Letter Sequence RAI |
|---|
CAC:001028, (Approved, Closed) EPID:L-2017-NEW-0002, Interim Storage Partners (ISP) First Request for Additional Information (RAI) Proposed Submittal Schedule, Docket 72-1050 Cac/Epid 001028/L-2017-NEW-0002 (Open) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, ... further results|Supplement]]
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, ... further results|Meeting]]
Results
- Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, ... further results|Approval]]
Other: L-18-006, ISFSI - Site-Specific License Renewal Application, Revision 0, July 2018, L-23-005, Independent Spent Fuel Storage Installation License Renewal Application, Revision 1 (Cac/Epid No. 001028/L-2022-RNW-0007), ML17311A450, ML18018A018, ML18022A077, ML18022A078, ML18022A079, ML18087A056, ML18087A057, ML18087A058, ML18087A059, ML18087A060, ML18087A061, ML18087A062, ML18100A185, ML18100A188, ML18100A190, ML18100A191, ML18100A193, ML18101A024, ML18108A052, ML18131A047, ML18131A048, ML18141A561, ML18141A562, ML18141A563, ML18141A564, ML18141A565, ML18141A567, ML18179A258, ML18179A260, ML18179A266, ML18201A455, ML18205A179, ML18222A351, ML18228A530, ML18228A531, ML18228A532, ML18228A533, ML18234A012, ML18248A121, ML18255A093, ML18255A094, ML18255A096, ML18255A097, ML18255A098, ML18255A101, ML18255A102, ML18324A577, ML18324A594... further results
|
MONTHYEARML19255E7911997-05-31031 May 1997 Enclosure 1 - Ecological Assessment of the Low Level Waste Depository, Andrews County, Tx Project stage: Other ML19255E7952004-10-25025 October 2004 Enclosure 2 - Habitat Characterization and Rare Species Survey for the Proposed Low Level Waste Repository, Andrews County, Tx Project stage: Other ML19255E7982007-03-16016 March 2007 Enclosure 3 - Supplemental Survey to Ecological Assessment of the Low Level Waste Depository, Andrews County, Texas Project stage: Supplement ML19337B5182007-03-16016 March 2007 Enclosure 10 - Applicable Sections of LLRW License Project stage: Other ML19217A2112007-04-30030 April 2007 Enclosure 1 - Report on Mapping of a Trench Through Pedogenic Calcrete (Caliche) Across a Drainage and Possible Lineament, Waste Control Specialists Disposal Site, Andrews County, Tx (Public) Project stage: Other ML19255E8002008-07-0303 July 2008 Enclosure 4 - Environmental Assessment Report Prepared for Application for Renewal of Radioactive Material License R04971 Waste Control Specialists LLC Andrews County, Texas Project stage: Request ML19217A2142008-07-28028 July 2008 Enclosure 4 - Report on Activities to Satisfy Byproduct RML Conditions 41A, 41C, and 43, July 2008 (Public) Project stage: Other ML19217A2132011-02-22022 February 2011 Enclosure 3 - Oag Water Levels: Empirical and Modeled Relationships Between Precipitation and Infiltration, 2011 (Public) Project stage: Other ML18100A1852013-04-11011 April 2013 Enclosure 6 - Procedure 12751-MNGP-OPS-01, Revision 0, Spent Fuel Cask Welding: 61BT/BTH NUHOMS Canisters Project stage: Other ML18100A1882013-04-11011 April 2013 Enclosure 7 - Procedure 12751-MNGP-QP-9.201, Revision 0, Visual Weld Examination Project stage: Other ML18100A1912014-01-30030 January 2014 Enclosure 9 - Structural Integrity Associates, Inc. Report 130415.402, Revision 0, Review of Trivis Inc. Welding Procedures Used for Field Welds on the Transnuclear NUHOMS 61BTH Type 1 & 2 Transportable Canister for BWR Fuel Project stage: Other ML18100A1902014-05-22022 May 2014 Enclosure 8 - Structural Integrity Associates, Inc. Report 130415.403, Revision 2, Assessment of Monticello Spent Fuel Canister Closure Plate Welds Based on Welding Video Records Project stage: Other ML18011A1582017-12-22022 December 2017 International HI-STORE Cis (Consolidated Interim Storage Facility) License Application Responses to Safeguards Related Requests for Supplemental Information Project stage: Supplement ML17249A1572018-01-11011 January 2018, 16 January 2018 Package: Vermont Yankee Nuclear Power Station ISFSI Environmental Assessment and Finding of No Significant Impact Related to Issuance of Exemption to Allow a New Loading Pattern and Loading Fuel Cooled for at Least 2 Years Project stage: Request ML18022A1522018-01-16016 January 2018 Enclosure 1: Meeting Attendees (Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay ISFSI License) Project stage: Meeting ML18022A1512018-01-16016 January 2018 Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay