ML24324A363
Letter Sequence Approval | |
---|---|
CAC:001028, (Approved, Closed) EPID:001028, Independent Spent Fuel Storage Installation - Submittal of Application for the License Renewal (Approved, Closed) EPID:L-2022-LLA-0145, NAC-MAGNASTOR Amd. 13 - TMI-2 Fbm (22A) Packing Slip (Open) | |
Initiation
Administration
Questions
Answers
Results
Other: L-18-006, ISFSI - Site-Specific License Renewal Application, Revision 0, July 2018, L-23-005, Independent Spent Fuel Storage Installation License Renewal Application, Revision 1 (Cac/Epid No. 001028/L-2022-RNW-0007), ML17311A450, ML17318A087, ML18022A077, ML18022A078, ML18022A079, ML18087A058, ML18087A059, ML18087A060, ML18087A061, ML18087A062, ML18100A188, ML18100A190, ML18100A191, ML18100A193, ML18101A024, ML18108A052, ML18131A047, ML18141A561, ML18141A562, ML18141A564, ML18141A567, ML18179A258, ML18179A260, ML18179A266, ML18201A455, ML18205A179, ML18222A351, ML18228A533, ML18234A012, ML18255A094, ML18255A098, ML18255A101, ML18255A102, ML18324A594, ML18347B336, ML18347B337, ML18351A173, ML18351A175, ML18351A176, ML18351A177, ML18351A178, ML18355A373, ML18355A379, ML18355A380, ML18355A382, ML18362A303, ML19028A402, ML19028A403... further results | |
MONTHYEARML19255E7911997-05-31031 May 1997
[Table View]Enclosure 1 - Ecological Assessment of the Low Level Waste Depository, Andrews County, Tx Project stage: Other ML19255E7952004-10-25025 October 2004 Enclosure 2 - Habitat Characterization and Rare Species Survey for the Proposed Low Level Waste Repository, Andrews County, Tx Project stage: Other ML19337B5182007-03-16016 March 2007 Enclosure 10 - Applicable Sections of LLRW License Project stage: Other ML19255E7982007-03-16016 March 2007 Enclosure 3 - Supplemental Survey to Ecological Assessment of the Low Level Waste Depository, Andrews County, Texas Project stage: Supplement ML19255E8002008-07-0303 July 2008 Enclosure 4 - Environmental Assessment Report Prepared for Application for Renewal of Radioactive Material License R04971 Waste Control Specialists LLC Andrews County, Texas Project stage: Request ML19217A2142008-07-28028 July 2008 Enclosure 4 - Report on Activities to Satisfy Byproduct RML Conditions 41A, 41C, and 43, July 2008 (Public) Project stage: Other ML19217A2132011-02-22022 February 2011 Enclosure 3 - Oag Water Levels: Empirical and Modeled Relationships Between Precipitation and Infiltration, 2011 (Public) Project stage: Other ML18100A1882013-04-11011 April 2013 Enclosure 7 - Procedure 12751-MNGP-QP-9.201, Revision 0, Visual Weld Examination Project stage: Other ML18100A1912014-01-30030 January 2014 Enclosure 9 - Structural Integrity Associates, Inc. Report 130415.402, Revision 0, Review of Trivis Inc. Welding Procedures Used for Field Welds on the Transnuclear NUHOMS 61BTH Type 1 & 2 Transportable Canister for BWR Fuel Project stage: Other ML18100A1902014-05-22022 May 2014 Enclosure 8 - Structural Integrity Associates, Inc. Report 130415.403, Revision 2, Assessment of Monticello Spent Fuel Canister Closure Plate Welds Based on Welding Video Records Project stage: Other ML17318A0872017-11-0909 November 2017 Intent to Pursue Subsequent License Renewal Project stage: Other BVY 17-041, Supplement to Exemption Request from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 to Support the Dry Fuel Loading Campaign2017-12-0707 December 2017 Supplement to Exemption Request from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 to Support the Dry Fuel Loading Campaign Project stage: Supplement ML18011A1582017-12-22022 December 2017 International HI-STORE Cis (Consolidated Interim Storage Facility) License Application Responses to Safeguards Related Requests for Supplemental Information Project stage: Supplement ML17249A1572018-01-11011 January 2018, 16 January 2018 Package: Vermont Yankee Nuclear Power Station ISFSI Environmental Assessment and Finding of No Significant Impact Related to Issuance of Exemption to Allow a New Loading Pattern and Loading Fuel Cooled for at Least 2 Years Project stage: Request ML18022A1542018-01-16016 January 2018 Enclosure 3: Handout-PG&E Presentation on Humboldt Bay ISFSI LRA (Memo to A. Hsia Summary of December 12, 2017, Meeting) Project stage: Meeting ML17249A1592018-01-16016 January 2018 Letter to C. C. Chappell Vermont Yankee Nuclear Power Station ISFSI Environmental Assessment and Finding of No Significant Impact