Letter Sequence ' |
---|
|
|
MONTHYEARML20074A7561983-04-27027 April 1983 Clarifies Proposed Changes in Undervoltage Protection & Reiterates Schedule for Implementation of Design Changes & Mods.Existing non-Class IE Undervoltage Relays Will Be Retained as Protection for 4,160-volt Buses Project stage: Request ML20212N6621985-08-31031 August 1985 Technical Evaluation Rept for Proposed Change to Operation of Ginna Fuel Pool Charcoal Filter Sys, Informal Rept Project stage: Request ML20135H5631985-08-31031 August 1985 Truth-Analysis/Action-Reaction Review of 480-Volt Essential Bus Tie Breaker Control Scheme, Final Rept Project stage: Other ML20137S3631985-09-13013 September 1985 Corrected Page 1 to Responding to 850614 Commitment to Perform Evaluation of Emergency Diesel Generator Control Logic Circuitry.Ltr Number Changed Project stage: Other IR 05000267/19850171985-09-13013 September 1985 Insp Rept 50-267/85-17 on 850617-0816.Violation Noted: Failure to Rept Nine Circulator Trips in 1984 & Seven Trips in 1985 & No Differential Helium Pressure Maintained When Pcrv Pressure Above 100 Psia Project stage: Request ML20135H5591985-09-13013 September 1985 Forwards Truth-Analysis/Action-Reaction Review of 480-Volt Essential Bus Tie Breaker Control Scheme, Final Rept & Provides Evaluation of Control Logic Design Project stage: Other ML20134A3651985-10-23023 October 1985 Amends Correction Portion of Item 2 (286G1A & 286G1B) in Util Re Results of Proto-Power Corp Analysis Concerning Emergency Electrical Power Sys Independence Project stage: Other ML20137B3561986-01-0303 January 1986 Informs That Design Changes Involving Emergency Diesel Generator (EDG) Control Logic Circuitry Implemented.No Single Failure Will Interfere W/Proper Operation of Redundant EDG Project stage: Other ML20137K9991986-01-14014 January 1986 Notifies That Design Changes in Emergency Diesel Generator Control Logic Circuitry Implemented,Per 850913 Commitment. Changes Assure That Failure Will Not Interfere W/Operation of Redundant Generator.Ltr Supersedes Project stage: Other ML20140H1101986-03-31031 March 1986 Submits Info Re Startup Check List for Automatic Operation of Emergency Diesel Generators,Sys Operating Procedure 92-04,in Response to NRC .Numbers Will Be Assigned to All Valves in Emergency Diesel Generator Rooms Project stage: Other ML17251A7911986-03-31031 March 1986 Reactor Containment Bldg Integrated Leakage Rate Test. Project stage: Request ML20206T7341986-07-0101 July 1986 Submits Summary & Schedule of Mods to Be Performed on Emergency Diesel Generator Control Circuitry in Response to 860515 & 21 Telcons.Mods Will Be Completed Prior to Startup from Current Equipment Qualification Outage Project stage: Other ML20213G5811986-08-0707 August 1986 Draft Review of Fort St Vrain Onsite AC 'Standby' Power Sys W/Regards to Compliance to Single Failure Criterion & Ser Project stage: Draft Other ML20213G5641986-11-12012 November 1986 Forwards Onsite Class 1E Power Sys Design Features Review Status Rept Based on FSAR & NRC 860814 Meeting W/Licensee & Inel Draft Review of Fort St Vrain Onsite AC 'Standby' Power.... Resolution to Problems Requested Before Restart ML20212D8641986-12-24024 December 1986 Summary of 861209 Meeting W/Util Re Plant Emergency Electrical Power Sys.Fsar Commitment Re Emergency Diesel Generators revised.Marked-up Draft Rept Re Ac Standby Power Sys Encl ML20212G8671987-01-0909 January 1987 Forwards Rev a to EE-92-0008, Engineering Evaluation of Load Shedding,Load Auto Start Prohibit,Load Sequencing,Bus Tie Breaker Alignment & Generator Breaker Closing Portions of Emergency Diesel Generator Control Circuitry Project stage: Other ML20207R9471987-03-0606 March 1987 Rev 1 to Review of Fort St Vrain Onsite AC `Standby' Power Sys Re Compliance to Single Failure Criterion & Ser Project stage: Other ML20207R9381987-03-0606 March 1987 Forwards Rev 1 to EGG-NTA-7456, Review of Fort St Vrain Onsite AC `Standby' Power Sys Re Compliance to Single Failure Criterion & Ser Project stage: Approval ML20207S6271987-03-12012 March 1987 Summary of 870210 Meeting W/Util Re Emergency Diesel Generator Electrical Independence.List of Attendees Encl Project stage: Meeting 1986-11-12
[Table View] |
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20205G8771999-03-26026 March 1999 Forwards Copy of Cover Page from Fort St-Vrain Welding Manual,Which Had Been Listed as Encl on Page 4 of 990325 Reply to EA 98-081.Cover Page Had Been Inadvertently Left Out with Original Reply ML20197H8811998-12-0101 December 1998 Forwards Proposed Change to Fsv ISFSI Physical Protection Plan in Which Commitment Is Made to Provide Feature to Security Posture for Facility ML20236R9191998-07-20020 July 1998 Ltr Contract:Mod 4 to Task Order 27, Task Area No 4 of Basic Contract - Fort St Vrain Insp Under Contract NRC-02-95-003 ML20199H8141997-11-21021 November 1997 Responds to Requesting Clarification as to Whether Increase in Tritium & Iron-55 Contamination Limits That Were Approved for Plant Apply to All Licensees ML20198K1931997-10-10010 October 1997 Provides Supplemental Info in Support of Util Proposed Rev to Physical Security Plan for Plant Plant Isfsi.Plan Withheld,Per 10CFR2.790(d) & 10CFR73.21 ML20198H5601997-09-16016 September 1997 Final Response to FOIA Request for Documents.Documents Listed in App a Being Released in Entirety ML20141F3521997-05-14014 May 1997 Forwards Proposed Issue 4 of Physical Security Plan for Fort St Vrain ISFSI for Review & Approval.Encl Withheld,Per 10CFR2.790(d) ML20141C8611997-05-0909 May 1997 Informs of Approval of Fsv Final Survey Rept & Effluent Pathway Survey Plan & Supporting Analysis ML20141K9881997-05-0505 May 1997 Forwards Amend 89 to License DPR-34 & Supporting Safety Evaluation.Amend Designates All Elements of Approved Decommissioning