application Project stage: RAI ML20111A2402020-04-13013 April 2020 Attachment 2: Proposed HI-STORM Umax CoC Amendment 4 Appendix a - Changed Pages (non-proprietary) Project stage: Other ML20111A2392020-04-13013 April 2020 Attachment 1: HI-STORM Umax Amendment 4 RAI Supplemental Response (non-proprietary) Project stage: Supplement ML20111A2382020-04-13013 April 2020 International - HI-STORM Umax Amendment 4 Responses to Requests for Additional Information - Supplemental Information Project stage: Supplement ML20094G4822020-04-15015 April 2020 GEH-Morris QAP Rev 4 Approval Project stage: Other ML20092L1732020-04-17017 April 2020 Safety Evaluation Report for the Pacific Gas and Electric Company Humboldt Bay Independent Spent Fuel Storage Installation Quality Assurance Plan HBI-L6 Revision 0 Project stage: Approval ML20120A2282020-04-29029 April 2020 Tn Americas LLC, Response to the Request for Additional Information to Application for Certificate of Compliance No. 1042, Amendment No. 2, to NUHOMS Eos System, (Docket No. 72-1042, CAC No. 001028 EPID: L-2019-LLA-0078)- Request for Extens Project stage: Request 2020-03-05 |
ML24043A095 | |
Person / Time | |
---|---|
Site: | Prairie Island |
Issue date: | 02/21/2024 |
From: | Janice Nguyen Storage and Transportation Licensing Branch |
To: | Roman C Division of Fuel Management |
References | |
CAC 001028, EPID L-2024-LLA-0002 | |
Download: ML24043A095 (4) | |
Similar Documents at Prairie Island | |
---|---|
Category:Meeting Summary
MONTHYEARML24149A1632024-05-29029 May 2024
[Table view]Summary of the May 8, 2024 Public Outreach to Discuss the NRC 2023 End-of-Cycle Plant Performance Assessment of Prairie Island Nuclear Generating Plant, Units 1 and 2 ML24088A1012024-03-29029 March 2024 Summary of March 6, 2024, Public Meeting with NSPM Regarding Planned LAR to Modify Technical Specifications Definitions and Incorporate Plant-Specific Methods for Response Time Testing for Prairie Island Nuclear Plant, Units 1 & 2 ML24043A0952024-02-21021 February 2024 Summary of January 31, 2024, Public Meeting with Xcel Energy to Discuss Amendment Application for Prairie Island Independent Spent Fuel Storage Installation ML23184A0862023-07-11011 July 2023 6/23/2023 Summary of Pre Application Public Meeting with Xcel Energy on Prairie Island ISFSI Amendment Application ML23179A2102023-06-28028 June 2023 Summary of June 5, 2023, Public Meeting with Northern States Power Company Regarding Neutron Fluence Values for Reactor Pressure Vessel Welds ML23157A0232023-06-0606 June 2023 Summary of the May 24, 2023, Public Outreach to Discuss the NRC 2022 End-of-Cycle Plant Performance Assessment of Prairie Island Nuclear Generating Plant, Units 1 and 2 ML23123A3942023-05-15015 May 2023 Summary of Public Meeting with Northern States Power Company Regarding Planned License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water System ML22130A7172022-05-10010 May 2022 Summary of the May 3, 2022, Public Outreach to Discuss the NRC 2021 End-Of-Cycle Plant Performance Assessment of Monticello and Prairie Island Nuclear Generating Plant, Units 1 and 2 ML21294A0442021-11-0808 November 2021 Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a License Amendment to Extended the Allowed Outage Time for the Vertical Motor Driven Cooling Water System Pump ML21229A1692021-08-23023 August 2021 Summary of August 11, 2021, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a Planned License Amendment Allow Bypass Testing of the Power Range Nuclear Instrumentation System Channels ML21167A1842021-06-16016 June 2021 Summary of the June 9, 2021, Public Outreach to Discuss the NRC 2020 End-Of-Cycle Plant Performance Assessment of Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant, Units 1 and 2 ML21137A1042021-05-20020 May 2021 Summary of May 6, 2021, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a Planned License Amendment to Transition to a 24 Month Operating Cycle ML21040A4612021-02-11011 February 2021 Summary