Letter Sequence RAI |
---|
|
Results
Other: ML20137L000, ML20206T655, ML20206T679, ML20206T705, ML20206T726, ML20206T748, ML20206T776, ML20206T792, ML20206T817, ML20206T843, ML20206T847, ML20206T875, ML20206T899, ML20206T913, ML20206T921, ML20206T931, ML20206T937, ML20206T949, ML20206T966, ML20206T981, ML20206T986, ML20206U003, ML20212B914, NLS8400108, Forwards Second 10-yr Inservice Insp Plan, NLS8600021, Forwards Addenda to Rev 3 to Inservice Insp Program for ASME Class 1,2 & 3 Components, NLS8600248, Forwards Rev 5 to Inservice Testing Program for ASME Class 1,2 & 3 Components, for Second 10-yr Testing Program. General Pump Testing Procedure 3.9 & General Valve Testing Procedure 3.10 Being Revised to Incorporate Rev 1 Changes
|
MONTHYEARML20206T9131978-10-23023 October 1978 Rev 5 to Surveillance Procedure 6.3.16.1, Reactor Equipment Cooling - Pump Operability Test Project stage: Other ML20206T9861981-08-28028 August 1981 Rev 0 to Surveillance Procedure 6.4.1.8, Control Rod Drive Hydraulic Control Unit Accumulator Leakage Test Project stage: Other NLS8400108, Forwards Second 10-yr Inservice Insp Plan1984-04-0303 April 1984 Forwards Second 10-yr Inservice Insp Plan Project stage: Other ML20206U0031984-07-23023 July 1984 Rev 13 to Nuclear Performance Evaluation Procedure 10.9, Control Rod Scram Time Evaluation Project stage: Other ML20100M8071984-11-28028 November 1984 Draft Rev 9 to QA Policy for Calvert Cliffs Nuclear Power Plant Project stage: Draft Other ML20206T9311984-12-0606 December 1984 Rev 6 to Surveillance Procedure 6.3.18.1, Svc Water Pump Operability Test Project stage: Other ML20206T9371984-12-0606 December 1984 Rev 10 to Surveillance Procedure 6.3.18.2, Svc Water Motor Operated Valve Operability Test Project stage: Other ML20206T8751985-01-0303 January 1985 Rev 11 to Surveillance Procedure 6.3.12.2, Diesel Generator Starting Air Compressor Operability Project stage: Other ML20206T9661985-05-0202 May 1985 Rev 13 to Surveillance Procedure 6.3.19.1, Standby Gas Treatment Operability Test Project stage: Other ML20129J6611985-07-12012 July 1985 Submits Revised Inservice Testing Relief Requests RV-03 Re Reactor Recirculation Loops a & B Discharge Bypass Valves, Reflecting Current Pipe Configuration & RP-05 Re HPCI Test Method & Updated Request Index Project stage: Request ML20206T7761985-08-18018 August 1985 Rev 11 to Surveillance Procedure 6.3.8.4, Standby Liquid Control Manual Initiation Test Tank to Reactor Vessel Project stage: Other ML20206T8171985-09-13013 September 1985 Rev 12 to Surveillance Procedure 6.3.10.2, Instrument Line Flow Check Valve Test Project stage: Other ML20137L0001985-10-31031 October 1985 Addenda to Rev 3 to Inservice Insp Program for ASME Class 1,2 & 3 Components Project stage: Other ML20206T7481985-11-21021 November 1985 Rev 15 to Surveillance Procedure 6.3.6.1, RCIC Test Mode Surveillance Operation Project stage: Other ML20206T8431985-12-11011 December 1985 Rev 0 to Surveillance Procedure 6.3.10.16, Check Valves in Cooling Sys of Diesel Generators Integrity Verification Project stage: Other ML20206T9211986-01-16016 January 1986 Rev 12 to Surveillance Procedure 6.3.16.2, Reactor Equipment Cooling Motor Operated Valve Operability Test Project stage: Other NLS8600021, Forwards Addenda to Rev 3 to Inservice Insp Program for ASME Class 1,2 & 3 Components1986-01-17017 January 1986 Forwards Addenda to Rev 3 to Inservice Insp Program for ASME Class 1,2 & 3 Components Project stage: Other ML20206T7051986-01-30030 January 1986 Rev 18 to Surveillance Procedure 6.3.4.1, Core Spray Test Mode Surveillance Operation Project stage: Other ML20154A5251986-02-12012 February 1986 Forwards Request for Addl Info Re Inservice Testing Program, Based on Review of 840615,850522 & 0722 Ltrs Describing Second 10-yr Inservice Testing Program.Response Requested within 45 Days Project stage: RAI ML20206T9491986-03-0606 March 1986 Rev 15 to Surveillance Procedure 6.3.18.3, Svc Water Surveillance Operation Project stage: Other ML20206T8471986-03-0606 March 1986 Rev 17 to Surveillance Procedure 6.3.12.1, Diesel Generator Operability Test Project stage: Other ML20206T7261986-03-13013 March 1986 Rev 21 to Surveillance Procedure 6.3.5.1, RHR Test Mode Surveillance Operation Project stage: Other ML20206T9811986-04-24024 April 1986 Rev 17 to Surveillance Procedure 6.3.20.1, RHR Svc Water Booster Pump Flow Test & Valve Operability Test Project stage: Other ML20211A1361986-04-28028 April 1986 Trip Rept of 860415-16 Site Visit for Pump & Valve Inservice Testing Program Working Meeting Re Questions Resulting from Program Review.List of Attendees,Questions Serving as Agenda for Meeting & Responses to Questions Encl Project stage: Meeting ML20211A0891986-05-30030 May 1986 Forwards Contractor Summary of 860412 & 16 Meetings at Facility Re to Recipient Requesting Addl Info on Second 10-yr Inservice Testing Program.Correction Made on Page 2 of Summary Project stage: Meeting ML20206T7921986-06-0505 June 1986 Rev 1 to Surveillance Procedure 6.3.9.1, MSIV Accumulator Functional Test Project stage: Other ML20206T8991986-06-0505 June 1986 Rev 3 to Surveillance Procedure 6.3.12.8, Diesel Generator Fuel Oil Transfer Pump Flow Test Project stage: Other ML20206T6791986-06-12012 June 1986 Rev 23 to Surveillance Procedure 6.3.3.1, HPCI Test Mode Surveillance Operation Project stage: Other ML20206T6551986-06-12012 June 1986 Rev 13 to Surveillance Procedure 6.3.2.1, Automatic Depressurization Sys Manual Valve Actuation Project stage: Other ML20206T6381986-06-30030 June 1986 Forwards Response to W Long 860212 Request for Addl Info Re Inservice Testing Program & 860415-16 Meetings Re Open Items.Surveillance Procedures,Including Procedure 6.3.2.1, Also Encl Project stage: Meeting NLS8600248, Forwards Rev 5 to Inservice Testing Program for ASME Class 1,2 & 3 Components, for Second 10-yr Testing Program. General Pump