Letter Sequence Other |
---|
CAC:001028, (Approved, Closed) EPID:L-2017-FPR-0044, Package: Request for Additional Information Regarding GE-Hitachi's Decommissioning Funding Plan Update for Morris ISFSI (Open) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Administration
- Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
Results
- Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, ... further results|Approval]]
Other: L-23-005, Independent Spent Fuel Storage Installation License Renewal Application, Revision 1 (Cac/Epid No. 001028/L-2022-RNW-0007), ML19276D398, ML20014E677, ML20049A082, ML20065N277, ML20065N278, ML20065N280, ML20065N281, ML20065N285, ML20071F156, ML20076D696, ML20094G482, ML20099A180, ML20104C015, ML20104C016, ML20104C018, ML20104C019, ML20105A135, ML20105A136, ML20105A137, ML20105A138, ML20105A139, ML20105A173, ML20111A240, ML20115E377, ML20121A272, ML20136A049, ML20136A050, ML20136A051, ML20150A300, ML20150A335, ML20150A421, ML20155K741, ML20155K742, ML20155K743, ML20155K744, ML20160A040, ML20161A088, ML20163A702, ML20163A703, ML20163A704, ML20181A211, ML20181A212, ML20192A328, ML20192A329, ML20212L768, ML20212L769, ML20212L878, ML20223A036, ML20224A287... further results
|
MONTHYEARML18060A3332018-02-28028 February 2018 Letter to S. P. Murray Request for Additional Information Regarding GE-Hitachi's Decommissioning Funding Plan Update for Morris ISFSI Project stage: RAI ML18060A3302018-02-28028 February 2018 Package: Request for Additional Information Regarding GE-Hitachi's Decommissioning Funding Plan Update for Morris ISFSI Project stage: Request ML18060A3322018-02-28028 February 2018 Enclosurequest for Additional Request (Request for Additional Information Regarding GE-Hitachi's Decommissioning Funding Plan Update for Morris ISFSI) Project stage: RAI ML19276D3982019-10-0303 October 2019 Exemption Request to Load and Store Spent Fuel in HI-STORM FW Spent Fuel Casks Utilizing Amendment 1, Revision 1 to CoC No. 1032 Project stage: Other ML20115E3782019-10-0303 October 2019 Independent Spent Fuel Storage Installation Exemption Safety Evaluation Report Project stage: Approval ML20014E6772020-01-0909 January 2020 Fws List of Threatened and Endangered Species That May Occur with Respect to the McGuire Exemption Request Project stage: Other ML20015A3142020-01-14014 January 2020 Package: Exemption Request McGuire Nuclear Facility Project stage: Request ML20049A0812020-01-31031 January 2020 Holtec International - HI-STORM 100 Storage CoC Renewal Application Project stage: Request ML20049A0822020-01-31031 January 2020 Holtec International - HI-STORM 100 Storage CoC Renewal Application Project stage: Other ML20055F3372020-02-20020 February 2020 Conversation Record - Clarification Call (02/20/2020) on RAI 1 for CoC 1040 Umax Amendment 4 Project stage: RAI ML20064F6162020-02-29029 February 2020 January 15, 2020, Summary of Meeting with Holtec International, Inc., to Discuss the Upcoming Submittal of the Application for Renewal of the Storage Certificate of Compliance No. 1014 for the HI-Storm 100 Cask System Project stage: Meeting ML20063M0152020-03-0303 March 2020 HI-STORM 100 Renewal Presubmittal Meeting (Holtec Slides, 1-15-20) Project stage: Meeting ML20064E6222020-03-0303 March 2020 U.S. Nuclear Regulatory Commission Approval of NAC International Request for Withholding Information from Public Disclosure for Coc 1025 Renewal (CAC No. 001028) Project stage: Withholding Request Acceptance ML20071J0552020-03-0505 March 2020 Notice of Cancelled Meeting with the U.S. Department of Energy, Idaho Operations Office to Discuss the Upcoming Submittal of the Application for Renewal of the Idaho Spent Fuel Facility License (SNM-2512) Project stage: Meeting ML20065K2162020-03-0505 March 2020 Notice of Meeting with U.S. Department of Energy, Idaho Operations Office to Discuss the Upcoming Submittal of the Application for Renewal of the Idaho Spent Fuel Facility License (SNM-2512) Project stage: Meeting ML20071F1532020-03-0505 March 2020 Interim Storage Partners, LLC - Supplemental Information in Support of Nrc'S