Related to Issuance of Exemption to Allow a New Loading Pattern and Loading Fuel Cooled for at Least 2 Years Project stage: Approval ML18022A1532018-01-16016 January 2018 Enclosure 2: Agenda (Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay ISFSI License) Project stage: Meeting ML18018B2972018-01-19019 January 2018 Federal Registered Notice: Correction of Certificate of Compliance No. 1004, Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 Project stage: Request ML18022A0792018-01-22022 January 2018 Enclosure 2: Revised Title for Figure 1-5 Corrected Technical Specifications for Certificate of Compliance No. 1004 Renewed Amendment No. 13, Revision 1 Project stage: Other ML18022A0772018-01-22022 January 2018 Letter to J. Bondre Correction to Tn Americas LLC Technical Specifications for Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 to Standardized NUHOMS Certificate of Compliance No. 1004 for Spent Fuel Storage Casks Project stage: Other ML18022A0782018-01-22022 January 2018 Enclosure 1: Revised Title for Figure 1-5 Corrected Technical Specifications for Certificate of Compliance No. 1004 Renewed Amendment No. 11, Revision 1 Enclosure 1 Project stage: Other ML18024A2732018-01-24024 January 2018 Letter to D. G. Stoddard U.S. NRC Approval of Virginia Electric and Power Company Request for Withholding Information from Public Disclosure for North Anna Power Station ISFSI (Cac/Epid Nos. 001028/L-2017-RNW-0010 and 000993/L-2017-LNE-0008 Project stage: Withholding Request Acceptance ML18030A1722018-01-29029 January 2018 Letter to J. P. Zimmerman Request for Additional Information for the Technical Review of the Application for Renewal of the Three Mile Island Unit 2 Independent Spent Fuel Storage Installation License No.: SNM-2508 Project stage: RAI ML17311A4502018-01-31031 January 2018 ISFSI License Renewal Final Environmental Assessment Project stage: Other ML18031A4572018-01-31031 January 2018 Submittal Date for Response to NRCs Requests for Additional Information (Rais) for License Amendment Request 1032-4 to HI-STORM FW CoC No. 1032 (CAC No. 001028) Project stage: Request ML17298A1352018-02-0202 February 2018 Safety Evaluation Report (Letter to C. C. Chappell Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Issuance of Exemption (CAC No.: 001028, Docket Nos. 50-271, 72-59, and 72-1014; EPID L-2017-LLE-0005) Project stage: Approval ML17298A1332018-02-0202 February 2018 Package: Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Issuance of Exemption (CAC No.: 001028, Docket Nos. 50-271, 72-59, and 72-1014; EPID L-2017-LLE-0005) Project stage: Request ML17298A1342018-02-0202 February 2018 Letter to C. C. Chappell Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Issuance of Exemption (CAC No.: 001028, Docket Nos. 50-271, 72-59, and 72-1014; EPID L-2017-LLE-0005) Project stage: Approval ML18040A0502018-02-0606 February 2018 Conversation Record with Dominion Energy Virginia Discuss North Power Station (NAPS) Independent Spent Fuel Storage Installation (ISFSI) Technical Specification Project stage: Other ML18031A2212018-02-0606 February 2018, 8 February 2018 Package: Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation (Cac/Epid Nos. 001028/L-2017-RNW-0010 and 000993/L-2017-LNE-0008) Project stage: Request ML18031A2242018-02-0606 February 2018 Enclosure 1: Preamble-SNM-2507 License Renewal Order (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation) Project stage: Approval ML18031A2272018-02-0606 February 2018 Enclosurenewed License SNM-2507 Technical Specifications (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18031A2222018-02-0606 February 2018 Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation (Cac/Epid Nos. 001028/L-2017-RNW-0010 and 000993/L-2017-LNE-0008) Project stage: Approval ML18031A2252018-02-0606 February 2018 Enclosurenewed License SNM-2507 (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation) Project stage: Approval ML18031A2282018-02-0606 February 2018 Enclosure 2: Safety Evaluation Report (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18031A2312018-02-0808 February 2018 Federal Register Notice - Notice of Issuance for License Renewal (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18058A0562018-02-23023 February 2018 Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.S Decommissioning Funding Plan Update Project stage: RAI