ML20137X381

From kanterella
Jump to navigation Jump to search
Integrated Insp Repts 50-424/97-01 & 50-425/97-01 on 970202- 0315.Violations Noted.Major Areas Inspected:Operations, Maint,Engineering & Plant Support
ML20137X381
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 04/14/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20137X373 List:
References
50-424-97-01, 50-424-97-1, 50-425-97-01, 50-425-97-1, NUDOCS 9704220016
Download: ML20137X381 (33)


See also: IR 05000424/1997001

Text

.

.

U. S. NUCLEAR REGULATORY COMMISSION (NRC)

REGION II

Docket Nos. 50-424 and 50-425

License Nos. NPF-68 and NPF-81

Report No: 50-424/97-01, 50-425/97-01

Licensee: Southern Nuclear Operating Company. Inc.

Facility: Vogtle Electric Generating Plant (VEGP) Units 1 and 2

Location: 7821 River Road

Waynesboro. GA 30830

Dates: February 2 through March 15, 1997 l

Inspectors: C. Ogle. Senior Resident Inspector ,

M. Widmann Resident Inspector i

K. O'Donohue. Resident Inspector (in training)

W. Miller, Reactor Inspector (Sections F1.1. F2.1 F2.2. F3.

F5. F7. F8.1 F8.2)

J. Ganiere. Electrical Engineer. NRR (Sections E7.1. E7.3.

E7.4) l

M. Waterman. Senior Electrical Engineer. NRR (Sections E7.1.

E7.2. E7.4)

D. Wheeler. Senior Project Manager Vogtle NRR

Approved by: P. Skinner. Chief

Reactor Projects Branch 2

Division of Reactor Projects

,

l

Enclosure 2

"'

9704220016 970414

PDR

G ADOCK 05000424

PDR

.. _ _ _ . _ _ _ _ _ _ . - _ . _ _ _ _ _ . _ . _ . . _ _ . . - . . _ _ _

. ,

l~

l

EXECUTIVE SUMMARY

l Vogtle Electric Generating Plant Units 1 and 2  :

NRC Inspection Report 50-424/97-01, 50-425/97-01

'

This integrated inspection included aspects of licensee operations,

l engineering, maintenance, and plant support. The report covers a six-week

period of- resident inspection. It includes the results of an announced

inspection by a regional fire protection inspector. In addition. it includes

the results of a saecial inspection conducted on January 29 and 30, 1997 by ,

NRR personnel of. t1e Instrumentation and Controls Branch, Division of Reactor  ;

. Controls and Human Factors.  !

,

Ooerations

e In general, the conduct of operations was professional and

! safety-conscious (Section 01.1). ,

e Plant Review Board (PRB) discussions observed by the inspectors were

thorough and appropriately focused on safety (Section 07.1). '

,

e The Independent Safety Engineering Group (ISEG) assessment of

'

configuration control deficiencies was a positive example of licensee

.

!

self-assessment (Section 07.2).

e The inspectors' review of a licensee-identified issue associated with

j the quality of rounds performed by an operator on January 6. 1997, found 1

l that the rounds were of questionable quality (Section 08.1).

t

Maintenance

o Maintenance activities were generally completed thoroughly and

professionally (Section M1.1),

e An example of poor work practices was identified for the inadvertent

defeating of an automatic start feature for the Unit 1 engineered safety 1

,

. feature (ESF) 1A chiller during corrective maintenance (Section M1.3). '

i

e A violation was identified as a result of the discovery by the

inspectors that the positions of six valves in the Unit 2 auxiliary

feedwater system were not being properly verified (Section M3.1).

j Enaineerina ,

e The engineering evaluation associated with maintenance on valve -

2-HV-3548, reactor coolant system hot leg sam)1e line valve, was-  !

detailed, thorough, and appropriate (Section :1.1).

-e The commercial grade item dedication process at Cooper Energy Services

(CES) was not acceptable in that CES did not verify the adequacy of the

-

701 DSC design by the performance of an acceptable design review or by

the performance of a suitable testing program (Section E7.1).

?

Enclosure 2

, ,

.- - . . . . . . . - -. . - . - - - - - . - . - . . . - - . . - - . -

. ,

,

.

.

1

2

i

e The' lice ~nsee failed to maintain records of safety-related equipment

settings and calibration constants under configuration control for the

diesel generator governor modifications (Section E7.2),

e The licensee performed appropriate point of installation Electromagnetic  !

Interference (EMI) emissions testing. The 701 DSC EMI qualification was -1

sufficient to ensure proper operation in the actual EMI environment in )

which it will be used (Section E7.3). j

-e -The licensee's 10 CFR 50.59 safety evaluation _and supporting

documentation did not provide an acceptable basis to conclude that the

701 governor modification does not create a possibility for a

malfunction of a different type than any previously evaluated-in the

UFSAR. The 10 CFR 50.59 safety evaluation did not provide adequate

justification to conclude that installing the 701 governor does not

involve an unreviewed safety question (Section E7.4).

Plant SuDDort

e Appropriate action has been taken to resolve the Thermo-Lag issue at

Vogtle (Section F1.1).

e The relatively low number of open maintenance work orders (MW0), minimal

number of degraded fire barrier assemblies, and good material condition

of the fire protection com)onents and fire brigade equipment, indicated

that appropriate emphasis lad been taken on the maintenance and

operability of the fire protection components (Section F2.1). l

1

e Fire brigade radio communication transmission problems and one pre- l

action sprinkler system not being maintained to the design requirements '

l were identified as program weaknesses (Section F2.1).

,

e Appropriate surveillance and test procedures were provided for the fire

'

protection features. However, a violation was identified due-to the  ;

failure to meet the 12-month operability test frequency required for the  :

fire detection devices (Section F2.2).

1

,

e

'

l The fire protection program implementing procedures were adequate and

met licensee and NRC requirements. Implementation of arocedures was
good. Control of ignition sources, transient combusti)les, and general

L housekeeping was very good (Section F3).

! e The fire brigade organization and training met procedure requirements.

L Performance by the brigade during a drill was good, except for radio

'

communications problems between the fire brigade leader and brigade

members. A well qualified state-certified fire brigade training

instructor and good fire brigade training facilities were provided on

L , site (Section F5).

l

.

Enclosure 2

.

- -- - . . - . . -. - -- . . .

. .

.

3

e Thorough audits and assessments were made of the facility's fire

protection program and appropriate corrective actions were taken to

resolve the identified issues (Section F7).

  • A violation was identified for the failure to revise the Updated Final

Safety Analysis Report (UFSAR) to reflect as-built Appendix R fire

protection related plant configurations (Section F8.1).

Enclosure 2

l

l

l

.

. .

l

.

Report Details

Summary ~of Plant Status

{

Unit 1 operated at- full power throughout the entire inspection period.  ;

Unit 2 operated at- full _ power throughout the entire inspection period.

I. Operations

01 Conduct of Operations

]

01.1 General Comments-(71707)

Using Inspection Procedure 71707, the inspectors conducted frequent  ;

reviews of ongoing plant operations. In general, the reviews.irdicated

.that the conduct of operations was satisfactory. '

.

02 Operational Status of Facilities and Equipment- l

02.1 Safety-Related Walkdowns

a. Insoection Scooe (71707) l

The inspectors walked down the following engineered safety feature (ESF)

systems as part of the routine inspection effort to verify availability

and overall condition of the safety-related systems.

Unit 1 and 2 Residual Heat Removal (RHR) Systems

b. Observations and Findinas j

,The ins)ectors verified proper system configurations both electrically

and meclanically for the above ESF systems through walkdowns of selected

)ortions of the system in the plant, etalkdowns of main control room  !

Joards. and reviews of system drawings. The inspectors also observed  !

the overall material condition of system components during-the ,

walkdowns. Minor issues identified were provided to the licensee for

resolution.

c .- Conclusions

The inspectors concluded that the systems reviewed were available to

perform their intended function and that the systems were properly

aligned. No significant items or discrepancies were noted during these 1

inspections. The inspectors did note that the licensee has

substantially improved the general area conditions in the four RHR pump

rooms. These pump rooms have been decontaminated and are no longer  !

posted as contaminated areas.

Enclosure 2

y .-' *m m - - - -t w m --1ri-- -

w P - cu- r -m - - *e-- "

-t-+* --#'

T

- - . - . . - - - - - - . . - -

.

. .

.

i

-

2

.