Plan as License Termination Plan ML20138G2701997-04-28028 April 1997 Provides Response to NRC Comments Re Proposed Sampling & Survey Plan for Fsv Effluent Pathway.Response Documents Fsv Liquid Effluent Discharge Pathway Areas Are Acceptable for Release for Unrestricted Use IAW Draft NUREG/CR-5849 ML20148D4651997-04-24024 April 1997 Forwards Revised Interim Ltr Rept Which Describes Procedures & Results of Confirmatory Survey of Group E Effluent Discharge Pathway Areas at Fsv Station NUREG/CR-5849, Requests That Licensee Provide Evidence That Average Contamination Levels in Group E Effluent Discharge Pathway Areas Meet Averaging Criteria in Draft NUREG/CR-58491997-04-23023 April 1997 Requests That Licensee Provide Evidence That Average Contamination Levels in Group E Effluent Discharge Pathway Areas Meet Averaging Criteria in Draft NUREG/CR-5849 ML20138B0511997-04-22022 April 1997 Forwards Copy of Proposed Amend to Fsv NPDES Permit, Wastewater Discharge Permit CO-0001121 Requested to Support Repowering Activities,Iaw Section 3.2.d of Fsv Non-Radiological Ts,App B to License DPR-34 ML20140E1061997-04-10010 April 1997 Forwards Confirmatory Survey of Group Effluent Discharge Pathway Areas for Fsv Nuclear Station,Platteville,Co ML20137S4481997-04-0808 April 1997 Informs That Decommissioning Activities at Fsv Are Complete & NRC Issued Exemption from Requirements of 10CFR50.54(w) in .Property Damage Insurance Policy Is Maintaned to Protect Fsv balance-of-plant Assets ML20137S0821997-04-0707 April 1997 Forwards Insp Rept 50-267/97-01 on 970310-11.No Violations Noted ML20137S1691997-04-0707 April 1997 Fifth Partial Response to FOIA Request for Documents. Forwards Documents Listed in App K ML20137S5421997-04-0707 April 1997 Forwards Final Quarterly 10CFR50.59 Rept of Changes,Tests & Experiments Affecting Decommissioning of Fort St Vrain Nuclear Station ML20148D5951997-04-0404 April 1997 Forwards Confirmatory Survey for Fsv Nuclear Station, Psc,Platteville,Co, Final Rept ML20137R6921997-04-0404 April 1997 Informs of Approval for Request for Addl 45 Days to Remedy Deficiencies Identified in NRC Re Financial Assurance Mechanism for Fsv Decommissioning Costs ML20137J8051997-03-31031 March 1997 Third Partial Response to FOIA Request for Documents.Records in App F Encl & Will Be Available in Pdr.App G & H Records Withheld in Part (Ref FOIA Exemptions 5 & 7) ML20148D5811997-03-26026 March 1997 Forwards Confirmatory Survey Plan for Group E Effluent Discharge Pathway Areas at Fsv Nuclear Station, Covered in Final Survey Rept,Vol 6 ML20137G7361997-03-25025 March 1997 Requests Addl Time for Util to Respond to NRC Comments in Re Financial Assurance Mechanism for Fort St Vrain Decommissioning Costs ML20137G9521997-03-24024 March 1997 Forwards Quarterly 10CFR50.59 Rept for Period 961201-970228 Re Changes,Tests & Experiments for Fort St Vrain Decommissioning ML20137H1131997-03-24024 March 1997 Second Partial Response to FOIA Request for Documents. Forwards Documents Listed in App D.Documents Also Available in Pdr.Documents Listed in App E Withheld in Part (Ref FOIA Exemption 6) ML20137C0181997-03-18018 March 1997 Documents That No Personnel Has Received Radiation Exposure at Fsv in 1997 or at Any Time Subsequent to ML20137C0061997-03-18018 March 1997 Documents That There Have Been No Activities Involving Release of Radioactive Matls from Fsv Nuclear Station That Potentially Could Have Affected Environ,Subsequent to Previous Radiological Envion Operating Rept ML20136G1201997-03-11011 March 1997 Forwards Annual Radioactive Effluent Release Rept for Jan- Dec 1996 & Jan-Mar 1997. All Effluent Releases Completed as of 960703.Repts on Activities After 960703 Reflect Disposal of Solid Waste ML20136B1331997-02-28028 February 1997 First Partial Response to FOIA Request for Documents. Documents Listed in App a Already Available in Pdr.Forwards App B Documents.App C Documents Being Withheld in Entirety (Ref FOIA Exemption 5) ML20135D7891997-02-27027 February 1997 Forwards Responses to Comments Re Fort St Vrain Final Survey Rept ML20135D9531997-02-27027 February 1997 Forwards Copy of Amend to Util Npdes,Wastewater Discharge Permit CO-0001121,which Clarifies That Monitoring of Farm Pond Outlet Required When Industrial Wastewater Being Discharged Through Upstream Goosequill Ditch ML20135A8711997-02-14014 February 1997 Requests That Encl Deficiencies Identified in Financial Assurance Mechanism for Fort St Vrain Decommissioning Cost Be Addressed within 45 Days ML20134D1551997-01-31031 January 1997 Forwards Util Responses to NRC Comments Provided in NRC Ltr Re Sampling & Survey Plan Used for Final Radiological Survey of Liquid Effluent Pathway at Ft St Vrain ML20134C8481997-01-30030 January 1997 Forwards Draft Confirmatory Survey Rept for Fsv Nuclear Station,Psc,Platteville,Co Providing Info on Essap Activities on 960930-1003 ML20133L4961997-01-0707 January 1997 Forwards Comments That Need to Be Resolved Before Final Approval of Util Submittal Entitled, Proposed Sampling & Survey Plan for Effluent Pathway,Ft St Vrain Final Survey Program ML20133E0481997-01-0202 January 1997 Forwards Comments to Fsv Nuclear Station, Decommissioning Project Final Survey Rept (Volumes 4-11), for Consideration ML20132G0421996-12-23023 December 1996 Forwards Insp Rept 50-267/96-05 on 961203-05.No Violations Noted ML20132F2841996-12-19019 December 1996 Forwards Quarterly 10CFR50.59 Rept of Changes,Tests & Experiments Affecting Decommissioning of Plant,Covering Period of 960901-1130 ML20133A8591996-12-16016 December 1996 Forwards Original & Copy Transcripts of Public Hearing,Held on 961203 in Platteville,Co Re Decommissioning & License Termination of Util Ft Saint Vrain Nuclear Generating Station ML20133N0011996-12-0404 December 1996 Recommends That NRC Require License to Modify