Letter Sequence Acceptance Review |
---|
|
|
MONTHYEARML19276D3982019-10-0303 October 2019 Exemption Request to Load and Store Spent Fuel in HI-STORM FW Spent Fuel Casks Utilizing Amendment 1, Revision 1 to CoC No. 1032 Project stage: Other ML20115E3782019-10-0303 October 2019 Independent Spent Fuel Storage Installation Exemption Safety Evaluation Report Project stage: Approval ML20014E6772020-01-0909 January 2020 Fws List of Threatened and Endangered Species That May Occur with Respect to the McGuire Exemption Request Project stage: Other ML20015A3142020-01-14014 January 2020 Package: Exemption Request McGuire Nuclear Facility Project stage: Request ML20049A0812020-01-31031 January 2020 Holtec International - HI-STORM 100 Storage CoC Renewal Application Project stage: Request ML20049A0822020-01-31031 January 2020 Holtec International - HI-STORM 100 Storage CoC Renewal Application Project stage: Other ML20055F3372020-02-20020 February 2020 Conversation Record - Clarification Call (02/20/2020) on RAI 1 for CoC 1040 Umax Amendment 4 Project stage: RAI ML20064F6162020-02-29029 February 2020 January 15, 2020, Summary of Meeting with Holtec International, Inc., to Discuss the Upcoming Submittal of the Application for Renewal of the Storage Certificate of Compliance No. 1014 for the HI-Storm 100 Cask System Project stage: Meeting ML20063M0152020-03-0303 March 2020 HI-STORM 100 Renewal Presubmittal Meeting (Holtec Slides, 1-15-20) Project stage: Meeting ML20064E6222020-03-0303 March 2020 U.S. Nuclear Regulatory Commission Approval of NAC International Request for Withholding Information from Public Disclosure for Coc 1025 Renewal (CAC No. 001028) Project stage: Withholding Request Acceptance ML20071J0552020-03-0505 March 2020 Notice of Cancelled Meeting with the U.S. Department of Energy, Idaho Operations Office to Discuss the Upcoming Submittal of the Application for Renewal of the Idaho Spent Fuel Facility License (SNM-2512) Project stage: Meeting ML20065K2162020-03-0505 March 2020 Notice of Meeting with U.S. Department of Energy, Idaho Operations Office to Discuss the Upcoming Submittal of the Application for Renewal of the Idaho Spent Fuel Facility License (SNM-2512) Project stage: Meeting ML20071F1562020-03-0505 March 2020 Interim Storage Partners, LLC - Affidavit Project stage: Other ML20071F1532020-03-0505 March 2020 Interim Storage Partners, LLC - Supplemental Information in Support of Nrc'S Environmental Review Project stage: Supplement ML20066K5782020-03-0606 March 2020 Acceptance Review of Request for Amendment No. 7 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System Project stage: Acceptance Review ML20065L3442020-03-0606 March 2020 Amendment No. 15 to Certificate of Compliance No. 1014 for the Hi-Storm 100 Multipurpose Canister Storage System - Request for Additional Information Project stage: RAI ML20066K2702020-03-0606 March 2020 Updated GEH Morris Operation (Mo) Decommissioning Funding Plan (DFP) Project stage: Request ML20065N2772020-03-0909 March 2020 ISFSI Renewal Cover Letter Project stage: Other ML20065N2852020-03-0909 March 2020 ISFSI Renewed Technical Specifications Project stage: Other ML20065N2812020-03-0909 March 2020 ISFSI Preamble-License Renewal Order Project stage: Other ML20071D9942020-03-11011 March 2020 Submittal of HI-STAR 100 Updated FSAR, Revision 4 Project stage: Request ML20065N2782020-03-11011 March 2020 ISFSI FRN Notice of Issuance for License Renewal Project stage: Other ML20076D6962020-03-11011 March 2020 Interim Storage Partners, LLC - Submittal of Clarifications to Support Nrc'S Continued Review of the Safety Case for the WCS CISF Project stage: Other ML20104C0202020-03-30030 March 2020 International - HI-STORM Umax Amendment 4 Responses to Requests for Additional Information - Supplemental Information Project stage: Supplement ML20104C0192020-03-30030 March 2020 International - Affidavit for Kimberly Manzione Project stage: Other ML20104C0182020-03-30030 March 2020 International - HI-STORM Umax Amendment 4 FSAR - Changed Pages Project stage: Other ML20104C0162020-03-30030 March 2020 International - Proposed HI-STORM Umax CoC