03 Operations Proce~dures and Documentation

[ 03.1 Walkdown of' Clearances (71707)

-

During the inspection period, the inspectors walked down the following

. clearances:

i~

19600324 RHR, 1oop 1. is01ation

29600289 RHR. pump A. downstream, suction from hot leg

i 19700085 Parts removed from spare breaker-

l 19700131 Emergency Hydraulic Control pump train B. repair oil leaks

"

b. Observations:and Findinas

,

The inspectors did not identify any problems during these walkdowns.

4

t 07 Quality Assurance in Operations

~

i 07.1 Plant Review Board (PRB) Meetinas (40500)

!

The inspectors attended PRB meetings on February 4 and 5, 1997. The

meeting on February 4 was a normally scheduled PRB and the majority of

the items discussed-were routine in nature. Included in'the PRB review.

i at this meeting was proposed temporary modification 96-V2T054. This

! temporary modification was develo)ed as a contingency in the event that

j. repairs were required to valve 2-iV-8812A, Refueling Water Storage Tank

'

(RWST) to RHR Isolation Valve. The temporary modification was developed

(- to install freeze seals on either side of the valve if repairs to the

j valve were necessary.

'

This temporary modification was-also discussed at length during the

February 5..PRB meeting.

l

The PRB discussions were thorough and appropriately focused on safety.
In particular, the inspectors noted that questions raised Dy the PRB

'

.

'

j enhanced the quality of the safety evaluation performed for the

j temporary modification.

07.2 Confiauration Control Self-Assessment' (40500)

t

t

The inspectors reviewed an Independent Safety Engineering Group (ISEG)

i document titled " Configuration Control Deficiency Card (DC)

2

Assessment." It provided'ISEG's review of the licensee's performance in

the area of configuration control as documented in DCs generated between

f August 1995 and January 1997. The inspectors-observed that the analysis

contained in this assessment was extremely detailed and thorough.

Further, specific recommendations for enhancements to. improve licensee

performance in'this area were also included. The inspectors concluded

that this was a positi_ve example of licensee self-assessment.

Enclosure 2

-h. Ad +erou ...aii ne r4 4=. o.J -

c A - - .a. -.h-+ . . -4+4- 4 a

.

. .

.

3

'

08 Miscellaneous Operations Issues

08.1 Review of Non-Technical Soecification (TS) Operator Rounds

a. Insoection Scooe (71707)

The inspectors reviewed an issue concerning rounds completed by a plant

equipment operator (PE0) in Unit 2 on January 6, 1997. The NRC was

informed of this issue by the licensee at the beginning of the report

period. The licensee indicated that the performance of these rounds did

not meet their expectations. An independent review of this issue was

conducted by the ins)ectors. As part of this review, the inspectors

also reviewed other 3E0 rounds documented during January 1997. The

inspectors also discussed with plant management the circumstances

surrounding the performance of the rounds on January 6. as well as,

management's expectations in this area.

b. Observations and Findinas

l

PE0 non-technical specification rounds are grouped by specific buildings

and areas. Auxiliary building rounds are performed in accordance with l

Procedure 11881-1/2. Auxiliary Building Round Sheets. l

This issue involved PE0 performance of the Unit 2 auxiliary building

rounds. This effort requires general inspection and numerous readings

(approximately 58) of gauges and other indicators regarding the status I

of various components within the building. A review of the completed

Unit 2 auxiliary building rounds for January 6.1997. indicated that

data was recorded where appropriate. The rounds were completed in

approximately 44 minutes. A review of three other documented PE0 rounds

examined by the inspectors indicated that the average length of time to

complete a round was approximately 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> 20 minutes. Based on computer

records, the January 6 rounds were entered into the hand-held computer

used by building operators. when the PE0 was in the technical support

center and not in the auxiliary building.

The licensee documented this issue in deficiency card (DC) 2-97-033.

The inspector's review of the DC identified that the initial disposition

did not address the issue of the adequacy of the rounds performed by the

PEO. The insaectors' observations of the initial disposition was

discussed wit 1 plant management. As a result, the licensee revised the

dispcsition. Disciplinary action was taken against the involved PEO.

In addition, the licensee has and is currently counseling shift

.

'

operators en management's expectations for the proper performance of TS

and non-TS roends.

Enclosure 2

i

- - -- - ..

. .

4

c. Conclusion I

The inspectors concluded that the rounds completed by a PE0 in the

Unit 2 auxiliary building on January 6.1997 were of questionable

quality.

II. Maintenance

M1 Conduct of Maintenance

'

M1.1 Maintenance Work Order Observations

4

a. Insoection Scooe (62707)

The inspectors observed portions of maintenance activities involving the l'

following work orders:

19700757 Unit 1 alarm panel module change out {

29602495 Reactor coolant system hot leg sample isolation valve l

2-HV-3548 packing leak i

29700212 2B Diesel Generator (DG) bypass line fuel oil leaks '

29700474 2B DG left bank fuel oil leaks

29700476 28 DG fuel oil injection pump number 6. troubleshoot

b. Observations and Findinas I

The observed maintenance activities were performed satisfactorily.

M1.2 Surveillance Observation i

5

a. Insoection Scooe (61726) 1

The inspectors observed the performance or reviewed the following

surveillances and plant procedures:

i 14420-1 Solid state protection system and reactor trip breaker train

A operability test

14495-2 Motor driven auxiliary feedwater (MDAFW) pump train A flow

path verification

14545-2 MDAFW train A pump operability test

14802-1 Nuclear service water cooling (NSCW) system train B pump

(1-1202-P4-002) and check valve (1-1202-U4-027) inservice

test (IST)

14807-2 Quarterly MDAFW pump train A IST

14980-2 DG 2B operability test

b. Observations and Findinas

The observed surveillance activities were performed satisfactorily.

Enclosure 2

!

l

,

_ - -

.

5

M1.3 Uriit 1 Enaineered Safety Feature (ESF) Train A Chiller Failed To Start

a. Insoection Scooe (62707)

The inspectors reviewed an issue concerning a failure to start of the

ESF 1A chiller on February 3. 1997.

b. Observations and Findinas

On February 3. at 4:20 a.m. the ESF 1A chiller evaporator chill water

low flow loop.1-F1-22425, was removed from service to allow corrective

maintenance to be conducted on flow indicator switch 1-FISL-22425 in

accordance with maintenance work order (MWO) 19700319. At 4:39 a.m..

ESF Chiller Train B was placed in "Stop." in accordance with Procadare

14400-1. Control Room Emergency Filtration nctuation Logic Test.

Section 5.2. ESF Chiller Actuation Logic Test. At 4:46 a.m . during

performance of a subsequent step in the procedure, operations personnel

identified that the ESF 1A chiller failed to start. At 4:49 a.m. the

ESF Train B chiller was restored to auto. 0)erations verified the auto

start of ESF Train A chiller at 5:02 a.m.. 40 other adverse equipment

conditions resulted during performance of Procedure 14400-1 or MWO

19700319. Limiting condition for operation (LCO) action statements for

the ESF chillers were entered / exited as appropriate.

A review of the circumstances surrounding performance of MWO 19700319

indicated that there was a failure of the Unit Shift Supervisor (USS)

and the instrument and controls (I&C) technician to properly communicate

the scope of the work to be performed and the impact on plant eauipment.

A subsequent review of the single line electrical diagram reveal'ed that

u)on removing the flow indicator loop from service, that a low flow

cailler trip was generated, preventing the auto start. The electrical

drawing was not reviewed by the USS prior to authorizing this work. In

addition, other factors contributed to the failed chiller start. This

included: the performance of the ESF 1A chiller surveillance

simultaneously with the flow indicator MWO; the MWO being authorized on

an op)osite train week (i.e.. Train A com)onent being worked on a Train

B weeO indicating that the work may not lave been scheduled properly or

thoroughly pre->lanned; the USS not following the )lan-of-the-day

schedule; and t1e MWO being removed from a work scleduler's desk

prematurely rather than the package being issued to the field as is

typically done.

During the review of this event, the inspectors learned that, in

general. USSs were unaware of the impact of flow indicator loop on the

chiller system (i.e.. loss of the automatic start feature) when removed

from service. As a result, the licensee has proposed a revision to

Procedure 24362-1. ESF Chiller Chilled Water Flow Trains A and B

1F-22425/1F-22426 Channel Calibration, to include a precaution on the

impact of removing the flow indicator from service on the ESF chiller

system.

Enclosure 2

. _ . _ ._ . _ . _ _ _ _ . _ _ _ _ . .______ . . _ _ _ . _

'

. .

'

.

6

c. Conclusi'ons  ;

The inspectors concluded that the inadvertent inoperability of a safety-

related component due to a lack of understanding of the work authorized

and poor communications between departments was an example of poor work

practices.

.