Submission of Unexecuted Draft Trust Agreement Remaining Decommissioning Costs for Ft St Vrain Nuclear Generating Station in Listed Ways ML20135B3861996-11-25025 November 1996 Informs That NRC Reviewed Util 961114 Submittal (P-96096) Entitled, Fort St Vrain Final Emergency Response Plan, & Meets Requirements of 10CFR50.54(q) ML20135A5861996-11-25025 November 1996 Submits Suppl Info Re Annual Environ Rept for 1995 Operation of Fsv ISFSI ML20135A6361996-11-20020 November 1996 Submits Copy of Describing Discharge Practices for Groundwater Seeping Into Fsv'S Reactor Building Sump ML20134L4721996-11-14014 November 1996 Notifies NRC That Util Adopted Fsv ISFSI Emergency Response Plan to Direct Emergency Response for Radiological Accidents Occuring at Site,Until 10CFR50 License Is Terminated ML20134F4351996-10-30030 October 1996 Forwards Sections 1,2,6 & 8 from Survey Packages F0015, F0039 & F0126 & Sections 1,2 & 6 from Survey Package F0115 to Support on-site NRC Insp ML20134G5991996-10-30030 October 1996 Forwards Volumes 1-12 to Final Survey Rept for Groups A,B,C Rev 1,D Rev 1,E,F Rev 1 & G-J for NRC Approval in Support of Forthcoming Request for Termination of Fsv 10CFR50 License ML20133D7691996-10-22022 October 1996 Forwards Preliminary Rept Re Orise Support of NRC License Insp at Fsv on 960930-1003 ML20136B1411996-10-15015 October 1996 FOIA Request for Documents Re NOV Addressed to Scientific Ecology Group Re NRC Insp Rept 50-267/94-03 & OI Investigation Repts 4-94-010 & 4-95-015 ML20128M6181996-10-0404 October 1996 Forwards Ltr from PSC to Co Dept of Public Health & Environ Describing Monitoring Practices at Plant ML20128G8041996-10-0101 October 1996 Forwards Fsv Decommissioning Fire Protection Plan Update 1999-03-26
[Table view] Category:NRC TO UTILITY
MONTHYEARML20058J0121990-11-16016 November 1990 Forwards Insp Rept 50-267/90-20 on 901029-1102.Violations Noted But Not Cited IR 05000267/19900161990-10-30030 October 1990 Discusses Insp Rept 50-267/90-16 on 900928 & 901018 Enforcement Conference & Forwards Notice of Violation ML20062B3971990-10-15015 October 1990 Forwards Insp Rept 50-267/90-14 on 900801-0930.No Violations or Deviations Noted ML20058A0941990-10-12012 October 1990 Confirms 901018 Enforcement Conference in Region IV Ofc Re Violations & Radiation Program Weakness Noted in Insp Rept 50-267/90-16.Proposed Agenda Encl ML20059N8231990-10-0303 October 1990 Forwards FEMA Final Radiological Emergency Preparedness Exercise Rept, for 891115 Exercise.One Deficiency & Several Areas Requiring Corrective Actions Identified ML20059C1381990-08-24024 August 1990 Forwards Notice of Consideration of Issuance of Amend to License DPR-34 & Opportunity for Hearing Re 900605 Application,For Info ML20056B4021990-08-20020 August 1990 Forwards Insp Rept 50-267/90-11 on 900601-0728.No Violations or Deviations Noted ML20058M8681990-08-0808 August 1990 Forwards Insp Rept 50-267/90-13 on 900709-13.No Violations or Deviations Identified.Licensee Commitment to Revise Manual Dose Assessment Procedure to Incorporate Appropriate Unit Conversion Factor,Noted ML20055J3951990-07-31031 July 1990 Ack Receipt of 900713 Request for Exemption from FY90 Annual Fee Requirements of 10CFR171.Annual Fee Will Not Be Billed ML20056A3601990-07-31031 July 1990 Forwards Insp Rept 50-267/90-10 on 900611-15.No Violations or Deviations Noted.Actions Taken Re Previously Identified Insp Findings & Status Examined ML20059D1281990-07-30030 July 1990 Ack Receipt of 900713 Request for Full Exemption from FY90 Annual Fee Requirements of 10CFR171 for Plant.Annual Fee Will Not Be Billed While Request Under Review ML20055G5921990-07-19019 July 1990 Agrees W/Removal of B Helium Circulator,Per Requesting NRC Concurrence.Solution to Correct Leakage Problem by Removal of Circulator Acceptable ML20055D2031990-06-26026 June 1990 Ack Receipt of 900525 Response to 900402 Emergency Preparedness Insp Rept & 900427 Notice of Violation ML20055C8021990-06-18018 June 1990 Concludes That Financial Info Forwarded by Meets Requirements of 10CFR140.21 ML20248H7751989-10-0303 October 1989 Forwards Insp Rept 50-267/89-19 on 890821-26 & 29-30.No Violations or Deviations Noted IR 05000267/19890171989-10-0202 October 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-267/89-17. Implementation of Corrective Actions Will Be Examined During Future Insps IR 05000267/19890081989-10-0202 October 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-267/89-08. Understands That Revised Flow Test Surveillance Procedures Performed on 890821 & 0921 & cross-connect Valves Stroked ML20248B2971989-09-26026 September 1989 Forwards Insp Rept 50-267/89-16 on 890716-0831 & Notice of Violation IR 05000267/19890121989-09-22022 September 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violation Noted in Insp Rept 50-267/89-12 ML20247L1381989-09-19019 September 1989 Advises That Request to Delete Requirement to Provide Status Repts on Performance Enhancement Program Approved.Updated List of Commitments Encl ML20247K7741989-09-15015 September 1989 Informs That Partial Review of 890125 & 0320 Submittals Re Helium Circulators complete.Ten-yr Insp Recently Conducted on Circulator C-2105.Insp Revealed No Defects or Unacceptable Conditions ML20247K4141989-09-15015 September 1989 Advises That Tech Specs Re Upgrade Program,Requested in NRC ,Must Be Approved by NRC Before Defueling ML20247D4691989-09-11011 September 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-267/89-15 ML20247H3431989-09-0808 September 1989 Ack Receipt of Informing NRC of Status of Security Sys Upgrades ML20247H2891989-09-0606 September 1989 Concurs W/Util 890714 Request for Changes to Basis for Limiting Condition for Operation 4.2.2 of Facility Tech Specs Re Statement About Automatic Initiation of Backup Bearing Water Sys