Amendment 4 Appendix a - Changed Pages Project stage: Other ML20104C0152020-03-30030 March 2020 International - Amendment No. 4 to the HI-STORM Umax Canister Storage System Project stage: Other ML20104C0482020-03-31031 March 2020 International - HI-STORM Umax Amendment 3 Responses to Requests for Additional Information Project stage: Response to RAI ML20065N2802020-03-31031 March 2020 ISFSI License Renewal SER Project stage: Other ML20091L0642020-03-31031 March 2020 Enclosure 1 - Request for Additional Information - Non-Proprietary Project stage: RAI ML20091L0632020-03-31031 March 2020 Transmittal Letter - CoC 1042 Amendment Number 2 Request for Additional Information Project stage: RAI ML20101P3992020-03-31031 March 2020 Interim Storage Partners, LLC - Submittal of Draft Responses for Several Rals and Associated Document Markups from First Request for Additional Information, Parts 1, 2 and Clarifications Project stage: Draft Request ML20105A1352020-03-31031 March 2020 Enclosure 1 - Affidavits Project stage: Other ML20099A1802020-04-0606 April 2020 Application for Renewal of the Certificate of Compliance No. 1014 for the Hi-Storm 100 Storage Cask System Accepted for Review (Cac/Epid Nos. 001028/L-2020-RNW-0007) Project stage: Other ML20105A1732020-04-0606 April 2020 Interim Storage Partners, LLC - Affidavits Project stage: Other ML20105A1342020-04-0707 April 2020 Submission of ISP Responses for RAIs and Associated Document Markups from First Request for Additional Information, Parts 2, 3, and 4 Project stage: Request ML20105A1392020-04-0707 April 2020 Enclosure 8 - Referenced Documents Project stage: Other ML20105A1362020-04-0707 April 2020 Enclosure 3 - RAIs and Responses Project stage: Other ML20105A1372020-04-0707 April 2020 Enclosure 5 - La Changed Pages Project stage: Other ML20105A1382020-04-0707 April 2020 Enclosure 7 - SAR Changed Pages Project stage: Other ML20105A1722020-04-0707 April 2020 Interim Storage Partners, LLC - Submittal of Supplemental Information in Support of RAI, Part 3 Project stage: Supplement ML20100F2952020-04-0909 April 2020 Tn Americas LLC - Submittal of Renewal Application for the TN-68 Dry Storage Cask - CoC 1027 Project stage: Request ML20104A0402020-04-10010 April 2020 Request for Additional Information for HI-STAR 100 CoC Renewal Application Project stage: RAI ML20111A2382020-04-13013 April 2020 International - HI-STORM Umax Amendment 4 Responses to Requests for Additional Information - Supplemental Information Project stage: Supplement ML20111A2402020-04-13013 April 2020 Attachment 2: Proposed HI-STORM Umax CoC Amendment 4 Appendix a - Changed Pages (non-proprietary) Project stage: Other ML20111A2392020-04-13013 April 2020 Attachment 1: HI-STORM Umax Amendment 4 RAI Supplemental Response (non-proprietary) Project stage: Supplement ML20094G4822020-04-15015 April 2020 GEH-Morris QAP Rev 4 Approval Project stage: Other ML20092L1732020-04-17017 April 2020 Safety Evaluation Report for the Pacific Gas and Electric Company Humboldt Bay Independent Spent Fuel Storage Installation Quality Assurance Plan HBI-L6 Revision 0 Project stage: Approval ML20120A2282020-04-29029 April 2020 Tn Americas LLC, Response to the Request for Additional Information to Application for Certificate of Compliance No. 1042, Amendment No. 2, to NUHOMS Eos System, (Docket No. 72-1042, CAC No. 001028 EPID: L-2019-LLA-0078)- Request for Extens Project stage: Request 2020-03-05
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML22319A0142022-11-15015 November 2022 Emails Transmitting EA for Proposed Renewal of GEH Morris Operation ISFSI License SNM-2500 ML22222A0522022-08-0909 August 2022 Email to Illinois State Agencies Request for Review of Draft Environmental Assessment - Proposed License Renewal for the Morris Operation Independent Spent Fuel Storage Installation ML22116A0992022-04-19019 April 2022 4-19-2022 E-Mail Request for Clarification on GEH Responses to RAIs on Morris License Renewal Application ML22063B1752021-08-30030 August 2021 Email and Letter from D. Hunter of Miami Tribe NRC Preliminary Determination Under Section 106 of the NHPA for Proposed GE-Hitachi