Letter Sequence RAI |
---|
EPID:L-2017-RNW-0011, Screenshot/References Used in Environmental Assessment Prepared for the Trojan Independent Spent Fuel Storage Installation License Licensee Renewal Request (Approved, Closed) |
|
MONTHYEARML19296B6361999-03-31031 March 1999 Renewed License (Correction) Project stage: Other ML18113A3382018-04-23023 April 2018 Package: Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028) Project stage: Request ML18113A3392018-04-23023 April 2018 Enclosurai (Letter to B. Jenkins Package: Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028)) Project stage: RAI ML18113A3412018-04-23023 April 2018 Letter to B. Jenkins Package: Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028) Project stage: RAI ML18264A0212018-09-19019 September 2018 E-Mail from C. Markley to M. Tursa Revised RAI Response Date for Trojan ISFSI Renewal Application Project stage: RAI ML18365A1712018-12-31031 December 2018 E-Mail from C. Markley to T. Mark and L. Kim Revised RAI Response Date for Trojan ISFSI Renewal Application Project stage: RAI ML19035A6112019-02-0404 February 2019 Enclosurai (Letter to B. Jenkins Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028)) Project stage: RAI ML19035A6092019-02-0404 February 2019 Package: Letter to B. Jenkins Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028) Project stage: Request ML19035A6102019-02-0404 February 2019 Letter to B. Jenkins Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028) Project stage: RAI ML19078A2432019-03-19019 March 2019 E-Mail from C. Markley to M. Tursa Summary of Trojan ISFSI Renewal RAI Supplement Scope/Schedule Project stage: RAI ML17242A2152019-04-0808 April 2019 Screenshot/References Used in Environmental Assessment Prepared for the Trojan Independent Spent Fuel Storage Installation License Licensee Renewal Request Project stage: Request ML19058A2642019-06-26026 June 2019 Final Environmental Assessment for the Proposed Renewal of the U.S. Nuclear Regulatory Commission License SNM-2509 for the Trojan Independent Spent Fuel Storage Installation in Columbia County, Oregon Project stage: Request ML19169A0542019-07-0101 July 2019 Federal Register Notice for Environmental Assessment for the Proposed Renewal of NRC License Number SNM-2509 for the Trojan Independent Spent Fuel Storage Installation in Columbia County, Oregon Project stage: Request ML19221B6492019-08-0909 August 2019 Enclosure to Enclosure 1: Renewed License SNM-2509 (Letter to B. Nicholson Issuance of Renewed Materials License No. SNM-2509 for the Trojan Independent Spent Fuel Storage Installation) Project stage: Approval ML19221B6502019-08-0909 August 2019 Enclosurenewed License SNM-2509 Technical Specifications (Letter to B. Nicholson Issuance of Renewed Materials License No. SNM-2509 for the Trojan Independent Spent Fuel Storage Installation) Project stage: Approval ML19221B6512019-08-0909 August 2019 Enclosure 2: Safety Evaluation Report (Letter to B. Nicholson Issuance of Renewed Materials License No. SNM-2509 for the Trojan Independent Spent Fuel Storage Installation) Project stage: Approval ML19221B6482019-08-0909 August 2019 Enclosure 1: Preamble-SNM-2509 License Renewal Order (Letter to B. Nicholson Issuance of Renewed Materials License No. SNM-2509 for the Trojan Independent Spent Fuel Storage Installation) Project stage: Approval ML19221B6472019-08-0909 August 2019 Letter to B. Nicholson Issuance of Renewed Materials License No. SNM-2509 for the Trojan Independent Spent Fuel Storage Installation (Cac/Epid Nos. 001028/L-2017-RNW-0011 and 000993/L-2017-LNE-0009) Project stage: Approval ML19221B6522019-08-12012 August 2019 Federal Register Notice - Notice of Issuance for License Renewal (Letter to B. Nicholson Issuance of Renewed Materials License No. SNM-2509 for the Trojan Independent Spent Fuel Storage Installation) Project stage: Approval ML19296B6372019-10-23023 October 2019 Renewed License Technical Specifications (Correction) Project stage: Other 2019-02-04
[Table View] |
|
---|
Category:Request for Additional Information (RAI)
MONTHYEARML19035A6112019-02-0404 February 2019 Enclosurai (Letter to B. Jenkins Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028)) ML18113A3412018-04-23023 April 2018 Letter to B. Jenkins Package: Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028) ML18113A3392018-04-23023 April 2018 Enclosurai (Letter to B. Jenkins Package: Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028)) ML18094A4872018-04-0303 April 2018 Enclosurequest for Additional Information (Request for Additional Information Regarding Portland General Electric Company'S Decommissioning Funding Plan Update for Trojan Independent Spent Fuel Storage Installation) ML15149A3762015-05-28028 May 2015 Information Request to Support NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) 2019-02-04
[Table view] |
Text
REQUEST FOR ADDITIONAL INFORMATION Portland General Electric Company License Renewal Application Docket No. 72-17 License No. SNM-2509 This request for additional information (RAI) identifies information needed by the U.S. Nuclear Regulatory Commission (NRC) staff to complete its review of the license renewal application and to determine whether the applicant has demonstrated compliance with the regulatory requirements.
CHAPTER 1 - GENERAL INFORMATION RAI 1-1. In its submittal, Portland General Electric Company (PGE) stated, in part, that itself and co-owners of the Trojan Independent Spent Fuel Storage Installation (ISFSI) will remain financially qualified to carry out the operation and decommissioning of the ISFSI during the period of the renewed material license as required by 10 CFR 72.22(e). Additionally, PGE provided web links to the annual financial reports for PGE, PacifiCorp, and the Eugene Water and Electric Board (EWEB) current at that time. Two of the web links are currently inactive.
The regulation at 10 CFR 72.22(e) Contents of application: General and Financial Information, states:
Except for DOE, information sufficient to demonstrate to the Commission the financial qualifications of the applicant to carry out, in accordance with the regulations in this chapter, the activities for which the license is sought. The information must state the place at which the activity is to be performed, the general plan for carrying out the activity, and the period of time for which the license is requested. The information must show that the applicant either possesses the necessary funds, or that the applicant has reasonable assurance of obtaining the necessary funds or that by a combination of the two, the applicant will have the necessary funds available to cover the following:
(1) Estimated construction costs; (2) Estimated operating costs over the planned life of the ISFSI; and (3) Estimated decommissioning costs, and the necessary financial arrangements to provide reasonable assurance before licensing, that decommissioning will be carried out after the removal of spent fuel, high level radioactive waste, and/or reactor related GTCC waste from storage.
After reviewing PGEs submittal, it appears that the estimated operating and maintenance costs, as well as sources of funds to operate the Trojan ISFSI were not specifically provided in the application for license renewal, nor could this information be easily obtained from staffs review of the PGE annual report.
Enclosure
Request for Additional Information 1 Provide the current estimated operating and maintenance costs for the Trojan ISFSI, as well as sources of funds, over the planned life of the ISFSI. Additionally, provide the rationale for these cost projections.
This information is required to determine compliance with 10 CFR 72.22(e).