ML20247B2661989-08-30030 August 1989 Forwards Summary of Region Iv/Senior Util Executives Meeting on 890818 in Arlington,Tx.Topics Discussed Included, Improving Communications,Salp Process in Region IV & Enforcement.List of Attendees & Agenda Encl ML20246J2911989-08-30030 August 1989 Forwards Amend 72 to License DPR-34 & Safety Evaluation. Amend Imposes Early Shutdown by Limiting Reactor Power to 2% of Full Power After 900630 ML20246E5941989-08-21021 August 1989 Forwards Insp Rept 50-267/89-14 on 890710-14 & Notice of Violation.Two Separate Findings of Missing Info in Semiannual Effluent Rept,Resulting in Failure to Satisfy Tech Spec Administrative Requirements Identified ML20246A2651989-08-16016 August 1989 Forwards Insp Rept 50-267/89-13 on 890626-30.Violations Noted But No Citation Issued.Expresses Concern About Status of Model FSV-1 & FSV-1A Shipping Casks ML20245J3511989-08-14014 August 1989 Forwards Amend 71 to License DPR-34 & Safety Evaluation. Amend Revises Provisions in Tech Specs Re Radiological Effluents ML20246A6841989-08-14014 August 1989 Forwards Exam Rept 50-267/OL 89-02 Administered During Wk of 890710 ML20245J5651989-08-10010 August 1989 Forwards Insp Rept 50-267/89-17 on 890717-21 & Notice of Violation ML20245H3891989-08-0808 August 1989 Forwards Insp Rept 50-267/89-12 on 890601-0715 & Notice of Violation ML20245J4421989-08-0808 August 1989 Forwards Safety Evaluation,Responding to Issues Re Tech Spec Upgrade Program & Defueling of Plant.Requests That Tech Spec Changes Be Requested within 30 Days of Ltr Date ML20248E0041989-08-0303 August 1989 Forwards Team Insp Rept 50-267/89-08 on 890522-26 & Notice of Violation.Response Should Include Corrective Actions Taken or Planned to Ensure That Reactor Water Cooling Sys 46 Operated as Designed IR 05000267/19890071989-07-28028 July 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-267/89-07 ML20247N7581989-07-26026 July 1989 Discusses Licensee 890616 Request Re Changes to Previous Commitments Concerning Plans to Shut Down Plant.Commitment 2c to Be Subj of Separate Correspondence.Commitment 7 to Be Considered Not Applicable.W/Revised Summary of Commitments ML20247M4281989-07-25025 July 1989 Responds to 890120 & 0616 Requests for Relief from Requirements of Fuel Surveillance Program.Nrc Considers Util Obligations Under Fuel Surveillance Program Will Terminate W/Planned Shutdown of Reactor by 900630 ML20247M4521989-07-25025 July 1989 Forwards Request for Addl Info Re Reactor Defueling.Info Needed within 30 Days of Ltr Date ML20247L9801989-07-14014 July 1989 Discusses 890711 Meeting in Region IV Ofc Re Introduction of AC Crawford & Future Plans for Facility.Slides Presented at Meeting & List of Attendees Encl ML20247L5971989-07-14014 July 1989 Forwards Insp Rept 50-267/89-15 on 890623-27 & Notice of Violation.Response Should Describe Corrective Actions to Assure That safety-related Changes Introduced by Other Parts of Organization Are Properly Incorporated Into Procedures ML20246M6941989-07-11011 July 1989 Forwards Agenda for 890808 Meeting of Senior Util Executives Sponsored by Region IV at Univ of Texas.Map to Facilitate Access to Meeting Room Also Encl ML20246F4851989-07-10010 July 1989 Discusses Util Re Alternative Compensatory Measures Instituted,Per Fire Protection Operability Requirement-16.Proposed Guidance Adequate ML20246J2791989-07-0707 July 1989 Forwards Safety Evaluation Concluding That Operators Role in Mitigating High Energy Line Break at Facility Acceptable. Technical Evaluation Rept Also Encl ML20245G4491989-06-22022 June 1989 Forwards Exam Rept 50-267/OL-89-01 Administered During Wk of 890523 ML20245G4831989-06-20020 June 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-267/89-06 ML20245F8161989-06-20020 June 1989 Proposes Meeting in Region IV to Discuss SALP Process in Region Iv,Improving Communication W/Licensee Mgt,Region IV Enforcement Philosophy,How to Improve Safety Performance & Topics Util Wishes to Discuss ML20245A2201989-06-15015 June 1989 Forwards Insp Rept 50-267/89-10 on 890501-31.No Violations or Deviations Noted ML20244C1221989-06-0808 June 1989 Forwards Insp Rept 50-267/89-07 on 890319-0430 & Notice of Violation ML20248B8741989-06-0505 June 1989 Forwards Draft Reg Guide, Assuring Availability of Funds for Decommissioning Nuclear Reactors, Task CE 025-4,for Use in Preparing Preliminary Decommissioning Plan for Plant 1990-08-08
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20236R9191998-07-20020 July 1998 Ltr Contract:Mod 4 to Task Order 27, Task Area No 4 of Basic Contract - Fort St Vrain Insp Under Contract NRC-02-95-003 ML20199H8141997-11-21021 November 1997 Responds to Requesting Clarification as to Whether Increase in Tritium & Iron-55 Contamination Limits That Were Approved for Plant Apply to All Licensees ML20198H5601997-09-16016 September 1997 Final Response to FOIA Request for Documents.Documents Listed in App a Being Released in Entirety ML20141C8611997-05-0909 May 1997 Informs of Approval of Fsv Final Survey Rept & Effluent Pathway Survey Plan & Supporting Analysis ML20141K9881997-05-0505 May 1997 Forwards Amend 89 to License DPR-34 & Supporting Safety Evaluation.Amend Designates All Elements of Approved Decommissioning Plan as License Termination Plan NUREG/CR-5849, Requests That Licensee Provide Evidence That Average Contamination Levels in Group E Effluent Discharge Pathway Areas Meet Averaging Criteria in Draft NUREG/CR-58491997-04-23023 April 1997 Requests That Licensee Provide Evidence That Average Contamination Levels in Group E Effluent Discharge Pathway Areas Meet Averaging Criteria in Draft NUREG/CR-5849 ML20137S1691997-04-0707 April 1997 Fifth Partial Response to FOIA Request for Documents. Forwards Documents Listed in App K ML20137S0821997-04-0707 April 1997 Forwards Insp Rept 50-267/97-01 on 