Letter Sequence Other |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement
Results
- Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval
Other: ML19156A113, ML19156A114, ML19182A147, ML19322C260, ML19360A047, ML20224A287, ML20267A102, ML21083A302, ML21181A389, ML21322A219, ML23025A350, ML23061A129, ML23075A181, ML23075A182, ML23076A279
|
MONTHYEARML18088A0302018-03-28028 March 2018 Letter to J. Tomlinson Holtec International'S Application for Specific ISFSI License for the HI-Store Consolidated Interim Storage Facility for Spent Nuclear Fuel-First Request for Additional Information, Part 1 (W/Enclosure) Project stage: RAI ML18257A2402018-09-13013 September 2018 Letter to K. Manzione Holtec International'S Application for Specific ISFSI License for the HI-STORE Consolidated Interim Storage Facility for Spent Nuclear Fuel - First Request for Additional Information, Part 2 (W/Enclosure 1) Project stage: RAI ML18284A4272018-10-11011 October 2018 Letter to E. Mayer Holtec International'S Application for Specific ISFSI License for the HI-STORE Consolidated Interim Storage Facility for Spent Nuclear Fuel - First Request for Additional Information, Part 3 Project stage: RAI ML19156A1142019-06-0404 June 2019 Letter to E. Mayer Audit Plan for NRC Staff Visit of Proposed Site for the HI-STORE Consolidated Interim Storage Facility Project stage: Other ML19156A1132019-06-0404 June 2019 Enclosuaudit Plan (Letter to E. Mayer Audit Plan for NRC Staff Visit of Proposed Site for the HI-STORE Consolidated Interim Storage Facility) Project stage: Other ML19182A1472019-07-0101 July 2019 Letter to K. Manzione Holtec International'S Application for Specific ISFSI License for the HI-STORE Consolidated Interim Storage Facility for Spent Nuclear Fuel - Revised Review Schedule Project stage: Other ML19322C2602019-11-14014 November 2019 Holtec International'S Application for Specific Independent Spent Fuel Storage Installation License for the Hi-Store Consolidated Interim Storage Facility for Spent Nuclear Fuel Project stage: Other ML19360A0472019-12-26026 December 2019 Holtec International'S Application for Specific Independent Spent Fuel Storage Installation License for the Hi-Store Consolidated Interim Storage Facility for Spent Nuclear Fuel - Request for Clarification of Responses Related to Emergency Project stage: Other ML20198M6382020-07-16016 July 2020, 21 October 2020 International, Supplemental Archeological Information Project stage: Request ML20224A2872020-08-10010 August 2020 Letter to K. Manzione, Holtec International, Holtec International'S Application for Specific Independent Spent Fuel Storage Installation License for the Hi-Store Consolidated Interim Storage Facility for Spent Nuclear Fuel Project stage: Other ML20267A1022020-09-22022 September 2020 Letter to K. Manzione, Holtec International, Holtec International'S Application for Specific Independent Spent Fuel Storage Installation License for the Hi-Store Consolidated Interim Storage Facility for Spent Nuclear Fuel - Revised Review Project stage: Other ML20283A7892020-10-0909 October 2020, 23 October 2020 International HI-STORE Cis (Consolidated Interim Storage Facility) License Application Responses to Requests for Additional Information - Part 6, Response Set 1 Project stage: Request ML20326A0052020-11-20020 November 2020, 18 December 2020 International HI-STORE Cis (Consolidated Interim Storage Facility) License Application Responses to Requests for Additional Information, Part 6, Response Set 2 Project stage: Request ML20326A0092020-11-20020 November 2020 Attachment 3 - Proposed HI-STORE License and Technical Specifications Project stage: Request ML21004A2422021-01-0404 January 2021 International HI-STORE Cis (Consolidated Interim Storage Facility) License Application Supplemental Information Project stage: Supplement ML21004A2412021-01-0404 January 2021, 5 March 2021 International HI-STORE Cis (Consolidated Interim Storage Facility) License Application Supplemental Information Project stage: Request ML21083A3022021-03-25025 March 2021 Letter to K. Manzione Holtec International Application for the Hi-Store Consolidated Interim Storage Facility - Safety Review Delay and Discussion of Issues Project stage: Other ML21124A3082021-05-20020 May 2021 Letter to K. Manzione - Second Request for Additional Information, Holtec International'S Application for the HI-STORE Consolidated Interim Storage Facility Project stage: RAI ML21154A2092021-06-0303 June 2021 International, Schedule for Responses to HI-STORE RAIs Round 2 Project stage: Request ML21224A1052021-06-30030 June 2021 International, HI-STORE Cis (Consolidated Interim Storage Facility) License Application Responses to Requests for Addition Information - 2nd Round, Part 1 Project stage: Request ML21181A3892021-07-0202 July 2021 Letter to K. Manzione - Holtec International'S Application for Specific ISFSI License for the HI-STORE CISF - Revised Review Schedule Project stage: