Letter Sequence Other |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, ... further results|Supplement]]
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, ... further results|Meeting]]
Results
- Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, ... further results|Approval]]
Other: L-18-006, ISFSI - Site-Specific License Renewal Application, Revision 0, July 2018, L-23-005, Independent Spent Fuel Storage Installation License Renewal Application, Revision 1 (Cac/Epid No. 001028/L-2022-RNW-0007), ML17311A450, ML18018A018, ML18022A077, ML18022A078, ML18022A079, ML18087A056, ML18087A057, ML18087A058, ML18087A059, ML18087A060, ML18087A061, ML18087A062, ML18100A185, ML18100A188, ML18100A190, ML18100A191, ML18100A193, ML18101A024, ML18108A052, ML18131A047, ML18131A048, ML18141A561, ML18141A562, ML18141A563, ML18141A564, ML18141A565, ML18141A567, ML18179A258, ML18179A260, ML18179A266, ML18201A455, ML18205A179, ML18222A351, ML18228A530, ML18228A531, ML18228A532, ML18228A533, ML18234A012, ML18248A121, ML18255A093, ML18255A094, ML18255A096, ML18255A097, ML18255A098, ML18255A101, ML18255A102, ML18324A577, ML18324A594... further results
|
MONTHYEARML19255E7911997-05-31031 May 1997 Enclosure 1 - Ecological Assessment of the Low Level Waste Depository, Andrews County, Tx Project stage: Other ML19255E7952004-10-25025 October 2004 Enclosure 2 - Habitat Characterization and Rare Species Survey for the Proposed Low Level Waste Repository, Andrews County, Tx Project stage: Other ML19337B5182007-03-16016 March 2007 Enclosure 10 - Applicable Sections of LLRW License Project stage: Other ML19255E7982007-03-16016 March 2007 Enclosure 3 - Supplemental Survey to Ecological Assessment of the Low Level Waste Depository, Andrews County, Texas Project stage: Supplement ML19217A2112007-04-30030 April 2007 Enclosure 1 - Report on Mapping of a Trench Through Pedogenic Calcrete (Caliche) Across a Drainage and Possible Lineament, Waste Control Specialists Disposal Site, Andrews County, Tx (Public) Project stage: Other ML19255E8002008-07-0303 July 2008 Enclosure 4 - Environmental Assessment Report Prepared for Application for Renewal of Radioactive Material License R04971 Waste Control Specialists LLC Andrews County, Texas Project stage: Request ML19217A2142008-07-28028 July 2008 Enclosure 4 - Report on Activities to Satisfy Byproduct RML Conditions 41A, 41C, and 43, July 2008 (Public) Project stage: Other ML19217A2132011-02-22022 February 2011 Enclosure 3 - Oag Water Levels: Empirical and Modeled Relationships Between Precipitation and Infiltration, 2011 (Public) Project stage: Other ML18100A1882013-04-11011 April 2013 Enclosure 7 - Procedure 12751-MNGP-QP-9.201, Revision 0, Visual Weld Examination Project stage: Other ML18100A1852013-04-11011 April 2013 Enclosure 6 - Procedure 12751-MNGP-OPS-01, Revision 0, Spent Fuel Cask Welding: 61BT/BTH NUHOMS Canisters Project stage: Other ML18100A1912014-01-30030 January 2014 Enclosure 9 - Structural Integrity Associates, Inc. Report 130415.402, Revision 0, Review of Trivis Inc. Welding Procedures Used for Field Welds on the Transnuclear NUHOMS 61BTH Type 1 & 2 Transportable Canister for BWR Fuel Project stage: Other ML18100A1902014-05-22022 May 2014 Enclosure 8 - Structural Integrity Associates, Inc. Report 130415.403, Revision 2, Assessment of Monticello Spent Fuel Canister Closure Plate Welds Based on Welding Video Records Project stage: Other ML18011A1582017-12-22022 December 2017 International HI-STORE Cis (Consolidated Interim Storage Facility) License Application Responses to Safeguards Related Requests for Supplemental Information Project stage: Supplement ML17249A1572018-01-11011 January 2018, 16 January 2018 Package: Vermont Yankee Nuclear Power Station ISFSI Environmental Assessment and Finding of No Significant Impact Related to Issuance of Exemption to Allow a New Loading Pattern and Loading Fuel Cooled for at Least 2 Years Project stage: Request ML18022A1512018-01-16016 January 2018 Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay Independent Spent Fuel Storage Installation License Project stage: Meeting ML17249A1592018-01-16016 January 2018 Letter to C. C. Chappell Vermont Yankee Nuclear Power Station ISFSI