970310-11.No Violations Noted ML20137R6921997-04-0404 April 1997 Informs of Approval for Request for Addl 45 Days to Remedy Deficiencies Identified in NRC Re Financial Assurance Mechanism for Fsv Decommissioning Costs ML20137J8051997-03-31031 March 1997 Third Partial Response to FOIA Request for Documents.Records in App F Encl & Will Be Available in Pdr.App G & H Records Withheld in Part (Ref FOIA Exemptions 5 & 7) ML20137H1131997-03-24024 March 1997 Second Partial Response to FOIA Request for Documents. Forwards Documents Listed in App D.Documents Also Available in Pdr.Documents Listed in App E Withheld in Part (Ref FOIA Exemption 6) ML20136B1331997-02-28028 February 1997 First Partial Response to FOIA Request for Documents. Documents Listed in App a Already Available in Pdr.Forwards App B Documents.App C Documents Being Withheld in Entirety (Ref FOIA Exemption 5) ML20135A8711997-02-14014 February 1997 Requests That Encl Deficiencies Identified in Financial Assurance Mechanism for Fort St Vrain Decommissioning Cost Be Addressed within 45 Days ML20133L4961997-01-0707 January 1997 Forwards Comments That Need to Be Resolved Before Final Approval of Util Submittal Entitled, Proposed Sampling & Survey Plan for Effluent Pathway,Ft St Vrain Final Survey Program ML20132G0421996-12-23023 December 1996 Forwards Insp Rept 50-267/96-05 on 961203-05.No Violations Noted ML20135B3861996-11-25025 November 1996 Informs That NRC Reviewed Util 961114 Submittal (P-96096) Entitled, Fort St Vrain Final Emergency Response Plan, & Meets Requirements of 10CFR50.54(q) ML20128G1421996-09-25025 September 1996 Advises NRC Approved Decommissioning Plan, Impact Of... Fsv Final Decommissioning, Satisfies All Elements of License Termination Plan as Required by Rev to Reactor Decommissioning Rule 10CFR50.82(a)(9) ML20136B2561996-04-0202 April 1996 Informs That NOV Issued on 951030 Revised to Reflect NRC Reanalysis of Info Re Falsification of Radiation Survey Records.Revised NOV Encl ML20136B2731996-04-0202 April 1996 Informs That NOV Issued on 951030 Revised to Reflect NRC Reanalysis of Info Re Util Failure to Assure Compliance w/10CFR50.9 Concerning Accuracy of Radiation Survey Records. Revised NOV Encl ML20136B3241996-04-0202 April 1996 Informs That NRC Will Be Withdrawing NOV ,based on Reevaluation of Evidence Provided & Response to NOV ML20058G9671993-12-0707 December 1993 Ack Receipt of Ltrs of 931110,responding to Notice of Violation & Proposed Imposition of Civil Penalty Issued on 931013 IR 05000267/19930021993-09-0303 September 1993 Ack Receipt of Informing NRC of Steps Taken to Correct Deviations Noted in Insp Rept 50-267/93-02. Deficiency Determined to Have Contributed to 930527 Crane Overload Event IR 05000267/19930011993-09-0303 September 1993 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-267/93-01 ML20056G0041993-06-25025 June 1993 Submits Info Re Implementation of Training Rule 10CFR50.120 for Licensees of Plant in Decommissioning Process ML20128D6931992-12-0101 December 1992 Forwards Exemption from Requirement in 10CFR50,app E,Section IV.F.2 to Change to Biennial Emergency Plan Exercise Rather than Annual Following Completion of Next Scheduled Exercise. EA & SE Also Encl ML20198C7511991-06-25025 June 1991 Suggests That Region Iv/Senior Util Executive Conference Be Held During Month of Sept 1991 in Arlington,Tx to Provide Open Forum for Candid Discussions Limited to Topics of General Interest & Not Pertain to Plant Specific Issues ML20058K0231990-11-30030 November 1990 Forwards Insp Rept 50-267/90-17 on 901001-1109.No Violations or Deviations Noted ML20062H8131990-11-29029 November 1990 Forwards Partially Withheld Insp Rept 50-267/90-18 on 901022-26 & Notice of Violation ML20062H2041990-11-21021 November 1990 Forwards Insp Rept 50-267/90-19 on 901015-19.No Violations or Deviations Noted ML20058J0121990-11-16016 November 1990 Forwards Insp Rept 50-267/90-20 on 901029-1102.Violations Noted But Not Cited IR 05000267/19900161990-10-30030 October 1990 Discusses Insp Rept 50-267/90-16 on 900928 & 901018 Enforcement Conference & Forwards Notice of Violation ML20062B3971990-10-15015 October 1990 Forwards Insp Rept 50-267/90-14 on 900801-0930.No Violations or Deviations Noted ML20058A0941990-10-12012 October 1990 Confirms 901018 Enforcement Conference in Region IV Ofc Re Violations & Radiation Program Weakness Noted in Insp Rept 50-267/90-16.Proposed Agenda Encl ML20059N8231990-10-0303 October 1990 Forwards FEMA Final Radiological Emergency Preparedness Exercise Rept, for 891115 Exercise.One Deficiency & Several Areas Requiring Corrective Actions Identified ML20059C1381990-08-24024 August 1990 Forwards Notice of Consideration of Issuance of Amend to License DPR-34 & Opportunity for Hearing Re 900605 Application,For Info ML20056B4021990-08-20020 August 1990 Forwards Insp Rept 50-267/90-11 on 900601-0728.No Violations or Deviations Noted ML20058M8681990-08-0808 August 1990 Forwards Insp Rept 50-267/90-13 on 900709-13.No Violations or Deviations Identified.Licensee Commitment to Revise Manual Dose Assessment Procedure to Incorporate Appropriate Unit Conversion Factor,Noted ML20056A3601990-07-31031 July 1990 Forwards Insp Rept 50-267/90-10 on 900611-15.No Violations or Deviations Noted.Actions Taken Re Previously Identified Insp Findings & Status Examined ML20055J3951990-07-31031 July 1990 Ack Receipt of 900713 Request for Exemption from FY90 Annual Fee Requirements of 10CFR171.Annual Fee Will Not Be Billed ML20059D1281990-07-30030 July 1990 Ack Receipt of 900713 Request for Full Exemption from FY90 Annual Fee Requirements of 10CFR171 for Plant.Annual Fee Will Not Be Billed While Request Under Review ML20055G5921990-07-19019 July 1990 Agrees W/Removal of B Helium Circulator,Per Requesting NRC Concurrence.Solution to Correct Leakage Problem