MONTHYEARML19255E7911997-05-31031 May 1997 Enclosure 1 - Ecological Assessment of the Low Level Waste Depository, Andrews County, Tx Project stage: Other ML19255E7952004-10-25025 October 2004 Enclosure 2 - Habitat Characterization and Rare Species Survey for the Proposed Low Level Waste Repository, Andrews County, Tx Project stage: Other ML19255E7982007-03-16016 March 2007 Enclosure 3 - Supplemental Survey to Ecological Assessment of the Low Level Waste Depository, Andrews County, Texas Project stage: Supplement ML19337B5182007-03-16016 March 2007 Enclosure 10 - Applicable Sections of LLRW License Project stage: Other ML19217A2112007-04-30030 April 2007 Enclosure 1 - Report on Mapping of a Trench Through Pedogenic Calcrete (Caliche) Across a Drainage and Possible Lineament, Waste Control Specialists Disposal Site, Andrews County, Tx (Public) Project stage: Other ML19255E8002008-07-0303 July 2008 Enclosure 4 - Environmental Assessment Report Prepared for Application for Renewal of Radioactive Material License R04971 Waste Control Specialists LLC Andrews County, Texas Project stage: Request ML19217A2142008-07-28028 July 2008 Enclosure 4 - Report on Activities to Satisfy Byproduct RML Conditions 41A, 41C, and 43, July 2008 (Public) Project stage: Other ML19217A2132011-02-22022 February 2011 Enclosure 3 - Oag Water Levels: Empirical and Modeled Relationships Between Precipitation and Infiltration, 2011 (Public) Project stage: Other ML18100A1882013-04-11011 April 2013 Enclosure 7 - Procedure 12751-MNGP-QP-9.201, Revision 0, Visual Weld Examination Project stage: Other ML18100A1852013-04-11011 April 2013 Enclosure 6 - Procedure 12751-MNGP-OPS-01, Revision 0, Spent Fuel Cask Welding: 61BT/BTH NUHOMS Canisters Project stage: Other ML18100A1912014-01-30030 January 2014 Enclosure 9 - Structural Integrity Associates, Inc. Report 130415.402, Revision 0, Review of Trivis Inc. Welding Procedures Used for Field Welds on the Transnuclear NUHOMS 61BTH Type 1 & 2 Transportable Canister for BWR Fuel Project stage: Other ML18100A1902014-05-22022 May 2014 Enclosure 8 - Structural Integrity Associates, Inc. Report 130415.403, Revision 2, Assessment of Monticello Spent Fuel Canister Closure Plate Welds Based on Welding Video Records Project stage: Other ML18011A1582017-12-22022 December 2017 International HI-STORE Cis (Consolidated Interim Storage Facility) License Application Responses to Safeguards Related Requests for Supplemental Information Project stage: Supplement ML17249A1572018-01-11011 January 2018, 16 January 2018 Package: Vermont Yankee Nuclear Power Station ISFSI Environmental Assessment and Finding of No Significant Impact Related to Issuance of Exemption to Allow a New Loading Pattern and Loading Fuel Cooled for at Least 2 Years Project stage: Request ML17249A1592018-01-16016 January 2018 Letter to C. C. Chappell Vermont Yankee Nuclear Power Station ISFSI Environmental Assessment and Finding of No Significant Impact Related to Issuance of Exemption to Allow a New Loading Pattern and Loading Fuel Cooled for at Least 2 Years Project stage: Approval ML18022A1512018-01-16016 January 2018 Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay Independent Spent Fuel Storage Installation License Project stage: Meeting ML18022A1542018-01-16016 January 2018 Enclosure 3: Handout-PG&E Presentation on Humboldt Bay ISFSI LRA (Memo to A. Hsia Summary of December 12, 2017, Meeting) Project stage: Meeting ML18022A1532018-01-16016 January 2018 Enclosure 2: Agenda (Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay ISFSI License) Project stage: Meeting ML18022A1522018-01-16016 January 2018 Enclosure 1: Meeting Attendees (Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay ISFSI License) Project stage: Meeting ML18018A0192018-01-17017 January 2018 Enclosurequest for Additional Information (Ltr to K. Manzione Application for Holtec International HI-STORM Umax Multipurpose Canister Storage System License Amendment Request No. 3 to Certificate of Compliance No. 1040-Accepted for Review) Project stage: RAI ML18018A0182018-01-17017 January 2018 Letter to K. Manzione Application for Holtec International HI-STORM Umax Multipurpose Canister Storage System License Amendment Request No. 3 to Certificate of Compliance No. 1040 - Accepted for Review Project stage: Other ML18022A6122018-01-19019 January 2018 Letter to K. Manzione Amendment No. 4 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System-Request for Additional Information Project stage: RAI ML18018B2972018-01-19019 January 2018 Federal Registered Notice: Correction of Certificate of Compliance No. 1004, Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 Project stage: Request ML18022A0782018-01-22022 January 2018 Enclosure 1: Revised Title for Figure 1-5 Corrected Technical Specifications for Certificate of Compliance No. 1004 Renewed Amendment No. 11, Revision 1 Enclosure 1 Project stage: Other ML18022A0762018-01-22022 January 2018 Package: Correction to Title of Figure 1-15 in Technical Specifications for Certificate of Compliance 1004 Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 Project stage: Request ML18022A0792018-01-22022 January 2018 Enclosure 2: Revised Title for Figure 1-5 Corrected Technical Specifications for Certificate of Compliance No. 1004 Renewed Amendment No. 13, Revision 