Text

Holtec Letter 5018101 Attachment 3 Multi-Purpose Canister (MPC) 3.1.1 ACTIONS (continued)

D. Required Actions and D.1 Remove all fuel assemblies 30 days associated Completion from the SFSC.

Times not met.

SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.1.1.1 Verify that the MPC cavity has been dried in Once, prior to accordance with the applicable limits in Table TRANSPORT 3-1. OPERATIONS SR 3.1.1.2 Verify MPC helium backfill quantity is within the Once, prior to limit specified in Table 3-2 for the applicable MPC TRANSPORT model. Re-performance of this surveillance is not OPERATIONS required upon successful completion of Action B.2.2.

SR 3.1.1.3 Verify that the helium leak rate through the MPC Once, prior to vent port confinement weld meets the leaktight TRANSPORT criteria of ANSI N14.5-1997 and verify that the OPERATIONS helium leak rate through the MPC drain port confinement weld meets the leaktight criteria of ANSI N14.5-1997. This surveillance does not need to be performed in the MPC utilizing the REDUNDANT PORT COVER DESIGN.

Certificate of Compliance No. 1032 Amendment No. 765 Appendix A 3.1.1-3 1 of 1