H3~ Maintenance-Procedures and Documentation

M3.1 Technical Soecification (TS) Surveillance Not Conducted

a. Jnipection Scooe (62707)

The inspectors reviewed the circumstances associated with the discovery  !

that the positions of six valves in the Unit 2 auxiliary feedwater (AFW)  !

system were not being properly verified. This included reviews of ,

Procedure 11610-2. AFW System Alignment: Procedure 11867-2. Safety

' . Related Locked Valve Verification Checklist: Procedure 14495-2.~AFW

System Flow Path Verification: Vogtle Electric Generating Plant Design

Manual . Design Control Number DC-1302. AFW System: Technical

Specifications (TSs): and Design Change Package (DCP) 95-V2N0019-1-1

AFW Hiniflow Bypass Addition.

b. Qbservations and Findinas

,

'

On February 13. 1997, the ins)ectors observed and notified operations

personnel that valves 2-1302-J4-180 through -185, though properly

i positioned, were not locked. Following the licensee's confirmation of

the inspectors' observation, the valves were locked in the proper

position and a deficiency card (DC) was generated.

These six valves are in the recirculation piping for the Unit 2 AFW

pumps and are downstream of three normally locked open valves. These

valves were installed during the fifth refueling outage (2RS) by DCP

. 95-V2N0019-1-1. Two valves are installed in parallel in each of the

-

three' Unit 2 AFW recirculation lines. The valves were installed to

.

permit AFW pump recirculation flow to be directed to the Unit 2

condensate storage tank (CST) serving as the AFW suction source.

.TS SR 3.7.5.1 requires verification that each AFW manual valve in each

water- flow path that is not locked, sealed or otherwise secured. is in

l the correct position every 31 days. Likewise. prior to implementation

of improved technical specification (ITS) on January 23. 1997. TS

l surveillance 4.7.1.2.1 required a similar verification once per 31' days

on a staggered test basis.

Procedure 14495-2. AFW System Flow Path Verification, is used to

, accomplish the current surveillance requirement. Prior to

[ implementation of ITS it was also used to satisfy TS surveillance

!

$

Enclosure 2

.

_ . . . _ _ _ _ _ . _ _ _ _.. . _ _ .

-

l

. .

1

.  !

7

4.~7.1.2.1. The six AFW valves in question were not included in this  !

surveillance.

The inspectors determined that the positions of the six valves were

verified following installation during a valve lineup conducted near the

end of Unit 2 Fifth Refueling Outage (2RS) on October 5,1996. The

positions of all six valves were verified again on February 13, 1997, in

the 3rocess of installing locks on the valves. (The positions of five

of t1e six valves were verified on February 6.1997, during an AFW

system lineup verification.)

.

)

l

c. Conclusion '

The inspectors concluded that the licensee failed to' update Procedure

14495-2 or install locks on the valves following installation of the

valves during 2R5. As a result, the licensee failed to conduct TS

required surveillance testing for approximately 4 months. This is .

identified as Violation (VIO) 50-425/97-01-01. AFW System Surveillance

Not Conducted As Required By TS.

III. Enaineerina

El Conduct of Engineering

El.1 Enaineerina Seismic Evaluation

a. Insoection Scooe (37551)

The inspectors reviewed an engineering evaluation performed to support

maintenance on the reactor coolant system (RCS) hot leg sample line

valve. 2-HV-3548.

1

b. Observations and Findinas '

Maintenance to correct a packing leak on 2-HV-3548 was conducted per

maintenance work order (MWO) 29602495. To support this activity,

engineering personnel performed an evaluation to seismically restrain

the valve actuator during the maintenance. The valve' stem packing work

required that the actuator be removed using a chain-fall connected to an

I-beam located in the overhead in the general vicinity of the valve.

The licensee was concerned that if a seismic event occurred during the ,

performance of the maintenance activity, with the valve actuator '

unrestrained, surrounding equipment could be susceptible to damage.

The valve maintenance was completed on February 7. 1997, without I

incident.

I

Enclosure 2

- - - - . - - - . - . - . .

. .

i

8

c. Conclusions

The inspectors reviewed and discussed the evaluation with onsite  ;

engineering personnel arior to commencement of the work activity. The

inspectors concluded tlat engineering. personnel appropriately addressed

equipment concerns while developing this evaluation. The inspectors

-concluded that this engineering evaluation was detailed, thorough, and I

appropriate.

E7 Quality Assurance in Engineering Activities Woodward 701 Digital

Governor Modification

a. Scope

i

The inspectors _ reviewed the licensee's software quality assurance i

measures related .to the Woodward 701 governor modification to the  !

emergency diesel generators.(DGs). Specifically, the inspectors l

reviewed.the commercial grade item dedication process' for the 701 i

governor startup test procedures and tuning results, electromagnetic

interference (EMI) qualification testing results, and the-10 CFR 50.59

safety evaluation. The licensee installed the Woodward 701 governor in

Units 1 and 2 in 1994 to replace analog. type Woodward governors. The

digital governor comprises a generator loading control (GLC) generator

load sensor (GLS), and a microprocessor-based digital speed control

(DSC) that.contains approximately 12.000 lines of-software code.

.

b. Observations and Findinas

The following paragraphs (E7.1_through E7.4) address the inspectors'

observations. findings, and conclusions.

E7.1 Commercial Grade Item Dedication of Woodward 701' Governor

a. Insoection Scooe (52002)

The inspectors reviewed the commercial grade item dedication activities

that were performed to qualify the Woodward-701 DSC software for a

safety-related application. Cooper Energy Services (CES) qualified the

Woodward 701 DSC under their 10 CFR 50 Appendix B program.

b. Observations and'Findinas

In May 1994. CES audited the Woodward Governor Company (WGC) software

development process for the 701 DSC. The NRC inspectors reviewed the

CES software audit checklist and found that.it provided a comprehensive

plan for evaluating the WGC software development process. -CES

identified several deficiencies during the audit, which were documented

in four vendor program deficiency notices dated September 13. 1993. The

deficiency notices described important software cuality assurance

functions that were not performed or documented curing the development

Enclosure 2

___ __ _ _ . _ . _ . _ _ _

,

.

.

-9-

of the 701 DSC software. Specifically, the audit report and deficiency

notices revealed that there was no formal software requirements

specification, no source code and unit module testing, no traceability

of the source code back to requirements, no regression testing, no

controls on supplier software, minimal verification and validation (V&V)

activities, and no notification of software modifications to external

users. CES also identified weaknesses in the WGC software configuration

management process.

In response to the audit findings, WGC placed the 701 DSC source code

l and the supporting software development tools under configuration

l

L

control prior to shipment of the deliverable software product to CES. l'

Additionally. WGC revised and developed several software development

'

procedures and indicated that future software development would be

performed according to the revised procedures. However, WGC did not  ;

apply the revised software development processes to the existing 701 DSC  !

I

software version. ~'

{

l

CES found that WGC did not perform source code validation testing or-  !

L regression testing of the 701 DSC software. Instead, WGC relied on  ;

j. early prototype testing and functional testing of the integrated

' l

hardware-software product to confirm coding accuracy. Vendor program l

deficiency notice 953829-02 recommended that WGC perform V&V of the  ;

software by means of comprehensive testing of the source code and unit  !

modules, including all decision points, loo)s, and range of conditions.  !

WGC did not perform this structural (white )ox) source code testing, but  ;

instead indicated that the current version of the 701 DSC software.has i'

eeen validated based on extensive non-nuclear field experience (over 800

un:ts in service). Subsequently at the request of CES WGC performed a

design review of the software. The inspectors reviewed the WGC software

design review documentation provided to CES but could not conclude from 1

the available documentation that the review was of acceptable detail, '

In CES Engineering Repo," GO-01-1994. " Software Verification and

Validation Plan for a Woodward 701 Governing System," dated April 15. -

1994, and Engineering Report GO-02-1994, " Software Validation Test

Report for a Woodward 701 Digital Speed Controller," dated May 23. 1994, )

,

CES described the V&V activities to be 3erformed as part of the 701 DSC l

! software qualification. Since the 701 )SC software lad been 3reviously

- developed CES used the Software Verification and Validation )lan (SVVP)

i , primarily to validate. rather than verify, the software product.

j Software validation was. accomplished through WGC factory testing and CES

i- bench (simulation) type testing. The SVVP also stated that site 1

!

installation testing would be performed and would serve as additional l

t validation. The inspectors found that the factory acceptance and bench l

i type tests did not a) pear to sufficiently test the entire design l

l envelope, including aounding conditions. of the Woodward 701 DSC. CES  :

i- did not perform a detailed analysis'of the abnormal conditions and  !

t" l,

<

Enclosure 2  ;

i

!