Environmental Assessment and Finding of No Significant Impact Related to Issuance of Exemption to Allow a New Loading Pattern and Loading Fuel Cooled for at Least 2 Years Project stage: Approval ML18022A1532018-01-16016 January 2018 Enclosure 2: Agenda (Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay ISFSI License) Project stage: Meeting ML18022A1522018-01-16016 January 2018 Enclosure 1: Meeting Attendees (Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay ISFSI License) Project stage: Meeting ML18022A1542018-01-16016 January 2018 Enclosure 3: Handout-PG&E Presentation on Humboldt Bay ISFSI LRA (Memo to A. Hsia Summary of December 12, 2017, Meeting) Project stage: Meeting ML18018A0192018-01-17017 January 2018 Enclosurequest for Additional Information (Ltr to K. Manzione Application for Holtec International HI-STORM Umax Multipurpose Canister Storage System License Amendment Request No. 3 to Certificate of Compliance No. 1040-Accepted for Review) Project stage: RAI ML18018A0182018-01-17017 January 2018 Letter to K. Manzione Application for Holtec International HI-STORM Umax Multipurpose Canister Storage System License Amendment Request No. 3 to Certificate of Compliance No. 1040 - Accepted for Review Project stage: Other ML18022A6122018-01-19019 January 2018 Letter to K. Manzione Amendment No. 4 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System-Request for Additional Information Project stage: RAI ML18018B2972018-01-19019 January 2018 Federal Registered Notice: Correction of Certificate of Compliance No. 1004, Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 Project stage: Request ML18022A0782018-01-22022 January 2018 Enclosure 1: Revised Title for Figure 1-5 Corrected Technical Specifications for Certificate of Compliance No. 1004 Renewed Amendment No. 11, Revision 1 Enclosure 1 Project stage: Other ML18022A0762018-01-22022 January 2018 Package: Correction to Title of Figure 1-15 in Technical Specifications for Certificate of Compliance 1004 Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 Project stage: Request ML18022A0792018-01-22022 January 2018 Enclosure 2: Revised Title for Figure 1-5 Corrected Technical Specifications for Certificate of Compliance No. 1004 Renewed Amendment No. 13, Revision 1 Project stage: Other ML18022A0772018-01-22022 January 2018 Letter to J. Bondre Correction to Tn Americas LLC Technical Specifications for Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 to Standardized NUHOMS Certificate of Compliance No. 1004 for Spent Fuel Storage Casks Project stage: Other ML18024A2732018-01-24024 January 2018 Letter to D. G. Stoddard U.S. NRC Approval of Virginia Electric and Power Company Request for Withholding Information from Public Disclosure for North Anna Power Station ISFSI (Cac/Epid Nos. 001028/L-2017-RNW-0010 and 000993/L-2017-LNE-0008 Project stage: Withholding Request Acceptance ML18031A4572018-01-31031 January 2018 Submittal Date for Response to NRCs Requests for Additional Information (Rais) for License Amendment Request 1032-4 to HI-STORM FW CoC No. 1032 (CAC No. 001028) Project stage: Request ML17311A4502018-01-31031 January 2018 ISFSI License Renewal Final Environmental Assessment Project stage: Other ML18036A2222018-02-0101 February 2018 International - Transmittal of HI-STORM Umax License Amendment Request No. 3 - Administrative RAI Response Project stage: Request ML17298A1342018-02-0202 February 2018 Letter to C. C. Chappell Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Issuance of Exemption (CAC No.: 001028, Docket Nos. 50-271, 72-59, and 72-1014; EPID L-2017-LLE-0005) Project stage: Approval ML17298A1352018-02-0202 February 2018 Safety Evaluation Report (Letter to C. C. Chappell Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Issuance of Exemption (CAC No.: 001028, Docket Nos. 50-271, 72-59, and 72-1014; EPID L-2017-LLE-0005) Project stage: Approval ML18031A2222018-02-0606 February 2018 Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation (Cac/Epid Nos. 001028/L-2017-RNW-0010 and 000993/L-2017-LNE-0008) Project stage: Approval ML18031A2242018-02-0606 February 2018 Enclosure 1: Preamble-SNM-2507 License Renewal Order (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation) Project