of February 3, 2021, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a Planned License Amendment to Combine the Emergency Plans and Create a Common Emergency Operations Facility ML20296A2382020-11-0303 November 2020 Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to the License Amendment to Adopt TSTF-505 Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML20274A2442020-10-16016 October 2020 Summary of 9/23/2020 Meeting with Northern States Power Co., Doing Business as Xcel Energy, on Potential License Exemption Request Related to Biennal Emergency Preparedness Exercise for Prairie Island Nuclear Generating Plant, Units 1 & 2 ML20216A6452020-08-0303 August 2020 Summary of the July 16, 2020, Public Webinar to Discuss the NRC 2019 End-of-Cycle Plant Performance Assessment of the Prairie Island Generating Plant ML20114E2302020-04-23023 April 2020 Meeting Summary from Call with S. Beimers Mnshpo and NRC January 2020 Prairie Island ISFSI EA ML20111A1322020-04-21021 April 2020 April 9, 2020, Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential License Amendment Request Related to Adopt TSTF-569 at Prairie Island Nuclear Generating Plant, Unit 1 and 2 ML20057D3912020-03-0909 March 2020 Summary of February 18, 2020, Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential License Ament Request Related to Low Temperature Overpressurization Protection ML19347D1592020-01-0707 January 2020 Summary of December 12, 2019, Meeting with Northern States Power Co., Doing Business as Xcel Energy, and Tennessee Valley Authority Planned License Amendment Requests for Prairie Island, Units 2 and 2, and Watts Bar, Units 1 and 2 ML19289A5322019-10-28028 October 2019 Summary of September 26, 2019, Teleconference with Northern States Power Company on Potential License Amendment Request to Adopt TSTF-505, Revision 2 ML19210D5432019-08-20020 August 2019 Summary of Teleconference with Northern States Power Company on Potential License Amendment Request to Adopt Probabilistic Risk Assessment Model ML19136A0272019-05-15015 May 2019 Memorandum to C. Regan Summary of March 28, 2019, Public Meeting with Xcel Energy to Discuss Seismic Consideration for a Proposed License Amendment Increasing the Amount of Special Nuclear Material Authorized for Storage at Prairie Island I ML19058A4672019-03-11011 March 2019 Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to the Amendment Request to Modify Renewed Facility Operating License Paragraph 2.C(4)(c) ML18065A5582018-03-12012 March 2018 Summary of February 20, 2018, Teleconference with Northern States Power Company, Doing Business as Xcel Energy, on Potential License Amendment Request to Adopt TSTF-425 ML17341A1292017-12-11011 December 2017 Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Changes to the Security Plans at the Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant, Units 1 and 2 ML17261B0362017-09-25025 September 2017 Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential Digital Feedwater Modifications at Prairie Island Nuclear Generating Plant, Units 1 and 2 ML17235B1802017-08-23023 August 2017 Summary of Open House to Discuss the 2016 End-Of-Cycle Plant Performance Assessment of Prairie Island ML17209A1192017-07-17017 July 2017 Summary of July 17, 2017, Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential License Amendment Request Related to Heavy Lifting Devices L-PI-17-014, Summary of Public Meeting and Plan for NRC Request for Additional Information Regarding License Amendment Request for Spent Fuel Pool Criticality Technical Specification Changes (CAC Nos. MF7121...2017-04-19019 April 2017 Summary of Public Meeting and Plan for NRC Request for Additional Information Regarding License Amendment Request for Spent Fuel Pool Criticality Technical Specification Changes (CAC Nos. MF7121... ML17093A6012017-04-0606 April 2017 March 9, 2017, Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to the Spent Fuel Pool Criticality License Amendment Request