Testing Procedure 3.9 & General Valve Testing Procedure 3.10 Being Revised to Incorporate Rev 1 Changes1986-07-30030 July 1986 Forwards Rev 5 to Inservice Testing Program for ASME Class 1,2 & 3 Components, for Second 10-yr Testing Program. General Pump Testing Procedure 3.9 & General Valve Testing Procedure 3.10 Being Revised to Incorporate Rev 1 Changes Project stage: Other ML20212B9141986-07-31031 July 1986 Vols I & II of Rev 5 to Inservice Testing Program for ASME Class 1,2 & 3 Components, for Second 10-yr Testing Program Project stage: Other ML20148C9481988-01-13013 January 1988 Forwards Safety Evaluation of Util Second 10-yr Inservice Testing Program Submitted w/860730 Ltr.Certain Relief Requests Denied Where Proposed Alternative Testing Unacceptable.Technical Evaluation Rept Also Encl Project stage: Approval ML20151H8461988-04-13013 April 1988 Forwards Response to Anomalies Identified in NRC 880113 SER Re Facility Inservice Testing Program.Reactor Equipment Pumps Will Be Tested in Accordance W/Section Xi.Util Evaluating Need for Any Relief Request in Performing Test Project stage: Request ML20151L3111988-07-29029 July 1988 Forwards Revised & New Relief Requests & Program Corrections to Second 10 Yr Inservice Testing Program.Addl Review of Program Identified Need for Further Changes to Program Including Rev of Existing Relief Requests Project stage: Request 1986-01-17
[Table View] |
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217N1931999-10-22022 October 1999 Forwards Insp Rept 50-298/99-12 on 990927-30.No Violations Noted.Insp Exam of Activities Under License as They Relate to Emergency Preparedness & to Compliance with Commission Rules & Regulations & with Conditions of License ML20217G8771999-10-14014 October 1999 Forwards Insp Rept 50-298/99-10 on 990920-24.No Violations Noted ML20217G7401999-10-14014 October 1999 Forwards MOR for Sept 1999 for Cooper Nuclear Station. Rept Includes Documentation of Challenges to Safety/Relief Valves,Iaw TS 5.6.4 ML20217C2671999-10-0808 October 1999 Forwards Insp Rept 50-298/99-03 on 990823-27 & 0907-10.No Violations Noted.Purpose of Insp to Ensure That Licensee Had Effective Programs for Identifying,Evaluating & Correcting Problems Which Could Impact Safe Plant Operations ML20212K9661999-09-30030 September 1999 Forwards Safety Evaluation Accepting plant-specific Safety Evaluation Rept for USI A-46 Program Implementation at Cooper Nuclear Station ML20216J1081999-09-28028 September 1999 Ltr Contract:Task Order 048, Cooper Safety Sys Design & Performance Capability Insp, Under Contract NRC-03-98-021 ML20212J5061999-09-27027 September 1999 Forwards Insp Rept 50-298/99-07 on 990718-0828.No Violations Noted.Inspectors Focused on Implementation of Licensee Reactor Safety & Emergency Preparedness Programs ML20212F3641999-09-22022 September 1999 Forwards Insp Rept 50-298/99-09 on 990823-26.No Violations Noted ML20216J8061999-09-20020 September 1999 Forwards Rev 37 to Safeguards Plan,Iaw Provisions of 10CFR50.(p).Rev Withheld,Per 10CFR73.21 ML20212C4921999-09-15015 September 1999 Forwards Monthly Operating Rept for Aug 1999 for Cooper Nuclear Station.Rept Includes Operating Data Rept,Unit SD Rept & Documentation of Challenges to Safety/Relief Valves ML20212A6061999-09-14014 September 1999 Forwards Insp Rept 50-298/99-08 on 9900816-20.No Violations Noted.Insp Focused on Implementation & Effective Performance of Access Authorization/Fitness-for-Duty (Behavior Observation) Program & Access Control of Personnel ML20211N5271999-09-0202 September 1999 Responds to NRC 990823 RAI Re Y2K Readiness at Cooper Nuclear Station,Per GL 98-01,Suppl 1 05000298/LER-1999-006, Forwards LER 99-006-00 for Cns.Commitments Made by Util Encl1999-08-26026 August 1999 Forwards LER 99-006-00 for Cns.Commitments Made by Util Encl ML20211F1311999-08-24024 August 1999 Forwards Rev 1 to Calculation Nedc 97-044, NPSH Margins for RHR & CS Pumps, in Support of 990615 Proposed Amend to DPR-46 Re Containment Overpressure Contribution to ECCS Pumps NPSH Requirements 05000298/LER-1999-003, Informs That Commitment Re Insp Rept 50-298/98-15 & LER 99-003,to Bound Extent of Condition & Take Appropriate C/As Is Now Complete.Addl Time Is Required to Accommodate Training of Engineering Support Personnel1999-08-23023 August 1999 Informs That Commitment Re Insp Rept 50-298/98-15 & LER 99-003,to Bound Extent of Condition & Take Appropriate C/As Is Now Complete.Addl Time Is Required to Accommodate Training of Engineering Support Personnel ML20211F4661999-08-23023 August 1999 Discusses GL 98-01 Issued by NRC on 980511 & NPPD Responses for Cooper Nuclear Station & 990628 & Results of Visit to Plant on 990811-12.Staff Determined That Integrated Contigency Plan Incomplete & CNS Not Y2K Ready ML20210R0301999-08-12012 August 1999 Forwards Monthly Operating Rept for July 1999 for Cooper Nuclear Station,Iaw Guidance Provided by GL 97-02.Rept Also Includes Documentation of Challenges to Srvs,Per TS 5.6.4 ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl ML20210P6761999-08-10010 August 1999 Requests That Following Changes Be Made to Distribution on NRC Correspondence ML20210P6861999-08-0909 August 1999 Forwards Insp Rept 50-298/99-06 on 990530-0717.No Violations Noted.During Insp,Inspectors Identified Two Issues Categorized as Being Low Risk Significance & within Licensee Response Band ML20210N1331999-08-0606 August 1999 Forwards Notice of Withdrawal of Application for Amend to FOL DPR-46.By Ltr Licensee Withdrew Amend Request Which Would Have Revised Usfar to Reflect as-built Configuration of Reactor Bldg Isolation Dampers ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams ML20210K6071999-08-0202 August 1999 Submits Withdrawal of Proposed License Amend Re Secondary Containment Isolation Description & Refueling Accident Analysis Results ML20210K3811999-08-0202 August 1999 Forwards Listed