From:

Markley, Christopher To:

Mark Tursa Cc:

Kim Lehman

Subject:

Summary of Trojan ISFSI renewal RAI supplement scope/schedule Date:

Tuesday, March 19, 2019 12:31:00 PM Good day Mark,

By letter dated February 4, 2019, the NRC transmitted a request additional information (RAI) associated with requirements in 10 CFR 72.22(e). By letter dated Feb 21, 2019, Portland General Electric (PGE) responded the RAI. On March 6, 2019, the NRC and PGE had a clarification telephone call. During the call PGE provided plans to supplement the RAI response (ML19078A156). On March 13, 2019, the NRC and PGE had a call to confirm the scope and schedule for providing the supplement (ML19078A154). NRC approved PGEs request to provide a supplement to the RAI response by June 13, 2019.

Docket No. 72-17 License No. SNM-2509 CAC No. 001028 EPID No. L-2017-RNW-0011

Thanks,

-Chris

Christopher T. MARKLEY PhD l Systems Performance Analyst l Office of Nuclear Materials Safety and Safeguards l Division of Spent Fuel Management l Renewals and Materials Branch United States Nuclear Regulatory Commission l Washington, DC 20555-0001 l

christopher.markley@nrc.gov l (: (301) 415-6293 l 7: (301) 415-0020 l