Public Service'
=; -lL 16805 WCR 191/2; Platteville, Colorado 80651 March 24,1997 Fort St. Vrain P-97017 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C.
20555 Docket No. 50 267 SUETECT:
QUARTERLY SUBMITTAL OF THE 10 CFR 50.59 REPORT OF CHANGES, TESTS AND EXPERIMENTS R)R FORT ST. VRAIN l
DECOMMISSIONING-
REFERENCE:
NRC Letter dated November 23,1992, Erickson to J
Crawford (G-92244)
Gentlemen.
1 This letter transmits the quarterly 10 CFR 50.59 Report of Changes, Tests, and Experiments affecting Decommissioning of the Fort St. Vrain (FSV) Nuclear Station. The attached report includes a description of each change, test and experiment as well as a summary of the safety evaluation. This report covers the period of December 1,1996 through February 28,1997.
This report is being submitted pursuant to Condition (b)(2) of the " Order Approving
. Decommissioning Plan and Authorizing Decommissioning of Facility", transmitted in the referenced letter, which states the fohowing:
l "The licensee shall submit, as specified in 10 CFR 50.4, a report containing a brief description of any changes, tests and experiments, including a summary of the safety evaluation of each. The report must be submitted quarterly."
If you have any questions concerning this report, please contact Mr. M. H. Holmes at (303) 620-1701.
Sincerely, b
b L[
j i Frederic{ J. Borst Decomm13sdning Program Director gll]gg[g]gjjjgll-l]l*((-
9704020010 970324 PDR ADOCK 05000267 R
. =
P-97017 i-
' March 24,1997 Page 2 '
FJB/SWC Attachment cc:
Mr. John W. Hickey, Chief Decommissioning and Regulatory Issues Branch Regional Administrator, Region IV Mr. Robert M. Quiliin, Director Radiation Control Division Colorado Department of Public Health and Environment l
l
,7 I
March 1997 QUARTERLY 10 CFR 50.59 REPORT OF CHANGES, TESTS AND EXPERIMENTS
+
FOR FSV DECOMMISSIONING 4
2 Backgrouruh The following is a brief discussion of 10 CFR 50.59 changes to the Fort St. Vrain (FSV) facility or procedures as described in the Decommissioning Plan (DP) and tests and experiments not j
described in the DP, in the time period from December 1,1996 through February 28,1997, 1
I While this report is similar to past reports of changes, tests and experiments submitted in accordance with 10 CFR 50.59, the quarterly decommissioning reports are submitted pursuant to Paragraph (b)(2) of the FSV Decommissioning Order (issued in NRC letter dated November 3
23,1992, Erickson to Crawford), which states:
"The licensee shall submit, as specified in 10 CFR 50.4, a report containing a brief i
description of any changes, tests and experiments, including a summary of the safety evaluation of each. The report must be submitted quarterly."
Proiect Status:
Public Service Company of Colorado submitted the FSV Final Survey Report in October,1996, and requested in November,1996, that the NRC terminate the FSV 10 CFR 50 Possession Only
- License, i
PSCo will provide a final summary 10 CFR 50.59 report by April 10, 1997, to support final license termination activities.
1 Changes to the FSV Facility or its Procedures as Described in the Decommissionine Plan There were no changes to the FSV facility or its procedures as described in the DP during this period from December 1,1996 to February 28,1997.
Tests or Exneriments not Described in the Decommissioning Plan No tests or experiments were conducted this reporting period that are not described in the DP.