Info,Which NPPD Believes Demonstrates Ability to Obtain Funds in Amount of $10 Million for Payment of Such Premiums within Specified Three Month Period,Iaw 10CFR140.21 ML20210G5101999-07-28028 July 1999 Forwards fitness-for-duty Program semi-annual Performance Rept for Period of 990101-0630,per Provisions of 10CFR26.71(d) ML20210D2541999-07-21021 July 1999 Forwards Insp Rept 50-298/99-02 on 990628-0702.Purpose of Insp Was Primarily to Evaluate Effectiveness of Licensed Operator Requalification Program.No Violations Were Identified ML20210C2041999-07-20020 July 1999 Discusses 990715 Mgt Meeting with Midamerican Energy Co Re risk-informed Baseline Insp Program Recently Implemented at Cooper & Fort Calhoun Stations ML20209H8191999-07-15015 July 1999 Forwards Safety Evaluation on GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Cooper Nuclear Station ML20209E6951999-07-12012 July 1999 Discusses Response to RAI on GL 92-01,rev 1,suppl 1, Rv Structural Integrity. Recommends Review of New Database Diskettes on Listed Website.Comments Due by 990901 or Data Entered Into Rvid for Plant Will Be Acceptable ML20209D8731999-07-0808 July 1999 Refers to 990707 Meeting Re Licensee Recent Maintenance Program self-assessment.Also Discussed How Licensee Incorporated Assessment Findings Into Rev of Maintenance Performance Improvement Plan.List of Attendees Encl ML20209B7851999-07-0101 July 1999 Forwards Corrected Occupational Radiation Exposure Repts, for Cys 1996 & 1997.Util Stated That Repts Did Not Properly Tabulate Number of Personnel Receiving Exposures Less than 100 Mrem by Work & Job Functions in CY96 & CY97 05000298/LER-1999-005, Forwards LER 99-005-00 for Cns.Commitments Made by Util Encl1999-07-0101 July 1999 Forwards LER 99-005-00 for Cns.Commitments Made by Util Encl ML20196J2471999-06-29029 June 1999 Discusses Completion of Licensing Action for GL 97-04, Assurance of Sufficient Net Positive Suction Head for ECC & Containment Heat Removal Pumps, 05000298/LER-1999-004, Forwards LER 99-004-01.Commitments Made by Util Are Encl1999-06-28028 June 1999 Forwards LER 99-004-01.Commitments Made by Util Are Encl ML20209B5451999-06-28028 June 1999 Submits Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Nuclear Power Plants. Disclosure Encl ML20196H0331999-06-24024 June 1999 Informs NRC of Deletion of 1991 Commitment Contained in Ltr Re Feedwater Nozzle Bypass Leakage Monitoring at Plant ML20196F7511999-06-24024 June 1999 Discusses 990622 Meeting with Public at Arbor Manor, Alburn,Ne to Provide Overview of Pilot Insp Program ML20209A7221999-06-23023 June 1999 Submits Revised Pages to Proposed Change to Plant TS Previously Submitted in ,Per 990615 Telcon with NRC ML20196F5331999-06-22022 June 1999 Forwards Examination Summary Rept for FW Nozzle Examinations Performed During 1998 Fall Refueling Outage at Cooper Nuclear Station.Rept Covers Past Examinations Up to & Including 1998 Fall Refueling Outage ML20196B4681999-06-17017 June 1999 Forwards TS Bases Changes Made at Plant Subsequent to Receipt of License Amend 178,dtd 980731,for Conversion to Its,Through 990610.List of Effective Pages for TS Bases, Encl ML20196E1411999-06-16016 June 1999 Forwards Insp Rept 50-298/99-05 on 990502-29.Noncited Violations Identified ML20195H8891999-06-14014 June 1999 Forwards Response to NRC 990315 RAI Re GL 95-07, Pressure Locking & Thermal-Binding of SR Power-Operated Gate Valves, 180-day Response Submitted by District on 960213 ML20195F6171999-06-0909 June 1999 Informs That GE Rept, Matl Presented by GE 970709 Meeting at Cooper Nuclear Power Station Re Replacement of ECCS Pump Suction Strainers Between Nppd,Ge & NRC Staff, Will Be Withheld from Public Disclosure as Requested ML20207G3031999-06-0808 June 1999 Ack Receipt of Which Transmitted Changes to Cooper Nuclear Station EP Implementing Procedure EPIP 5.7.1, Emergency Classification,Rev 24,under 10CFR50,App E,Section V Provisions.No Violations Identified ML20195E2351999-06-0808 June 1999 Forwards Response to NRC 990517 RAI Re Util Proposed Change to TS Re Calibr Frequency of Reactor Recirculation Flow Transmitters Associated with APRM ML20207G4481999-06-0808 June 1999 Ack Receipt of Which Transmitted Changes to Cooper Nuclear Station EP Implementing Procedure,Epip 5.7.1, Emergency Classification,Rev 23 C2,under Provisions of 10CFR50,App E,Section V ML20207G3001999-06-0707 June 1999 Ack Receipt of Which Transmitted Changes to Cooper Nuclear Station Ep,Rev 33,under Provisions of 10CFR50,App E,Section V.No NRC Approval Required Based on Determination That EP Effectiveness Not Affected by Changes ML20207G4531999-06-0707 June 1999 Ack Receipt of Which Transmitted Changes to Cooper Nuclear Station EP Implementing Procedure EPIP 5.7.1, Emergency Classification,Revision 25,under Provisions of 10CFR50,App E,Section V ML20207D3811999-05-27027 May 1999 Informs That During Next 6 to 12 Months,Starting 990530,NRC Plans to Conduct Insps Shown in Attached Insp Plan.Insps Include Both Planned Baseline & Supplemental Insps (Formerly Core & Regional Initiative Insps) ML20207A5191999-05-19019 May 1999 Forwards Insp Rept 50-298/99-04 on 990321-0501.Four Violations Identified & Being Treated as non-cited Violations 1999-09-30
[Table view] Category:NRC TO UTILITY