. _ -

.= .-. - .. -

'

. .

I

3

)

- 10 -

events that could potentially interfere with the software accomplishing 1

its safety function. Section E7.2 describes the inspectors' review of l

the site installation testing results. '

Lastly, CES credited the operating history of the 701 DSC in commercial

applications for providing a statistical basis for historical software i

validation. However, documentation supporting this statistical basis '

was not available for review. Therefore, the inspectors could not

conclude that there was sufficient data available to credit 701 DSC

field experience as part of the software validation,

c. Conclusion

Based on the review of the CES audit report and the software audit

checklist, the ins)ectors concluded that the software audit was well-

planned and very t1orough. However, WGC corrective actions for the

problems identified in the vendor program deficiency notices were not

applied to the existing 701 DSC software version. The inspectors

concluded that the WGC design review of the software was too cursory to

resolve the issues identified in the audit and that there was not  ;

adequate analysis of historical commercial experience to credit i

validation based on successful operating history. In addition, the

inspectors concluded that the factory acceptance and bench simulation

type tests do not appear to satisfy the system validation requirements

since they do not address abnormal conditions that could potentially

interfere with the software accomplishing its safety function.

Consequently, the inspectors concluded that the lack of a structured i

software development process and lack of source code validation presents I

a vulnerability for introduction of a previously unanalyzed software '

failure mechanism for the 701 DSC.

Based on these findings, the inspectors concluded that the commercial

grade item dedication process at CES was not acceptable. Specifically,

the inspectors concluded that, contrary to 10 CFR 50. Ap

Quality Assurance Criteria.Section III. Design Control.pendix B.not

CES did

verify the adequacy of the 701 DSC design by the performance of an

acceptable design review or by the performance of a suitable testing

program. This is identified as an example of Violation (VIO)

50-424, 425/97-01-04 Inadequate Testing of 701 Governor - Two Examples.

E7.2 Vogtle Site AcceDtance Testina of Woodward 701 Governor

l

a. Insoection Scooe (52002) l

The inspectors reviewed the CES startup test procedures for the Woodward I

701 governor to determine whether all safety functions and appropriate

t

input / output combinations were tested. Additionally, the inspectors l

,

Enclosure 2

i

_ _ _ . . _ . _ _ _ _ . _ _ _ _ _ _ _ _ . _ _ _ .. . .. _ _ ,_._m

'

. .

..  !

!

e - 11 - l

!

compared the current system setpoints for the 701 DSC in the Train'1A DG  !

,

I

to those contained.in the dynamic tuning procedure data sheets. '

b. Observations and Findings '

The startup test procedures contained both static and dynamic test

'

. procedures for the 701 governor. system. The static test procedure was  !

'

.

intended to verify that the 701 governor components were correctly

! installed and operating. Specifically, this procedure contained '

instructions for presetting the GLC and GLS and for verifying the 701

,

l

DSC field device inputs and parameter settings. The dynamic test 3

procedure provided methods for tuning the 701 governor for optimal i

performance. The objective of the dynamic adjustments was to obtain the '

optimal, stable engine speed response from minimum load to full load. l

All setpoints are saved permanently in a nonvolatile memory, which does  ;

not require batteries or other power sources to retain data. Entries .i

can be changed using a removable hand-held programmer. The inspectors l

l

i

found that the startup tests did not appear to sufficiently test the i

entire design envelope, including. bounding conditions, of the 701 i

governor.

j

' '

The licensee accompanied CES to witness 701 governor tuning procedures-

on a diesel generator operated by the City of Springville. Utah. The  !

l licensee stated that this trip provided many insights into the 701-  !

i~ governor tuning process. The licensee used this experience to develoa  ;

i

better tuning practices on the Vogtle DGs. The licensee stated that WGC i

701 governor tuning does compensate for some DG performance  :

characteristics: however, tuning alone did not resolve all DG i

idiosyncracies. For example, differences in compression pressures  ;

'

l between the DG pistons and the location of the speed sensing magnetic j

pickup units also affected governor performance. l

, Using the 701 DSC hand-held programmer, the licensee downloaded the  !

701 DSC setpoints from the Train 1A DG. The inspectors compared these  :

setpoints to the setpoints in the original startup test procedure data  !

sheets dated September 30, 1994. The documented setpoints did not agree l

with the downloaded setpoints. The licensee indicated that the magnetic j

pickup unit for sensing engine speed was relocated from the front of the  :

.

engine to the generator side of the engine shortly after the completion  !

i

of the original startup test procedure and, as a result, the original

l data sheets had been updated. The licensee was unable to locate the

!' revised data sheets during the inspection period.

i

The licensee obtained a record of the 701 DSC calibration constants for

!

'

the Train 1A DG from CES dated March 24, 1996. The inspectors compared I

the CES data with the data downloaded from the Train 1A DG. Table 1

! ' lists 3arameter values which the inspectors found to be inconsistent

!.

>

with't1e CES recorded values. In a conference call with the inspectors

[ Enclosure 2

u . _ ._. _. , , ._ __

.

- 12 -

on February 11. 1997, the licensee could not explain the reason for the

data discrepancies; however, none of the data discrepancies affect

system performance within the design specifications of the Train 1A DG.

Table 1. Calibration Constant Variations

Variable As Found by NRC As Recorded by CES

Window Width 1* 13.0 15.0

Gain 2* 0.1064 0.07270

Reset 2** 1.00 0.90

Compensation 2** 0.10 0.050

20 mA Tach * 490 458

4 mA Tach * 440 442

Torque Limit Breakpoint + 447 450

'hI

Identified by licensee

    • Identifed by inspectors

c. Conclusions

The inspectors found the licensee's actions to dynamically tune the 701

governor for optimal performance to be acceptable. However, the

inspectors concluded that the startu) test procedures did not test an

acceptable range of input / output com)inations including conditions that

bound the 701 governor design envelope. Therefore, the inspectors

concluded that the licensee tests do not appear to satisfy the software

, and integrated system validation requirements. Based on these findings,

the inspectors concluded that, centrary to 10 CFR 50. Ap

Qaality Assurance Criteria.Section III. Design Control,pendix B.

the licensee

did not verify the adequacy of the 701 governor design by the

performance of an acceptable design review or by the performance of a

suitable testing program. This is identified as an example of

VIO 50-424. 425/97-01-04. Inadequate Testing of 701 Governor - Two

Examples.

In addition contrary to 10 CFR 50. Appendix B. Quality Assurance

Criteria.Section XVII. Quality Assurance Records, the licensee failed

to maintain records of safety-related equipment settings and calibration

l constants under configuration control. Tests of the Train 1A DG have

!

shown that the settings in question have had no adverse affect on system

performance. The discrepancies between the current 701 DSC setpoints ,

for the Train 1A DG and the setpoints contained in the test data sheets

i

Enclosure 2

i

l

!

. .. - - -- . = . -

'

,

'

l

- 13 -

is identified as VIO 50-424, 425/97-01-05, Failure to Maintain Records

of 701 DSC Setpoints.

j

,E7.3 Electromaanetic Interference Qualification of Woodward 701 DSC

a. Insoection Scoce (52002) I

l

'

The inspectors reviewed EMI testing results to verify that the Woodward

701 DSC EMI qualification was sufficient to ensure proper operation in

the actual EMI environment in which it will be used.

b. Observations and Findinaq

WGC performed laboratory EMI testing of the Woodward 701 DSC using the 4

guidance in MIL-STD-461C, " Electromagnetic Emission and Susceptibility

Requirements for Control of EMI." Specifically. WGC performed radiated

susceptibility testing using MIL-STD-461C test methods RS01 and RS03 and i

conducted susceptibility testing using MIL-STD-461C test methods CS01,

CS02, and CS06.

As documented in Test Report 31319-94M, " Test Report for Point of

Installation EMI Mapping of Diesel Generator Room " National Technical

System (NTS) performed an EMI point of installation mapping of DG 4

room 2A at Vogtle. The EMI mapping presented the actual EMI levels

the 701 DSC would be exposed to when installed. Specifically NTS

3erformed emissions measurements using MIL-STD-462 test methods CE01 (30

iz to 15 kHz) CE03 (15 kHz to 50 MHz), and CE07 (switching transients,

time domain) and radiated electric and magnetic field emission

measurements using test methods REXX ('0C magnetic field) RE01 (30 Hz to

50 kHz) RE02 (14 kHz to 1 GHz), and RE02.1 (hand-held radio profile).