Environmental Review Project stage: Supplement ML20071F1562020-03-0505 March 2020 Interim Storage Partners, LLC - Affidavit Project stage: Other ML20065J4272020-03-0505 March 2020 Submittal of Renewal Application for the TN-32 Dry Storage Cask - CoC 1021 Project stage: Request ML20066K5782020-03-0606 March 2020 Acceptance Review of Request for Amendment No. 7 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System Project stage: Acceptance Review ML20065L3442020-03-0606 March 2020 Amendment No. 15 to Certificate of Compliance No. 1014 for the Hi-Storm 100 Multipurpose Canister Storage System - Request for Additional Information Project stage: RAI ML20065N2852020-03-0909 March 2020 ISFSI Renewed Technical Specifications Project stage: Other ML20065N2772020-03-0909 March 2020 ISFSI Renewal Cover Letter Project stage: Other ML20065N2812020-03-0909 March 2020 ISFSI Preamble-License Renewal Order Project stage: Other ML20071D9942020-03-11011 March 2020 Submittal of HI-STAR 100 Updated FSAR, Revision 4 Project stage: Request ML20076D6962020-03-11011 March 2020 Interim Storage Partners, LLC - Submittal of Clarifications to Support Nrc'S Continued Review of the Safety Case for the WCS CISF Project stage: Other ML20065N2782020-03-11011 March 2020 ISFSI FRN Notice of Issuance for License Renewal Project stage: Other ML20104C0202020-03-30030 March 2020 International - HI-STORM Umax Amendment 4 Responses to Requests for Additional Information - Supplemental Information Project stage: Supplement ML20104C0192020-03-30030 March 2020 International - Affidavit for Kimberly Manzione Project stage: Other ML20104C0182020-03-30030 March 2020 International - HI-STORM Umax Amendment 4 FSAR - Changed Pages Project stage: Other ML20104C0162020-03-30030 March 2020 International - Proposed HI-STORM Umax CoC Amendment 4 Appendix a - Changed Pages Project stage: Other ML20104C0152020-03-30030 March 2020 International - Amendment No. 4 to the HI-STORM Umax Canister Storage System Project stage: Other ML20091L0642020-03-31031 March 2020 Enclosure 1 - Request for Additional Information - Non-Proprietary Project stage: RAI ML20091L0632020-03-31031 March 2020 Transmittal Letter - CoC 1042 Amendment Number 2 Request for Additional Information Project stage: RAI ML20104C0482020-03-31031 March 2020 International - HI-STORM Umax Amendment 3 Responses to Requests for Additional Information Project stage: Response to RAI ML20105A1352020-03-31031 March 2020 Enclosure 1 - Affidavits Project stage: Other ML20101P3992020-03-31031 March 2020 Interim Storage Partners, LLC - Submittal of Draft Responses for Several Rals and Associated Document Markups from First Request for Additional Information, Parts 1, 2 and Clarifications Project stage: Draft Request ML20065N2802020-03-31031 March 2020 ISFSI License Renewal SER Project stage: Other ML20099A1802020-04-0606 April 2020 Application for Renewal of the Certificate of Compliance No. 1014 for the Hi-Storm 100 Storage Cask System Accepted for Review (Cac/Epid Nos. 001028/L-2020-RNW-0007) Project stage: Other ML20105A1732020-04-0606 April 2020 Interim Storage Partners, LLC - Affidavits Project stage: Other ML20105A1392020-04-0707 April 2020 Enclosure 8 - Referenced Documents Project stage: Other ML20105A1342020-04-0707 April 2020 Submission of ISP Responses for RAIs and Associated Document Markups from First Request for Additional Information, Parts 2, 3, and 4 Project stage: Request ML20105A1722020-04-0707 April 2020 Interim Storage Partners, LLC - Submittal of Supplemental Information in Support of RAI, Part 3 Project stage: Supplement ML20105A1382020-04-0707 April 2020 Enclosure 7 - SAR Changed Pages Project stage: Other ML20105A1372020-04-0707 April 2020 Enclosure 5 - La Changed Pages Project stage: Other ML20105A1362020-04-0707 April 2020 Enclosure 3 - RAIs and Responses Project stage: Other ML20100F2952020-04-0909 April 2020 Tn Americas LLC - Submittal of Renewal Application for the TN-68 Dry Storage Cask - CoC 1027 Project stage: Request ML20104A0402020-04-10010 April 2020 Request for Additional Information for HI-STAR 100 CoC Renewal Application Project stage: RAI ML20111A2382020-04-13013 April 2020 International - HI-STORM Umax Amendment 4 Responses to Requests for Additional Information - Supplemental Information Project stage: Supplement ML20111A2402020-04-13013 April 2020 Attachment 2: Proposed HI-STORM Umax CoC Amendment 4 Appendix a - Changed Pages (non-proprietary) Project stage: Other ML20111A2392020-04-13013 April 2020 Attachment 1: HI-STORM Umax Amendment 4 RAI Supplemental Response (non-proprietary) Project stage: Supplement 2020-03-30