MONTHYEARIR 05000298/19900291990-11-0909 November 1990 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-298/90-29 ML20217A3691990-11-0707 November 1990 Forwards Insp Rept 50-298/90-33 on 900904-1016.Violations Noted But Not Cited ML20058G1461990-11-0505 November 1990 Ack Receipt of Submitting Rev 13 to Emergency Plan.Changes Acceptable for Implementation.Commitment Date for Submission of Changes Is 901031 ML20058H0581990-11-0101 November 1990 Forwards List of Unimplemented Gsis,Per Generic Ltr 90-04 IR 05000298/19900251990-10-16016 October 1990 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-298/90-25 ML20059M8751990-10-0202 October 1990 Informs That Util Response to Generic Ltr (GL) 90-03, Relaxation of Staff Position in Generic Ltr 83-28,Item 2.2, Part 2 'Vendor Interface for Safety-Related Components,' Acceptable ML20059M7391990-09-28028 September 1990 Forwards Sys Entry & Retest Insp Rept 50-298/90-31 on 900910-14 & 17.No Violations or Deviations Noted ML20059M4651990-09-27027 September 1990 Forwards Insp Rept 50-298/90-30 on 900827-31 & Notice of Violation ML20059E2691990-08-31031 August 1990 Forwards Safety Evaluation Granting Licensee 900525 Relief Requests RP-14 & RP-15 for Relief from Requirements to Measure Pump Inlet Pressure & Instrument Ranges, Respectively ML20058P4151990-08-0808 August 1990 Forwards Insp Rept 50-298/90-26 on 900616-0715.No Violations or Deviations Noted ML20056A1701990-07-30030 July 1990 Advises That Written Licensing Exams Scheduled on 901119 & Operating Licensing Exams Scheduled on 901120.Preliminary Applications Should Be Submitted at Least 30 Days Prior to Exam Date to Review Training & Experience of Candidates ML20055J2301990-07-24024 July 1990 Forwards Insp Rept 50-298/90-27 on 900709-13.No Violations or Deviations Noted.Actions Taken Re Previous Insp Findings Examined ML20055G8751990-07-20020 July 1990 Forwards Insp Rept 50-298/90-20 on 900611-15 & 25-29.No Violations or Deviations Noted ML20055G1841990-07-18018 July 1990 Confirms 900720 Mgt Meeting in Region IV Ofc Re Emergency Actions Levels,Annual Exercise & Emergency Preparedness Program Enhancements ML20055E6841990-07-0909 July 1990 Discusses Generic Implications & Resolution of Control Element Assemblies at Plant.Util Should Submit Plans & Justification for Any Continued Use of Old Style Control Element Assemblies Beyond Current Cycle for NRC Review ML20055D9441990-07-0505 July 1990 Forwards Insp Rept 50-298/90-22 on 900516-0615.No Violations or Deviations Noted.Actions Taken W/Regard to Previously Identified Insp Findings Examined IR 05000298/19900121990-06-28028 June 1990 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-298/90-12 IR 05000298/19900051990-06-27027 June 1990 Ack Receipt of Informing NRC That Util Evaluated Observation Re Vital Area Key Control,Per Insp Rept 50-298/90-05.Initiatives to Delineate Responsibilities for Vital Key Exchange During Shift Turnover Appropriate ML20055C7741990-06-18018 June 1990 Forwards Insp Rept 50-298/90-18 on 900416-0515.No Violations or Deviations Noted ML20059M9251990-06-13013 June 1990 Forwards NRC Performance Indicators for First Quarter 1990. W/O Encl ML20248H2791989-10-0606 October 1989 Forwards Comments from Bnwl Re Util Scenario for Exercise Planned on 891025 IR 05000298/19890251989-10-0505 October 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-298/89-25 ML20248E8151989-10-0202 October 1989 Confirms 890926 Telcon Re Change of Dates for Maint Team Insp Preparation Meetings from 891023-25 to 891031-1102 ML20247Q6071989-09-21021 September 1989 Forwards Amend 11 to Indemnity Agreement B-57,reflecting Changes to 10CFR140, Financial Protection Requirements & Indemnity Agreements, for Signature IR 05000298/19890291989-09-19019 September 1989 Forwards Insp Rept 50-298/89-29 on 890801-31.No Violations Noted IR 05000298/19890161989-09-14014 September 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-298/89-16. Implementation of Corrective Actions Will Be Reviewed During Future Insp IR 05000298/19890061989-09-13013 September 1989 Discusses Insp Rept 50-298/89-06 on 890206-10 & Forwards Notice of Violation.Concerns Raised Re Various Failures to Log or Rept Security Incidents.Decision Re Ofc of Investigations Findings Will Be Sent Separately ML20247G8531989-09-12012 September 1989 Forwards Insp Rept 50-298/89-24 on 890731-0804 & Notice of Deviation ML20247D4731989-09-0606 September 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-298/89-22 ML20247C0581989-09-0505 September 1989 Forwards Insp Rept 50-298/89-27 on 890821-25.No Violations or Deviations Noted ML20247G8051989-08-30030 August 1989 Forwards Summary of 890712 Meeting W/Util Re SALP for 880201-890415.Util 890811 Response to SALP Also Encl ML20247B3801989-08-30030 August 1989 Summarizes 890818 Region Iv/Senior Util Executives Meeting in Arlinton,Tx Re General Matters on Topics Discussed, Including SALP Process in Region 4.List of Attendees & Agenda Encl ML20246H9501989-08-28028 August 1989 Forwards Insp Rept 50-298/89-26 on 890717-21.No Violations or Deviations Noted ML20246F8171989-08-25025 August 1989 Forwards Insp Rept 50-298/89-30 on 890807-11.Violations Noted,But No Citation Issued ML20246G3201989-08-22022 August 1989 Forwards Insp Rept 50-298/89-25 on 890701-31 & Notice of Deviation ML20246G1341989-08-22022 August 1989 Documents NRC 890810 Meeting W/Licensee,Including H Parris & Staff in Region IV Ofc to Discuss General Issues of Interest to Licensee & Nrc,Region Iv.Topics Covered During Licensee Presentation Described ML20246E1291989-08-21021 August 1989 Forwards Insp Rept 50-298/89-28 on 890731-0804 & Notice of Violation.Response to One of Two Violations Required ML20245K9991989-08-11011 August 1989 Confirms 890808 Conversation in Which Util Agreed to Participate in 891012 NRC Regulatory Impact Survey.Info Re Survey Provided ML20245J7291989-08-0909 August 1989 Advises of Maint Team Insp Scheduled for Wks of 891113-1204, Per 890807 Telcon.Purpose of Meetings Is to Define Scope of Insp,To Discuss Interfaces Between Team & Staff & to Receive Info to Support Badging Team Members for Unescorted Access ML20245H1131989-08-0404 August 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-298/89-18 ML20248C2121989-08-0303 August 1989 Ack Receipt of in Response to 890608 Notice of Violation Re Insp Rept 50-298/89-19.Util Basis for Denial of Violation Not Substantiated & NRC Concludes That Violation Did Occur ML20247M1671989-07-27027 July 1989 Forwards Insp Rept 50-298/89-21 on 890626-30.No Violations