Letter Sequence Other |
|---|
CAC:001028, SR 3.5.1.2 Notation (Approved, Closed) EPID:L-2017-FPR-0013, Encl: Environmental Assessment Memo to File: Environmental Assessment & Finding of No Significant Impact for Exelon Generation Co. Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Calvert Cliffs ISFSI (Open) EPID:L-2017-FPR-0045, Encl: Environmental Assessment Memo to File: Environmental Assessment & Finding of No Significant Impact for Exelon Generation Co. Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Calvert Cliffs ISFSI (Open) EPID:L-2017-FPR-0058, Encl: Environmental Assessment Memo to File: Environmental Assessment & Finding of No Significant Impact for Exelon Generation Co. Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Calvert Cliffs ISFSI (Open) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, ... further results|Supplement]]
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, ... further results|Meeting]]
Results
- Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, ... further results|Approval]]
Other: L-18-006, ISFSI - Site-Specific License Renewal Application, Revision 0, July 2018, L-23-005, Independent Spent Fuel Storage Installation License Renewal Application, Revision 1 (Cac/Epid No. 001028/L-2022-RNW-0007), ML17311A450, ML18018A018, ML18022A077, ML18022A078, ML18022A079, ML18087A056, ML18087A057, ML18087A058, ML18087A059, ML18087A060, ML18087A061, ML18087A062, ML18100A185, ML18100A188, ML18100A190, ML18100A191, ML18100A193, ML18101A024, ML18108A052, ML18131A047, ML18131A048, ML18141A561, ML18141A562, ML18141A563, ML18141A564, ML18141A565, ML18141A567, ML18179A258, ML18179A260, ML18179A266, ML18201A455, ML18205A179, ML18222A351, ML18228A530, ML18228A531, ML18228A532, ML18228A533, ML18234A012, ML18248A121, ML18255A093, ML18255A094, ML18255A096, ML18255A097, ML18255A098, ML18255A101, ML18255A102, ML18324A577, ML18324A594... further results
|
MONTHYEARML19255E7911997-05-31031 May 1997 Enclosure 1 - Ecological Assessment of the Low Level Waste Depository, Andrews County, Tx Project stage: Other ML19255E7952004-10-25025 October 2004 Enclosure 2 - Habitat Characterization and Rare Species Survey for the Proposed Low Level Waste Repository, Andrews County, Tx Project stage: Other ML19255E7982007-03-16016 March 2007 Enclosure 3 - Supplemental Survey to Ecological Assessment of the Low Level Waste Depository, Andrews County, Texas Project stage: Supplement ML19337B5182007-03-16016 March 2007 Enclosure 10 - Applicable Sections of LLRW License Project stage: Other ML19217A2112007-04-30030 April 2007 Enclosure 1 - Report on Mapping of a Trench Through Pedogenic Calcrete (Caliche) Across a Drainage and Possible Lineament, Waste Control Specialists Disposal Site, Andrews County, Tx (Public) Project stage: Other ML19255E8002008-07-0303 July 2008 Enclosure 4 - Environmental Assessment Report Prepared for Application for Renewal of Radioactive Material License R04971 Waste Control Specialists LLC Andrews County, Texas Project stage: Request ML19217A2142008-07-28028 July 2008 Enclosure 4 - Report on Activities to Satisfy Byproduct RML Conditions 41A, 41C, and 43, July 2008 (Public) Project stage: Other ML19217A2132011-02-22022 February 2011 Enclosure 3 - Oag Water Levels: Empirical and Modeled Relationships Between Precipitation and Infiltration, 2011 (Public) Project stage: Other ML18100A1852013-04-11011 April 2013 Enclosure 6 - Procedure 12751-MNGP-OPS-01, Revision 0, Spent Fuel Cask Welding: 61BT/BTH NUHOMS Canisters Project stage: Other ML18100A1882013-04-11011 April 2013 Enclosure 7 - Procedure 12751-MNGP-QP-9.201, Revision 0, Visual Weld Examination Project stage: Other ML18100A1912014-01-30030 January 2014 Enclosure 9 - Structural Integrity Associates, Inc. Report 130415.402, Revision 0, Review of Trivis Inc. Welding Procedures Used for Field Welds on the Transnuclear NUHOMS 61BTH Type 1 & 2 Transportable Canister for BWR Fuel Project stage: Other ML18100A1902014-05-22022 May 2014 Enclosure 8 - Structural Integrity Associates, Inc. Report 130415.403, Revision 2, Assessment of Monticello Spent Fuel Canister Closure Plate Welds Based on Welding Video Records Project stage: Other ML18011A1582017-12-22022 December 2017 International HI-STORE Cis (Consolidated Interim Storage Facility) License Application Responses to Safeguards Related Requests for Supplemental Information Project stage: Supplement ML17249A1572018-01-11011 January 2018, 16 January 2018 Package: Vermont Yankee Nuclear Power Station ISFSI Environmental Assessment and Finding of No Significant Impact Related to Issuance of Exemption to Allow a New Loading Pattern and Loading Fuel Cooled for at Least 2 Years Project stage: Request ML18022A1512018-01-16016 January 2018 Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay Independent Spent Fuel Storage Installation License Project stage: Meeting ML18022A1542018-01-16016 January 2018 Enclosure 3: Handout-PG&E Presentation on Humboldt Bay ISFSI LRA (Memo to A. Hsia Summary of December 12, 2017, Meeting) Project stage: Meeting ML18022A1532018-01-16016 January 2018 Enclosure 2: Agenda (Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay ISFSI License) Project stage: Meeting ML17249A1592018-01-16016 January 2018 Letter to C. C. Chappell Vermont Yankee Nuclear Power Station ISFSI Environmental Assessment and Finding of No Significant Impact Related to Issuance of Exemption to Allow a New Loading Pattern and Loading Fuel Cooled for at Least 2 Years Project stage: Approval ML18022A1522018-01-16016 January 2018 Enclosure 1: Meeting Attendees (Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay ISFSI License) Project stage: Meeting ML18018A0182018-01-17017 January 2018 Letter to K. Manzione Application for Holtec International HI-STORM Umax Multipurpose Canister Storage System License Amendment Request No. 3 to Certificate of Compliance No. 1040 - Accepted for Review Project stage: Other ML18018A0192018-01-17017 January 2018 Enclosurequest for Additional Information (Ltr to K. Manzione Application for Holtec International HI-STORM Umax Multipurpose Canister Storage System License Amendment Request No. 3 to Certificate of Compliance No. 1040-Accepted for Review) Project stage: RAI ML18018B2972018-01-19019 January 2018 Federal Registered Notice: Correction of Certificate of Compliance No. 1004, Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 Project stage: Request ML18022A6122018-01-19019 January 2018 Letter to K. Manzione Amendment No. 4 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System-Request for Additional Information Project stage: RAI ML18022A0762018-01-22022 January 2018 Package: Correction to Title of Figure 1-15 in Technical Specifications for Certificate of Compliance 1004 Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 Project stage: Request ML18022A0772018-01-22022 January 2018 Letter to J. Bondre Correction to Tn Americas LLC Technical Specifications for Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 to Standardized NUHOMS Certificate of Compliance No. 1004 for Spent Fuel Storage Casks Project stage: Other ML18022A0782018-01-22022 January 2018 Enclosure 1: Revised Title for Figure 1-5 Corrected Technical Specifications for Certificate of Compliance No. 1004 Renewed Amendment No. 11, Revision 1 Enclosure 1 Project stage: Other ML18022A0792018-01-22022 January 2018 Enclosure 2: Revised Title for Figure 1-5 Corrected Technical Specifications for Certificate of Compliance No. 1004 Renewed Amendment No. 13, Revision 1 Project stage: Other ML18024A2732018-01-24024 January 2018 Letter to D. G. Stoddard U.S. NRC Approval of Virginia Electric and Power Company Request for Withholding Information from Public Disclosure for North Anna Power Station ISFSI (Cac/Epid Nos. 001028/L-2017-RNW-0010 and 000993/L-2017-LNE-0008 Project stage: Withholding Request Acceptance ML18031A4572018-01-31031 January 2018 Submittal Date for Response to NRCs Requests for Additional Information (Rais) for License Amendment Request 1032-4 to HI-STORM FW CoC No. 1032 (CAC No. 001028) Project stage: Request ML17311A4502018-01-31031 January 2018 ISFSI License Renewal Final Environmental Assessment Project stage: Other ML18036A2222018-02-0101 February 2018 International - Transmittal of HI-STORM Umax License Amendment Request No. 3 - Administrative RAI Response Project stage: Request ML17298A1342018-02-0202 February 2018 Letter to C. C. Chappell Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Issuance