[Table View] |
|
---|
Category:Letter
MONTHYEARML24284A1182024-10-10010 October 2024 GEH - Notification of GE Company Stock Beneficial Ownership Filing ML24156A0752024-06-10010 June 2024 Application for Exemption from Select Requirements of Title 10 of the Code of Federal Regulations Part 73 for the Morris Operation - Acknowledgement of Withdrawal and Notification of the U.S. Nuclear Regulatory Commission Staff Efforts Clos ML24145A1292024-05-24024 May 2024 Morris Operation Request to Withdraw Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notifications Implementation IR 07200001/20230012024-03-0707 March 2024 GE Hitachi Morris (Gehmo) Independent Spent Fuel Storage Installation NRC Inspection Report 07200001/2023001 ML24057A2742024-02-26026 February 2024 GE-Hitachi Nuclear Energy Americas, LLC, 2023 GEH Morris Operation Annual Effluent Report ML24032A1082024-02-0101 February 2024 GEH Notification of GE Company Stock Beneficial Ownership Filing ML24004A1652024-01-0404 January 2024 Morris Operation (Mo) Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23345A0812023-12-11011 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23283A3292023-11-30030 November 2023 NRC Issuance of Order Consenting to Indirect Transfer of Control of Ge/Geha/Gnfa Licenses ML23334A2222023-11-30030 November 2023 GE Hitachi Nuclear Energy - NRC Notice Before Actions Necessary to Accomplish the Indirect Transfers of Control Are Completed IR 07200001/20234012023-11-28028 November 2023 GE Hitachi Morris (Gehmo) Independent Spent Fuel Storage Installation NRC Security Inspection Report 07200001/2023401 ML23276B3952023-10-13013 October 2023 the U.S. Nuclear Regulatory Commission Staff Assessment of Ge/Geha/Gnfa Reponses to Acceptance Observations Application for the U.S. Nuclear Regulatory Commission Consent to Indirect Transfer of Licenses ML23229A5122023-08-17017 August 2023 GE-Hitachi Nuclear Energy Americas, LLC, Response to NRC Staff Observations Enclosed with NRC Acceptance Letter (Reference 2) Related to GE, Geha and GNF-A Application (Reference 1) ML23191A8592023-07-27027 July 2023 Acceptance Letter GE GNFA and Geha Application for NRC Consent to Indirect Transfer of Licenses ML23177A0892023-06-26026 June 2023 Geha and GNF-A Application for Indirect Transfer of Control - Revision 2 ML23171A9762023-06-20020 June 2023 Geha and GNF-A Application for Indirect Transfer of Control - Revision 1 ML23152A1162023-05-30030 May 2023 Application for Order Consenting to Indirect Transfer of Control with Respect to Reactor Licenses, Materials Licenses, and Export Licenses, and Notification Regarding Other Approvals ML23104A4172023-03-31031 March 2023 GNF-AGEH Financial Assurance of Decommissioning Funds - Surety Bond Riders Cover Letter and Affidavit ML23054A3332023-02-23023 February 2023 GEH Notification of GE Company Stock Beneficial Ownership Filing ML23044A3282023-02-10010 February 2023 GEH Morris Operation Submittal of Updated Consolidated Safety Analysis Report (CSAR, Rev 15A, Feb 2023) ML22350A4702022-12-12012 December 2022 GEH Morris Operation Submittal of Biennial Report 10CFR72.48; Changes, Tests, and Experiments ML22242A0162022-11-22022 November 2022 Cover Letter for GEH Morris Operation ISFSI Subsequent License Renewal ML22313A1452022-11-0909 November 2022 Usfws Illinois-Iowa Ecological Services Field Office - Species List for Proposed License Renewal for GE-Hitachi Morris Operation Independent Spent Fuel Storage Installation - Project Code: 2022-0044583 ML22249A0952022-09-0808 September 2022 Proprietary Determination