or Deviations Noted IR 05000298/19880291989-07-27027 July 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-298/88-29 ML20236E6561989-07-24024 July 1989 Forwards Insp Rept 50-298/89-23 on 890626-30.No Violations or Deviations Noted ML20247L9501989-07-24024 July 1989 Forwards Insp Rept 50-298/89-22 on 890601-30 & Notice of Violation ML20246M4961989-07-11011 July 1989 Provides Agenda for 890809 Meeting of Senior Util Executives Sponsored by Region IV at Univ of Texas.Recipient Scheduled to co-lead Discussion of SALP Process W/J Milhoan ML20246N2051989-07-10010 July 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-298/89-17 ML20246A7091989-06-22022 June 1989 Forwards Insp Rept 50-298/89-18 on 890416-0531 & Notice of Violation.Nrc Considers Inadequate Station Mod Work Instructions Significant.Other Weaknesses in Plant Mod Process Identified in Paragraph 6 in Insp Rept ML20245K5371989-06-22022 June 1989 Forwards NRR Ack Receipt of Petition Filed by Ecology Ctr of Southern California & Stating That Petition Being Treated Under 10CFR2.206 of NRC Regulations ML20245B5591989-06-20020 June 1989 Forwards SALP Board Rept 50-298/89-12 for 880201-890415.NRC Pleased Overall,Although Sys for Identifying to Mgt Areas Where Corrective Actions Needed Should Be Improved 1990-09-28
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20217N1931999-10-22022 October 1999 Forwards Insp Rept 50-298/99-12 on 990927-30.No Violations Noted.Insp Exam of Activities Under License as They Relate to Emergency Preparedness & to Compliance with Commission Rules & Regulations & with Conditions of License ML20217G8771999-10-14014 October 1999 Forwards Insp Rept 50-298/99-10 on 990920-24.No Violations Noted ML20217C2671999-10-0808 October 1999 Forwards Insp Rept 50-298/99-03 on 990823-27 & 0907-10.No Violations Noted.Purpose of Insp to Ensure That Licensee Had Effective Programs for Identifying,Evaluating & Correcting Problems Which Could Impact Safe Plant Operations ML20212K9661999-09-30030 September 1999 Forwards Safety Evaluation Accepting plant-specific Safety Evaluation Rept for USI A-46 Program Implementation at Cooper Nuclear Station ML20216J1081999-09-28028 September 1999 Ltr Contract:Task Order 048, Cooper Safety Sys Design & Performance Capability Insp, Under Contract NRC-03-98-021 ML20212J5061999-09-27027 September 1999 Forwards Insp Rept 50-298/99-07 on 990718-0828.No Violations Noted.Inspectors Focused on Implementation of Licensee Reactor Safety & Emergency Preparedness Programs ML20212F3641999-09-22022 September 1999 Forwards Insp Rept 50-298/99-09 on 990823-26.No Violations Noted ML20212A6061999-09-14014 September 1999 Forwards Insp Rept 50-298/99-08 on 9900816-20.No Violations Noted.Insp Focused on Implementation & Effective Performance of Access Authorization/Fitness-for-Duty (Behavior Observation) Program & Access Control of Personnel ML20211F4661999-08-23023 August 1999 Discusses GL 98-01 Issued by NRC on 980511 & NPPD Responses for Cooper Nuclear Station & 990628 & Results of Visit to Plant on 990811-12.Staff Determined That Integrated Contigency Plan Incomplete & CNS Not Y2K Ready ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl ML20210P6861999-08-0909 August 1999 Forwards Insp Rept 50-298/99-06 on 990530-0717.No Violations Noted.During Insp,Inspectors Identified Two Issues Categorized as Being Low Risk Significance & within Licensee Response Band ML20210N1331999-08-0606 August 1999 Forwards Notice of Withdrawal of Application for Amend to FOL DPR-46.By Ltr Licensee Withdrew Amend Request Which Would Have Revised Usfar to Reflect as-built Configuration of Reactor Bldg Isolation Dampers ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams ML20210D2541999-07-21021 July 1999 Forwards Insp Rept 50-298/99-02 on 990628-0702.Purpose of Insp Was Primarily to Evaluate Effectiveness of Licensed Operator Requalification Program.No Violations Were Identified ML20210C2041999-07-20020 July 1999 Discusses 990715 Mgt Meeting with Midamerican Energy Co Re risk-informed Baseline Insp Program Recently Implemented at Cooper & Fort Calhoun Stations ML20209H8191999-07-15015 July 1999 Forwards Safety Evaluation on GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Cooper Nuclear Station ML20209E6951999-07-12012 July 1999 Discusses Response to RAI on GL 92-01,rev 1,suppl 1, Rv Structural Integrity. Recommends Review of New Database Diskettes on Listed Website.Comments Due by 990901 or Data Entered Into Rvid for Plant Will Be Acceptable ML20209D8731999-07-0808 July 1999 Refers to 990707 Meeting Re Licensee Recent Maintenance Program self-assessment.Also Discussed How Licensee Incorporated Assessment Findings Into Rev of Maintenance Performance Improvement Plan.List of Attendees Encl ML20196J2471999-06-29029 June 1999 Discusses Completion of Licensing Action for GL 97-04, Assurance of Sufficient Net Positive Suction Head for ECC & Containment Heat Removal Pumps, ML20196F7511999-06-24024 June 1999 Discusses 990622 Meeting with Public at Arbor Manor, Alburn,Ne to Provide Overview of Pilot Insp Program ML20196E1411999-06-16016 June 1999 Forwards Insp Rept 50-298/99-05 on 990502-29.Noncited Violations Identified ML20195F6171999-06-0909 June 1999 Informs That GE Rept, Matl Presented by GE 970709 Meeting at Cooper Nuclear Power Station Re Replacement of ECCS Pump Suction Strainers Between Nppd,Ge & NRC Staff, Will Be Withheld from Public Disclosure as Requested ML20207G3031999-06-0808 June 1999 Ack Receipt of Which Transmitted Changes to Cooper Nuclear Station EP Implementing Procedure EPIP 5.7.1, Emergency Classification,Rev 24,under 10CFR50,App E,Section V Provisions.No Violations Identified ML20207G4481999-06-0808 June 1999 Ack Receipt of Which Transmitted Changes to Cooper Nuclear Station EP Implementing Procedure,Epip 5.7.1, Emergency Classification,Rev 23 C2,under Provisions of 10CFR50,App E,Section V