ML18058A0242018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to G. Van Noordennen Request for Additional Information Regarding Zionsolutions, LLCs Decommissioning Funding Plan Update for Zion Independent Spent Fuel Storage Installation) Project stage: RAI ML18058A0572018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.S Decommissioning Funding Plan Update) Project stage: RAI ML18058A6082018-02-23023 February 2018 HI-2177593, Rev 0, Holtec International & Eddy Lea Energy Alliance (Elea) Underground CISF - Financial Assurance & Project Life Cycle Cost Estimates Project stage: Request ML18057A2182018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to A. Zaremba Request for Additional Information for Review of Duke Energys Decommissioning Funding Plan Update) Project stage: RAI ML18057A2172018-02-23023 February 2018 Letter to A. Zaremba Request for Additional Information for Review of Duke Energys Decommissioning Funding Plan Update Project stage: RAI ML18058A6072018-02-23023 February 2018 HI-2177565, Rev 0, Holtec International & Eddy Lea Energy Alliance (Elea) Cis Facility - Decommissioning Cost Estimate and Funding Plan Project stage: Request ML18057A2162018-02-23023 February 2018 Package: Request for Additional Information for Review of Duke Energy'S Decommissioning Funding Plan Update Project stage: Request ML18058A0232018-02-23023 February 2018 Letter to G. Van Noordennen Request for Additional Information Regarding Zionsolutions, LLCs Decommissioning Funding Plan Update for Zion Independent Spent Fuel Storage Installation Project stage: RAI ML18058A0812018-02-27027 February 2018 Enclosurequest for Additional Information(Rai for Review of Southern Nuclear Operating Companys Decommissioning Funding Plan Updates for Joseph M. Farley,Unit 1 and 2;Edwin I. Hatch,Units 1 and 2; and Vogtle Electric Generating Plant, Units Project stage: RAI ML18058A0822018-02-27027 February 2018 Letter: RAI for Review of Southern Nuclear Operating Companys Decommissioning Funding Plan Updates for Joseph M. Farley, Unit 1 and 2; Edwin I. Hatch, Units 1 and 2; and Vogtle Electric Generating Plant, Units 1 and 2 ISFSI Project stage: RAI ML18058A0532018-02-27027 February 2018 Letter: Request for Additional Information Regarding Florida Power and Light/Nextera Decommissioning Funding Plan Updates for St. Lucie, Units 1 and 2; Seabrook Station; Duane Arnold Energy Center; and Point Beach Units 1 and 2 ISFSI Project stage: RAI ML18058A0522018-02-27027 February 2018 Enclosurequest for Additional Information (Letter: RAI Regarding Florida Power and Light/Nextera Decommissioning Funding Plan Updates for St. Lucie, Units 1 & 2; Seabrook Station; Duane Arnold Energy Center; and Point Beach, Units 1 and 2) Project stage: RAI ML18060A0212018-02-28028 February 2018 Enclosurequest for Additional Information (Request for Additional Information Regarding Indiana Michigan Power Companys Decommissioning Funding Update for Donald C Cook Nuclear Plant Units 1 and 2 ISFSI) Project stage: RAI 2018-01-11 |
ML24324A363 | |
Person / Time | |
---|---|
Site: | 07201031 |
Issue date: | 11/20/2024 |
From: | Yoira Diaz-Sanabria Storage and Transportation Licensing Branch |
To: | Baldner H NAC International |
Shared Package | |
ML24324A362 | List: |
References | |
EPID L-2022-LLA-0145, CAC 001028 | |
Download: ML24324A363 (1) | |
Similar Documents at 07201031 | |
---|---|
Category:Letter
MONTHYEARML24324A3632024-11-20020 November 2024
[Table view]1. Letter to H. Baldner Issuance of Final Certificate of Compliance No. 1031, Amendment No. 13 for the Magnastor Storage Cask (Cac/Epid No. 001028/L-2022-LLA-0145) ML24323A2072024-11-18018 November 2024 NAC - Hitachi Zosen Corporation Rebranding ML24283A0852024-10-0808 October 2024 Submittal of Responses to the Nuclear Regulatory Commissions (NRC) Request for Additional Information for the Amendment Request to NAC International Magnastor Cask System Amendment No. 15 ML24226B2182024-09-0606 September 2024 Cover Letter - Request for Additional Information for Review of the Magnastor Storage System Amendment No. 15, Certificate of Compliance No. 1031 ML24219A2272024-08-0606 August 2024 NAC International Magnastor Cask System Amendment No. 14 Supplement ML24179A0722024-06-26026 June 2024 Submittal of Responses to the Nuclear Regulatory Commission Request for Additional Information for NAC International