UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Christopher OMullane Licensing Engineer Holtec International Holtec Technology Campus 1 Holtec Blvd.

Camden, NJ 08104

SUBJECT:

APPROVAL OF HOLTEC INTERNATIONAL REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE OF THE APPLICATION FOR HOLTEC HI-STORM FLOOD/WIND MULTIPURPOSE CANISTER STORAGE SYSTEM, AMENDMENT NO. 6 (DOCKET NO. 72-1032)

Dear Christopher OMullane:

During the review of Amendment No. 6 of the Model No. Holtec International Storage Module (HI-STORM) Flood and Wind (FW) Multipurpose Canister (MPC) Storage System (hereafter HI-STORM FW system or HI-STORM FW), Holtec International submitted affidavits dated October 2, 2019 [Agencywide Documents Access and Management System (ADAMS)

Accession No. ML19282C380], June 30, 2020 (ML20182A870), December 21, 2020 (ML20356A336), August 2, 2021 (ML21214A137), and November 29, 2021 (ML21333A143),

requesting that the information contained in the documents included in the table below be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 2, Section 2.390.

Affidavits Date Information Requested to be Withheld by Holtec International October 2, 2019Attachments to Holtecs Submittal Letter ID 5018071: 6) Proposed Proprietary Drawing (proprietary); 7) Structural Calculation Package (Proprietary); and

8) Shielding Calculation Package (Proprietary)

June 30, 2020Attachments to Holtecs Submittal Letter ID 5018078: 5) HI-STORM FW FSAR Proposed Revision 7.A (Proprietary); and 7) Holtec Report HI-2200647R0 (Proprietary)

December 21, 2020Attachments to Holtecs Submittal Letter ID 5018081: 3) HI-STORM FW FSAR Proposed Revision 7.B (Proprietary); 5) Holtec Drawing 11695, Proposed Rev. 1 (Proprietary); 6) Holtec Report HI-2188720R1 (Proprietary); and 7) Holtec Report HI-2200647R1 (Proprietary)

August 2, 2021Attachments to Holtecs Submittal Letter ID 5018089: 3) Holtec Licensing Drawing 11695, HI-STORM FW Version E Anchored Cask, Revision 1 (Proprietary); and 4) Holtec Report HI-2200647, Analysis of the Postulated Drop and Missile Impact Events for the Loaded HI-STORM FW Version E Cask and the Loaded HI-TRAC VW System, Revision 3 (Proprietary)

November 29, 2021Attachment 2 to Holtec Submittal Letter 5018092, HI-STORM FW FSAR Proposed Revision 7.D Revised (Proprietary)November 3, 2022 C. OMullane 2 In general, the affidavit notes that the information submitted should be considered exempt from mandatory public disclosure for the following reasons:

The information discloses descriptions of the design and analysis of the Model No.

HI-STORM FW system, where prevention of its use by competitors of Holtec International, without license from Holtec International, constitutes a competitive economic advantage over other companies.

The information, if used by a competitor, would reduce their expenditure of resources or improve their competitive position in the design, manufacturing, shipment, installation, and assurance of quality or licensing of a similar product.

The information includes certain portions of the safety analysis report related to the design of the Model No. HI-STORM FW system, which are owned and are held in confidence by Holtec International.

Therefore, the version(s) of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified of the date of public disclosure in advance which will be a reasonable time thereafter.

If you have any questions regarding this matter, you may contact me at Norma.GarciaSantos@nrc.gov.

Sincerely, Norma García Santos, Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 72-1032 EPID L-2019-LLA-0231 Signed by Garcia Santos, Norma on 11/03/22