Independent Spent Fuel Storage Installation License Project stage: Meeting ML17249A1592018-01-16016 January 2018 Letter to C. C. Chappell Vermont Yankee Nuclear Power Station ISFSI Environmental Assessment and Finding of No Significant Impact Related to Issuance of Exemption to Allow a New Loading Pattern and Loading Fuel Cooled for at Least 2 Years Project stage: Approval ML18022A1532018-01-16016 January 2018 Enclosure 2: Agenda (Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay ISFSI License) Project stage: Meeting ML18022A1542018-01-16016 January 2018 Enclosure 3: Handout-PG&E Presentation on Humboldt Bay ISFSI LRA (Memo to A. Hsia Summary of December 12, 2017, Meeting) Project stage: Meeting ML18018A0192018-01-17017 January 2018 Enclosurequest for Additional Information (Ltr to K. Manzione Application for Holtec International HI-STORM Umax Multipurpose Canister Storage System License Amendment Request No. 3 to Certificate of Compliance No. 1040-Accepted for Review) Project stage: RAI ML18018A0182018-01-17017 January 2018 Letter to K. Manzione Application for Holtec International HI-STORM Umax Multipurpose Canister Storage System License Amendment Request No. 3 to Certificate of Compliance No. 1040 - Accepted for Review Project stage: Other ML18018B2972018-01-19019 January 2018 Federal Registered Notice: Correction of Certificate of Compliance No. 1004, Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 Project stage: Request ML18022A6122018-01-19019 January 2018 Letter to K. Manzione Amendment No. 4 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System-Request for Additional Information Project stage: RAI ML18022A0762018-01-22022 January 2018 Package: Correction to Title of Figure 1-15 in Technical Specifications for Certificate of Compliance 1004 Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 Project stage: Request ML18022A0782018-01-22022 January 2018 Enclosure 1: Revised Title for Figure 1-5 Corrected Technical Specifications for Certificate of Compliance No. 1004 Renewed Amendment No. 11, Revision 1 Enclosure 1 Project stage: Other ML18022A0792018-01-22022 January 2018 Enclosure 2: Revised Title for Figure 1-5 Corrected Technical Specifications for Certificate of Compliance No. 1004 Renewed Amendment No. 13, Revision 1 Project stage: Other ML18022A0772018-01-22022 January 2018 Letter to J. Bondre Correction to Tn Americas LLC Technical Specifications for Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 to Standardized NUHOMS Certificate of Compliance No. 1004 for Spent Fuel Storage Casks Project stage: Other ML18024A2732018-01-24024 January 2018 Letter to D. G. Stoddard U.S. NRC Approval of Virginia Electric and Power Company Request for Withholding Information from Public Disclosure for North Anna Power Station ISFSI (Cac/Epid Nos. 001028/L-2017-RNW-0010 and 000993/L-2017-LNE-0008 Project stage: Withholding Request Acceptance ML18031A4572018-01-31031 January 2018 Submittal Date for Response to NRCs Requests for Additional Information (Rais) for License Amendment Request 1032-4 to HI-STORM FW CoC No. 1032 (CAC No. 001028) Project stage: Request ML17311A4502018-01-31031 January 2018 ISFSI License Renewal Final Environmental Assessment Project stage: Other ML18036A2222018-02-0101 February 2018 International - Transmittal of HI-STORM Umax License Amendment Request No. 3 - Administrative RAI Response Project stage: Request ML17298A1352018-02-0202 February 2018 Safety Evaluation Report (Letter to C. C. Chappell Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Issuance of Exemption (CAC No.: 001028, Docket Nos. 50-271, 72-59, and 72-1014; EPID L-2017-LLE-0005) Project stage: Approval ML17298A1342018-02-0202 February 2018 Letter to C. C. Chappell Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Issuance of Exemption (CAC No.: 001028, Docket Nos. 50-271, 72-59, and 72-1014; EPID L-2017-LLE-0005) Project stage: Approval ML18031A2272018-02-0606 February 2018 Enclosurenewed License SNM-2507 Technical Specifications (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18031A2242018-02-0606 February 2018 Enclosure 1: Preamble-SNM-2507 License Renewal Order (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation) Project stage: Approval ML18031A2252018-02-0606 February 2018 Enclosurenewed License SNM-2507 (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation) Project