MONTHYEARML19296B6361999-03-31031 March 1999 Renewed License (Correction) Project stage: Other ML18113A3382018-04-23023 April 2018 Package: Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028) Project stage: Request ML18113A3392018-04-23023 April 2018 Enclosurai (Letter to B. Jenkins Package: Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028)) Project stage: RAI ML18113A3412018-04-23023 April 2018 Letter to B. Jenkins Package: Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028) Project stage: RAI ML18264A0212018-09-19019 September 2018 E-Mail from C. Markley to M. Tursa Revised RAI Response Date for Trojan ISFSI Renewal Application Project stage: RAI ML18365A1712018-12-31031 December 2018 E-Mail from C. Markley to T. Mark and L. Kim Revised RAI Response Date for Trojan ISFSI Renewal Application Project stage: RAI ML19035A6112019-02-0404 February 2019 Enclosurai (Letter to B. Jenkins Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028)) Project stage: RAI ML19035A6092019-02-0404 February 2019 Package: Letter to B. Jenkins Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028) Project stage: Request ML19035A6102019-02-0404 February 2019 Letter to B. Jenkins Request for Additional Information for the Technical Review of the Application for Renewal of the Trojan Independent Spent Fuel Storage Installation License No. SNM-2509 (CAC No. 001028) Project stage: RAI ML19078A2432019-03-19019 March 2019 E-Mail from C. Markley to M. Tursa Summary of Trojan ISFSI Renewal RAI Supplement Scope/Schedule Project stage: RAI ML17242A2152019-04-0808 April 2019 Screenshot/References Used in Environmental Assessment Prepared for the Trojan Independent Spent Fuel Storage Installation License Licensee Renewal Request Project stage: Request ML19058A2642019-06-26026 June 2019 Final Environmental Assessment for the Proposed Renewal of the U.S. Nuclear Regulatory Commission License SNM-2509 for the Trojan Independent Spent Fuel Storage Installation in Columbia County, Oregon Project stage: Request ML19169A0542019-07-0101 July 2019 Federal Register Notice for Environmental Assessment for the Proposed Renewal of NRC License Number SNM-2509 for the Trojan Independent Spent Fuel Storage Installation in Columbia County, Oregon Project stage: Request ML19221B6492019-08-0909 August 2019 Enclosure to Enclosure 1: Renewed License SNM-2509 (Letter to B. Nicholson Issuance of Renewed Materials License No. SNM-2509 for the Trojan Independent Spent Fuel Storage Installation) Project stage: Approval ML19221B6502019-08-0909 August 2019 Enclosurenewed License SNM-2509 Technical Specifications (Letter to B. Nicholson Issuance of Renewed Materials License No. SNM-2509 for the Trojan Independent Spent Fuel Storage Installation) Project stage: Approval ML19221B6512019-08-0909 August 2019 Enclosure 2: Safety Evaluation Report (Letter to B. Nicholson Issuance of Renewed Materials License No. SNM-2509 for the Trojan Independent Spent Fuel Storage Installation) Project stage: Approval ML19221B6482019-08-0909 August 2019 Enclosure 1: Preamble-SNM-2509 License Renewal Order (Letter to B. Nicholson Issuance of Renewed Materials License No. SNM-2509 for the Trojan Independent Spent Fuel Storage Installation) Project stage: Approval ML19221B6472019-08-0909 August 2019 Letter to B. Nicholson Issuance of Renewed Materials License No. SNM-2509 for the Trojan Independent Spent Fuel Storage Installation (Cac/Epid Nos. 001028/L-2017-RNW-0011 and 000993/L-2017-LNE-0009) Project stage: Approval ML19221B6522019-08-12012 August 2019 Federal Register Notice - Notice of Issuance for License Renewal (Letter to B. Nicholson Issuance of Renewed Materials License No. SNM-2509 for the Trojan Independent Spent Fuel Storage Installation) Project stage: Approval ML19296B6372019-10-23023 October 2019 Renewed License Technical Specifications (Correction) Project stage: Other 2019-02-04