ML17034A1202017-02-0909 February 2017 Summary of January 24, 2017, Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential Revision to the Emergency Action Level ML16111B1912016-04-28028 April 2016 Summary of Meeting with Northern States Power Company, a Minnesota Corporation, Doing Business as Xcel Energy, on National Fire Protection Association (NFPA) 805 License Amendment Request ML15271A2072015-10-0202 October 2015 July 9, 2015 Summary of Closed Meeting Between Representatives of the U.S. Army Corps of Engineers, U.S, Nuclear Regulatory Commission and Northern States Power Company- Minnesota to Discuss Flood Analysis Associated with Monticello Nuclear ML15141A5092015-05-21021 May 2015 Meeting Summary with Public to Discuss the Results of the 2014 Problem Identification and Resolution Inspection for Prairie Island Nuclear Generating Plant ML15107A0592015-05-15015 May 2015 Summary of the April 14, 2015, Public Meeting with Xcel Energy and Westinghouse to Discuss a Future License Amendment Request Regarding the Use of Ifba Rods in Nuclear Fuel at the Prairie Island Nuclear Generating Plant ML15131A4482015-05-0707 May 2015 Reactor Oversight Process Task Force FAQ Log - April 16, 2015 ML14220A2832014-09-0808 September 2014 Summary of August 5, 2014, Closed Meeting Between Representatives of the U.S. Army Corps of Engineers, NRC, and Northern States Power Company - Minnesota to Discuss Flooding Analysis Associated with Monticello and Prairie Island Nuclear Gen ML14223A8012014-08-11011 August 2014 Public Meeting Summary to Discuss the 2013 Performance of Prairie Island Nuclear Generating Plant Units 1 and 2 ML14227A8852014-07-0202 July 2014 E-mail P Longmire, NRC, Re e-mail Fr Samuel Chesnutt, Xcel Energy, Re Meeting Summary for the June 16, 2014 Prairie Island ISFSI License Renewal Application RAI Discussion ML14153A0252014-06-20020 June 2014 Meeting Summary - Public Meeting on May 16, 2014, to Discuss Xcel Energy'S Flood Hazard Reevaluation Extension Request for the Monticello and Prairie Island Nuclear Generating Plants ML14168A0182014-05-16016 May 2014 Xcel Energy Responses to NRC Questions Regarding Flood Hazard Reevaluation Report Extension Requests ML14056A4942014-03-10010 March 2014 Summary of the February 19, 2014, Pre-Application Meeting to Discuss the Diesel Generator Voltage and Frequency Limits License Request ML13210A3022013-07-29029 July 2013 Summary of Public Meeting with Northern States Power Company to Discuss the 2012 Prairie Island Nuclear Generating Plant End-of-Cycle Performance Assessment ML13171A2472013-06-20020 June 2013 7/11/2013 - Notice of Public Meeting to Discuss 2012 End-Of-Cycle Performance Assessment for Prairie Island Nuclear Generating Plant, Units 1 and 2 ML13004A3722013-01-11011 January 2013 December 6, 2012, Summary of Meeting to Discuss the Licensee'S Proposed FLEX Strategy in Response to NRC Order EA-12-049 ML12326A9702012-11-21021 November 2012 Summary of October 24, 2012, Meeting with the Northern States Power Company, D/B/A Excel Energy Regarding Security Requirements and Changes Pertaining to Prairie Island TAC L24689 W/ Encl 1 (Attendees) and Encl 2 (Agenda) ML12292A4202012-11-0707 November 2012 September 27, 2012 - Summary of Pre-Application Meeting to Discuss the Diesel Generator Voltage and Frequency Limits License Amendment Request ML12214A2332012-07-31031 July 2012 July 17, 2012 Summary of Public Meeting to Discuss the Prairie Island Nuclear Generating Plant, Units 1 and 2, End-of-Cycle Plant Performance Assessment ML12121A5842012-05-17017 May 2012 Meeting Summary with Northern States Power Co, to Discuss the National Fire Protection Association Standard 805 (NFPA 805) License Amendment Request 2024-05-29 Category:Memoranda MONTHYEARML24043A0952024-02-21021 February 2024