Tests CE01, CE03 CE07. RE01, and RE02 were performed with the diesel

generator shutdown and with the diesel generator operating at 0%, 50%.

and 100% generator power. Test RE02.1 was performed with hand-held

radios.

In Test Report 31319-94M-1. " Test Report for Analysis of Point-of-

Installation and Generic Emissions EMI Mapping Data " NTS compared the

measured EMI emission levels to the EMI susceptibility test results

obtained during the WGC laboratory EMI testing. As indicated in this

test report, NTS recommended at least a six-decibel (dB) safety margin

between the measured EMI emission level and the EMI susceptibility test i

results. The inspectors confirmed that the worst case signal spectra y

from the conducted susceptibility tests (CS01 CS02 and CS06) is at i

least 69 dBs greater than the conducted emissions levels found during I

the site survey. In addition, the worst case signal spectra from the

radiated electric field susceptibility tests (RS03) is at least 16 dBs

greater than the radiated electric field emission levels. However, the i

worst case signal spectra from the radiated magnetic field

. Enclosure 2

e

,

.

.

- 14 -

susceptibility tests (RS01) was only five dBs greater than the radiated

magnetic field emissions level in the frequency range of 30 to 60 Hz.

Including the plus or minus two-dB measurement amplitude accuracy error

of the test equipment resulted in only a three-dB margin. The safety

margin increases to the recommended six-dB safety margin at 85 Hz and

continues to increase from that point until a frequency of 50 kHz is

reached. Based on these test results. NTS proposed that the radiated

magnetic field susceptibility test be repeated at a level of 170 dBs to

verify that a six-dB safety margin exists above the measured emission

,

i

level.

WGC originally performed the radiated magnetic field susceptibility test

at a level of 166 dBs. The original susceptibility test was not

>erformed at the level prescribed in MIL-STD-461C (180 dB at 50 Hz)

3ecause the WGC test equipment did not.have the capability to test at

that level. WGC indicated that they were confident that the 701 DSC

would pass a 170-dB test between 30 and 85 Hz and that they would

perform the test at 170 dBs if requested. However, CES and the licensee

concluded that the existing three-dB safety margin provided sufficient

conservatism and that a revised susceptibility test was not necessary.

Subsequent to the inspection. CES and NTS confirmed the 3-dB margin was

associated with the level measured at the generator control ]anel, l

bay 1-2 rear. However, the licensee indicated that the 701 )SC was  !

actually installed in bay 3. As supported by Test Report 31319-94M, the  !

specific measurements at bay 3 show at least a 23-dB safety margin

between the radiated magnetic field susceptibility and emissions levels.

Based on this information, by letters dated February 18 and February 27,

1997, CES and NTS concluded that additional testing is not necessary

since the recommended six-dB safety margin is met at the specific point

of installation (bay 3).

c. Conclusions 1

i

The inspectors concluded that the licensee performed appropriate point  ;

of installation EMI emissions testing. The recommended six-dB safety

margin between the radiated and conducted susceptibility and emissions

tests was satisfied for the specific point of installation of the

701 DSC. Therefore, the inspectors concluded that the 701 DSC EMI

qualification was sufficient to ensure proper operation in the actual

EMI environment in which it will be used.

Enclosure 2

_- .-. .- . .. .. .- -. -

'

. .

.

- 15 -

E7.4 10 CFR 50.59 Safety Evaluation

a. Insoection Scoce (52002)

The inspectors reviewed the licensee's 10 CFR 50.59 safety evaluation to  ;

determine whether the licensee addressed digital equipment failures l

including software common mode failure considerations, and to determine

whether an unreviewed safety question was associated with the 701 DSC

modification,

b. Observations and Findinas

The licensee's 10 CFR 50.59 safety evaluation associated with Design

Change Package (DCP) 93-V1N0050-0-1. dated February 28. 1994 stated

that the system level failure modes for the Woodward 701 governing '

system were the same as for the analog guverning system: (1) fail in a

manner where the engine speed increases. (2) fail in a manner where the

engine speed decreases, and (3) fail as is. In the case of a failure

causing the engine speed to increase. a backup mechanical ball head

governor would automatically assume control of the engine speed. Should l

the mechanical governor fail, the engine overspeed trip would stop the l

engine. The licensee concluded that in the cases of a failure causing '

the engine speed to decrease or to fail as is. the opposite train DG

would be available.

.

In addition the licensee did not view software common mode faliure as ,

being credible, based on the qualification of the software and the i

results of EMI. seismic, and 300 start tests. The inspectors did not

concur with the licensee's conclusion that software common mode failure

is not credible. The inspectors noted that the identical software i

versions are loaded in each 701 DSC. J

c. Conclusions

In reviewing the licensee's 10 CFR 50.59 safety evaluation and

supporting documentation, the inspectors concluded that the licensee did

not consider software common-mode failure in their 10 CFR 50.59

evaluation as a possible different type of malfunction than any i

previously evaluated in the Updated Final Safety Analysis Report. The '

licensee's determination that software common mode failures are not

credible based on the software qualification performed by CES and the

results of EMI. seismic, and 300 start tests is not considered

acceptable. Therefore, the ins)ectors concluded that there is no basis

i for the licensee's conclusion tlat, for the DG failure modes where the

i

i engine speed decreases or fails as is, the opposite train DG would be

available.

Enclosure 2

i

!

.

i.

- 16 -

Based on this information. the inspectors concluded that the licensee's

10 CFR 50.59 safety evaluation and supporting documentation did not

provide an acceptable basis to conclude that the 701 governor

modification does not create a possibility for a malfunction of a

different type than any previously evaluated in the FSAR. As a result.

the inspectors concluded that the 10 CFR 50.59 safety evaluation did not

provide adequate justification to conclude that installing the 701 i

governor does not involve an unreviewed safety question. This is i

identified as VIO 50-424, 425/97-01-06. 10 CFR 50.59 Unreviewed Safety l

Question Determination for Woodward 701 Governor.

E8 Miscellaneous Engineering Issues

'

. E8.1 (Closed) Unresolved Item (URI) 96-02-05: Condensate storage tank (CST)

ininimum water volume required by Technical Specifications (TSs)

URI 50-424. 425/96-02-05 documents inspector concerns with a discrepancy

between the minimum CST volume required by TSs and that determined from

analysis of possible accident scenarios. The inspectors reviewed

revisions to TS 3.7.6 and 3.7.6.a and the following. Procedures 11610-1

and 11610-2. Auxiliary Feedwater System (AFW) Alignment: Procedures  ;

17017-1 and 17017-2. Annunciator Response Procedures for ALB 17 on l

Panel 182 on Main Control Board: Procedures 14000-1 and 14000-2.

Operations Shift and Daily Surveillance Logs; and drawings 2X4DB161-1.

Condensate Storage and Degasifier System and 2X4DB161-2. AFW System.

The inspectors concluded that the changes made to these documents

resolve this discrepancy. This item is closed.

l IV. Plant Support

1

P1 Conduct of Emergency Preparedness (EP) Activities

Pl .'1 EP Exercise

a. Insoection Scoce (71750.).

! On March 10. 1997 the licensee conducted an EP drill. The inspectors

reviewed the EP procedures prior to commencement of the drill and

discussed the critique findings with plant management at the completion

of the scenario.

I b. Observations and Findinas

The inspectors observed and reviewed the manning of the emergency

facilities. All facilities were manned in a timely manner and as

appropriate. Emergency organization manager positions were filled by

qualified personnel and. except for some telephones supplied for Nuclear

Enclosure 2

-

,. _ _ . _ , _. - _ _ _ _ . . _ . _ . _ _ _ _ _ - . _ _ _ _ _ _ . _ _ _ _ . .

'

l

l .

L.

- 17 -

Regulatory Commission (NRC) use, the facilities were arranged in

l

accordance with the site plan.

At the conclusion' of the exercise, the licensee performed a critique

-that identified a number of exercise objectives which were not met.

liost notably, the classification of the event and accountability did not

meet.their stated objectives. As the. event progressed, the emergency

director declared a GENERAL emergency although the conditions did not

l

'

warrant the classification. Also, although the accountability was

completed in the required time there were 21 missing personnel 30

minutes after the SITE AREA EMERGENCY declaration.

! c. Conclusions

The licensee did not meet all its stated drill objectives. However, the

inspectors concluded that performance of the drill to identify EP

l deficiencies accomplished it; purpose and was therefore useful. The.

L licensee informed the inspectors that as a result of the unsatisfactory

objectives, additional drills will be conducted in the near term.

l

i- F1: Control of Fire Protection (FP) Activities  !

