yu o,, UNITED STATES g g NUCLEAR REGULATORY COMMISSION

: E WASHINGTON, D. C. 20555

\ July 26,1989 Docket No. 50-267 Mr. R. O. Williams, Jr.

Senior Vice President, Nuclear Operations Public Service Company of Colorado Post Office Box 840 Denver, Colorado 80201-0840

Dear Mr. Williams:

SUBJECT:

FORT ST. VRAIN SCHEDULE COMMITMENT ITEMS REVISION 8 (TAC NO. 72063)

By letter dated June 16, 1989, you requested certain changes to previous commitments concerning Fort St. Vrain (FSV). These changes reflect your plans to shutdown FSV. The staff has reviewed your submittal and individually examined each change. Our discussion follows:

Annual Report of Moisture Ingress You have requested that the last two reports be scheduled for July 15, 1989 and 1990 respectively. This coincides with the remaining plant operating cycle.

The staff agrees with this modified commitment.

Evaluate Control of Moisture in Control Rod Drive Mechanism (CRDM) Purge System You have requested that this report be scheduled for July 15, 1989. You have also requested that this report focus on the effectiveness of CRDM moisture control. The staff agrees with this modified commitment.

Prestressed Concrete Reactor Vessel (PCRV) Tendon Surveillance You have requested that Tendon Surveillance Program results be provided to the i staff by July 21, 1989 and one month after final depressurization. This coincides with the remaining plant operating cycle. The staff agrees with this modified commitment. (The staff also agrees that these changes do not need to be included in the Technical Specifications.)

Five Protection Modifications (Including Alternate Cooling Method (ACM) Backfeed)

You have requested that the performance enhancements involving the ACM backfeed be removed. Since the staff is considering issuing other correspondence conce.rning these matters, all fire protection modification commitments are deleted from this listing.

Control Room Habitability You have committed to submit an amendment to the Technical Specifications addressing this issue by September 30, 1985. This amendment would provide for additional protection if gaseous chlorine use on site is continred. The staff accepts this commitment t; address the issue as noted.

A I

VP t i 8905030146 890726 i FDR ADOCK 05000267 I I P ppc  ;

I

Mr. R. O. Williams Station Blackout You have committed to not disable or remove the ACM system without prior noti-fication to the NRC. The staff accepts this commitment to address the issue of station blackout as noted.

Control Room Design Review Modifications You have committed to prepare a summary document on the Control Room Design Review by December 15, 1989. Furthermore, you have committed to maintain con-trol room improvements for the balance of plant life. The staff accepts these commitments to address the issue of control room design review modifications.

A revised summary of your commitments is enclosed. The staff notes that Commitment 2c. will be the subject of separate correspondence. Commitment 7.

will be considered not applicable since the control rod drive mechanisms are considered less likely to fail in the shutdown condition.

Sincerely,

/s/

Kenneth L. Heitner, Project Manager Project Directorate - IV Division of Reactor Projects - III, IV, V and Special Projects Office of Nuclear Reactor Regulation

Enclosure:

As stated cc w/ enclosure:

See next page DISTRIBUTION Docket File NRC PDR Local PDR PD4 Reading G. Holahan ADR4 F. Hebdon P. Noonan K. Heitner OGC-Rockville E. Jordan B. Grimes ACRS (10) PD4 Plant File DOCUMENT NAME: FSV 8975 l

l PD4/LA- PD4/PM rb PD4/Dd.

PNoona k KHeitner:bj FHebdoh 07f4/89 07//[3/89 07/l(/89 l

1

g ,. ; ,

c Mr. R. O. Williams.  ;

Station Blackout You have comitted to not disable or remove the ACM system without prior noti-fication to the NRC. The staff accepts this comitment to address the issue of station blackout as noted.

Control Room Design Review Modifications You have comitted to prepare a sumary document on the Control Room Design Review by December 15, 1989. Furthermore, you have comitted to maintain con-trol room improvements for the balance of plant life. The staff accepts these comitments to address the issue of control room design review modifications.

A revised sumary of your comitments is enclosed. The staff notes that Comitment 2c. will be the subject of separate correspondence. Comitment 7.

will be considered not applicable since the control rod drive mechanisms are considered less likely to fail in the shutdown condition.

Sincerely.