1 Project stage: Other ML18022A0772018-01-22022 January 2018 Letter to J. Bondre Correction to Tn Americas LLC Technical Specifications for Renewed Amendments No. 11, Revision 1 and No. 13, Revision 1 to Standardized NUHOMS Certificate of Compliance No. 1004 for Spent Fuel Storage Casks Project stage: Other ML18024A2732018-01-24024 January 2018 Letter to D. G. Stoddard U.S. NRC Approval of Virginia Electric and Power Company Request for Withholding Information from Public Disclosure for North Anna Power Station ISFSI (Cac/Epid Nos. 001028/L-2017-RNW-0010 and 000993/L-2017-LNE-0008 Project stage: Withholding Request Acceptance ML18031A4572018-01-31031 January 2018 Submittal Date for Response to NRCs Requests for Additional Information (Rais) for License Amendment Request 1032-4 to HI-STORM FW CoC No. 1032 (CAC No. 001028) Project stage: Request ML17311A4502018-01-31031 January 2018 ISFSI License Renewal Final Environmental Assessment Project stage: Other ML18036A2222018-02-0101 February 2018 International - Transmittal of HI-STORM Umax License Amendment Request No. 3 - Administrative RAI Response Project stage: Request ML17298A1342018-02-0202 February 2018 Letter to C. C. Chappell Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Issuance of Exemption (CAC No.: 001028, Docket Nos. 50-271, 72-59, and 72-1014; EPID L-2017-LLE-0005) Project stage: Approval ML17298A1352018-02-0202 February 2018 Safety Evaluation Report (Letter to C. C. Chappell Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Issuance of Exemption (CAC No.: 001028, Docket Nos. 50-271, 72-59, and 72-1014; EPID L-2017-LLE-0005) Project stage: Approval ML18031A2252018-02-0606 February 2018 Enclosurenewed License SNM-2507 (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation) Project stage: Approval ML18031A2242018-02-0606 February 2018 Enclosure 1: Preamble-SNM-2507 License Renewal Order (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation) Project stage: Approval ML18031A2222018-02-0606 February 2018 Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station Independent Spent Fuel Storage Installation (Cac/Epid Nos. 001028/L-2017-RNW-0010 and 000993/L-2017-LNE-0008) Project stage: Approval ML18031A2272018-02-0606 February 2018 Enclosurenewed License SNM-2507 Technical Specifications (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18031A2282018-02-0606 February 2018 Enclosure 2: Safety Evaluation Report (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18031A2312018-02-0808 February 2018 Federal Register Notice - Notice of Issuance for License Renewal (Letter to D. G. Stoddard Issuance of Renewed Materials License No. SNM-2507 for the North Anna Power Station ISFSI) Project stage: Approval ML18053A2222018-02-15015 February 2018 Application for Amendment 1 to the NUHOMS Eos System, Revision O (Docket No. 72-1042) Project stage: Request ML18053A2342018-02-15015 February 2018 Enclosure 6: Proposed Amendment 1, Revision 0 Changes to the NUHOMS Eos System Updated Final Safety Analysis Report, Chapters 1 to 14 Project stage: Request ML18053A2332018-02-15015 February 2018 Enclosure 4: CoC 1042 Amendment 1 Proposed Technical Specifications, Revision 0 Project stage: Request ML18058A6082018-02-23023 February 2018 HI-2177593, Rev 0, Holtec International & Eddy Lea Energy Alliance (Elea) Underground CISF - Financial Assurance & Project Life Cycle Cost Estimates Project stage: Request ML18057A2182018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to A. Zaremba Request for Additional Information for Review of Duke Energys Decommissioning Funding Plan Update) Project stage: RAI ML18057A2172018-02-23023 February 2018 Letter to A. Zaremba Request for Additional Information for Review of Duke Energys Decommissioning Funding Plan Update Project stage: RAI ML18058A0572018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.S Decommissioning Funding Plan Update) Project stage: RAI ML18058A6072018-02-23023 February 2018 HI-2177565, Rev 0, Holtec International & Eddy Lea Energy Alliance (Elea) Cis Facility - Decommissioning Cost Estimate and Funding Plan Project stage: Request ML18058A0562018-02-23023 February 2018 Letter to J. Giddens Request for Additional Information Regarding Entergy Operations, Inc.S Decommissioning Funding Plan Update Project stage: RAI ML18058A0242018-02-23023 February 2018 Enclosurequest for Additional Information (Letter to G. Van Noordennen Request for Additional Information Regarding Zionsolutions, LLCs Decommissioning Funding Plan Update for Zion Independent Spent Fuel Storage Installation) Project stage: RAI ML18058A0232018-02-23023 February 2018 Letter to G. Van Noordennen Request for Additional Information Regarding Zionsolutions, LLCs Decommissioning Funding Plan Update for Zion Independent Spent Fuel Storage Installation Project stage: RAI 2018-01-11
[Table View] |
Text
From:
Cox, Lee To:
Chen, Yen-Ju
Subject:
[External_Sender] RE: [External] DRAFT ENVIRONMENTAL ASSESSMENT: EXEMPTION REQUEST FOR MCGUIRE NUCLEAR STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATION Date:
Tuesday, June 23, 2020 7:38:03 AM Hi Yen-Ju:
The benefit of saving dose to personnel, not creating additional contaminated waste, reducing fuel handling and heavy load lifting outweigh the risks of meeting the current TS. Agree with the exemption.