F1.1. Resolut1on of Thermo-Lao Fire Barrier Issbe (64704)

a. Insoection Scooq

!.

,

The ins)ectors reviewed the action taken to resolve the degraded-

l Thermo _ag fire barrier issues at Vogtle to determine if this action-was

consistent with licensee and NRC requirements.

b. ' Observations and Findinos  !

-

In 1991, the NRC found that Thermo-Lag fire barrier material did not

perform to the manufacturer's specifications. The NRC issued NRC 1

Bulletin 92-01. " Failure of Thermo-Lag 330 Fire Barrier System to- '

Maintain Cabling in Wide Cable Trays and Small Conduits Free from Fire-

Damage." and requested licensees with Thermo-Lag fire barriers to take

( the a)propriate compensatory measures for the areas where the Thermo-Lag

'

fire )arriers were installed.

Based on the unfavorable results of Thermo-Lag fire barrier installation-

tests performed during 1993 and 1994 by the nuclear industry, the

licensee elected to remove the Thermo-Lag fire barriers installed at

.Vogtle. Design Change Package (DCP) 94-V1N0061 and DCP 94-V2N0062 were

i

prepared which provided a design to either re-route the electrical

.

raceways enclosed within Thermo-Lag fire barriers or to replace the

! Thermo-Lag fire barriers with fire barriers which had been reviewed.

, tested and approved by a nationally recognized testing laboratory. such

,

l Enclosure 2

i

l-

!-

5 _ _ -___ _ _ _ _ . . .

. .- .. - . .

'

. .

e

e

- 18 -

as Underwriters Laboratories. Inc. These DCPs provided separation

between safe shutdown components which met the separation requirements

,

of 10 CFR 50, Appendix R Section III.G.

Work on these DCPs had been completed except for. the replacement:of the

Thermo-Lag'on one electrical raceway in the Unit 1 reactor building.

This work was scheduled to be completed during the Fall 1997 refueling

outage.

L

The replacement fire barriers consisted of several different types of

3-hour fire rated designs, including: hollow concrete block, gypsum

board, Carboline Pyrolite. WR Grace Monokote, and 3M Interam.

'

The inspectors reviewed the DCP work packages, performed walkdown

inspections of the rerouted cables and new fire barriers, and verified  ;

that the required changes had been completed. During these walkdown

inspections, the inspectors noted that the 3-hour Monokote fire barriers ,

installed around the required redundant circuits for the raceways in 3

Room B77 of the Unit 1 control building and around the redundant cables '

in the raceways above the mezzanine of Room B31 of the Unit 2 control-

L building contained a number of cracks. The licensee determined that

'

these barriers were degraded and implemented the required compensatory

.

actions. The compensatory measures included an hourly fire watch. The

l

inspectors verified that this required fire watch had been' implemented. )

)

,

c. Conclusions i

i

riate action had been taken to resolve the Thermo-Lag issue at

'

F2 Status of Fire Protection Facilities and Equipment

F2.1 ODerability of FP Facilities and Eauioment (64704)

a; Insoection Scooe

,

,

l

The inspectors reviewed open fire protection related maintenance work

orders (MW0s), the maintenance department's list of fire protection

deficiencies, and operation's list of out-of-service fire protection  !

'

equipment to assess the licensee's performance for returning degraded

L fire protection components to service. In addition, walkdown  !

t

inspections were made to assess the material condition of the plant's i

fire protection systems, equipment and features. l

1

f

Enclosure 2  :

._ _

4-

.

- 19 -

b. Observations and Findinas

' Maintenance of FP Eauioment and Comoonents:

-

As of February 13, 1997, there were ap3roximately 29 fire protection

related open work requests. Most of t1ese work requests involved minor

corrective maintenance work items which did not affect the operability

of the components or involved systems in non-safety related areas. Two

items were related to degraded fire barriers that were identified during

-

this inspection. One item involved a pre-action sprinkler-system for.

the Unit 1A emergency diesel generator (DG) building which was not being

maintained in its design configuration', i.e.. valve was set wet and

water flow alarm had been disconnected. In this configuration.

inadvertent sprinkler actuation could go undetected and result in water

damage to the emergency DG. This condition had existed since October

1995 due to'an exhaust leak on the diesel engine. This leak activated

the fire detection system which tripped the sprinkler system each time

the diesel engine was operated. During the exit interview, the licensee

stated that this situation would be promptly resolved and the sprinkler

system restored to its design configuration.

The inspectors toured the plant and noted that, with the exception of

-the two degraded fire barriers and the one sprinkler system not being

maintained in conformance to the design requirements, the fire

protection systems were operational, material condition was _very good. ,

and' components were well maintained.

Fire Briaade Eauioment:

The fire brigade turnout gear was stored in the control building

-

adjacent to the control room. Sufficient sets of turnout gear,

consisting of coats, pants, boots, helmets, etc., were provided to equip i

the fire brigade members expected to respond in the event of a fire or '

other emergency. The equipment was properly stored and well maintained.

During recent fire brigade drills, the fire brigade experienced problems

with radio communication. On one drill, the brigade had to rely on

runners in order for the fire brigade leader to communicate with the '

fire brigade members. The licensee determined that this arrangement was

not satisfactory. To resolve this issue, the licensee appointed a task ,

force to identity the extent of the problem, and to im)lement

appropriate corrective actions. Pending correction, t1e poor radio

communication problem is identified as a program weakness. Otherwise, i

the fire brigade equipment was operable, properly stored, and well

maintained.

<

'

Enclosure 2

4

.

\ ,

- 20 -

!

c. Conclusions  !

>

!

The relatively low number of open MW0s, minimal (two) degraded fire  !

L

barrier assemblies, and good material condition'of the fire protection

j

com)onents and fire brigade equipment indicated that appropriate

emplasis had been placed on the maintenance and operability of the fire.

protection components. However, the problems associated with the poor

fire brigade radio communications and the one pre-action sprinkler

system not bein

as weaknesses. g maintained to the design configuration were identified

,

L F2.2 Surveillance of FP Features and Eauioment

i

a, Insoection Scooe (64704)

The inspectors reviewed the following completed surveillance and test.

procedures:

! -

14951-C Fire Suppression System Operability Test-(Fire Pumps).

Monthly, Completed February 4, 1997.

14952-C. Fire' Suppression System Operability Test.(Fire Pumps),

-

Annually. Completed June 26, 1996. l

-

14956-C, Fire Suppression - 3-Year Flow Verification. Performed i

!

under T-0PER 95-003, Revision 0, Fire Suppression System REA

l VG-2720 Flow Verification Completed October 10, 1995.

-

29227-1 and -2 Fire and Smoke Detector Operational Test (Panel-

l LZIP 2-1813-03-F27. Completed January 22, 1997.

l

-

29231-1 and -2 Fire and Smoke Detector Operational Test-(Panel

LZIP 1-1813-03-F31. Completed October ~'4, 1996.

Ib. Observations and Findinos

The completed fire protection surveillance tests reviewed by the

inspectors had been appropriately completed and met the acceptance

criteria. The test procedures were good. The data obtained and

recorded for each fire. pump included multiple points on the pump curve

~ to verify pump 3erformance. The completed test procedures included an

evaluation of tie test data by the site fire protection system engineer

which provided good technical oversight of the tests on the fire

protection systems.

!

l 'The inspectors noted that the surveillance tests for the two fire

detector panels included two specific work tasks. These two tasks were

<

initially scheduled to be performed every two years on a staggered test

, basis. One task performed an operability test on the fire detectors

i

,

Enclosure 2

..

l

! . - . -_. _

-

_ _. . _. .- __ . . _ . -_- _ . - . - -

'

! .

,

.

.

i

- 21 -

l -

supplied by the fire alarm panel. The second test included preventive

maintenance and sensitivity adjustments for each fire detector followed

by an operability test. These tests had initially been scheduled on an ,

annual staggered test frequency to meet the 12-month test frequency

specified by Updated Final Safety Analysis Report (UFSAR) Table

9.5.1-10. FP Operability Requirements. Section-1.4.1. 'However, recently e

the staggered test frequency had been changed such that the required >

12-month test frequency was not being aerformed. For example, the time ,

between the current test for Panel LZ13 2-1813-03-F27. com)leted on e

January 22. 1997, and.the previous test com)leted on Novem]er.1. 1994,

was approximately 25 months and 22 days. T1e time between the last two -

tests for Panel LZIP. 1-1813-03-F31, completed on October 4. 1996, and >

the test completed on February 11. 1996, was 9 months but the time

between this test and the previous test completed on June 17, 1994, was

approximately 19 months 11 days.