ML20207G4531999-06-0707 June 1999 Ack Receipt of Which Transmitted Changes to Cooper Nuclear Station EP Implementing Procedure EPIP 5.7.1, Emergency Classification,Revision 25,under Provisions of 10CFR50,App E,Section V ML20207G3001999-06-0707 June 1999 Ack Receipt of Which Transmitted Changes to Cooper Nuclear Station Ep,Rev 33,under Provisions of 10CFR50,App E,Section V.No NRC Approval Required Based on Determination That EP Effectiveness Not Affected by Changes ML20207D3811999-05-27027 May 1999 Informs That During Next 6 to 12 Months,Starting 990530,NRC Plans to Conduct Insps Shown in Attached Insp Plan.Insps Include Both Planned Baseline & Supplemental Insps (Formerly Core & Regional Initiative Insps) ML20207A5191999-05-19019 May 1999 Forwards Insp Rept 50-298/99-04 on 990321-0501.Four Violations Identified & Being Treated as non-cited Violations ML20206Q6171999-05-17017 May 1999 Forwards RAI Re 990301 & 10 Ltrs Re Proposed TS Changes to Calibr Frequency of Recirculation Flow Transmitters from Once Every 184 Days to Once Every 18 Months.Util Responses Should Be Provided within 30 Days of Ltr Date ML20206P0171999-05-12012 May 1999 Discusses GL 96-05 Issued on 960918 & NPPD Responses Submitted on 961118,970317,980504 & 990222 for Cooper Nuclear Station.Forwards Safety Evaluation Concluding That NPPD Adequately Addressed Actions Requested in GL 96-05 IR 05000298/19980091999-05-12012 May 1999 Refers to Insp Rept 50-298/98-09 Conducted Between 981227-990130.During Insp,Apparent Violation of 10CFR50.50 Identified & Being Treated as non-cited ML20206M1791999-05-11011 May 1999 Informs That NRC Ofc of NRR Reorganized Effective 990328. Reorganization Chart Encl ML20206H4191999-05-0707 May 1999 Informs That on 990407,NRC Administered Gfes of Written Operator Licensing Exam.Licensee Facility Did Not Participate in Exam,However,Copy of Master Exam with Answer Key,Encl for Info.Without Encl ML20206P8961999-05-0707 May 1999 Refers to Meeting Conducted at Region IV Office on 990506 Re Licensee Upcoming Rev to Strategy for Achieving Engineering Excellence & Plans to Achieve Performance Improvements.List of Attendees & Util Presentation,Encl ML20206H7541999-05-0505 May 1999 Forwards Insp Rept 50-298/99-01 on 990207-0320.Violations Being Treated as non-cited Violations ML20205R5541999-04-16016 April 1999 Submits Summary of 990330 Public Meeting in Brownville,Ne to Discuss Results of PPR Completed on 990211,which Allowed for Exchange on New Assessment Process,Current Performance Review & Upcoming Actions Taken in Response to Y2K Concerns IR 05000298/19980221999-03-19019 March 1999 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-298/98-22 on 990107.Finds Reply Responsive to Concerns Raised in NOV ML20205E8991999-03-19019 March 1999 Advises of Completion of Plant Performance Review on 990209 to Develop Integrated Understanding of Safety Performance. Overall Performance Was Acceptable.Problems with Communication in CR Resulted in Several Minor Events ML20204D9451999-03-18018 March 1999 Forwards Insp Rept 50-298/98-09 on 981227-990206.Three Violations Identified & Being Treated as Noncited Violations,Consistent with App C of Enforcement Policy ML20207M9591999-03-15015 March 1999 Forwards Request for Addl Info Re Licensee Response to GL 95-07, Pressure-Locking & Thermal-Binding of Safety-Related Power-Operated Gate Valves, for Cooper Nuclear Station ML20204B6771999-03-15015 March 1999 Submits Withdrawal of Amend Request for Operating License DPR-46.Proposed Change Would Have Modified Facility TSs Pertaining to Neutron Monitoring Neutron Detectors ML20207M9811999-03-15015 March 1999 Advises That Which Withdrew 980415 Amend Request, Being Treated as Withdrawal.Proposed Change Would Have Modified Facility TSs Pertaining to Neutron Monitoring,Flow Biased Rod Block Monitor ML20204B3301999-03-11011 March 1999 Forwards SE Accepting Third 10-year Interval Inservice Insp Program Plan Requests for Relief Numbers RI-13,RI-17 & RI-25 for Plant ML20204B7061999-03-11011 March 1999 Requests Approval of Proposed Operability Criteria for Use in Evaluation & Interim Resolution of Degraded & Nonconforming Conditions with Piping & Pipe Supports at Facility ML20205A5811999-03-0909 March 1999 Forwards Exam Rept 50-298/99-301 for Exam Administered on 990212.Exam Included Evaluation of Four Applicants for Reactor Operator License ML20207K3231999-03-0808 March 1999 Discusses 990224 Meeting Re Staff Critique of Refueling & Equipment Outage RE-18 & Implementation Status of Improvement Strategy for Engineering.List of Attendees & Matl Used in Presentation Encl ML20202G1701999-02-0202 February 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam at Util Facility on 990407.Authorized Representative from Facility Must Submit Ltr Listing Names of Candidates ML20202E3121999-01-22022 January 1999 Forwards Insp Rept 50-298/98-08 on 981115-1226 & Notice of Violation.First Violation Re Staff Failure to Follow Procedures (Two in Operations,One in Maint & One in Plant Support) ML20199G6041999-01-19019 January 1999 Informs That Effective 990118,JN Donohew Has Assumed NRC Project Mgt Responsibility for Cooper Nuclear Station ML20199E1521999-01-0707 January 1999 Forwards Insp Rept 50-298/98-22 on 981116-1208 & Notice of Violation Re Lack of Effective Oversight by Plant Mgt 1999-09-30
[Table view] |
Text
,
.- DISTRIBUTIO.'l IRfCKELFILE ACRS (10)
PD#2 RF Plant File PDR/LPDR RBernero OELD EJordan BGrines JPartloe ,a ULono * /7 ')/'7h-Sflorris Mr. J. M. Pilant, Technical February 12, 1986 Staff Manager Nuclear Power Group Nebraska Public Power District Post Office Box 499 Columbus. Nebraska 68601 Dear Mr. Pilant
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION - INSERVICE TESTING PROGRAM Re: Cooper Nuclear Station Your letters dated June 15, 1984, May 22, 1985, and July 12, 1985 describe the Cooper Nuclear Station second 10 year IST pogram.
