IR 05000424/1986010

From kanterella
Jump to navigation Jump to search
Insp Repts 50-424/86-10 & 50-425/86-05 on 860210-14.No Violations or Deviations Noted.Major Areas Inspected:Pipe Support Base Plate Designs Using Concrete Expansion Anchors & Seismic Analysis for as-built Piping Sys
ML20138C597
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 03/19/1986
From: Blake J, Vias S
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20138C579 List:
References
50-424-86-10, 50-425-86-05, 50-425-86-5, IEB-79-02, IEB-79-14, IEB-79-2, NUDOCS 8604020539
Download: ML20138C597 (5)


Text

?

'

.

ONITED STATES

[AS Mouq'o,

NUCLEAR REGULATORY COMMISSION l

^

J REGION li h 101 MARIETTA STREET. * ,,'c ATLANTA. GEORGI A 30323

. %" &

.....

Report Nos.: 50-424/86-10 and 50-425/86-05 Licensee: . Georgia Power Company P. O. Box 4545 Atlanta, GA 30302 Docket Nos.: 50-424 and 50-425 License Nos.: CPPR-108 and CPPR-109 Facility Name: Vogtle ,

Inspection .. e d- abruary 10-14, 1986 Inspecto : ~

'

/ 3 1 66 S s Da e Signed Appro db bw 3 /f 6 J/ p'Alake, Section Chief Date Signed ngineering Branch s

/D(vision of Reactor Safety SUMMARY Scope: This routine unannounced inspection involved 38 inspector-hours on site in the areas of pipe support baseplate designs using concrete expansion anchors (IEB 79-02) and seismic analysis for as-built safety-related piping systems (IEB 79-14).

Results: No violations or deviations were identifie PDR ADOCK O

'

.

REPORT DETAILS Persons Contacted Licensee Employees

  • D.O. Foster, Vice President Project Support
  • C.W. Hayes, Quality Assurance (QA) Manager
  • E.D. Groover, QA. Site Manager - Construction
  • G.A. McCauley, Project Compliance Coordinator
  • B.C. Harbin, Mechanical Quality Control (QC)

Other licensee employees contacted included . construction craftsmen, engineers, technicians, security office members and office personne Other Organizations

  • B. L. Edwards, Construction Manager - Pullman Power Products (PPP)
  • J. E. Miller, QA/QC Manager - PPP
  • T. M. Sinclair, Assistant Construction Manager - PPP

'J. Rudd, QA, Bechtel (BPC)

NRC Resident Inspectors

  • H. Livermore - Senior Resident Inspector - Construction
  • J. Rogge - Senior Resident Inspector - Operations
  • Attended exit interview Exit Interview The inspection scope and findings were summarized on February 14, 1986, with those persons indicated in paragraph 1. above. The inspector described the areas inspected and discussed in detail the inspection finding No dissenting comments were received from the license (0 pen) Unresolved Item 50-424/86-10-01 and 50-425/86-05-01, " Traceability of Components for Mechanical Shock Arrestors", Paragraph 5. (0 pen) Unresolved Item 50-424/86-10-02. and 50-425/86-05-02, " Control of Process Sheets Used for QC Signatures", Paragraph 5. (0 pen) Unresolved Item 50-424/86-10-03 and 50-425/86-05-03, " Handling, Storage and Preservation of Materials for Pipe Supports", Para-graph The licensee did not identify as proprietary any of the material provided to or reviewed by the inspector during this inspectio . . _ - - - ~ _ - - . . . - - _ _ . - . - _. __ -

j .o-

.

.

!

l2

!

i

r J Licensee Action on Previous Enforcement Matters l

'

This subject was not addressed in the inspectio !

i Unresolved Items Unresolved items are matters about which more information is required to determine whether they are acceptable or may involve violations or devia-i tions. Three new unresolved items identified during this inspection are j discussed in paragraph i Safety-Related Pipe Supports and Restraint Systems (50090) Unit 1 i Observation of Work-and Work Activities i

!

i (1) The inspector observed . inspection of four mechanical snubbers prior to installation and torquing of bolts to the support plates.