, Paragraph 2.G of the operating license for Units 1 and 2 requires the l

L licensee to implement and maintain in effect all provisions of the

'

approved fire protection program as described in the UFSAR. The failure

to aerform an operability test at least once 3er 12 months, as required

by JFSAR Table 9.5.1-10. Section 1.4.1. for t1e fire detectors supplied

by these two panels is identified as Violation (VIO)

50-424, 425/97-01-02. Failure to Demonstrate Fire Detectors Were.

Operable at Least Once per 12 Months. ,

The licensee reviewed the current test completion data on the

approximately 60 fire alarm panels installed within the power block and

concluded that there were no current operability concerns. All of the

panels had been tested within the past'12 months. However, the two 24

month surveillances for at least 12 panels had been completed on the

same date or within 30 days of each other. Tnis resulted in the next

!

'

scheduled surveillance for 24 months. This would have exceeded the <

. required 12-month test frequency. The licensee was also reviewing

historical test data to determine if the 12-month test frequency had

been exceeded on additional fire detectors.

c. Conclusions

Appropriate surveillance and test procedures were provided for the fire

protection features. However, a violation was identified due to the

failure to meet the 12 month operability test frequency required for the

j fire detection devices

,

1

2

.

J

l

,

Enclosure 2

t

6.

4

.

- 22 -

l

F3 Fire Protection Procedures and Documentation

.

a. Insoection Scooe (64704)

The inspectors reviewed the following procedures for compliance with the

NRC requirements and guidelines: 1

-

92000-C. Fire Protection Program

-

92005-C. Fire Response Procedure

l

-

92010-C, Control of Ignition Sources I

-

92015-C, Use. Control and Storage of Flammable / Combustible j

Materials l

1

-

92035-C, Fire Protection Operability Requirements l

-

92040-C. Fire Protection Limiting Condition for Operation (LCO) l

Program

Plant tours were performed to determine procedure compliance. i

b. Observations and Findinas l

The above procedures were the principle procedures issued to implement

the fire protection program at Vogtle. These procedures contained the ,

requirements for program administration, controls over combustibles and )

ignition sources, fire brigade organization and training, and l

o)erability requirements for the fire protection systems and features.  !

T1e 3rocedures were satisfactory and met the licensee's commitments to I

the VRC.

The inspectors performed plant tours and noted that implementation of I

the site's fire prevention program for the control of ignition sources,

transient combustibles, and general housekeeping was very good.

The coordination and oversight of the facility's fire protection program

s were good and met the licensee and NRC requirements.

c. Conclusions

The fire protection program implementing procedures were adequate and

met licensee and NRC requirements. Implementation of 3rocedures was

good. Control of ignition sources, transient combusti)les, and general

housekeeping was very good.

Enclosure 2

- - - - . - - - - . - - .- - - - - - - .- - -. .. - - ~. -

'

.

!'

.

'

- 23 -

[ .

.

4

] F5 Fire Protection Staff Training and Qualification

a. Insoection Scoce (64704)

h The inspectors reviewed the fire brigade organization 'and training

program, and the site's fire fighting preplans to determine if these

were in compliance with the facility's fire' protection program and the.

NRC guidelines and requirements.

~

b. Observations and Findinas

i'

The organization and training requirements for the plant fire brigade

were established by Procedures 92000-C, FP Program, and 92030-C. Fire

Drill Program. The fire brigade for each shift was composed of a fire

j'

'

brigade leader and at least four brigade members from operations. The

fire brigade leader was a shift supervisor or shift support supervisor.

The.other members from operations were plant equipment (non-licensed)

operators.

Each fire brigade member was required to receive initial, quarterly and: l

annual fire fighting related training and to satisfactorily complete an  !

annual medical evaluation and certification for participation in fire l

brigade fire fighting activities. In. addition, each member was required

to participate in at least two drills per year. '

'

As of the date of this inspection. there was a total of 35 operations

trained fire brigade leaders and 41 operations personnel on the. plant's - 1

fire brigade .

The inspectors reviewed the training and medical records for the fire l

brigade members and-verified that the training and medical records were

up to date. A well qualified state-certified fire brigade training

instructor and good fire brigade training facilities were provided on

site. I

During this inspection, the inspectors witnessed a fire brigade drill  !

involving a simulated fire in a charcoal filter unit on Level 3 of the  :

control building. The response of the fire brigade to the simulated  ;

fire was good, except for radio communication problems noted between the i

fire brigade leader and fire brigade members. At times the leader's

radio transmissions to the brigade were not received. A critique to

discuss the brigade performance and identified weaknesses was held

following the drills.

c. Conclusions

!

The fire brigade organization and training met the requirements of the

site procedures. Performance by the brigades during a drill was very

Enclosure 2-

.

,

.

- 24 -

good, except for minor radio communications problems between the fire

brigade leader and brigade members. A well qualified state-certified

fire brigade training instructor and good fire brigade training

facilities were provided on site.

F7 Quality Assurance (QA) in Fire Protection Activities

a. Insoection Scoce (64704)

The following audit and self assessment reports were reviewed:

-

0A Audit OP20-96/14 Annual / Biennial FP Audit of June 5, 1996

-

0A Audit OP20-95/15 Annual / Triennial FP Audit of May 1 - 12,

1995

-

NML Inspections Loss Prevention Reports for inspections

conducted June 1996 and November 1996

b. Observations and Findinas

The OA audits of the site's fire protection program were comprehensive

and identified a number of finoings, observations and issues to enhance

the facility's fire protection program. The inspectors reviewed the

audit findings from occh OA report and the corrective actions taken on

the identified discrepancies. These items had been resolved.

c. Conclusions

Thorough audits and assessments were made of the facility's fire

protection program and appropriate corrective actions were taken to

resolve the identified issues.

JF8 Miscellaneous Fire Protection Issues (64704) (92904)

F8.1 FP Related NRC Information Notices (ins)

The inspector reviewed the licensee's evaluation for the following NRC

ins:

-

IN 92-18 Potential Loss of Shutdown Capacity During a Control

Room Fire

-

IN 92-28. Inadequate Fire Suppression System Testing

,

-

IN 93-41, One Hour Fire Endurance Tests Results For Thermal

Ceramics, 3M Company FS 195 and 3M Company E-50 Interim Fire

Barrier Systems

Enclosure 2

- .- . . = - . - - - . ,-

'

,

.

- 25 -

-

IN 94-28 Potential Problems with Fire Barrier Penetration Seals

-

IN 94-31 Potential Failure of WILCO, LEXAN-Type HN-4-L. Fire Hose

Nozzles

-

IN 94-58 Reactor Coolant Pump Lube Oil Fire

-

IN 95-36. Emergency Lighting

The licensee's evaluations and corrective actions for these ins were

appropriate, except that the evalcation for IN 92-18 had not been

completed.

The licensee's review of this issue identified a number of UFSAR

discrepancies. Most of these discrepancies were related to 10 CFR 50

Apperiix R safe shutdown components and their performance following an

A3pendix R fire. A number of apoarent errors were identified related tc

t1e safe shutdown components listed in UFSAR Table 9.5.1-1. Following

the identification of these apparent errors in June 1994, the reviewing

organization initiated Licensing Document Change Request (LDCR)

No.94-029, to complete an evaluation and provide appropriate UFSAR

changes to correct these errors. These UFSAR changes to reflect actual

plant design conditions were not made.

Procedure 00402-C. Licensing Document Change Request (LDCR), requires  ;

the person identifying plant or licensing discrepancies'to complete LDCR

Figure 1. The originating department manager is required to implement

appropriate action to provide a safety evaluation on the identified

issue. This procedure was issued to provide instructions for making

changes to licensing documents such as the UFSAR. 10 CFR 50.71(e)

requires the UFSAR to be maintained to properly describe actual plant  ;

conditions. Revision 5 of the UFSAR was issued September 1995 but did

not address these items. In addition, since an LDCR had not been issued

to address these discre3ancies, the revision currently being made to the .

UFSAR did not include taese changes. The failure to implement the LDCR l

to maintain the UFSAR up to date for these Appendix R fire protection l

issues is identified as Violation 50-424, 425/97-01-03. Failure to l

Revise UFSAR to Conform to As-Built Appendix R Plant Configurations.  !

The inspectors reviewed the LDCR Coordinator's logbook and noted nine

additional requests for LDCR change numbers in which appropriate action

had not been taken for resolution. All of these involved items l

identified prior to 1996, as follows: one in 1989, one in 1990, three  !

in 1991, one in 1992, three in 1994, and one in 1995. The safety i

significance on these issues were not known since safety evaluations for

these items had not been completed.

i

.