Other ML21243A5252021-08-31031 August 2021 International HI-STORE Cis (Consolidated Interim Storage Facility) License Application Responses to Requests for Additional Information - 2nd Round, Part 2 Project stage: Request ML21304A0032021-10-29029 October 2021 International HI-STORE Cis (Consolidated Interim Storage Facility) License Application Responses to Requests for Additional Information - 2nd Round, Supplemental Information Project stage: Request ML21322A2192021-11-19019 November 2021 Letter to K. Manzione - Review Schedule Delay for the Holtec HI-STORE CISF License Application Project stage: Other ML21341B3592021-12-0808 December 2021 Enclosure 1 - Audit Plan for HI-STORE Second RAI Responses, Non-Proprietary Project stage: RAI ML21341B3602021-12-0808 December 2021 Letter to K. Manzione - Audit Plan for NRC Audit of Holtec'S Responses to Second RAI - HI-STORE CISF License Application Project stage: Request ML21341B3582021-12-0808 December 2021 Letter to K. Manzione - Audit Plan for NRC Audit of Holtec'S Responses to Second RAI - HI-STORE CISF License Application Project stage: RAI ML22018A1872022-01-20020 January 2022 Enclosure 1 - Audit Plan for January 19-20, 2022, NRC Audit of HI-STORE Second RAI Responses, Non-Proprietary Project stage: RAI ML22018A1862022-01-20020 January 2022 Letter to K. Manzione - Audit Plan for January 19-20, 2022, NRC Audit of Holtec Responses to Second RAI - HI-STORE CISF License Application Project stage: RAI ML22062B6692022-03-23023 March 2022 Letter to K. Manzione - Third Request for Additional Information, Holtec International'S Application for the HI-STORE Consolidated Interim Storage Facility Project stage: RAI ML22331A0082022-08-0909 August 2022 Attachment 5 - HI-2177593, Holtec International & Eddy Lea Energy Alliance (Elea) Underground CISF - Financial Assurance & Project Life Cycle Cost Estimates Project stage: Request ML22265A1932022-08-15015 August 2022 EPA Comment Letter for the NRC Holtec Spent Nuclear Fuel Final Environmental Impact Statement (Feis) Project stage: Request ML22331A0122022-11-16016 November 2022 Attachment 9 - HI-2177565, Holtec International & Eddy Lea Energy Alliance (Elea) Cis Facility - Decommissioning Cost Estimate and Funding Plan Project stage: Request ML22331A0172022-11-17017 November 2022 Attachment 14 - HI-2177938, HI-STORE Cis Facility Fire Protection Plan Project stage: Request ML22331A0152022-11-17017 November 2022 Attachment 12 - HI-2177535, Holtec International & Eddy Lea Energy Alliance (Elea) Underground Consolidated Interim Storage Facility - Emergency Response Plan Project stage: Request ML22331A0052022-11-23023 November 2022 Attachment 2 - Proposed HI-STORE License/Technical Specifications Project stage: Request ML22357A1172022-12-22022 December 2022, 23 December 2022 International HI-STORE Cis (Consolidated Interim Storage Facility) Additional Supplemental Information Project stage: Request ML23020A1282023-01-20020 January 2023 International HI-STORE Cis (Consolidated Interim Storage Facility) Additional Supplemental Information Project stage: Request ML23025A1122023-01-20020 January 2023 Redacted - Attachment 3 - HI-2167374, Rev 0T, Licensing Report on the HI-STORE Cis Facility Project stage: Request ML23025A3502023-01-26026 January 2023 Letter to K. Manzione - Revised Review Schedule for Holtec International'S License Application for the HI-STORE CISF Project stage: Other ML23096A0762023-03-14014 March 2023 CISF EIS - Species List New Mexico Ecological Services Field Office March 2023 Project stage: Request ML23076A2792023-03-20020 March 2023 Letter to K. Manzione, Holtec International'S License Application for the HI-STORE CISF, Revised Schedule for Final Licensing Decision Project stage: Other ML23116A1802023-05-0202 May 2023 Letter to K. Manzione, Holtec International, Re Request for Withholding Information from Public Disclosure - HI-STORE CISF License Application Project stage: Withholding Request Acceptance ML23097A1712023-05-0808 May 2023 Review of New and Potentially Significant Information for the Holtec Environmental Impact Statement for a Consolidated Interim Storage Facility for Spent Nuclear Fuel in Lea County, New Mexico Project stage: Request ML23103A4202023-05-0909 May 2023 Letter to D. Cooper, Apache Tribe of Oklahoma, Re Issuance of Record of Decision and Materials License for Holtec HI-STORE CISF Project stage: Approval ML23061A1292023-05-0909 May 2023 International Consolidated Interim Storage Facility NEPA Record of Decision Project stage: Other ML23075A1812023-05-0909 May 2023 Mat License No SNM-2516 for HI-STORE Consolidated Interim Storage Fac ISFSI Docket 72 1051 Holtec Int Project stage: Other ML23075A1822023-05-0909 May 2023 Appendix a to Materials License No. SNM-2516, Technical Specifications for the HI-STORE Consolidated Interim Storage Facility ISFSI, Docket No. 72-1051, Holtec International Project stage: Other ML23103A4152023-05-0909 May 2023 Letter to E. Martinez, Mescalero Apache Tribe, Re Issuance of Record of Decision and Materials License for Holtec HI-STORE CISF Project stage: Approval ML23103A4162023-05-0909 May 2023 Letter to L. Spottedbird, Kiowa Tribe, Re Issuance of Record of Decision and Materials License for Holtec HI-STORE CISF Project stage: Approval 2021-06-03