W. Lee Cox, III Chief Division of Health Service Regulation, Radiation Protection Section North Carolina Department of Health and Human Services
Help protect your family and neighbors from COVID-19.
Know the 3 Ws. Wear. Wait. Wash.
- StayStrongNC and get the latest at nc.gov/covid19.
Office: 919-814-2252 Mobile: 919-413-2506 lee.cox@dhhs.nc.gov
5505 Creedmoor Rd., Suite 100, Raleigh, NC 27612 1645 Mail Service Center 27699-1645
Twitter l Facebook l Instagram l YouTube l LinkedIn
Disclosures To ensure the required disclosure statement appears at the bottom of all DHHS emails, do not add any disclosures to your signature in Outlook. Even though you cannot see it in your draft message, Outlook automatically adds the disclosure below to all DHHS emails once you hit send.
From: Chen, Yen-Ju <Yen-Ju.Chen@nrc.gov>
Sent: Thursday, June 18, 2020 3:38 PM To: Cox, Lee <lee.cox@dhhs.nc.gov>
Subject:
[External] DRAFT ENVIRONMENTAL ASSESSMENT: EXEMPTION REQUEST FOR MCGUIRE NUCLEAR STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATION
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to report.spam@nc.gov
Dear Mr. Cox:
The U.S. Nuclear Regulatory Commission (NRC) received, by a letter dated September 12, 2019, and supplemented on February 3 and June 15, 2020, a request for an exemption, from Duke Energy
Carolinas, LLC (Duke Energy) in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 72.7, from the requirements of 10 CFR 72.212(b)(3), 72.212(b)(5)(i), and 72.212(b)(11) that requires compliance with the terms, conditions, and specifications of the Certificate of Compliance (CoC) No.
72-1031 for spent nuclear fuel stored at the McGuire Nuclear Station independent spent fuel storage installation (ISFSI). The CoC is the NRC-approved design for each dry storage cask system used for spent fuel storage.
This exemption would allow Duke Energy to maintain MAGNATOR Cask 0FCTKN045 at its McGuire Nuclear Station ISFSI in a storage condition where the helium density is above the range specified in CoC No. 1031, Amendment No. 7, Technical Specification 3.1.1. The exemption request is publicly available from the NRCs Agencywide Documents Access and Management System (ADAMS),
accessible at: http://www.nrc.gov/reading-rm/adams.html. The ADAMS Accession Number for the exemption request and supplemental information are ML19270E395, ML20052D934, and ML20168A426, respectively.
As established in Title 10 Code of Federal Regulations Part 51, the NRC regulation that implements the National Environmental Policy Act of 1969, as amended, the NRC is preparing an environmental assessment (EA) for the proposed action. The purpose of the EA is to assess potential environmental impacts that may significantly affect the human environment. No significant change in the types or amounts of any effluent released, no significant increase in individual or cumulative radiation exposures, and no significant increase in the potential for or consequences of radiological accidents will occur as the result of the exemption request. For these reasons, the NRC concludes in the draft EA that approval of the exemption request will not significantly affect the quality of the human environment.
The NRC is providing your office with the opportunity to review the attached draft EA and comment on environmental issues prior to public issuance of the EA. We request that the distribution and use of the draft EA be limited only to those staff involved in the review and comment process. We further request that your office provide any comments to the NRC staff by July 20, 2020. You can provide your comments to me, via email, if that is convenient for you. We will consider your timely comments and will revise the EA, as appropriate, before its final issuance.
If you have any questions, please contact me at Yen-Ju.Chen@nrc.gov or by telephone at 3014151018.
Yen-Ju Chen Sr. Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Email correspondence to and from this address is subject to the North Carolina Public Records Law and may be disclosed to third parties by an authorized State official. Unauthorized disclosure of juvenile, health, legally privileged, or otherwise confidential information, including confidential information relating to an ongoing State procurement effort, is prohibited by law. If you have received this email in
error, please notify the sender immediately and delete all records of this email.