stage: Approval ML18031A2252018-02-0606 February 2018 Enclosurenewed License SNM-2507 (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation) Project stage: Approval ML18031A2272018-02-0606 February 2018 Enclosurenewed License SNM-2507 Technical Specifications (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18031A2282018-02-0606 February 2018 Enclosure 2: Safety Evaluation Report (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18031A2312018-02-0808 February 2018 Federal Register Notice - Notice of Issuance for License Renewal (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18053A2222018-02-15015 February 2018 Application for Amendment 1 to the NUHOMS Eos System, Revision O (Docket No. 72-1042) Project stage: Request ML18053A2342018-02-15015 February 2018 Enclosure 6: Proposed Amendment 1, Revision 0 Changes to the NUHOMS Eos System Updated Final Safety Analysis Report, Chapters 1 to 14 Project stage: Request ML18053A2332018-02-15015 February 2018 Enclosure 4: CoC 1042 Amendment 1 Proposed Technical Specifications, Revision 0 Project stage: Request ML18057A2182018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to A. Zaremba Request for Additional Information for Review of Duke Energys Decommissioning Funding Plan Update) Project stage: RAI ML18058A0242018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to G. Van Noordennen Request for Additional Information Regarding Zionsolutions, LLCs Decommissioning Funding Plan Update for Zion Independent Spent Fuel Storage Installation) Project stage: RAI ML18058A6072018-02-23023 February 2018 HI-2177565, Rev 0, Holtec International & Eddy Lea Energy Alliance (Elea) Cis Facility - Decommissioning Cost Estimate and Funding Plan Project stage: Request ML18058A0562018-02-23023 February 2018 Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.S Decommissioning Funding Plan Update Project stage: RAI ML18058A6082018-02-23023 February 2018 HI-2177593, Rev 0, Holtec International & Eddy Lea Energy Alliance (Elea) Underground CISF - Financial Assurance & Project Life Cycle Cost Estimates Project stage: Request ML18057A2172018-02-23023 February 2018 Letter to A. Zaremba Request for Additional Information for Review of Duke Energys Decommissioning Funding Plan Update Project stage: RAI ML18058A0572018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.S Decommissioning Funding Plan Update) Project stage: RAI ML18058A0232018-02-23023 February 2018 Letter to G. Van Noordennen Request for Additional Information Regarding Zionsolutions, LLCs Decommissioning Funding Plan Update for Zion Independent Spent Fuel Storage Installation Project stage: RAI 2018-01-11
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. Steven D. Wahnschaffe DOE NRC Programs License Manager U.S. Department of Energy Idaho Cleanup Project 1955 Fremont Avenue Idaho Falls, ID 83415
SUBJECT:
RESPONSE TO U.S. DEPARTMENT OF ENERGY REGARDING IDAHO SPENT FUEL FACILITY LICENSE EXPIRATION DATE EXTENSION (CAC/EPID NOS. 001028/L-2019-LRM-0080)
Dear Steven Wahnschaffe:
By letter dated January 19, 2021, the U.S. Department of Energy, Idaho Cleanup Project (DOE-ICP) notified the U.S. Nuclear Regulatory Commission (NRC) of the DOE-ICP planned license extension strategy for the Idaho Spent Fuel Facility (ISFF) License No. SNM-2512 (Agencywide Documents Access and Management System {ADAMS} Accession No. ML21048A151). The NRC staff appreciates the early communication regarding DOE-ICPs expected licensing request for the ISFF, as communicated in your January 19, 2021, letter and the July 16, 2020, pre-application meeting (ADAMS Accession No. ML20230A197).
The ISFF is licensed under NRCs requirements for spent fuel storage, in Title 10 of the Code of Federal Regulations (10 CFR) Part 72, Licensing requirements for the independent storage of spent nuclear fuel, high-level radioactive waste, and reactor-related greater than Class C waste. License No. SNM-2512 was issued on November 30, 2004, for a 20-year period, and is set to expire on November 30, 2024. The ISFF has not been constructed or operated. This is the first 10 CFR Part 72 license for a facility that has not been constructed or operated that is set to expire.