[Table View] |
|
---|
Category:Audit Plan
MONTHYEARML22018A1872022-01-20020 January 2022 Enclosure 1 - Audit Plan for January 19-20, 2022, NRC Audit of HI-STORE Second RAI Responses, Non-Proprietary ML21341B3592021-12-0808 December 2021 Enclosure 1 - Audit Plan for HI-STORE Second RAI Responses, Non-Proprietary ML19156A1132019-06-0404 June 2019 Enclosuaudit Plan (Letter to E. Mayer Audit Plan for NRC Staff Visit of Proposed Site for the HI-STORE Consolidated Interim Storage Facility) 2022-01-20
[Table view] |
Text
Audit Plan for NRC Staff Visit of Proposed Site for the HI-STORE Consolidated Interim Storage Facility in Lea County, NM June 18-19, 2019 A. Location The site audit will be held on June 18-19, 2019 at the addresses below:
Center of Excellence for Hazardous Materials Management 505 North Main Street Carlsbad, New Mexico 88220 Holtec HI-STORE CISF Site County Road 55 & US Hwy 62 Hobbs, NM 88240 B. Background The NRC staff is currently conducting a detailed safety, security, and environmental review of Holtec Internationals application for a site-specific independent spent fuel storage installation license to construct and operate the HI-STORE Consolidated Interim Storage Facility (CISF). In connection with its safety review, the staff has identified several areas related to the information provided by the applicant in its safety analysis report (SAR) with respect to site geology, seismology, geotechnical engineering, and nearby structures that the staff wants to examine.
The site audit will allow the staff to observe and examine these specific areas and better inform its safety review of the license application.
C. Audit Scope The staff proposes a General Site Vicinity Tour highlighting important structural features (or the lack of visible structures) that include the following:
- Examine representative examples of active or abandoned oil and gas exploration and extraction wells or boreholes and other oil, gas or mining activities to determine the current or future potential for surface deformation, as described in the SAR. These examples include:
- Temporary gas-gathering pipelines and three permanent pipelines (if visible);
- Gas/oil production operations at the site and nearby including fracking;
- Locations of past drilling activities at three nearby drill islands;
- Locations of nearby potash mining (including solution mining);
- Any salt mining from underground, or any injection wells nearby;
- Proposed location for site fuel storage tank(s) at the site and the supply route(s).
- Examine representative examples of circular features of unknown origin, observed in several figures in SAR Section 2.6, to support the review of the subsurface materials and the potential for surface deformation.
- Examine small, shallow depressions in the Mescalero Caliche that the applicant attributes to dissolution of the Mescalero Caliche, as discussed in SAR Section 2.6.
- Examine outcrops of surface and near-surface stratigraphic units, including outcrops of the Dockum Group, to clarify the site stratigraphy discussed in SAR Section 2.6.
Enclosure
- Examine the proposed location of site facilities, which include the approximate location of the storage pads, Canister Transfer Facility, security buildings, among others, and the types of soils present at these locations (any trenching done, etc.), and the approximate cask haulage path(s).
The staff would also like to examine the core and boring logs from the boring program.
Specifically, the staff would like to see core from the upper 100 ft, core with fractures and slickensides, caliche and evidence of dissolution of caliche in core, core from each subsurface unit encountered in the boring program, and soil samples, if available, as discussed in the SAR and the Geotechnical Data Report: HI-STORE CISF Phase 1 Site Characterization, Lea County, New Mexico.
D. Audit Team
- 1. Christopher Regan, Deputy Director, Division of Spent Fuel Management, NMSS
- 2. Michael Dudek, Chief, Radiological and Geotechnical Review Branch, NRO
- 3. Jose Cuadrado, Project Manager
- 4. Jenise Thompson, Geologist
- 5. Amitava Ghosh, Geotechnical Engineer
- 6. Luissette Candelario, Geotechnical Engineer
- 7. Zuhan Xi, Geotechnical Engineer
- 8. Gerry Stirewalt, Senior Geologist
- 9. Randall Fedors, Senior Hydrologist E. Special Requests Appropriate handling and protection of proprietary information shall be acknowledged and observed throughout the audit.
F. Deliverables The audit team will issue an audit summary after completing the audit. The audit summary will support the NRC staff in its review of Holtecs application for the HI-STORE CISF.
2