In order to complete our review of the IST program additional information is necessary. Our Request for Additional Information (RAI)is enclosed. Please respond to the RAI within 45 days of receipt of this letter.
The reporting and/or record keeping requirements of this letter affect fewer than ten respondentsi therefore, OMB clearance is not required under P.L.96-511.
Sincerely, 8603040073 860212 8 th L 0* v'P -
ADOCK 050 William D. Long, Project Manager gDR BWR Project Directorate #2 Division of BWR Licensing
Enclosure:
As stated -- l l
I cc w/ enclosure: i See next phge 1
DCL:PD#2 DBL:PDD DBL:PD#2 S: s 2/21/06 ULongQ 2ha /86 tf
/86
Mr. J. M. Pilant Nebraska Public Power District Cooper Nuclear Station cc:
Mr. G. D. Watson. . General Counsel Nebraska Public Power District P. O. Box 4999 Columbus, Nebraska 68601 Mr. Arthur C. Gehr, Attorney Snell & Wilmer 3100 Valley Center Phoenix, Arizona 85073 Cooper Nuclear Station ATTN: Mr. Paul Thomason, Division 3 Manager of Nuclear Operations i P. O. Box 98 Brownville, Nebraska 68321 Director i Nebraska Department of Environmental Control P. O. Box 94877 State House Station Lincoln, Nebraska 68509 Mr. William Siebert, Commissioner Nemaha County Board of Commissioners Nenaha County Courthouse Auburn, Nebraska 68305 Resident Inspector U.S. Nuclear Regulatory Commission P. O. Box 218 Brownville, Nebraska 68321 Regional Administrator, Region IV ,
U.S. Nuclear Regulatory Commission <
611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011 >
/
H. Ellis Simmons, Director (
Division of Radiological Health [
D(;: rtment of Health 301 Centennial Mall, South ;y P. O. Box 95007 il Lingoln, Nebraska 68509 4
g.-
. T
COOPER NUCLEAR STATION PUMP AND VALVE INSERVICE TESTING PROGRAM OUESTIONS AND COMMENTS
- 1. VALVE TESTING PROGRAM A. General Questions and Comments
- 1. Provide a listing of the limiting values of full-stroke time for all power operated valves in the Cooper IST program for our rev iew.
- 2. Solenoid operated valves are not exempted from the stroke time measurement requirements of Section XI; their stroke times must be measured and corrective action taken if these times exceed the limiting value of full-stroke time. The NRC staff will grant relief from the trending requirements of Section XI (Paragraph IWV-3417 (a)) for these rapid acting valves, however, in order to obtain this relief the licensee must assign a maximum limiting stroke time of 2 seconds to these valves.
- 3. The NRC staff position is that the emergency diesel generators
- perform a safety-related function and the appropriate pumps and t valves in the emergency diesel air start, service water cooling, and fuel oil transfer systems should be included in the IST l
program and be tested in accordance with the Code. Engine
' mounted pumps are considered to be part of the diesel and need o not be tested separately.
- 4. Are all valves that are Appendix J type C leak-rate tested l included in the Cooper IST program and categorized A or A/C7 i
- 5. .
The NRC has concluded that the applicable leak test procedures and requirements for containment isolation valves are determined by 10 CFR 50 Appendix J, however, the licensee must comply with 4
1
t.he stnaly:;is of Lcakag2 Rat:s and Ctrrective Actirn Requirements Paragraphs of Section XI, IWV-3426 and 3427. Does the current Cooper IST program meet this NRC staff position?
- 6. Are any valves at Cooper Nuclear Station currently leak-rate tested to verify a pressure boundary isolation function? Those
- valves that serve both a pressure boundary isolation function and a containment isolation function must be leak tested to both the Appendix J and Section XI requirements.
- 7. It is the NRC staff position that excess flow check valves perform a safety-related function and should be included in the IST program.
- 8. When flow through a check valve is' used to indicate a full-stroke exercise of the valve disk, the NRC staff position is that verification of the maximum flow rate identified in any of the plant's safety analyses through the valve would be an adequate demonstration of the full-stroke requirement. Any flow rate less than this will be considered partial-stroke exercising unless it can be shown (by some means such as measurement of the differential pressure across the valve), that the check valve's f disk position at the lower flow rate would permit maximum l
required flow through the valve.
t Do the licensee's testing procedures which are based on observing
- "substantially free flow" (Cooper IST Program, Rev. 4,Section VIII.B.4.b.4) meet this staff position?
I
- 9. The Code permits valves to be exercised during cold shutdowns where it is not practical to exercise during plant operation and these valves are specifically identified by the licensee and are
- full-stroke exercised during cold shutdowns. The staff requires that the licensee provide a technical justification for each valve that cannot be exercised quarterly during power operation .
2
r- MatuclCarly Cxplains the difficulti;s cr hazards encount: rcd
,1d gr.ing that testing. The staff will then verify that it is not practical to exercise those valves and that the testing should be performed during cold shutdowns. Cold shutdown testing of valves identified by the licensee is acceptable when the following conditions are met:
- a. The licensee is to commence testing as soon as the cold shutdown condition is achieved, but not later than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> after shutdown, and continue until complete or the plant is ready to return to power.
Completion of all velve testing is not a prerequisite to b.
return to power.
. c. Any testing not completed during one cold shutdown should be performed during any subsequent cold shutdowns starting from the last test performed at the previous cold shutdown.
- d. For planned cold shutdowns, where ample time is available
+ and testing all the valves identified for the cold shutdown test frequency in the IST program will be accomplished,
. exceptions to the 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> may be taken.
i
- 10. A relief request from tihe Section XI exercising requirements must f be provided for Category A/C valves whose closed position can be
{
}; verified only by leak testing.
- 11. Is Cooper Station required to have an operational safety grade post accident sampling system? If so, the associated valves fi should be included in the IST program and be tested in accordance with Section XI.
- 12. Does the control room ventilation system perform any safety related function? If so, the appropriate support system valves .
~
should be included in the IST program.
3
- 13. R; view s -relattd functi:n of th2 RIactor Building Cics;d
' Cooling S; t,.'.EC) to determine if the system should be included in '.ne IST program and the applicable components tested in accordance with the requirements of Section XI.