At the time ISFF was licensed, the regulation in 10 CFR 72.42, Duration of license; renewal, allowed initial license terms of up to 20 years. In 2011, the NRC amended § 72.42 to increase the initial license terms and renewal terms from not to exceed 20 years to not to exceed 40 years. Your letter presented an approach to change the current initial license term for the ISFF from 20 years to 40 years via a license amendment, resetting the initial license expiration date to November 30, 2044. Under such an approach, DOE-ICP would submit a license amendment request (LAR) under 10 CFR 72.56, Application for amendment of license.
Changing the initial license term from 20 years to 40 years via a license amendment under the 10 CFR Part 72 regulations appears to be a viable licensing option.
February 11, 2022
S. Wahnschaffe 2
As was discussed in the July 16, 2020, pre-application meeting, renewing the license term an additional 20 years via a license renewal request under the 10 CFR Part 72 regulations also appears to be a viable licensing option. The provisions in the § 72.42 regulation allow licenses to be renewed by the NRC at the expiration of the license term upon application by the licensee for a period not to exceed 40 years.
There are NRC review process similarities for either a license amendment or license renewal, including noticing an opportunity for hearing and conducting an environmental review under the National Environmental Policy Act and 10 CFR Part 51. Under either a license amendment or license renewal approach, the application should be clear regarding the scope of the request and how it impacts the current 20-year licensing bases. For example, a LAR should be clear in explaining where the current 20-year licensing bases remain unchanged versus where there is new or updated environmental information, technical information, or safety analysis that supports the LAR. A clear application scope, particularly in the case of a LAR, is important for the NRC staffs technical and environmental reviews and for the opportunity for hearing that will be provided regarding the proposed licensing action. The NRC staffs review of either a LAR or a license renewal application will include a technical review to determine if the materials performance of any existing structures, systems, and components and the spent fuel contents is adequately addressed for an additional 20 years. The NRC staff expects that the NRC review cost would be similar between a LAR or license renewal application.
Finally, the NRC staff encourages DOE-ICP to carefully consider the timing of its submittal.
Under the NRC staffs current workload prioritization, the review of either a LAR or a license renewal application for the ISFF would be prioritized as a routine licensing activity and would be subject to the 10 CFR Part 72 review metric of three years. Per 10 CFR 72.54, Expiration and termination of licenses and decommissioning of sites and separate buildings or outdoor areas, each license expires at the end of the day on the license expiration date except when a licensee has filed an application for renewal pursuant to 10 CFR 72.42 not less than two years before the expiration of the existing license. Specifically, the regulation in 10 CFR 72.42(c) provides timely renewal protection to licensees that submit sufficient license renewal applications at least two years before the expiration of the existing license. This timely renewal protection only applies to license renewal applications submitted under 10 CFR 72.42.
There is no similar protection under either the timely renewal provisions in NRC regulations or the Administrative Procedure Act, 5 U.S.C. § 558(c), for a LAR submitted under 10 CFR 72.56.
Should DOE-ICP seek to avoid the expiration of the license, DOE-ICP should consider the need for any exemptions associated with either of the licensing approaches described above (i.e., so that the license will not expire if the NRC review of the LAR continues after the current expiration date, or if DOE-ICP instead submits a license renewal application after the 2-year timely renewal date of November 30, 2022). The NRC staff would consider the criteria in 10 CFR 72.7, Specific exemptions, in determining whether to approve any requested exemption.
S. Wahnschaffe 3
Please continue to keep the NRC staff apprised of your licensing plans and schedule as you move forward. The NRC staff encourages pre-application discussions to ensure a mutual understanding of DOE-ICPs planned path forward and the associated regulatory implications.
Please reference Docket No. 72-25 and CAC/EPID Nos. 001028/L-2019-LRM-0080 in future correspondence related to this request. If you have any questions regarding this matter, please contact me at 301-287-9104 or Kristina Banovac of my staff at 301-415-7116 or Kristina.Banovac@nrc.gov.
