Letter to K. Manzione, Holtec International'S License Application for the HI-STORE CISF, Revised Schedule for Final Licensing Decision
ML23076A279
Person / Time
Site: HI-STORE
Issue date: 03/20/2023
From: Yoira Diaz-Sanabria
Storage and Transportation Licensing Branch
To: Manzione K
Holtec
References
CAC 001028, EPID L-2018-NEW-0001
Download: ML23076A279 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 20, 2023 Kimberly Manzione Director of Licensing - NMSS Projects Holtec International Holtec Technology Campus One Holtec Boulevard Camden, NJ 08104

SUBJECT:

HOLTEC INTERNATIONALS APPLICATION FOR A SPECIFIC INDEPENDENT SPENT FUEL STORAGE INSTALLATION LICENSE FOR THE HI-STORE CONSOLIDATED INTERIM STORAGE FACILITY - REVISED SCHEDULE FOR FINAL LICENSING DECISION

Dear Kimberly Manzione:

By letter dated March 30, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17115A431), as supplemented, Holtec International (Holtec) submitted to the U.S. Nuclear Regulatory Commission (NRC) an application for a specific independent spent fuel storage installation license to construct and operate the HI-STORE Consolidated Interim Storage (CIS) Facility, in Lea County, New Mexico, in accordance with the requirements of Part 72 of Title 10 of the Code of Federal Regulations (10 CFR Part 72),

Licensing Requirements for the Independent Storage of Spent Nuclear Fuel, High-Level Radioactive Waste and Reactor-Related Greater than Class C Waste. The license application seeks NRC approval to store up to 8,680 metric tons of commercial spent nuclear fuel in the HI-STORM UMAX Canister Storage System for a 40-year license term.

We write to inform you that, due to unforeseen resource constraints, the staff will not be able to issue its final licensing decision by its previously estimated date of the end of March 2023. The staff now estimates that it will issue its final licensing decision and final safety evaluation report on or before the end of May 2023. The staff will continue to keep you apprised of any changes to the estimated date for its licensing decision.

K. Manzione 2 If you have any questions regarding these matters, please contact Mr. Jose R. Cuadrado, Project Manager, at (301) 415-0606.

Sincerely, White, Bernard signing on behalf of Diaz-Sanabria, Yoira on 03/20/23 Yoira K. Diaz-Sanabria, Chief Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 72-1051 CAC/EPID No.: 001028/07201051/

L-2018-NEW-0001

Ltr ML23076A279 OFFICE NMSS/DFM/STLB NMSS/DFM/STLB NMSS/DFM/STLB JCuadrado-Caraballo YDiaz-Sanabria NAME WWheatley WW JC BWhite for BW DATE Mar 17, 2023 Mar 20, 2023 Mar 20, 2023