Letter for GEH-Morris License Renewal Application Submittals ML22249A3652022-09-0606 September 2022 GEH Notification of GE Company Stock Beneficial Ownership Filing ML22146A3512022-05-19019 May 2022 Usfws Illinois-Iowa Ecological Services Field Office - Species List for Proposed License Renewal for Morris Operation Independent Spent Fuel Storage Installation - Project Code: 2022-0044583 ML22132A0722022-05-12012 May 2022 GEH Morris Operation (Mo) Response to NRC Request for Additional Information for the Technical Review of the Application for Renewal of the Morris Operation License No. SNM-2500 ML22084A5782022-03-23023 March 2022 GNF-A/GEH Financial Assurance of Decommissioning Funds - Surety Bond Riders Cover Letter and Affidavit ML22068A1322022-03-0909 March 2022 GE-Hitachi Nuclear Energy Americas, LLC, Notification of Stock Beneficial Ownership Filing ML22054A0292022-02-22022 February 2022 GE-Hitachi Nuclear Energy Americas, LLC, 2021 Morris Operation Annual Effluent Report ML22042A4152022-02-11011 February 2022 GE-Hitachi Nuclear Energy Americas, LLC - GEH Notification of GE Company Stock Beneficial Ownership Filings ML22027A5162022-01-27027 January 2022 GEH - Morris Operation (Mo) Response to Request for Additional Information for the Technical Review of the Application for Renewal of the Morris Operation License No. SNM-2500 ML21216A2752022-01-0505 January 2022 GEH Morris DFP Close-out Letter ML21326A2662021-11-22022 November 2021 GEH Notification of GE Company Stock Beneficial Ownership Filing ML21319A2202021-11-17017 November 2021 Letter - Proprietary Determination for GEH Morris DFP Submittals ML21340A2432021-09-28028 September 2021 Illinois Threatened and Endangered Species by County, as of December 2020 IR 07200001/20214012021-09-27027 September 2021 GE-Hitachi Morris (Gehmo) Independent Spent Fuel Storage Installation - NRC Security Inspection Report 07200001/2021401 ML21252A1382021-09-0909 September 2021 GEH - Morris Operation (Mo) Decommissioning Funding Plan (DFP) Redacted Versions ML22063B1752021-08-30030 August 2021 Email and Letter from D. Hunter of Miami Tribe NRC Preliminary Determination Under Section 106 of the NHPA for Proposed GE-Hitachi Morris Operation ISFSI License Renewal ML21214A3102021-08-30030 August 2021 Request for Additional Information for the Technical Review of the Application for Renewal of the Morris Operation License No. SNM-2500 (Cac/Epid Nos. 001028/L-2020-RNW-0024) ML21193A1312021-08-0202 August 2021 Letter to Peoria Tribe of Indians of Oklahoma Re NRC Preliminary Determination Under Section 106 of the NHPA ML21138A9052021-08-0202 August 2021 Letter to Hannahville Indian Community Re NRC Preliminary Determination Under Section 106 of the National Historic Preservation Act ML21186A0112021-08-0202 August 2021 Letter to Ho-Chunk Nation Re NRC Preliminary Determination Under Section 106 of the NHPA ML21188A2052021-08-0202 August 2021 Letter to Kickapoo Tribe in Kansas Re NRC Preliminary Determination Under Section 106 of the NHPA ML21189A2312021-08-0202 August 2021 Letter to Little Traverse Bay Bands of Odawa Indians Re NRC Preliminary Determination Under Section 106 of the NHPA ML21189A2522021-08-0202 August 2021 Letter to Match-E-Be-Nash-She-Wish Band of Potawatomi Indians Re NRC Preliminary Determination Under Section 106 of the NHPA ML21189A2602021-08-0202 August 2021 Letter to Menominee Indian Tribe of Wisconsin Re NRC Preliminary Determination Under Section 106 of the NHPA ML21189A3092021-08-0202 August 2021 Letter to Miami Tribe of Oklahoma Re NRC Preliminary Determination Under Section 106 of the NHPA ML21189A3342021-08-0202 August 2021 Letter to Nottawaseppi Huron Band Re NRC Preliminary Determination Under Section 106 of the NHPA ML21193A1462021-08-0202 August 2021 Letter to Prairie Band Potawatomi Nation Re NRC Preliminary Determination Under Section 106 of the NHPA 2024-06-10
[Table view] |
Text
PRE-DECISIONAL INFORMATION. THIS INFORMATION IS LIMITED TO USE BY THE ILLINOIS EMERGENCY MANAGEMENT AGENCY. THIS INFORMATION SHALL NOT BE DISCLOSED WITHOUT PRIOR NRC PERMISSION.
