International, Schedule for Responses to HI-STORM FW Amd. 7 Requests for Supplemental Information
ML21251A550
Person / Time
Site: 07201032
Issue date: 09/08/2021
From: Elisio D
Holtec
To: Yen-Ju Chen
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
5018090, CAC 001028, EPID L-2021-LLA-0053
Download: ML21251A550 (2)


Text

Holtec Technology Campus, One Holtec Blvd, Camden, NJ 08104 Telephone (856) 797-0900 Fax (856) 797-0909 September 8, 2021 Yen-Ju Chen, Sr. Project Manager Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 72-1032, Certificate of Compliance (CoC) No. 1032 CAC No. 001028, EPID No. L-2021-LLA-0053

Subject:

Schedule for Responses to HI-STORM FW Amd. 7 Requests for Supplemental Information

Reference:

[1] Acceptance Review of Request for Amendment No. 7 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System (Docket No. 72-1032, CAC No. 001028, EPID: L-2021-LLA-0053) Request for Supplemental Information, letter from Y. Chen (NRC) to D. Elisio (Holtec) dated August 25, 2021.

Dear Ms. Chen:

By letter dated August 25, 2021 [1], the NRC staff requested that additional technical information be provided in order for the staff to begin the technical review of Amendment 7 for the HI-STORM FW Certificate of Compliance No. 1032 and requested that Holtec provide this information by September 25, 2021.

In order to provide quality responses to the staffs questions and to ensure adequate time to complete any additional analyses that may need to be completed to support these responses, Holtec plans to submit responses by October 15, 2021.

Holtec requests that NRC review of this Amendment 7 proceed according to the standard approximately 2-year review cycle such that the amendment will be effective for clients starting in the summer of 2023.

If you have any questions, please contact me at 856-797-0900 ext. 3326.

Document ID 5018090 Page 1 of 1

Holtec Technology Campus, One Holtec Blvd, Camden, NJ 08104 Telephone (856) 797-0900 Fax (856) 797-0909 Sincerely, Denise Elisio Licensing Engineer, Holtec International cc:(via email)

John McKirgan (USNRC)

Kimberly Manzione (Holtec)

Document ID 5018090 Page 2 of 2