stage: Approval ML18031A2222018-02-0606 February 2018 Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation (Cac/Epid Nos. 001028/L-2017-RNW-0010 and 000993/L-2017-LNE-0008) Project stage: Approval ML18031A2282018-02-0606 February 2018 Enclosure 2: Safety Evaluation Report (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18031A2312018-02-0808 February 2018 Federal Register Notice - Notice of Issuance for License Renewal (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18053A2222018-02-15015 February 2018 Application for Amendment 1 to the NUHOMS Eos System, Revision O (Docket No. 72-1042) Project stage: Request ML18053A2332018-02-15015 February 2018 Enclosure 4: CoC 1042 Amendment 1 Proposed Technical Specifications, Revision 0 Project stage: Request ML18053A2342018-02-15015 February 2018 Enclosure 6: Proposed Amendment 1, Revision 0 Changes to the NUHOMS Eos System Updated Final Safety Analysis Report, Chapters 1 to 14 Project stage: Request ML18057A2182018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to A. Zaremba Request for Additional Information for Review of Duke Energys Decommissioning Funding Plan Update) Project stage: RAI ML18058A6082018-02-23023 February 2018 HI-2177593, Rev 0, Holtec International & Eddy Lea Energy Alliance (Elea) Underground CISF - Financial Assurance & Project Life Cycle Cost Estimates Project stage: Request ML18057A2172018-02-23023 February 2018 Letter to A. Zaremba Request for Additional Information for Review of Duke Energys Decommissioning Funding Plan Update Project stage: RAI ML18058A0242018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to G. Van Noordennen Request for Additional Information Regarding Zionsolutions, LLCs Decommissioning Funding Plan Update for Zion Independent Spent Fuel Storage Installation) Project stage: RAI ML18058A0562018-02-23023 February 2018 Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.S Decommissioning Funding Plan Update Project stage: RAI ML18058A0572018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.S Decommissioning Funding Plan Update) Project stage: RAI ML18058A6072018-02-23023 February 2018 HI-2177565, Rev 0, Holtec International & Eddy Lea Energy Alliance (Elea) Cis Facility - Decommissioning Cost Estimate and Funding Plan Project stage: Request ML18058A0232018-02-23023 February 2018 Letter to G. Van Noordennen Request for Additional Information Regarding Zionsolutions, LLCs Decommissioning Funding Plan Update for Zion Independent Spent Fuel Storage Installation Project stage: RAI 2018-01-11
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 5, 2019 Mr. Jeffrey D. Isakson Chief Executive Officer/President Interim Storage Partners LLC P.O. Box 1129 Andrews, TX 79714
SUBJECT:
INTERIM STORAGE PARTNERS LLCs LICENSE APPLICATION TO CONSTRUCT AND OPERATE THE WASTE CONTROL SPECIALISTS CONSOLIDATED INTERIM STORAGE FACILITY, ANDREWS COUNTY, TEXAS, DOCKET NO. 72-1050 - FIRST REQUEST FOR ADDITIONAL INFORMATION, PART 4
Dear Mr. Isakson:
By letter dated July 19, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18206A595), as supplemented May 31 and July 31, 2019 (ADAMS Accession Nos. ML19156A038 and ML19217A210), Interim Storage Partners LLC (ISP), a joint venture of Waste Control Specialists LLC (WCS) and Orano CIS LLC (a subsidiary of Orano USA), requested that the U.S. Nuclear Regulatory Commission (NRC) resume all safety and environmental review activities associated with the proposed WCS Consolidated Interim Storage Facility (CISF) license application. ISP requested authorization to store up to 5,000 metric tons of uranium for a period of 40 years in the WCS CISF.
The NRC staff is conducting a detailed technical review of your application and has determined that additional information is necessary to complete its review. The information needed by the NRC staff is discussed in the enclosed requests for additional information (RAI). We request that you provide responses within 30 days from the date of this letter. If you are unable to meet this deadline, please notify NRC staff in writing, within two weeks of receipt of this letter, of your new submittal date and the reasons for the delay.
J. Isakson Please reference Docket No. 72-1050 and CAC/EPID 001028/L-2017-NEW-0002 in future correspondence related to the technical review for this licensing action. If you have any questions, please contact me at (301) 415-0262.
