Informs That Design Changes Involving Emergency Diesel Generator (EDG) Control Logic Circuitry Implemented.No Single Failure Will Interfere W/Proper Operation of Redundant EDG
ML20137B356
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 01/03/1986
From: Warembourg D
PUBLIC SERVICE CO. OF COLORADO
To: Berkow H
Office of Nuclear Reactor Regulation
References
P-86003, TAC-59801, NUDOCS 8601150283
Download: ML20137B356 (2)


Text

r hf, Public Service- o . ,*.

Company of Colorado 2420 W. 26th Avenue, Suite 100D, Denver, Colorado 80211 January 3, 19f6 Fort St. Vrain Unit No. 1 P-86003 Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Comission Washington, DC 20555 Attn: Mr. H.N. Berkow, Project Director Standardization and Special Projects Directorate Docket No. 50-267

SUBJECT:

Emergency Electrical Power System Independence

REFERENCES:

1) PSC Letter Warembourg to Johnson dated June 14, 1985 (P-85208)
2) NRC Letter Johnson to Lee dated July 10, 1985 (G-85268)
3) PSC Letter Warembourg to Hunter dated September 13, 1985 (P-85313)
4) PSC Letter Warembourg to Berkow dated December 17, 1985 (P-85475)

Dear Mr. Berkow:

In a letter. dated September 13, 1985 (Reference 3), Public Service Company (PSC) comitted to the implementation of design changes involving the Emergency Diesel Generator (EDG) control logic circuitry.

The aforementioned design changes have been implemented and will assure that no single failure will interfere with the proper operation of a redundant EDG.

8601150283 860103 ,

g#!

DR ADOCK 050 27

. .-o.

Should you ~ have any questions regarding this matter, please contact Mr. M. H. Holmes at (303) 480-6960.

Very truly yours,

b. & fYwJ D.W. Warembourg, Man Nuclear Engireering Division DW/BS:pa

~