of Exemption (CAC No.: 001028, Docket Nos. 50-271, 72-59, and 72-1014; EPID L-2017-LLE-0005) Project stage: Approval ML17298A1352018-02-0202 February 2018 Safety Evaluation Report (Letter to C. C. Chappell Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Issuance of Exemption (CAC No.: 001028, Docket Nos. 50-271, 72-59, and 72-1014; EPID L-2017-LLE-0005) Project stage: Approval ML18031A2222018-02-0606 February 2018 Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation (Cac/Epid Nos. 001028/L-2017-RNW-0010 and 000993/L-2017-LNE-0008) Project stage: Approval ML18031A2282018-02-0606 February 2018 Enclosure 2: Safety Evaluation Report (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18031A2242018-02-0606 February 2018 Enclosure 1: Preamble-SNM-2507 License Renewal Order (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation) Project stage: Approval ML18031A2252018-02-0606 February 2018 Enclosurenewed License SNM-2507 (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation) Project stage: Approval ML18031A2272018-02-0606 February 2018 Enclosurenewed License SNM-2507 Technical Specifications (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18031A2312018-02-0808 February 2018 Federal Register Notice - Notice of Issuance for License Renewal (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18053A2222018-02-15015 February 2018 Application for Amendment 1 to the NUHOMS Eos System, Revision O (Docket No. 72-1042) Project stage: Request ML18053A2332018-02-15015 February 2018 Enclosure 4: CoC 1042 Amendment 1 Proposed Technical Specifications, Revision 0 Project stage: Request ML18053A2342018-02-15015 February 2018 Enclosure 6: Proposed Amendment 1, Revision 0 Changes to the NUHOMS Eos System Updated Final Safety Analysis Report, Chapters 1 to 14 Project stage: Request ML18058A0232018-02-23023 February 2018 Letter to G. Van Noordennen Request for Additional Information Regarding Zionsolutions, LLCs Decommissioning Funding Plan Update for Zion Independent Spent Fuel Storage Installation Project stage: RAI ML18058A0562018-02-23023 February 2018 Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.S Decommissioning Funding Plan Update Project stage: RAI ML18057A2172018-02-23023 February 2018 Letter to A. Zaremba Request for Additional Information for Review of Duke Energys Decommissioning Funding Plan Update Project stage: RAI ML18058A0242018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to G. Van Noordennen Request for Additional Information Regarding Zionsolutions, LLCs Decommissioning Funding Plan Update for Zion Independent Spent Fuel Storage Installation) Project stage: RAI ML18058A6072018-02-23023 February 2018 HI-2177565, Rev 0, Holtec International & Eddy Lea Energy Alliance (Elea) Cis Facility - Decommissioning Cost Estimate and Funding Plan Project stage: Request ML18058A0572018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.S Decommissioning Funding Plan Update) Project stage: RAI ML18057A2182018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to A. Zaremba Request for Additional Information for Review of Duke Energys Decommissioning Funding Plan Update) Project stage: RAI ML18058A6082018-02-23023 February 2018 HI-2177593, Rev 0, Holtec International & Eddy Lea Energy Alliance (Elea) Underground CISF - Financial Assurance & Project Life Cycle Cost Estimates Project stage: Request 2018-01-11
[Table View] |
Text
November 20, 2020 Shane Smith, Vice President Finance Constellation Energy 1310 Point Street Baltimore, MD 21231
SUBJECT:
U.S. NUCLEAR REGULATORY COMMISSIONS ANALYSIS OF CONSTELLATION ENERGY NUCLEAR GROUP, LLCS INITIAL DECOMMISSIONING FUNDING PLANS FOR THE CALVERT CLIFFS, NINE MILE POINT, AND R.E. GINNA INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS
Dear Mr. Smith:
By letter dated December 17, 2012, Constellation Energy Nuclear Group, LLC (CENG) submitted, for U.S. Nuclear Regulatory Commission (NRC) staff review and approval, the initial decommissioning funding plans (DFPs) for the Independent Spent Fuel Storage Installations (ISFSIs) at Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Calvert Cliffs); Nine Mile Point Nuclear Station, Units 1 and 2 (Nine Mile Point); and R.E. Ginna Nuclear Power Plant (R.E.