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML20275A2542020-09-30030 September 2020 State of Oregon No Comment E-Mail ML20244A1532020-08-27027 August 2020 NRC E-Mail Transmitting Draft EA to State of Oregon ML20140A0172020-05-19019 May 2020 Trojan Probability E-Mail ML19175A1302019-05-30030 May 2019 E-Mail to K. Niles/Oregon State Trojan ISFSI Decommissioning Funding Plan: Review Draft Ea/Fonsi ML19078A2432019-03-19019 March 2019 E-Mail from C. Markley to M. Tursa Summary of Trojan ISFSI Renewal RAI Supplement Scope/Schedule ML18365A1712018-12-31031 December 2018 E-Mail from C. Markley to T. Mark and L. Kim Revised RAI Response Date for Trojan ISFSI Renewal Application ML18264A0212018-09-19019 September 2018 E-Mail from C. Markley to M. Tursa Revised RAI Response Date for Trojan ISFSI Renewal Application ML14157A2412014-06-0404 June 2014 NRR E-mail Capture - Joseph M. Farley, Unit 1 and Unit 2, Regarding the Licensees Updated Schedule to Respond to NRCs NFPA-805 Request for Additional Information 2020-09-30
[Table view] |
Text
From: Markley, Christopher To: Mark Tursa Cc: Kim Lehman
Subject:
RE: Revised RAI Response Date for Trojan ISFSI Renewal Application Date: Monday, December 31, 2018 9:47:00 AM Attachments: image001.jpg image002.jpg image010.jpg image011.jpg image012.jpg image013.jpg image014.jpg image015.jpg image016.jpg image017.jpg image018.jpg image019.jpg image020.jpg image021.jpg image022.jpg image023.jpg Hi Mark, I approve the two week extension as noted below.
- Thanks,
-Chris Christopher T. MARKLEY PhD l Systems Performance Analyst l Office of Nuclear Materials Safety and Safeguards l Division of Spent Fuel Management l Renewals and Materials Branch United States Nuclear Regulatory Commission l Washington, DC 20555-0001 l
- christopher.markley@nrc.gov l (: (301) 415-6293 l 7: (301) 415-0020 l From: Mark Tursa [1]
Sent: Thursday, December 27, 2018 2:39 PM To: Markley, Christopher <Christopher.Markley@nrc.gov>
Cc: Kim Lehman <Kim.Lehman@pgn.com>
Subject:
[External_Sender] RE: Revised RAI Response Date for Trojan ISFSI Renewal Application Importance: High
- Chris, We appreciate the extended schedule for our responses, and I have one additional schedule request. Were currently resolving comments on our submittal with multiple parties including our Independent Safety Review Committee (ISRC) who must approve it before we submit. The ISRC th
provided numerous comments prior to and during our meeting with them on December 19 , and due to holiday schedules were finding it challenging to get them all resolved in a timely way. If possible we would appreciate a two week extension to January 30, 2019 to fully close the comments and ensure all changes are consistently documented between our RAI responses, LRA markups, SAR markups, and list of changes. Based on our current status I have high confidence that we will meet the extended date. Please let me know if this extension is acceptable so that we can plan accordingly.
Thank you for considering this request.
Mark From: Markley, Christopher <Christopher.Markley@nrc.gov>
Sent: Wednesday, September 19, 2018 7:24 AM To: Mark Tursa <Mark.Tursa@pgn.com>
Subject:
Revised RAI Response Date for Trojan ISFSI Renewal Application
- Please take care when opening links, attachments or responding to this email as it originated outside of PGE.***
Good morning Mark, By letter dated March 23, 2017, Portland General Electric (PGE) submitted an application for renewal of the Trojan site-specific Independent Spent Fuel Storage Installation license, SNM-2509. By letter dated April 23, 2018, (ML18113A338) the U.S. Nuclear Regulatory Commission (NRC) requested additional information to continue its review of the application. That letter requested the additional information be provided by October 31, 2018. Per our discussion, I have agreed to extend the response date to January 16, 2019.
This email documents that discussion. Inform us at your earliest convenience, but no later than December 31, 2018, if you are not able to provide the information by that date. To assist us in rescheduling your review, you should include a new proposed submittal date and the reasons for the delay.
If you have any questions in the meantime, please let me know.
Thank you,
-Chris Docket No. 72-17 CAC/EPID No. 001028/L-2017-RNW-0011 Christopher T. MARKLEY PhD l Systems Performance Analyst l Office of Nuclear Materials Safety and Safeguards l Division of Spent Fuel Management l Renewals and Materials Branch United States Nuclear Regulatory Commission l Washington, DC 20555-0001 l
- christopher.markley@nrc.gov l (: (301) 415-6293 l 7: (301) 415-0020 l