by Removal of Circulator Acceptable ML20055D2031990-06-26026 June 1990 Ack Receipt of 900525 Response to 900402 Emergency Preparedness Insp Rept & 900427 Notice of Violation ML20055C8021990-06-18018 June 1990 Concludes That Financial Info Forwarded by Meets Requirements of 10CFR140.21 ML20248H7751989-10-0303 October 1989 Forwards Insp Rept 50-267/89-19 on 890821-26 & 29-30.No Violations or Deviations Noted IR 05000267/19890081989-10-0202 October 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-267/89-08. Understands That Revised Flow Test Surveillance Procedures Performed on 890821 & 0921 & cross-connect Valves Stroked IR 05000267/19890171989-10-0202 October 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-267/89-17. Implementation of Corrective Actions Will Be Examined During Future Insps ML20248B2971989-09-26026 September 1989 Forwards Insp Rept 50-267/89-16 on 890716-0831 & Notice of Violation IR 05000267/19890121989-09-22022 September 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violation Noted in Insp Rept 50-267/89-12 ML20247K9051989-09-19019 September 1989 Advises That 890726 Request for Approval of Route to Transport Spent Reactor Fuel Approved.Route,From Facility to DOE Inel in Idaho,Encl ML20247L1381989-09-19019 September 1989 Advises That Request to Delete Requirement to Provide Status Repts on Performance Enhancement Program Approved.Updated List of Commitments Encl 1998-07-20
[Table view] |
Text
_
h, [ UNITED STATES y' [ g NUCLEAR REGULATORY COMMISSION L j WASHINGTON, D. C. 20555
% ,, November 12, 1986 Docket No. 50-267 Mr. R. O. Williams, Jr.
Vice President, Nuclear Operations Public Service Company of Colorado Post Office Box 840 Denver Colorado 80201-0840
Dear Mr. Williams:
SUBJECT:
FORT ST. VRAIN'S EMERGENCY ELECTRICAL POWER SYSTEM DESIGN COMPLIANCE WITH THE SINGLE FAILURE CRITERION - REVIEW STATUS REPORT
References:
- 1. NRC, Region IV letter (E. H. Johnson) to PSC (O. R.
Lee), dated July 10, 1985.
- 2. PSC's letter (D. W. Warembourg) to NRC, Region IV (P.R. Hunter),datedSeptember 13, 1986.
In Reference 1, we identified certain design discrepancies in the automatic control circuitry of the emergency diesel generator's (EDG's) circuit
, breakers, which compromised the independence requirements that Fort St.
Vrain (FSV) has committed to meet in the FSAR. Because of the inherent capability of the FSV design to withstand the total loss of AC power (i.e.,
all offsite power sources and the two class IE EDGs) for at least two hours without the need for cooling the core, the plant was allowed to operate in the interim, while the necessary modifications in the breaker's automatic control circuitry were being incorporated. These modifications eliminate the single failure problems. Also, the FSV design provides for an alternate cooling method (ACM), which includes a non-class IE power source that is independent from the offsite power sources and class IE EDGs. Furthermore, Reference 1 indicated that no single failure in the automatic control circuit of the EDGs' circuit breakers (preventing both of them from closing) would result in the loss of manual capability to close at least one EDG circuit breaker. The manual operation of these EDG breakers or the manual initiation of the ACM could readily be accomplished within the time frame available to assure core cooling.
In Reference 2, Public Service Company of Colorado (PSC) submitted a response to our concerns and proposed certain wiring changes to eliminate the discrepancies identified in Reference 1. The submittal was reviewed by our contractor, EG8G Idaho, Inc., whose findings are contained in the enclosed draft Technical Evaluation Report (TER) (Enclosure 2).
At FSV, the class IE electric power system is comprised of three buses (two redundant and one swing bus) with two 100% load capacity EDGs and an 8611180203 861112 PDR ADOCK 05000267 P PDR
)
. _- .- - - .- .. - . - - - - - _ .~ .
/
.I Mr. R. O. Williams, Jr. 4 1
offsite power source connection to each bus. A loss of voltage or degraded voltage condition from the offsite power sources reflected on any two of the three class 1E buses would result in the automatic starting of both EDGs.
The EDG that attains the rated voltage and frequency first is automatically connected to its asscciated bus and the swing bus. The DC control power i
for breakers on each of the three buses is provided from two redundant, 125 volt class IE battery supplies. The FSV design also provides for a non-class
- IE, non-redundant system, which includes the ACM diesel generator.
In Reference 1, we identified that the automatic closing circuit of one
, redundant EDG circuit breaker is dependent on the operation of relays or contacts associated with the other redundant EDG circuit breaker. As such, the interlocks from one division used in the breaker close circuitry of the other division, could potentially prevent the operation of both circuits due 4 to a single interlock failure. In the case of the DC control supply to the 1
breakers on each of the three buses, the FSV design provides automatic switching between the redundant divisions of the DC power supplies. We noted that a fault in one division could be propagated to the redundant l counterpart leading to the total loss of DC power.
1 To discuss your proposed modification (Reference 2) and the draft TER (Enclosure 2), a meeting was held among NRC staff EG8G's representatives, 2
and PSC's personnel on August 14, 1986. The staff explained why the proposed modification (Reference 2) fails to provide the required
, independence in the automatic control circuitry of redundant EDG circuit breakers. The staff also stated its concerns that the automatic switch-over of DC control power from one redundant division to the other can lead to i
the total loss of DC power.