Sincerely, Shana R. Helton, Director Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 72-25 License No. SNM-2512 CAC/EPID Nos. 001028/L-2019-LRM-0080 cc: Service List Signed by Helton, Shana on 02/11/22
S. Wahnschaffe 4
SUBJECT:
RESPONSE TO U.S. DEPARTMENT OF ENERGY REGARDING IDAHO SPENT FUEL FACILITY LICENSE EXPIRATION DATE EXTENSION (CAC/EPID NOS. 001028/L-2019-LRM-0080) DOCUMENT DATE:
DISTRIBUTION:
NMSS/DFM r/f NMSS_DFM_STLB Distribution NMSS_DFM_MSB Distribution CRegan, NMSS GMiller, NMSS JWeil, NMSS TTerry, NMSS HGonzalez, NMSS AMoreno, OCA LBrookhart, RIV ESimpson, RIV GWarnick, RIV ADAMS Accession Number: ML21348A050 OFFICE NMSS/DFM/STLB NMSS/DFM/STLB NMSS/DFM/MSB NMSS/DFM/STLB NAME KBanovac WWheatley TBoyce YDiaz-Sanabria DATE 12/14/2021 12/14/2021 12/14/2021 01/13/2022 OFFICE OGC NMSS/DFM NAME ACoggins SHelton DATE 02/03/2022 02/11/2022 OFFICIAL RECORD COPY February 11, 2022
cc:
Mr. Steven Ahrendts DOE NRC Licensed Facility Director U.S. Department of Energy Idaho Cleanup Project 1955 Fremont Ave., MS-1222 Idaho Falls, ID 83415 Mr. Steven Wahnschaffe DOE NRC Programs License Manager U.S. Department of Energy Idaho Cleanup Project 1955 Fremont Ave., MS-1222 Idaho Falls, ID 83415 Mr. David Bland Program Manager for NRC Programs Spectra Tech Inc.
1955 Fremont Ave.
Idaho Falls, ID 83401 Mr. John Scaglione Business Manager for NRC Programs Spectra Tech Inc.
132 Jefferson Court Oak Ridge, TN 37830 Mr. David R. Einan U.S. EPA Region 10 Hanford/INL Project Office 825 Jadwin Ave., Suite 210 Richland, WA 99352 The Honorable Blaine Edmo Chairman, Fort Hall Business Council Shoshone-Bannock Tribes P. O. Box 306 Fort Hall, ID 83203 Ms. Talia Martin Director, Tribal DOE Program Shoshone-Bannock Tribes P.O. Box 306 Fort Hall, ID 83203 Mr. John Tanner Coalition 21 2175 Tasman Ave Idaho Falls, ID 83404 Snake River Alliance Beatrice Brailsford Nuclear Program Director PO Box 1731 Boise, ID 83701 Mr. Mark Clough INL Oversight Coordinator DEQ State Office 1410 N. Hilton Boise, ID 83706 Chairman INL Committee Idaho Falls Chamber of Commerce 365 River Pkwy Idaho Falls, ID 83402 Mr. Chuck Broscious Environmental Defense Institute P.O. Box 220 Troy, ID 83871-0220 Mr. Bruce LaRule State of Idaho INL Oversight Program 900 N. Skyline Drive, Suite C Idaho Falls, ID 83402 Mr. Herb Bohrer Chair, Citizens Advisory Board c/o Ms. Jordan Davies North Wind 1425 Higham Street Idaho Falls, ID 83402 Chairman INL EM Site Specific Advisory Board c/o Lori MacNamara North Wind Group 1425 Higham St.
Idaho Falls, ID 83402 NRC Liaison State of Idaho INL Oversight Program 900 N. Skyline Drive, Suite C Idaho Falls, ID 83402
Ltr ML21348A050 OFFICE NMSS/DFM/STLB NMSS/DFM/STLB NMSS/DFM/MSB NMSS/DFM/CTCFB NAME KBanovac WWheatley TBoyce YDiaz-Sanabria DATE Dec 14, 2021 Dec 14, 2021 Dec 14, 2021 Jan 13, 2022 OFFICE OGC/GCRPS
/HLWFCNS/NLO NMSS/DFM/STLB NMSS/DFM NAME ACoggins KRoach for KBanovac SHelton DATE Feb 3, 2022 Feb 3, 2022 Feb 11, 2022