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 27, 2021 Adnan Khayyat Illinois Emergency Management Agency Division of Nuclear Safety 2200 S. Dirksen Parkway Springfield, IL 62703
SUBJECT:
REVIEW OF THE DRAFT ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT FOR THE MORRIS OPERATION DECOMMISSIONING FUNDING PLANS
Dear Mr. Khayyat:
By letter dated December 14, 2012 (Agencywide Documents Access and Management System
[ADAMS] Accession No. ML12352A103), GE Hitachi Nuclear Energy (referred to as GEH) submitted an initial decommissioning funding plan (DFP) for the Morris Operation Independent Spent Fuel Storage Installation (ISFSI), located in Illinois, for U.S. Nuclear Regulatory Commission (NRC) staff review and approval. By letters dated December 11, 2015, December 14, 2018, and March 6, 2020 (ADAMS Accession Nos. ML15345A191, ML18348A614, and ML20066K270), GEH submitted updated DFPs, for NRC staff review and approval.
The NRC initially consulted with the Illinois Emergency Management Agency on August 17, 2017, via a letter (ADAMS Accession No. ML17226A160). Subsequent to that initial consultation, the NRC staff completed its review of the updated DFPs. The NRC staff is seeking your consultation on the initial and updated DFPs, as a combined review, for the Morris Operation ISFSI.
The NRC regulations at Title 10 of the Code of Federal Regulations (10 CFR) Part 72, Licensing Requirements for the Independent Storage of Spent Nuclear Fuel, High-Level Radioactive Waste, and Reactor-Related Greater than Class C Waste, govern the storage of spent nuclear fuel at an ISFSI. The NRC requires its licensees to plan for the eventual decommissioning of their licensed facilities prior to license termination. On June 17, 2011, the NRC published a final rule amending its decommissioning planning regulations (76 Federal Register (FR) 35512). The final rule amended the NRC regulation, 10 CFR 72.30, which concerns financial assurance and decommissioning for ISFSIs. This regulation now requires each holder of, or applicant for, a license under 10 CFR Part 72 to submit, for NRC review and approval, a DFP. The purpose of the DFP is to demonstrate the licensees financial assurance (i.e., that funds will be available to decommission the ISFSI). The NRC staff is reviewing the information submitted by GEH. Specifically, the NRC must determine whether GEHs DFPs contain the information required by 10 CFR 72.30(b) and 10 CFR 72.30(c) and whether GEH has provided reasonable assurance that funds will be available to decommission the Morris Operation ISFSI.
Upon removal of the Enclosure, this document is uncontrolled.
PRE-DECISIONAL INFORMATION. THIS INFORMATION IS LIMITED TO USE BY THE ILLINOIS EMERGENCY MANAGEMENT AGENCY. THIS INFORMATION SHALL NOT BE DISCLOSED WITHOUT PRIOR NRC PERMISSION.
PRE-DECISIONAL INFORMATION. THIS INFORMATION IS LIMITED TO USE BY THE ILLINOIS EMERGENCY MANAGEMENT AGENCY. THIS INFORMATION SHALL NOT BE DISCLOSED WITHOUT PRIOR NRC PERMISSION.
A. Khayyat In accordance with 10 CFR Part 51, the NRC regulations that implement the National Environmental Policy Act of 1969, as amended, the agency has prepared a draft environmental assessment (EA) for the Morris Operation ISFSI for the proposed action (enclosed). We are providing your office with the opportunity to review the draft EA and comment on environmental issues prior to the public issuance and publication of the EA. We request that you share the enclosed draft EA with other appropriate State officials, as needed. We request that distribution and use of the enclosed draft EA be limited only to those staff involved in the review and comment process.
Please submit any comments within 30 days from the date of this letter to the U.S. Nuclear Regulatory Commission, Document Control Desk, ATTN: John McKirgan, Mail Stop: TWFN 4B34, U.S. Nuclear Regulatory Commission, Washington, DC 20555. If you have any questions, please contact Kristina Banovac of my staff by telephone at 301-415-7116, or by e-mail at Kristina.Banovac@nrc.gov. The NRC staff will consider your timely comments and will revise the EA, as appropriate, before its final issuance and publication. Thank you for your assistance.
Sincerely, John B. Digitally signed by John B.
McKirgan McKirgan Date: 2021.04.27 14:30:09
-04'00' John B. McKirgan, Chief Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 72-01 License No.: SNM-2500 EPID No.: L-2017-FPR-0044
Enclosure:
Draft Environmental Assessment PRE-DECISIONAL INFORMATION. THIS INFORMATION IS LIMITED TO USE BY THE ILLINOIS EMERGENCY MANAGEMENT AGENCY. THIS INFORMATION SHALL NOT BE DISCLOSED WITHOUT PRIOR NRC PERMISSION.
ML21110A163 (Pkg) ML21110A164 (Ltr)
ML21110A165 (Encl)
- concurrence via email OFFICE DFM/STLB DFM/STLB DFM/STLB NAME KBanovac* WWheatley* JMcKirgan*
DATE 4/14/2021 4/15/2021 4/27/2021