Magnastor Cask System Amendment No. 14 ML24169A5902024-06-21021 June 2024 NRC Approval of NAC International Request for Withholding Information Magnastor Amendment 15 ML24149A3682024-06-0505 June 2024 Request for NAC International Magnastor Cask System Amendment 15 - Accepted for Review - Cost Activity Code/Enterprise Project Identification Number 001028/L-2023-LLA-0143 ML24120A0362024-05-0707 May 2024 Application for Amendment No. 14 to the Model No. Magnastor Storage Cask - Request for Additional Information ML24082A1302024-04-18018 April 2024 NAC International - USNRC Inspection Report 0721031/2023201 Final Letter ML24108A1982024-04-16016 April 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Casks with Applied Changes Authorized by an Amended Certificate of Compliance ML24088A1752024-04-0909 April 2024 Amendment No. 14 and Magnastor Revisions to the Model No. Magnastor Storage Cask - Acceptance Letter ML24047A3632024-02-16016 February 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Transportable Storage Canisters Identification Numbers AMZDFX177, AMZDFX178, AMZDFX179 Vertical Concrete Cask Identification No. AMZDNE179, AMZDNE178 ML24008A2482024-01-0808 January 2024 NAC International, Response to Apparent Violations (a and B) in NRC Inspection Report 72-1031/2023-201; EA-2023-069 ML23283A2382023-12-0707 December 2023 NAC International, Inc. - U.S. Nuclear Regulatory Commission Inspection Report 72-1031/2023-201 ML23307A1332023-11-0101 November 2023 NAC International, Submittal of Final Safety Analysis Report (Fsar), Revision 14, for the NAC Magnastor Cask System ML23300A1382023-10-26026 October 2023 Supplement to NAC Internationals Submission of an Amendment Request for the NAC International Magnastor Cask System Amendment No. 15 ML23305A0462023-10-26026 October 2023 Submittal of Data Files to Support the Request to Amend the U.S. Nuclear Regulatory Commission Certificate of Compliance No. 1031 for the NAC International Magnastor Cask System, AmendmentNo.15, Supplement 01 ML23291A1672023-10-18018 October 2023 Supplement to the Amendment Request No. 14 for the NAC International Magnastor Cask System ML23258A2332023-09-15015 September 2023 Submission of Replacement Pages for Supplemental Responses to the Nuclear Regulatory Commissions (NRC) Request for Additional Information for the NAC International Magnastor Cask System, Amendment No. 13 ML23250A3242023-09-12012 September 2023 1. Transmittal Letter Magnastor Issuance of Amendment Nos 11 and 12 and Revision of Amendment Nos 0 Through 9 ML23241B0532023-08-29029 August 2023 Submission of an Amendment Request for the NAC International Magnastor Cask System Amendment No. 15 ML23243A8492023-08-29029 August 2023 NAC International, Submittal of Data Files to Support the Request to Amend the U.S. Nuclear Regulatory Commission Certificate of Compliance No. 1031 for Magnastor Cask System, Amendment No.15 ML23229A4812023-08-17017 August 2023 Submittal of Supplemental Responses to the Nuclear Regulatory Commissions (NRC) Request for Additional Information for the NAC International Magnastor Cask System, Amendment No. 13 ML23207A2492023-07-26026 July 2023 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Transportable Storage Canister Identification Numbers AMZDFX167 and AMZDFX169 and Vertical Concrete Cask Identification Numbers ML23205A2382023-07-24024 July 2023 Submittal of an Amendment Request for the NAC International Magnastor Cask System Amendment No. 14 ML23208A0622023-07-24024 July 2023 NAC International - Submission of Data Files to Support the Nuclear Regulatory Commissions (NRC) Review of Magnastor Amendment No. 14 ML23166B0832023-07-0505 July 2023 Independence Spent Fuel Storage Installation - Issuance of Exemption ML23178A2252023-06-27027 June 2023 Submission of Responses to the Nuclear Regulatory Commissions (NRC) Request for Additional Information for the NAC International Magnastor Cask System, Amendment No. 13 ML23143A3912023-05-23023 May 2023 Independent Spent Fuel Storage Installation - Request for Exemption from NAC-MAGNASTOR Certificate of Compliance 72-1031 - Cask Lid Batch 3 Design Requirements ML23074A2522023-03-29029 March 2023 Application for Amendment No. 13 to the Model No. Magnastor Storage Cask – Request for Additional Information ML23076A2272023-03-17017 March 2023 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Transportable