Morris Operation ISFSI License Renewal ML21340A2522021-08-18018 August 2021 Email from Il Shpo Determination of No Potential to Cause Effects - Proposed Renewal of NRC License for GE Hitachi Morris Operation ISFSI ML22063B1742021-08-10010 August 2021 Email from S. Thomas-Bear of Winnebago Tribe NRC Preliminary Determination Under Section 106 of the NHPA for Proposed GE-Hitachi Morris Operation ISFSI License Renewal ML21167A3322021-06-15015 June 2021 Request for Additional Information on Morris Operation Decommissioning Funding Plans ML21085A8592021-03-22022 March 2021 3/22/2021 E-mail Request for Clarification of 2/26/2021 Rsi Response for GEH-Morris License Renewal Application ML20213C3252020-07-31031 July 2020 7-31-2020 Email Acknowledgement of NRC Receipt of GEH Morris Operation LRA and Start of Acceptance Review.Pdf ML11192A0782011-04-20020 April 2011 Email from Christine Lipa, Subject: Plan for Addressing Stand Alone SFPs for Charlie Miller'S Task Force ML11192A0792011-04-20020 April 2011 Email from Vonna Ordaz, Subject: Plan for Addressing Stand Alone SFPs for Charlie Miller'S Task Force ML11192A0762011-04-0606 April 2011 E-mail from Vonna Ordaz, Subject: Fw: Plan for Addressing Stand Alone SFPs for Charlie Miller'S Task Force ML11192A0742011-04-0505 April 2011 Email from Vonna Ordaz, Subject: Course of Action for Inspections at Stand Alone Spent Fuel Pools ML11192A0752011-04-0505 April 2011 Email from Vonna Ordaz, Subject: Plan for Addressing Stand Alone SFPs for Charlie Miller'S Task Force ML11192A0702011-04-0101 April 2011 Email from Doug Weaver, Subject: FW: Japan Related Temporary Instruction ML11192A0712011-04-0101 April 2011 Email from Doug Weaver, Subject: Larry Camper Response Regarding Ti 2515/183 for Stand-alone Spent Fuel Pools ML11189A2392011-03-31031 March 2011 Email from Doug Weaver, Subject: Japan Related Temporary Instruction ML11189A2342011-03-21021 March 2011 Email from Eric Bowman, Subject: Reply: Spent Fuel Pools in Region II: Any post-Japan Related Actions? ML0722503042007-08-0909 August 2007 Request for Additional Information on Employee Transfers Val and Morris License Transfer Request ML0705906492007-02-27027 February 2007 E-mail Regarding Acceptance of Request for Approval of License Transfer and Conforming Amendments 2022-08-09
[Table view] |
Text
From: Banovac, Kristina To: Murray, Scott P. (GE Power Portfolio); McFadden, Anthony E (GE Power Portfolio)
Subject:
Acknowledgement of NRC receipt of GEH Morris Operation License Renewal Application and start of acceptance review Date: Friday, July 31, 2020 9:33:00 AM Good morning Scott and Tony, By letter dated June 30, 2020, GE Hitachi Nuclear Energy Americas LLC (GEH) submitted an application for renewal of License No. SNM-2500 for the Morris Operation Independent Spent Fuel Storage Installation.
This email acknowledges NRC receipt of your license renewal application. The 6/30/2020 transmittal letter and the supplement to the environmental report (Attachment 3 of the 6/30/2020 submittal) are publicly available in NRC's Agencywide Documents Access and Management System (ADAMS) at ADAMS Accession Nos. ML20182A700 and ML20182A703, respectively. The NRC staff is reviewing Attachments 1 and 2 of the 6/30/2020 application (updated Consolidated Safety Analysis Report) to determine if the attachments contain sensitive information. After our review is complete, the attachments will either be made publicly available, or a redacted version of the attachments will be made publicly available in ADAMS. I will keep you posted on our review.
The NRC staff has started the acceptance review of your application. We expect to provide you with the results of our acceptance review (request for supplemental information, or acceptance for a detailed technical and environmental review) in October 2020.
Please let me know if you have any questions in the meantime.
Thank you, and take care, Kris Kristina Banovac, Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission 301-415-7116 License No. SNM-2500 Docket No. 72-1 CAC/EPID Nos. 001028/L-2020-RNW-0024 (technical review), 000993/L-2020-LNE-0004 (environmental review)