1 In this meeting, the PSC personnel proposed a temporary modification in the i DC control power supply to the loss of voltage and degraded voltage logic i circuitry that provides signals to start the EDGs. This modification was
- necessary to eliminate a single failure problem in the logic, which PSC had recently identified (discussed in Enclosure 1). The staff noted that this 1
modification resolved a specific design problcm. However, the staff
, remains concerned about the vulnerability of.this design to the total loss of DC power from the existing automatic switch-over scheme. The PSC personnel agreed to examine the design and propose to implement a solution that will preclude the total loss of DC power as a result of a single j failure before restart of the plant. The addition of a third battery
- (preferred) or manual operation instead of the automatic switch-over scheme i between the redundant DC buses were presented as possible alternatives for
! resolving this problem. It is noted that these modifications must be done in such a manner that would not degrade the capability of the design to isolate the onsite AC system from the offsite power source during degraded grid conditions assuming a single failure. Also, the redundant portions of the standby AC system (EDGs) and the redundant portions of the DC supply
, should meet the single failure criterion. Since the proposed modifications i do not achieve the required independence in the automatic control circuitry
- of the EDG circuit breakers, the PSC personnel were requested to demonstrate that no single failure will disable the manual capabilities to r
i 1
j Mr. R. O. Williams, Jr. start the diesel generators, to close the EDG circuit breakers, and to start all necessary safety loads. In addition, PSC was requested to demonstrate that no single failure can cause paralleling of the redundant diesel generator sets, which may lead to the loss of both diesel generators. The acceptability of the design in these two cases must be established before restart of the plant.
Our discussion with your personnel identified differences among the actual design, system operation, and the FSAR. Also, the analysis performed by Proto Power Corporation (Reference 2) contained incorrect information, which PSC did not identify before submittal to the NRC. Our understanding of the proposed modifications and the operation of the class IE standby electric power systems, and its operation as described in the FSAR and by PSC in the meeting of August 14, 1986 is contained in our status report (Enclosure 1).
We request that PSC submit to us resolutions to these problems before restart of the plant. Your proposal should cover the major concerns addressed herein and contain a commitment to complete these changes on a well defined schedule. We would hold a second meeting with your staff approximately two weeks after your submittal was received to discuss and potentially accept your proposal as a basis for plant restart and continued operation.
A full description of the proposed modifications, the analysis to demonstrate manual capabilities as identified above, and the necessary FSAR changes to reflect the design capabilities of the as-built systems, should s be submitted for NRC review and approval prior to the actual changes being made.
The information requested in this letter affects fewer than 10 respondents; therefore, OMB clearance is not required under P.L.96-511.
Sincerely, R J 1-. h Kenneth L. Heitner, Project Manager Standardization and Special Projects Directorate Division of PWR Licensing-B Office of Nuclear Reactor Regulation
Enclosures:
As stated cc w/ enclosures:
See next page
November 12, 1986 Mr. R. 0. Williams, Jr. start the diesel generators, to close the EDG circuit breakers, and to start all necessary safety loads. In addition, PSC was requested to demonstrate that no single failure can cause paralleling of the redundant diesel generator sets, which may lead to the loss of both diesel generators. The acceptability of the design in these two cases must be established before restart of the plant.
Our discussion with your personnel identified differences among the actual design, system operation, and the FSAR. Also, the analysis performed by Proto Power Corporation (Reference 2) contained incorrect information, which PSC did not identify before submittal to the NRC. Our understanding of the proposed modifications and the operation of the class 1E standby electric power systems, and its operation as described in the FSAR and by PSC in the meeting of August 14, 1986 is contained in our status report (Enclosure 1).
We request that PSC submit to us resolutions to these problems before restart of the plant. Your proposal should cover the major concerns addressed herein and contain a commitment to complete these changes on a well defined schedule. We would hold a second meeting with your staff approximately two weeks after your submittal was received to discuss and potentially accept your proposal as a basis for plant restart and continued operation.
A full description of the proposed modifications, the analysis to demonstrate manual capabilities as identified above, and the necessary FSAR changes to reflect the design capabilities of the as-built systems, should be submitted for NRC review and approval prior to the actual changes being made.
The information requested in this letter affects fewer than 10 respondents; therefore, OMB clearance is not required under P.L.96-511.
Sincerely, Original signed by Kenneth L. Heitner, Project Manager Standardization and Special Projects Directorate Division of PWR Licensing-B Office of Nuclear Reactor Regulation
Enclosures:
DISTRIBUTION:
As stated Docket File PNoonan HBerkow NRC PDR KHeitner cc w/ enclosures: -
Local PDR 0 Lynch See next page PBSS Reading JCalvo P PBSS -
an KHeitner:ac ch PBPE /}%
JCalvo HBer PBS@kow lj /86 11/12/86 11/p/86 11/ n/86 11/ D/86
Mr. R. O. Williams Public Service Company of Colorado Fort St. Vrain cc:
Mr. D. W. Warembourg, Manager Albert J. Hazle, Director Nuclear Engineering Division Radiation Control Division Public Service Company Department of Health of Colorado 4210 East lith Avenue P. O. Box 840 Denver, Colorado 80220 Denver, Colorado 80201 Mr. David Alberstein, 14/159A Mr. J. W. Gahm, Manager GA Technologies, Inc. Nuclear Production Division Post Office Box 85608 Public Service Company of Colorado San Diego, California 92138 16805 Weld County Road 19-1/2 Platteville, Colorado 80651 Mr. H. L. Brey, Manager Nuclear Licensing and Fuel Division Mr. L. W. Singleton, Manager Public Service Company of Colorado Quality Assurance Division P. O. Box 840 Public Service Company of Colorado Denver, Colorado 80201 16805 Weld County Road 19-1/2 Platteville, Colorado 80651 Senior Resident Inspector U.S. Nuclear Regulatory Commission Mr. R. F. Walker P. 0. Box 840 Public Service Company of Colorado Platteville, Colorado 80651 Post Office Box 840 Denver, Colorado 92138 Kelley, Stansfield & 0'Donnell Public Service Company Building Commitment Control Program
, Room 900 Coordinator 550 15th Street Public Service Company of Colorado Denver, Colorado 80202 2420 W. 26th Ave. Suite 100-D Denver, Colorado 80211 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011 Chairman, Board of County Commissioners of Weld County, Colorado Greeley, Colorado 80631 Regional Representative Radiation Programs Environmental Protection Agency 1 Denver Place 999 18th Street, Suite 1300 Denver, Colorado 80202-2413
Enclosure 1 ONSITE CLASS 1E FORT ST. VRAIN (FSV)
POWER SYSTEMS DESIGN FEATURES REVIEW STATUS REPORT BASED ON THE FSAR AND AUGUST 14, 1986 MEETING WITH THE LICENSEE PUBLIC SERVICE COMPANY OF COLORADO DOCKET N0. 50-267
- 1) System Independence Paragraph 4 of Section 8.2.5.1 of the FSAR states:
"The onsite power supplies are completely independent and meet the single failure criterion."