{

The snubbers were checked for smoothness of shaft travel by j simulating normal operation by pulling and pushing the snubber shaft; the inspector also simulated unit activation by sudden

,

movemen It was also noted that there was no evidence of deterioration or l noticeable corrosion and that the support plates, and connecting Joints are not bent, deformed .or loos i

Hanger Number System Size i V1-1206-005-H004 Containment Spray PSA-1 VI-1217-105-H002 Auxiliary Component PSA-1 l 1 Cooling Water V1-1301-129-H002 Main Steam PSA-1 V1-1208-144-H010 Chemical and Volumo 'PSA-h

. Control i

'

During inspection for traceability by heat numbers, of the j snubbers, pins, studs, bolts and nuts, the inspector noted tnat i some of the parts did not have any identification numbers, while

! others had air scribed numbers visibl i l Pending review and evaluation by the licensee and further NRC j- inspection, this matter was identified as Unresolved Items

! 50-424/86-10-01 and 50-425/86-05-01, " Traceability of Components i for Mechanical Shock Arrestors."

e (2) During the inspection of the torquing of bolts for the support

'

plates to the snubbers, the inspector noted that the process j sheets that were to be used for QC signoffs differed from the t process sheets as referenced in PPP Procedure IX-32 " Installation

!

!

. . .. -

. - - - .-.- - - . _ - . - - - _ _ _

..

.

of Mechanical Shock Arrestors," Section This difference prompted PPP to issue PCN-#3 to IX-32 to include the process sheets that were an abbreviated version of the prucess sheets in the procedure. The inspector reviewed four other procedures in the pipe support area and compared the process sheets - in the various procedures, with the process sheets issued by the Hanger Group for use by the QC inspectors in the fiel The inspector did not find any differences in those four procedures. Pending review and evaluation of procedures that require process sheets for-QC signatures by the licensee and further NRC inspection, this matter was identified as Unresolved Items 50-424/86-10-02 and 50-425/86-05-02, " Control of Process Sheets Used for QC signa-tures."

(3) The inspector selected the following sample of four hangers /

supports in the area of dynamic pipe supports and component support structures that had been QC final inspected and final QA reviewe Documentation for the installation, inspection and design were reviewed; the hangers were reinspected with the assistance of QA/QC inspectors; and the results discussed with the QA/QC inspectors to determine the effectiveness of the hanger progra Hanger Number System Type V1-1213-005-H013 Spent Fuel Cooling #12 Strut V1-1213-006-H005 Spent Fuel Cooling #12 Spring V1-1213-003-H001 Spent Fuel Cooling #12 Spring V1-1302-031-H009 Auxiliary Feedwater #1.5 Strut The above hangers were reinspected against their detail drawings for configuration, identification, fastener / anchor installation, clearances, member size, welds and damage / protection. In general, the hangers were installed in accordance with design document No discrepancies were identified in the above Hangers / Support b. Review of QC Documentation and Records The inspector selected the following sample of four hanger / support QC documentation packages in the area of dynamic pipe support and component support structures that had been QC final inspected and final QA reviewe c:

,

.-

Hanger-N Comment /01screpancy V1-1213-006-H007 - None VI-1204-025-H007 - None'

VI-1213-006-H006 - Missing QA review signature on Drillco Maxi-Bolt Installation Sht 2 of 2 V1-1213-003-H001 - None The inspector has noted~that the above discrepancy, that was identi-fied during this inspection, has not been identified in previous inspection report In that this area will continue to be reviewed during future inspections, no action by the inspector other than noting the discrepancy to the licensee will be taken at this tim c. Construction Progress (Unit 1)

The inspector conducted a general inspection of the control and Auxiliary Building to observe construction progress and activities, such as welding, coatings, material handling and control, housekeeping-and storage. During the inspection of Restraint V1-1302-031-H009, in the Control Building area A/2E, erected and QC inspected in September 1985, it was noted that the restraints structural steel and welds had approximately 1/16" of oxidation covering them. Also, that prefab -

ricated pipe support structures were found to be left in an area not considered to be a temporary storage area for such materials. By the end of this inspection, this inspector was unable to determine whether adequate measures were in place for the protection of materials and equipment and, if measures were in place, why they were not followe Pending review and evaluation-of procedures that cover this area by the licensee and further NRC inspection, this matter was identified as Unresolved Items 50-424/86-10-03 and 50-425/86-05-03, " Handling, Storage and Preservation of Materials for Pipe Supports."