[Table view]Summary of January 31, 2024, Public Meeting with Xcel Energy to Discuss Amendment Application for Prairie Island Independent Spent Fuel Storage Installation ML23184A0862023-07-11011 July 2023 6/23/2023 Summary of Pre Application Public Meeting with Xcel Energy on Prairie Island ISFSI Amendment Application ML23044A3662023-02-15015 February 2023 Calendar Year 2022 Reactor Oversight Process Baseline Inspection Program Completion - Region III ML21055A5972021-03-25025 March 2021 Final Environmental Assessment and Finding of No Significant Impact for the Northern States Power Company'S Initial and Updated Decommissioning Funding Plans Submitted in Accordance with 10 CFR 72.30(B) and (C) ML20022A1982020-01-17017 January 2020 Summary of the Public Open House to Discuss NRC Activities and the 2018 End-of-Cycle Performance Assessment ML19136A0272019-05-15015 May 2019 Memorandum to C. Regan Summary of March 28, 2019, Public Meeting with Xcel Energy to Discuss Seismic Consideration for a Proposed License Amendment Increasing the Amount of Special Nuclear Material Authorized for Storage at Prairie Island I ML19071A0372019-03-0707 March 2019 Summary of Meeting with Xcel Energy to Discuss Increasing the Amount of Special Nuclear Material Authorized for Storage at the Prairie Island ISFSI (W/Enclosures 1 and 2) ML15181A0202015-07-0101 July 2015 July 9, 2015 Forthcoming Closed Meeting to Discuss Dam Failure Analysis for Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant, Units 1 and 2 ML15107A4932015-04-23023 April 2015 Memo C K Bladey, Notice of Issuance of Exemption, Northern States Power Company, Prairie Island Nuclear Generating Plant Independent Spent Fuel Storage Installation (50-282, 50-306, 72-10) ML14220A2832014-09-0808 September 2014 Summary of August 5, 2014, Closed Meeting Between Representatives of the U.S. Army Corps of Engineers, NRC, and Northern States Power Company - Minnesota to Discuss Flooding Analysis Associated with Monticello and Prairie Island Nuclear Gen ML14205A5242014-07-24024 July 2014 August5, 2014 Notice of Forthcoming Closed Meeting to Discuss Dam Failure Analysis for Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant, Units 1 and 2 ML14027A2312014-02-0505 February 2014 Notice of Pre-Application Meeting with Xcel Energy Concerning Prairie Island Nuclear Generating Plant, Units 1 and 2, to Discuss Licensee'S Proposed Changes to the Emergency Diesel Generator Voltage and Frequency Limits ML13169A2442013-06-17017 June 2013 Memorandum S. Wastler Technical Assistant Request - Review the Prairie Island Nuclear Generating Plant Independent Spent Fuel Storage Installation Request for Exemption from Physical Security Requirements (TAC L24750) ML13154A4702013-06-0404 June 2013 Rai'S Following Ifib Analysis 2013 Decommissioning Funding Status Report for Prairie Island 1 and 2 and Monticello ML13101A0292013-04-12012 April 2013 K. Hsueh Memo Site Visit Summary Regarding the Prairie Island ISFSI License Renewal ML12363A1722012-12-14014 December 2012 CFR 50 Appendix E Evacuation Time Estimate Study ML12326A9702012-11-21021 November 2012 Summary of October 24, 2012, Meeting with the Northern States Power Company, D/B/A Excel Energy Regarding Security Requirements and Changes Pertaining to Prairie Island TAC L24689 W/ Encl 1 (Attendees) and Encl 2 (Agenda) ML12318A0572012-11-13013 November 2012 12/6/2012 - Rescheduled Notice of Meeting with Xcel Energy Concerning Prairie Island Nuclear Generating Plant, Units 1 and 2 ML12306A3222012-11-0101 November 2012 Notice of Forthcoming Meeting with Xcel Energy Concerning Prairie Island Nuclear Generating Plant, Units 1 and 2 ML12291A7792012-10-17017 October 2012 S. Wastler Memorandum Technical Assistance Request - Review of Physical Security Plan of Prairie Island Nuclear Generating Plant Independent Spent Fuel Storage Installation (TAC No. L24689) ML12249A2702012-09-11011 September 2012 Notice of Forthcoming Pre-Application Meeting with Xcel Energy, Inc. Concerning Prairie Island Nuclear Generating Plant ML12223A4772012-08-0606 August 2012 10/4/2012 Notice of Significant NRC Meeting with Northern States Power Company to Discuss Prairie Island Nuclear Generating