Kenneth L. Heitner, Project Manager Project Directorate - IV Division of Reactor Projects - III, IV, V and Special Projects Office of Nuclear Reactor Regulation

Enclosure:

As stated cc w/ enclosure:

See next page

_ _ _ _ - _ _ - _ _ - - - _ _ _ _ _ i

p..

e .Mr. R. O. Williams, Jr.

Public Service Company of Colorado Fort St. Vrain ec:

Mr. D. W. Warembourg, Manager Albert J. Hazle, Director Nuclear Engineering Division Radiation Control Did sion Public Service Company Department of Health of Colorado 4210 East lith Avenue P. O. Eox 840 Denver, Colorado 80220 Denver, Colorado 80201-0840 Mr. David Alberstein, Manager Mr. Charles H. Fuller Fort St. Vrain Services Manager, Nuclear Production GA International Services Corporation and Station Manager Post Office Box 85608 Public Service Company of Colorado San Diego, California 92138 16805 Weld County Road 19-1/2 Platteville, Colorado 80651 Mr. H. L. Brey, Manager Nuclear Licensing and Resource Mr. P. F. Tomlinson, Manager Management Division Quality Assurance Division Public Service Company of Colorado Public Service Company of Colorado P. O. Box 840 16805 Weld County Road 19-1/2 Denver, Colorado 80201-0840 Platteville, Colorado 80651 l

Senior Resident Inspector Mr. D. D. Hock l U.S. Nuclear Regulatory Cemmission President and Chief Executive Officer P. O. Box 640 Public Service Company of Colorado Platteville, Colorado 80651 Post Office Box 840 Denver, Colorado 80201-0840 Kelley, Standfield & 0'Donnell ATTH: Mr. J. K. Tarpey Comitment Control Program Public Service Company Building Coordinator Room 900 Public Service Company of Colorado 550 15th Street 2420 W. 26th Ave. Suite 100-D Denver, Colorado 80202 Denver, Colorado 80211 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011 Chairman, Board of County Commissioners of Weld County, Colorado Greeley, Colorado 80631 Regional Representative Radiation Programs Environmental Protection Agency 1 Denver Place 999 18th Street, Suite 1300 Denver, Colorado 80202-2413

.y .

.? ( ,

p_

~~

. Enclosure-Revision 8 PUBLIC SERVICE COMPANY OF COLORADO COMMITMENTS RELATED TO THE OPERATION OF THE L FORT ST. VRAIN NUCLEAR GENERATING STATION Item Commitment Description / Requirement Schedule (Reference)

1. . Provide status reports on the Nuclear Approximately Performance Enhancement Program on an annually annual basis. (P-88031)
2. Implement the Technical S UpgradeProgram(P-85098)  : specifications (TS)
a. Provide a revised final draft proposal Complete
~ of the Upgraded TS for NRC oomment. (P-87063)
b. Sabmit a license amendment to incorporate 90 days after theUpgraded(TS). (P-65243) NRC comments on Item 2a.
c. Implement the Upgraded TS. (P-85243) Approximately 4th refueling outage (license emendment will define)'
3. Improve control rod and reserve shutdown (SeeItem2) reliability. Incorporate the interim Technical Specifications in the Upgrade Program.
4. Develop a plan to implement approved 7/15/89 and l modifications to control moisturr ingress 7/15/90(final) and submit annual re orts on progress. ~

(P-85022 and P-85082

5. Evaluate control of moisture in CRDM purge 7/15/89 system. (P-85021) (Focus on system effectiveness)
6. PCRV Tendon Surveillance Requirements:
a. Incorporate the revised Tendon Surveillance Cancelled l Program into the Technical Specifications. (P-85199)
b. Provide the results of the revised program 7/21/89 and to the NRC. one month after final depressuri-zation(final)

L.:

lee. _ , ' ' _.

~* Revision 8 Page 2

7. Provide an improved CRDM surveillance Five months program which includes consideration of after the start CRDM operational testing. (P-88012) of 4th refueling outage (not applicable) 8.- Provide a TS amendment to provide for chlorine 9/30/89 detection and appropriate emergency ventilation system actions.

.9. Notify the NRC prior to disabling or removing -

the ACM system.

10. Control Rocm Modifications:
a. Prepare a summary document. 12/15/89
b. Maintain control room improvements-for -

balance of plant life. l l

)