Storage Canister Identification Numbers AMZDFX165 and AMZDFX166 and Vertical Concrete Cask Identification Numbers ML23005A2572023-01-0505 January 2023 Request to Withdraw Administrative Controls for Adverse Weather Events During Operations from Magnastor Amendment 12 Supplement ML22349A4682022-12-19019 December 2022 Amendment No. 10 to Certificate of Compliance No. 1031 for the Magnastor Storage System ML22340A5902022-12-0808 December 2022 Acknowledgement Letter - Magnastor Amendment 13 ML22327A2252022-11-23023 November 2022 NAC International - Magnastor Cask System Users CoC Amendment 12 Supplement and Intent to Adopt Letters ML22321A2682022-11-17017 November 2022 Supplement to the Submission of an Amendment Request for the NAC International Magnastor Cask System, Amendment No. 13 ML22308A1942022-11-0909 November 2022 NAC International, Inc. - U.S. Nuclear Regulatory Commission Report No. 72-1031/2022-201 ML22287A0382022-10-13013 October 2022 Supplement to the Submission of an Amendment Request for the NAC International Magnastor Cask System, Amendment No. 13 ML22257A2562022-09-14014 September 2022 Registration of Dry Spent Fuel Transportable Storage Canisters Identification Numbers AMZDFX170 and AMZDFX174 and Vertical Concrete Cask Identification Numbers AMZDNE170 and AMZDNE174 ML22230D0802022-08-18018 August 2022 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Transportable Storage Container ML22216A1102022-08-0404 August 2022 Magnastor Cask System Users CoC Amendments 0 Thru 9 Intent to Adopt Letters ML22208A0782022-07-27027 July 2022 Registration of Use of Cask to Store Spent Fuel ML22196A0232022-07-15015 July 2022 Submittal of Supplemental Information to the NRCs Request for Additional Information for the NAC International Magnastor Cask System Amendment No. 11 ML22194A9082022-07-13013 July 2022 NAC, Submittal of an Amendment Request for the NAC International Magnastor Cask System, Amendment No. 13 ML22201A0662022-07-13013 July 2022 NAC International, Inc., Submittal of Data Disk for the Magnastor Cask System, Amendment No. 13 ML22111A3572022-05-16016 May 2022 Letter Issuing Exemption to Catawba ML22111A3112022-05-16016 May 2022 Letter Issuing Exemption to McGuire ML22110A1112022-05-13013 May 2022 Letter Issuing Exemption to TMI-1 ML22111A2842022-05-13013 May 2022 Independence Spent Fuel Storage Installation - Issuance of Exemption 2024-09-06 |
Text
Heath Baldner Licensing Manager NAC International 3930 East Jones Bridge Road, Suite 200 Norcross, GA 30092
SUBJECT:
ISSUANCE OF FINAL CERTIFICATE OF COMPLIANCE NO. 1031, AMENDMENT NO. 13 FOR THE MAGNASTOR STORAGE CASK (CAC/EPID NOS. 001028/L-2022-LLA-0145)
Dear Heath Baldner:
By letter dated July 13, 2022 (Agencywide Documents Access and Management System
[ADAMS] Accession No. ML22194A908), as supplemented on October 13, 2022, and November 30, 2022 (ML22287A038 and ML22321A269, respectively), NAC International (NAC) submitted an application in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 72 to amend Certificate of Compliance (CoC) No. 1031 for the Model No. MAGNASTOR storage system to add the remaining damaged core material from the Three Mile Island Unit 2 (TMI-2) reactor that experienced the March 28, 1979, reactor accident new damaged fuel basket and a shorter version of the canister, transfer cask, and storage cask.
As stated in the Federal Register (89 FR 83775, October 18, 2024), the effective date of the final CoC No. 1031, Amendment No. 13 is November 19, 2024. Attached are the final CoC No.
1031, Amendment No. 13, and the corresponding technical specifications and final safety evaluation report. This amended certificate constitutes the approval and conditions for the use November 20, 2024
H. Baldner 2
of the MAGNASTOR Storage Cask System for the storage of spent nuclear fuel under the general licensing provisions of 10 CFR 72.210.
Sincerely, Yoira Diaz Sanabria, Chief Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 72-1031 EPID L-2022-LLA-0145
Enclosures:
- 2. CoC 1031, A13, Appendix A
- 3. CoC 1031, A13, Appendix B
- 4. CoC 1031, A13, Final Safety Evaluation Report Signed by Diaz-Sanabria, Yoira on 11/20/24
ML24324A362 (pkg), ML24324A363 (ltr), ML24324A364 (Coc)
ML24324A365 (Appx A), ML24324A366 (Appx B), ML24324A367 (SER)
OFFICE NMSS NMSS NMSS NAME NDevaser WWheatley YDiaz-Sanabria DATE 11/19/2024 11/20/2024 11/20/2024