ML25199A184

From kanterella
Jump to navigation Jump to search

1) HI-STORM FW A10 RAI Letter Second Batch
ML25199A184
Person / Time
Site: 07201032
Issue date: 08/12/2025
From: Janice Nguyen
Storage and Transportation Licensing Branch
To: Manzione K
Holtec
Shared Package
ML25199A183 List:
References
EPID L-2025-LLA-0056, CAC 001028
Download: ML25199A184 (1)


Text

OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Kimberly Manzione, Director of Licensing Holtec International Holtec Technology Campus 1 Holtec Blvd Camden, NJ 08104

SUBJECT:

AMENDMENT NO. 10 TO CERTIFICATE OF COMPLIANCE NO. 1032 FOR THE HI-STORM FLOOD/WIND MULTI-PURPOSE CANISTER STORAGE SYSTEM - REQUEST FOR ADDITIONAL INFORMATION SECOND BATCH

Dear Kimberly Manzione:

By package dated April 18, 2024, (Agencywide Documents Access and Management System

[ADAMS] Accession No. ML24109A249), as supplemented on September 16, 2024 (ML24260A280), December 12, 2024 (ML24348A143), and February 28, 2025 (ML25062A248),

you submitted an application to the U.S. Nuclear Regulatory Commission (NRC) for the amendment of the HI-STORM Flood/Wind Multi-Purpose Canister Cask Storage System certificate of compliance.

On June 26, 2025, the NRC staff issued the first batch of requests for additional information (RAI) (ML25157A134). The enclosures to this letter contain the second batch of requests for the structural and operations reviews. Your response to the RAI is requested within 30 days of the date of this letter. If you are unable to meet this deadline, please notify us in writing, within 2 weeks of receipt of this letter, of your new submittal date and the reasons for the delay.

In accordance with Title 10 of the Code of Federal Regulations Part 2, Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records component of the NRCs ADAMS. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. The PDR is open by appointment. To make an appointment to visit the PDR, please send an email to PDR.Resource@nrc.gov or call 1-800-397-4209 or 301-415-4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through Friday, except Federal holidays. transmitted herewith contains Proprietary Information.

Upon removal of Enclosure 2, this document and Enclosure 1 are decontrolled.

August 12, 2025

OFFICIAL USE ONLY - PROPRIETARY INFORMATION K. Manzione 2

OFFICIAL USE ONLY - PROPRIETARY INFORMATION Please reference Docket No. 72-1032, CAC No. 001028, and Enterprise Project Identification No. L-2025-LLA-0056 in future correspondence related to this licensing action. If you have any questions, please contact me at 301-415-0262.

Sincerely, John-Chau Nguyen, Senior Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 72-1032 CAC No.: 001028 EPID No.: L-2025-LLA-0056

Enclosures:

1. RAI Second Batch (Non-Proprietary)
2. RAI Second Batch (Proprietary)

Signed by Nguyen, Chau on 08/12/25

ML25199A183 (pkg), ML25199A184 (ltr),

ML25199A185 (encl 1), ML25223A171 (encl 2, non-public)

OFFICE NMSS/DFM NMSS/DFM NMSS/DFM NMSS/DFM NAME JNguyen WWheatley JNguyen for JTapp BPatel DATE 7/25/2025 7/28/2025 7/28/2025 7/30/2025 OFFICE NMSS/DFM NMSS/DFM NMSS/DFM NMSS/DFM NAME LRegner GGeorge JNguyen YDiaz-Sanabria DATE 7/31/2025 8/1/2025 8/4/2025 8/5/2025 OFFICE NMSS/DFM NAME JNguyen DATE 8/12/2025