Ginna) (Agencywide Documents Access and Management System (ADAMS) Accession No. ML123550040). The NRC staff notes that Exelon Generating Company, LLC (Exelon) now holds the licenses for these facilities.1 In accordance with Title 10 of the Code of Federal Regulations (10 CFR), Sections 72.30(b),
and using NUREG-1757, Vol. 3, Rev. 1, Consolidated Decommissioning Guidance, the NRC staff reviewed the initial DFPs submitted by CENG, including the initial decommissioning cost estimates (DCEs) and the method of assuring funds for decommissioning.
Pursuant to 10 CFR 72.30(b), each holder of, or applicant for, a license under Part 72 must submit for NRC review and approval a DFP containing information on how reasonable assurance will be provided that funds will be available to decommission its ISFSIs. The DFP must contain a detailed DCE, in an amount reflecting: (1) the cost of an independent contractor to perform all decommissioning activities, (2) an adequate contingency factor, and (3) the cost of meeting the 10 CFR 20.1402 unrestricted use criteria (or the cost of meeting the 10 CFR 20.1403 restricted use criteria, provided the licensee can demonstrate its ability to meet these criteria). The licensees DFP must also identify and justify using the key assumptions 1 Exelon is an intermediate parent company and also is the co-licensee and the operator of Calvert Cliffs, R.E. Ginna, and Nine Mile Point nuclear power plants (NPPs). Exelon assumed the licenses for the operation of the facilities and associated ISFSIs, but the ownership of these facilities did not change (ADAMS Accession No. ML14063A125; ADAMS Accession No. ML14063A211; and ADAMS Accession No. ML14106A053).
By letter dated March 31, 2015, Exelon submitted updated DFPs for the ISFSIs at Calvert Cliffs; Nine Mile Point; and R.E. Ginna (ADAMS Accession No. ML15090A537). Included in the 2015 submission was information on other Exelon-licensed ISFSIs. Exelon provided RAI responses addressing the 2015 DFPs to the NRC staff on May 2, 2018 (ADAMS Accession No. ML18124A197).
contained in the DCE. Further, the DFP must describe the method of assuring funds for ISFSI decommissioning, including means for adjusting cost estimates and associated funding levels periodically over the life of the ISFSI. Additionally, the DFP must specify the volume of onsite subsurface material containing residual radioactivity that will require remediation to meet the criteria for license termination and contain a certification that financial assurance for ISFSI decommissioning has been provided in the amount of the DCE.
The NRC staff reviewed and analyzed the information submitted by CENG on how reasonable assurance will be provided that funds will be available to decommission the ISFSIs, including the amount of the DCE and the method of assuring funds for decommissioning.
CENG estimated the total costs to decommission the ISFSIs at Calvert Cliffs, Nine Mile Point, and R.E. Ginna for unrestricted use were $2,059,000, $2,163,0002, and $2,232,000, respectively, in 2012 dollars. Based on its analysis of CENGs submittals, the staff finds that the submitted DCEs for 2012: 1) are based on reasonable costs of a third-party contractor;
- 2) include an adequate contingency factor; 3) reflect the cost of meeting the 10 CFR 20.1402 unrestricted use criteria; and 4) are based on reasonable and documented assumptions.
Therefore, the NRC staff finds that the DCEs adequately estimate the cost, at this time, to carry out required ISFSI decommissioning activities prior to license termination, and that the DCEs are acceptable.
CENG relied on prepayment, as financial assurance for ISFSI decommissioning, a method authorized by 10 CFR 72.30(e)(1). The NRC staff finds that the 2012 aggregate dollar amount of the licensees financial instruments provided adequate financial assurance to cover its cost estimates, and therefore, that these financial instruments are acceptable.
Based on its review, the NRC staff finds that the Initial DFPs contained the information required by 10 CFR 72.30(b) and that CENG provided reasonable assurance that funds will be available to decommission the ISFSIs at Calvert Cliffs, Nine Mile Point, and R.E. Ginna.
Pursuant to 10 CFR 72.30(c), at the time of license renewal and at intervals not to exceed 3 years, the DFP required to be submitted by 10 CFR 72.30(b) must be resubmitted with adjustments as necessary to account for changes in costs and the extent of contamination.