Sincerely,
/RA/
John-Chau Nguyen, Senior Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 72-1050 CAC No. 001028 EPID L-2017-NEW-0002
Enclosure:
1st Round Safety RAIs - Part 4
ML19309E913 OFFICE:
NMSS/DFM NMSS/DFM NMSS/RESS NMSS/RESS NMSS/DFM NAME:
JNguyen WWheatley via e-mail TWertz via e-mail FMiller via e-mail DDoyle via e-mail DATE:
10/25/19 11/1/19 10/28/19 10/29/19 11/4/19
Enclosure First Request for Additional Information, Part 4 Docket No. 72-1050 WCS Consolidated Interim Storage Facility in Andrews County, Texas By letter dated July 19, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18206A595), Interim Storage Partners LLC (ISP), a joint venture of Waste Control Specialists LLC (WCS) and Orano CIS LLC (a subsidiary of Orano USA),
requested that the U.S. Nuclear Regulatory Commission (NRC) resume all safety and environmental review activities associated with the proposed WCS Consolidated Interim Storage Facility (CISF) license application. ISP requested authorization to store up to 5,000 metric tons of uranium for a license term of 40 years in the WCS CISF application.
The requests for additional information (RAI) identify additional information needed by the NRC staff to complete its safety review of the WCS CISF license application. The requested information refers to the specific part of the license application concerning funding. The NRC staff used the guidance in NUREG-1567, Standard Review Plan for Spent Fuel Dry Storage Facilities.
License Application RAI LA-1 Provide an estimated cost of construction (including a breakdown of the various cost components, such as materials, labor, engineering and design, etc.) for the proposed facility and how construction of the proposed facility will be funded (i.e., proposed amounts of debt financing, equity investment, other sources of funding, etc.) which is specific to the proposed facility and its location.
The application lists what a similar facility would cost per an Electric Power Research Institute (EPRI) study; however, the application does not provide information regarding what ISP estimates for the cost of construction. The licensee states, The Electric Power Research Institute estimated cost for construction of the CISF that will be used to store 5,000 MTU is approximately $170 million. Staff notes that the EPRI study is approximately 10 years old, and the application makes no allowance for possible cost variances, inflation or other possible cost increases; therefore, these statements do not provide adequate information to make a reasonable assurance determination with regard to the cost of construction activities.
With regard to funding construction activities, the application states that Orano and Waste Control Specialists will provide initial capitalization of ISP. It also states that [t]he funding for constructing the CISF is expected to be primarily through future contracts for storage of SNF with the DOE or other SNF Title Holder(s). The funding may include a combination of debt financing, equity investments, and net income. These statements do not provide adequate information for staff to make a reasonable assurance determination with regard to the funding of construction activities.
This information is necessary to determine compliance with 10 CFR 72.22(e).
2 RAI LA-2 Provide the estimated operating costs for the proposed facility (including a breakdown of labor, materials, security, etc.) and how ISP intends to fund the operation of the proposed facility using future contracts with SNF title holders which is specific to the proposed facility.
While the application lists what a similar facility would cost per an EPRI study, the application does not provide enough information regarding what ISP estimates the operating costs for the proposed facility will be. The licensee states, The Electric Power Research Institute estimated the operating and labor cost needed to store 5,000 MTU of SNF at an interim consolidated storage facility for 40 years at $394,612,500. Staff notes that the EPRI study is approximately 10 years old, and the application neither makes allowance for possible variances in costs nor accounts for inflation. Therefore, ISP needs to provide the estimated operating costs for a facility at the proposed site.
This information is necessary to determine compliance with 10 CFR 72.22(e).
RAI LA-3 Identify the funding mechanism to be used to provide decommissioning funding assurance.
While the application provides the projected total cost to decommission the facility (separate from the stored material), the application does not provide enough information for NRC staff to determine the type of method that the applicant intends to use for decommissioning funding assurance. The licensee states in the application, Alternatively, ISP may [emphasis added]
use a surety bond combined with a conformity external sinking fund as authorized by 10 CFR 72.30(e)(3). Payments from storage operations would be deposited into the external sinking fund as waste is received. A surety bond would be used to assure the difference in the decommissioning cost estimate and the value of the sinking fund until the sinking fund is fully funded. Therefore, ISP needs to provide more specificity about their plans to fund decommissioning of the proposed facility.
This information is necessary to determine compliance with 10 CFR 72.30(b)(6) and 10 CFR 72.30(e)(3).