Our review of emergency diesel generator (EDG) circuit breaker control circuitry revealed that single permissives or interlocks compromised the independence of redundant systems. In the August 14, 1986 meeting, the licensee indicated that the FSAR will be revised to indicate that the independence will be met only where it is consistent with the existing design. This would require a thorough review of all class IE Systems and an analysis to demonstrate that no single failure can disable both redundant systems.
Section 8.2.5.2 of the FSAR states:
" Loss of a DC Bus. The loss of a DC bus does not result in an unsafe condition, since two separate, normally independent systems are provided. A bus-tie switch is used to reenergize a DC bus from the other battery, if required.
The switchgear is provided with redundant DC control power supplies, so that failure of any one battery would not affect the operation of control circuits of any critical load. If one of the 125 V DC systems fails, control power to the switchgear affected is restored by switching to the alternate supply."
From this statement in the FSAR and its commitment to meet the redundancy and single failure criterion, it is inferred that the FSV design, which uses a bus-tie switch to restore the DC control power to one division equipment from the redundant division, will involve only a manual operation. However, the licensee has informed the staff that it is an automatic feature. This could propagate the fault in one division to the redundant counterpart and could lead to the total loss of DC power.
- 2) EDG Operation And Loading The following sections of the FSAR show automatic loading of 480 volt class IE buses 1, 2 and 3:
(a) Section 8.2.2.2 states:
"The essential 480 VAC load center buses 1, 2, and 3 are energized from the standby generators and essential loads are restarted by automatic sequencing programs."
, (b) Section 8.2.3.5 states:
"Two load-sequencing programmers are provided for each diesel generator set. For the first diesel generator in service, one programmer sequences the starting of essential equipment required for the safe shutdown of the plant (Sequence "A" loads shown in Tables 8.2-4 and 8.3-5). When the second diesel generator starts, a load-sequencing programmer will sequence the starting of sequence "B" loads (shown on Tables 8.2-6 and 8.2-7). Should the programmers become inoperable, the operator can manually sequence the restarting of essential equipment from the main control board."
Besides the automatic loading feature on each of the two divisions, sequence "A" or sequence "B", the data in Tables 8.2-4 and 8.2-5 indicate that the swing bus 2 loads are automatically energized along with the loads on bus 1 or 3 (sequence A or sequence B).
l
In the meeting of August 14, 1986, the licensee informed the staff that the swing bus 2 loading is only manual. Also, the EDG with both engines working is the one that is automatically connected to the bus. The other EDG, either with only one engine working or being second in line to reach rated voltage and frequency, is connected only manually to bus 1 or 3, whichever is second in line. When both EDGs are driven by only one engine each, the automatic closure of their output breakers is automatically inhibited. In this state, closing of the EDG breakers and loading of the EDGs is designed to be manual.
. 3) Additional Concerns a) Physical, Electrical Independence: A review of the electrical schematic diagrams for the 480 VAC essential buses indicated cases where the system physical and electrical independence appears to have been compromised. Redundant circuits are physically wired to common terminal blocks such that the circuits are in close proximity to each other. The electrical independence is compromised in those cases where the redundant circuits are wired to common devices such as relays. These relays are used for both control functions and permissive functions.
It has been the staff's practice not to accept such commonality in the case of the permissives, and has required electrical independence. It is possible for the contact block on a relay or circuit breaker to fail and thus disable all circuits connected to the control block.
b) Degraded Grid and Loss of Voltage Protection: During the licensee's study of FSV's degraded grid and loss of protection logic system, they discovered that two of the three logic trains (one on each 480 volt buses 1, 2 and 3) were powered from the j same 125 VDC source.
l
This 2-out-of-3 logic combination will start both EDGs. If the above stated DC power fails, the EDGs will not get a signal to automatically start on degraded grid voltage or loss of voltage as intended.
The licensee proposed to correct this situation by powering each of the three logic trains from the associated DC power supply circuit used for the control of the 480 VAC switchgear, rather than directly from the two DC buses. In this way, if one of the DC buses failed, the auto-throw-over (A-T-0) circuit would switch the affected logic train to the remaining DC bus. The A-T-0 scheme is an existing automatic control circuit that was
, installed at each of the three switchgear sets (bus 1, 2 and 3) to switch control power between the two redundant DC buses in the event that one of the buses fails.
The staff noted that this temporary modification resolved a specific design problem. However, the vulnerability of the design to the total loss of DC power still remains in the existing A-T-0 scheme.
The licensee agreed to examine and implement a solution that will preclude the loss of DC power as a result of a single failure.
Some of the possible solutions discussed during the meeting involved using the existing "C" battery as a third DC bus, changing relay logic from nonnally de-energized to normally energized, and manually switching the DC buses. In all cases, the proposed solutions involve plant modifications to existing circuits and the installation of additional equipment and hardware.
4 ACTION ITEMS At the conclusion of the meeting, the Public Service Company of Colorado (PSC) and the NRC agreed to the following actions items:
, 1. The NRC will write a memorandum to PSC regarding the FSV design i
of the EDGs and 480 VAC essential buses. This will contain the staff's position and concerns, regarding the licensee's proposed l
l
temporary modification involving the DC supply to the undervoltage relay logics. (This review status report completes this action).
- 2. The licensee will draft a letter outlining the actions that they are going to take to resolve the staff's concerns expressed in this review status report and discussed during the August 14, 1986 meeting.
- 3. The licensee will provide analyses that will show:
- a. Manual capability exists to control the 480 VAC circuit breakers;
- b. The EDGs can not be paralleled;
- c. No single failure in the automatic circuits will inhibit the manual controls for the EDGs or for the 480 VAC essential component circuits breakers, s
- 4. The licensee will remove common relays DEV-86RT and DEV-86ET1 from the EDG circuits prior to re-start. [Ref:
PSC letter dated 7-1-86 from D. W. Warembourg (PSC) to H.
Berkow(NRC).]
Prepared by: I. Ahmed, DPWRL-B Date:
l