Because Exelon is co-licensee and operator of the ISFSIs at Calvert Cliffs, Nine Mile Point, and R.E. Ginna, Exelon submitted updated DFPs for the ISFSIs in 2015, as required by 10 CFR 72.30(c). As discussed above, it did so by letter dated March 31, 2015 (ADAMS Accession No. ML15090A537). The NRC staff provided its financial analyses of the updated DFPs submitted by Exelon for Calvert Cliffs; Nine Mile Point; and R.E. Ginna by separate letter (ADAMS Accession No. ML20279A501). The financial analyses of Exelons 2015 DFP submission under 10 CFR 72.30(c) are not presented in this letter.3 2 Value is based on the Long Island Power Authority (LIPA) ownership share of Nine Mile Point Nuclear Station, Unit 2 of 18%. Since LIPAs DCE and DFP are included in the CENG letter, the NRC included its assessment of LIPAs portion of the decommissioning costs in this letter. Total DCE for R.E. Ginna is
$2,163,000 with individual DCEs for CENG of $1,821,000 and $342,000 for LIPA.
3 The NRC staff provided its financial analyses of the DFPs for Exelons other licensed ISFSIs in separate letters (ADAMS Accession No. ML20279A501; ADAMS Accession No. ML20307A533; ADAMS Accession No. ML20260H376).
In addition to the NRC staffs analyses of CENGs initial DFPs, the NRC staff completed environmental reviews of the DFPs submitted for the ISFSIs at Calvert Cliffs, Nine Mile Point, and R.E. Ginna. The NRC staff determined there were no environmental impacts from the NRC staffs review and approval of CENGs initial DFPs and Exelons updated DFPs. The NRC staff will publish a summary of the results of these environmental reviews in the Federal Register in November 2020.4 The environmental assessments and findings of no significant impacts and related documents for these ISFSIs will be available in https://www.regulations.gov under the Docket ID: NRC-2020-0132. The environmental assessments for Calvert Cliffs, R.E. Ginna, and Nine Mile Point are located at ADAMS Accession Nos. ML20212L589, ML20213C613, and ML20234A435, respectively.
If you have any questions regarding this matter, please contact me at (301) 415-5722 or John.McKirgan@nrc.gov Sincerely, John McKirgan, Chief Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket Nos.: 72-08, 72-1036, and 72-67 License Nos.: SNM-2505, SFGL-47, and SFGL-45 CAC No.: 001028 EPID Nos.: L-2017-FPR-0013, L-2017-FPR-0045, and L-2017-FPR-0058 cc: B. Hanson, Exelon 4 This Federal Register Notice also includes a summary of the results of the environmental reviews for the ISFSIs at Arkansas Nuclear One, Units 1 and 2; Braidwood Station, Units 1 and 2; Byron Station, Units 1 and 2; Clinton Power Station, Unit 1; Dresden Nuclear Power Station, Units 1, 2, and 3; Grand Gulf Nuclear Station, Unit 1; LaSalle County Station, Units 1 and 2; Limerick Generating Station, Units 1 and 2; Oyster Creek Nuclear Generating Station; Quad Cities Nuclear Power Station, Units 1 and 2; River Bend Station, Unit 1; Waterford Steam Electric Station, Unit 3; and Zion Nuclear Power Station, Units 1 and 2.
John B.
McKirgan Digitally signed by John B.
McKirgan Date: 2020.11.20 14:29:52
-05'00'
SUBJECT:
U.S. NUCLEAR REGULATORY COMMISSIONS ANALYSIS OF CONSTELLATION ENERGY NUCLEAR GROUP, LLCS INITIAL DECOMMISSIONING FUNDING PLANS FOR THE CALVERT CLIFFS, NINE MILE POINT, AND R.E. GINNA INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS DOCUMENT DATED: November 20, 2020 DISTRIBUTION:
PUBLIC DFM r/f RidsNmssRefsFab KLois, NMSS SHarwell, NMSS FMiller, NMSS MHenderson, NMSS BWhite, NMSS DHabib, NMSS JMaltese, OGC PJehle, OGC JMcKirgan, NMSS BVaidya, NRR BPurnell, NRR RGladney, NMSS RidsNMSSResource RidsNrrPMCalvertCliffs Resource RidsNrrPMNineMilePoint Resource RidsNrrPMREGinna Resource ADAMS Package Accession No.: ML20212L881
- via email OFFICE NMSS/DFM NMSS/DFM NMSS/REFS/FAB OGC (NLO)
NMSS/DFM/STLB NAME RGladney*
WWheatley*
FMiller PJehle*
JMcKirgan*
DATE 10/01/2020 10/26/2020 11/4/2020 11/17/2020 11/20/2020 OFFICIAL RECORD COPY