Plant, Unit 2 ML1121505252011-08-0404 August 2011 Notice of Forthcoming Pre-Application Meeting with Licensee for Prairie Island Nuclear Generating Plant, Units 1 and 2 to Discuss Extended Power Uprate License Amendment Request ML1113703982011-05-20020 May 2011 Notice of Forthcoming Pre-Application Meeting with Licensee for Prairie Island Nuclear Generation Plant, Units 1 and 2, to Discuss Proposed Technical Specification and Licensing Basis Changes to Diesel Fuel Oil System ML1104702792011-02-16016 February 2011 Notice of Forthcoming Meeting with Licensee for Prairie Island Nuclear Generating Plant, Unit 1 to Discuss License Amendment Request to Revise Surveillance Requirement Footnote in Technical Specification 3.8.1, AC Sources - Operating. ML1100502702011-01-0505 January 2011 Notice of Closed Pre-Application Meeting NSPM Staff to Discuss Proposed Physical Security Plan Changes That Will Be Submitted for NRC Review and Approval Via License Amendment Request ML1032603272010-11-24024 November 2010 Notice of Pre-Application Meeting with Licensee for Prairie Island Nuclear Generating Plant, Units 1 and 2 to Discuss Spent Fuel Pool Criticality and Extended Power Uprate ML1011601402010-04-22022 April 2010 Summary of Meeting with Northern States Power Company - Minnesota Corporation, Formerly Nuclear Management Company and Transnuclear Regarding License Amendment Request for the TN-40HT Cask Design ML0928900052009-10-15015 October 2009 Meeting Meeting Minutes of the the Plant License Renewal Subcommittee Meeting, July 7, 2009 ML0921204292009-09-0202 September 2009 Summary of Meeting with Northern States Power Company to Discuss License Amendment Request Concerning Unit 2 Emergency Diesel Generator Surveillance Test Loads ML0921005482009-08-0606 August 2009 Notice of Meeting with Licensee for Prairie Island Nuclear Generating Plant, Units 1 and 2 (PINGP) to Discuss Their Proposed Alternate Source Term License Amendment ML0918708182009-07-0808 July 2009 Meeting Notice, Meeting with Licensee for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Ping) to Discuss License Amendment Request Submitted on 11/04/2008 ML0914608092009-07-0101 July 2009 Issuance of Amendments Technical Specifications Changes to Allow Use of Westinghouse 0.422-Inch OD 14X14 Vantage + Fuel ML0910701602009-04-27027 April 2009 Draft Clarifications Concerning a Request for Additional Information Regarding Loss-of-Coolant/Mainstream Line Break Accident Dose Consequence Analyses License Amendment Request (Tac Nos. MD9141) ML0904400352009-02-24024 February 2009 Draft Request for Additional Information Regarding the Irradiated Fuel Management Plan and Preliminary Decommissioning Cost Estimates ML0900608522009-02-0404 February 2009 12/03/08 Summary of Telephone Conference Call Held Between . NRC & Northern States Power, Concerning Follow-Up Question Pertaining to the Pings, Units 1& 2, License Renewal Environmental Review and Site Audit ML0836600692009-01-23023 January 2009 Summary of Telephone Conference Call Held on December 9, 2008, Between the U. S. Nuclear Regulatory Commission and Northern States, Power, Concerning Follow Up Questions Pertaining to the SAMA RAI for Pings, Units 1 and 2, (TAC MD8528 & MD8 ML0832203772008-09-22022 September 2008 Scoping Comments from Kristen Eide-Tollefson ML0826102742008-09-15015 September 2008 Draft Pages of Amendment to Facility Operating Licenses DPR-42, DPR-060, & Materials License SNM-2506 ML0812007742008-05-0808 May 2008 Review of Revision 29 to the Updated Safety Analysis Report (Tac No. MD5651 and MD5652) ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0720000662007-08-0101 August 2007 Notice of Meeting with Nuclear Management Company, Llc., to Discuss Proposed Changes to PINGP Security Plan ML0710701822007-05-0202 May 2007 Memo Transmitting Prairie Island Nuclear Generating Plant: Report on Results of Staff Audit of Corrective Actions to Address Generic Letter 2004-02 ML0634003252006-12-0707 December 