Enclosure 2

r

.

i

i

__ _ _ . . _ ._ ... __ _ _... _ _ _ . _ _ . _ . . _ _ _ . . _._..m_

. .

s

- 26 -

i

F8.2 (Closed) VIO 50-424. 425/96-09-05. Control of transient combustibles.  ;

This violation identified-two examples of inadequate control over the

' storage of combustibles within the plant. The inspector verified that

the corrective ~ action initiated by the licensee on this issue was

complete, appropriate and adequate to prevent recurrence. i

V. Manaaement Meetinas and Other Areas

X Review of Updated Final Safety Analysis Report (UFSAR)  :

A recent discovery of a licensee o)erating its facility in a manner

contrary to the UFSAR description lighlighted the need for a special

focused review that compares plant practices' procedures and/or

parameters to the UFSAR descriptions. While performing the inspections

discussed in this- re) ort, the inspectors reviewed the applicable  :

portions of the UFSAR that related to the areas inspected. The

inspectors verified that the UFSAR wording was consistent with the >

observed plant, practices, procedures and/or parameters.

X1. Exit Meeting Summary

The inspectors ) resented the inspection results to members of licensee

-

management at tie conclusion of the inspection on March 19, 1997, The  !

licensee acknowledged the findings presented.-

The inspectors asked the licensee whether any materials examined during

the inspection should be considered proprietary. No proprietary

information was identified.

' X2' Pre Decisional Enforcement Conference Summary )

.

On March 10, 1997, a pre-decisional enforcement conference was held at

the Nuclear Regulatory Commi:dion (NRC) Region II office to discuss

potential enforcement issues identified in Inspection Report (IR)

50-424, 425/96-14. Discussion focused on configuration control issues

identified in that report as well as others identified over the last

eightecn months.

,

PARTIAL LIST OF PERSONS CONTACTED

Licensee

, J. Beasley. Nuclear Plant General Manager

. B. Brown. Plant Training and Emergency Preparedness Manager

i W. Burmeister.' Manager Engineering Support

,.

{ Enclosure 2

<

~ - .- -. . . .. . . - .. .-

-

. .

.

- 27 -

J. Gasser. Plant Operations Assistant General Manager

P. Rushton, Plant Support Assistant General Manager

S. Chestnut. Manager Operations

K. Holmes. Manager Maintenance

M. Sheibani. Nuclear Safety and Compliance Supervisor

C. Tippins Jr., Nuclear Specialist I

REFERENCED PROCEDURES AND DRAWINGS I

-

Drawing 2X4DB161-1 Revision 24. Condensate Storage and Degasifier

System

-

Drawing 2X4DB161-2. Revision 21. AFW System _

i

-

T-0PER 95-003. Revision 0. Fire Suppression System REA VG-2720 i

Flow Verification

-

Procedure 00402-C. Revision 15. LDCR i

-

Procedure 11610-1. Revision 13. AFW System Alignment )

-

Procedure 11610-2. Revision 15. AFW System Alignment  !

-

Procedure 11867-2. Revision 20. Safety Related Locked Valve

Procedure 11881-1/2. Auxiliary Building Round Sheets.  !

-

Procedure 14000-1. Revision 57. Operations Shift and Daily '

Surveillance Logs

-

Procedure 14000-2. Revision 41. Operations Shift and Daily

Surveillance Logs  !

-

Procedure 14495-2. Revision 3. AFW System Flow Path Verification

-

Procedure 14951-C. Revision 5. Fire Suppression System Operability

Test (Fire Pumps). Monthly

-

Procedure 14952-C. Revision 5. Fire Suppression System Operability

Test (Fire Pumps). Annually

-

Procedure 14956-C. Revision 2. Fire Suppression - 3-Year Flow

Verification

-

Procedure 17017-1. Revision 10. Annunciator Response Procedures

for ALB 17 on Panel 1B2 on Main Control Board

-

Procedure 17017-2. Revision 7. Annunciator Response Procedures for

ALB 17 on Panel 182 on Main Control Board

-

Procedure 24362-1. Revision 10. ESF Chiller Chilled Water Flow

Trains A and B 1F-22425/1F-22426 Channel Calibration

Verification Checklist  ;

-

Procedure 29227-1 and -2. Revision 1. Fire and Smoke Detector

Operational Test (Panel LZIP 2-1813-03-F27

-

Procedure 29231-1 and -2. Revision 2. Fire and Smoke Detector

Operational Test (Panel LZIP 1-1813-03-F31

-

Procedure 92000-C. Revision 11. Fire Protection Program

-

Procedure 92005-C. Revision 8. Fire Response Procedure

l

"

-

Procedure 92010-C. Revision 10. Control of Ignition Sources

-

Procedure 92015-C. Revision 14. Use. Control and Storage of

Flammable / Combustible Materials ,

-

Procedure 92030-C. Revision 6. Fire Drill Program

Enclosure 2

L

. .

. .

l

t

- 28 -

-

Procedure 92035-C. Revision 9. Fire Protection Operability

Requirements

-

Procedure 92040-C. Revision 12. Fire Protection LC0 Program

INSPECTION PROCEDURES USED

IP 37551: Onsite Engineering

IP 40500: Effectiveness of Licensee Controls In Identifying. Resolving and

Preventing Problems

IP 52002: Digital Retrofits not Receiving Prior Approval

IP 61726: Surveillance Observations

IP 62707: Maintenance Observations

IP 64704: Fire Protection / Prevention Program

IP 71707: Plant Operations 1

IP 71750: Plant Support Activities l

IP 92904: Followup - Plant Support

ITEMS OPENED AND CLOSED

Ooened l

i

50-425/97-01-01 VIO AFW System Surveillance Not Conducted As

Required By TS (Section M3.1).

50-424, 425/97-01-02 VIO Failure To Demonstrate Fire Detectors Were

, Operable At least Once Per 12 Months

l

(Section F2.2).

50-424, 425/97-01-03 VIO Failure to Revise UFSAR To Conform to As-Built

Appendix R Plant Configurations (Section F8.1).

50-424, 425/97-01-04 VIO Inadequate Testing of 701 Governor - Two ,

Examples (Sections E7.1 and E7.2).  !

I 50-424. 425/97-01-05 VIO Failure to Maintain Records of 701 DSC Setpoints

l (Section E7.2). ,

!

50-424, 425/97-01-06 VIO 10 CFR 50.59 Unreviewed Safety Question

l Determination for Woodward 701 Governor

(Section E7.4).  :

Closed

50-424. 425/96-02-05 URI CST Minimum Water Volume Required By TSs

(section E8.1)

50-424. 425/96-09-05 VIO Control Of Transient Combustibles (section F8.2)

'

Enclosure 2

..,

- - , , . __. . . . . -

'

. . ,

.

- 29 -

LIST OF ACRDNYMS USED

AFW - Auxiliary Feedwater System

CES - Cooper Energy Services

CFR - Code of Federal Regulations

CST - Condensate Storage Tank

dB - decibel

DC - Deficiency Card

DCP - Design Change Package

DG - Diesel Generator

DSC - Digital Speed Control

EMI - Electromagnetic Interference  !

'

EP - Emergency Preparedness

ESF - Engineered Safety Feature

FP - Fire Protection

GLC - Generator Loading Control

GLS - Generator Load Sensor

I&C - Instrumentation and Controls

IN - Information Notice

ISEG - Independent Safety Engineering Group

IST - Inservice Test

ITS - Improved Technical Specifications

'

LCO - Limiting Condition for Operation

,

'

LDCR - Licensing Document Change Request

MDAFW - Motor Driven Auxiliary Feedwater

MWO - Maintenance Work Order

NPF - Nuclear Power Facility

NRC - Nuclear Regulatory Commission '

NSCW - Nuclear Service Cooling Water

NTS - National Technical System

NUREG - Nuclear Regulations

PE0 - Plant Equipment Operator

l . PDR - Public Document Room

l PRB - Plant Review Board

l OA - Quality Assurance

!

RCS - Reactor Coolant System

RHR - Residual Heat Removal System

RWST - Refueling Water Storage Tank

SR - Surveillance Requirement

SVVP - Software Verification and Validation Plan

TS - Technical Specifications

1 UFSAR - Updated Final Safety Analysis Report

l URI - Unresolved Item l

!

USS - Unit Shift Supervisor

V&V - Verification and Validation

VIO - Violation )

.

'

WGC - Woodward Governor Company  ;

2R5 - Unit 2 Fifth Refueling Outage I

i

4

Enclosure 2 i

4.

-

l

!