2006 Notice of Presubmittal Conference for Proposed Emergency Plan Changes ML0629901712006-11-0303 November 2006 Safety Evaluation for Administrative Changes to the Technical Specifications ML0629000372006-10-20020 October 2006 Summary of 09/21/2006 Teleconference Re Extension of Relief Requests 2 & 3 for the Fourth 10-Year Inservice Testing Program Interval ML0624904012006-09-0808 September 2006 Notice of Meeting with Nuclear Management Company, LLC Regarding Extension of Completion Time for Emergency Diesel Generators for Prairie Island Units 1 and 2 ML0617805592006-07-10010 July 2006 Revised Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors. ML0602502942006-01-25025 January 2006 Canceled Notice of Meeting with Nuclear Management Company Regarding Fleet Transition to NFPA Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants ML0601101052006-01-12012 January 2006 Meeting Notice - Prairie Island, Units 1 and 2 - Forthcoming Meeting with Nuclear Management Company, LLC (NMC) to Discuss Extension of Completion Time for Emergency Diesel Generators 2024-02-21 |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001
February 21, 2024
MEMORANDUM TO: Cinthya Román, Deputy Director
Division of Fuel Management Office of Nuclear Material Safety and Safeguards Signed by Nguyen, Chau FROM: John-Chau Nguyen, Senior Project Manager on 02/21/24 Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards
SUBJECT:
SUMMARY
OF JANUARY 31, 2024, PUBLIC MEETING WITH XCEL ENERGY TO DISCUSS AMENDMENT APPLICATION FOR PRAIRIE ISLAND INDEPENDENT SPENT FUEL STORAGE INSTALLATION
On January 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) staff from the Division of Fuel Management held a public meeting with representatives from Xcel Energy. The purpose of the meeting was to discuss Xcel Energys planned amendment request to add grace period to several license conditions of the Prairie Island Independent Spent Fuel Storage Installation (PI ISFSI) license.
The meeting was noticed on January 8, 2024 (Agencywide Documents Access and Management System Accession No. ML24008A013). Two members of the public attended this meeting. A meeting attendees list is included in the enclosure. The meeting handout (ML24029A038) is available on the NRC public meeting website.
Xcel Energy plans to submit an amendment application to revise to License Conditions 23(a),
24(A)(2), and 24(B)(2) of the PI ISFSI. License Conditions 23(a), 24(A)(2), and 24(B)(2) currently include no allowance for a grace period. Additionally, the inspection interval descriptions use terms like not to exceed every quarter or not to exceed three months which is not consistent with the typical surveillance frequency in technical specifications of 92 days.
Staff questioned whether amendment request grace period information is consistent with the information specified the technical specifications and Xcel Energy confirmed that the information is consistent.
Xcel Energy plans to submit the amendment application by February 24, 2024, and seek the NRCs approval 12 months from acceptance with an implementation period of 90 days.
CONTACT: John-Chau Nguyen, NMSS/DFM 301-415-0262 C. Román
After the business portion of the meeting, members of the public participating by phone were given the opportunity to ask questions. There was no public comment.
The meeting adjourned before 12:00 p.m. No regulatory decisions were made at the meeting.
Docket No. 72-0010 CAC No. 001028 EPID No. L-2024-LLA-0002
Enclosure:
Meeting Attendees List
ML24043A095 OFFICE: NMSS/DFM NMSS/DFM NMSS/DFM NMSS/DFM NAME: JCNguyen SFigueroa YDiaz-Sanabria JCNguyen DATE: 2/12/2024 2/12/2024 2/20/2024 2/21/2024
MEETING ATTENDEES LIST
Date: January 31, 2024, 11:00 A.M. - 12:00 P.M.
NAME AFFILIATION
Tom Boyce John-Chau Nguyen Eliezer Goldfeiz Raju Patel The U.S. Nuclear Regulatory Jeremy Smith Commission Azmi Djapari Christopher Sydnor Marlone Davis Darrell Dunn
Kara Gibson Darius Ahrar Mike Miller Xcel Energy Jeff Kivi
Enclosure