B. CORE SPRAY SYSTEM
- 1. Review the safety function of valves CS-A0-13A and 138 to determine if they should be categorized A/C.
- 2. Do valves CS-CV-12,13,14, and 15 perform a safety related function in both the open and closed positions? How are these valves individually verified to perform their safety related function?
. 3. Are the following valves ever required to change position in order to perform a safety related function?
- CS-M0-llA CS-M0-26A CS-M0-5A CS-MO-7A CS-MO-llB CS-MO-268 CS-MO-5B CS-MO-78 i 4. Review the safety related function of valves CS-M0-15A and ISB to determine if they should be included in the IST program and categorized A.
f 'C. RESIDUAL HEAT REMOVAL SYSTEM i
i
- 1. Provide a detailed technical justification for not full-stroke l
exercising valves RHR-920-MV and 921-MV quarterly.
i l
- 2. Review the safety function of valves RHR-A0-68A and 688 to determine if they should be categorized A/C.
)
- 3. How are valves RHR-CV-10, 11, 12, and 13 verified to full-stroke exercise during the quarterly testing.
4
- 4. Do valves i:HR > l!' '
?d, and 25 p;rf rm a safety r]lat;d function in both the s,cen and closed positions? How is each valve individually verified to perform its safety related function.
- 5. Provide a detailed technical justification for not full-stroke
. exercising valve RHR-CV-20 quarterly in accordance with the requirements of Section XI.
- 6. Provide a detailed technical justification for not full-stroke exercising valves RHR-CV-21 and 22 quarterly in accordance with the requirements of Section XI.
- 7. What is the test interval designated IST-l?
- 8. What is the P&ID location of valves RHR-RV-10, 11, 12, and 13?
- 9. Are valves RHR-MO-17 and 18 ever required to change position in order to perform a safety related function?
t i 10. Review the safety related function of the following valves to determine if they should be included in the IST program and be i
categorized as indicated.
i t RHR-M0-15A A RHR-CV-23 A/C A RHR-M0-57 8 f RHR-M0-15B A RHR-M0-67 8 i RHR-M0-15C A RHR-M0-20 8 RHR-M0-150
[ A
- RHR-M0-274A RHR-M0-274B A i
- 11. Review the safety related function of valves RHR-FCV-43, RHR-LCV-71A, and RHR-LCV-71B to determine if they should be included in the IST program and tested in accordance with the Code. Do these valves have a required f ail-safe position?
O 5
{
D. STANDBY LIQUtu C0Ki *."*_ SYSTEM
- 1. Provide a detailed technical justification for not exercising valves SLC-CV-12 and 13 quarterly in accordance with the requirements of Section XI.
- 2. . .How is a full-stroke exercise verified for valves SLC-CV-10 and 11 quarterly?
E. HIGH PRESSURE COOLANT INJECTION
- 1. Would failure of HPCI-MO-15 in a nonconservative position during testing render an entire safety system inoperable?
Are there any adverse operational consequences that would result 2.
from full-stroke exercising valve HPCI-M0-16 quarterly? Should valves HPCI-M0-15 and 16 be tested during cold shutdowns?
- 3. How is valve HPCI-CV-15 exercised quarterly during extended cold
! shutdown periods?
i
- 4. Provide a detailed technical justification for not full-stroke f
exercising valve HPCI-CV-ll quarterly.
i
'i j 5. Do valves HPCI-CV-18 and 19 perform a safety related function in j both the open and closed positions? How are these valves individually verified to perform their safety related function?
- 6. What type of valves are HPCI-LVSC-44 and 50? How are these valves exercised quarterly?
- 7. What is the normal position of valve HPCI-MD-577
- 8. Review the safety related function of the following valves to determine if they should be included in the IST program. If it .
is determined that these valves do perform a safety related .
function, how will they be fail-safe tested?
6 a _ . _ _ _ _
V a h -s_ P&ID t:oord... ate 2 PCV-69A 204) F-1 PCV-698 2041 F-3 PCV-70A 2041 F-1 PCV-70B 2041 F-3
- 9. Review the safety related function of valves HPCI-M0-20, 21, and 24 to determine if they should be included in the IST program.
- 10. Review the safety related function of valves HPCI-CV-24, 25, 26, and 27 to determine if they should be included in the IST program.
F. REACTOR CORE ISOLATION COOLING
- 1. Would f ailure of RCIC-M0-15 in a nonconservative position during testing re,nder an entire safety system inoperable?
- 2. Provide a detailed technical justification for not full-stroke exercising valve RCIC-CV-ll quarterly.
- 3. Do valves RCIC-CV-18 and 19 perform a safety related function in
' both the open and closed positions? How are these valves individually verified to perform their safety related function?
l 4. What type of valves are RCIC-LVSC-37 and 42 and how are they i
, exercised quarterly? .
- 5. Review the safety related function of the following valves to j determine if they should be included in the IST program.
j RCIC-CV-22 RCIC-MO-20
- , RCIC-CV-23 RCIC-M0-30 t RCIC-CV-24 RCIC-MO-33
) RCIC-CV-25 S
7.
G. RSACTOR FEE 0 WATER
- 1. Provide a detailed technical justification for not full-stroke exercising valves RF-CV-13, 14, 15 and 16 quarterly.
H. MAIN STEAM
- 1. Review the safety related function of valves MS-RV-71A through H, to determine if they should be categorized B/C and be tested in accordance with the Section XI requirements for power operated valves.
- 2. It is the NRC staff position that the following valves be included in the IST program, i
Main Steam Safety and Relief Valve Tail Pipe Vacuum Breakers MS-CV-10 MS-CV-16 MS-CV-24 MS-CV-30 MS-CV-ll MS-CV-17 MS-CV-25 MS-CV-31
, MS-CV-12 MS-CV-20 MS-CV-26 MS-CV-32 MS-CV-13 MS-CV-21 MS-CV-27 MS-CV-33
! MS-CV-34 MS-CV-14 MS-CV-22 MS-CV-28 l MS-CV-15 MS-CV-23 MS-CV-29 MS-CV-35 r
I Check Valves in the Air / Nitrogen Supply Lines f to the AD5 Valve Accumulators i
-CV-17 -
-CV-19 -CV-21
-CV-18 -CV-20 -CV-22 i
I. REACTOR RECIRCULATION
- 1. Provide a more detailed technical justification for not exercising valves RR-MO-53A and 538 quarterly. The testing schedule on the valve table does not agree with the alternate testing described in relief request RV-03.
9
- 2. Valves RR-M0-54A and 548 should be deleted from the IST program.
~
e 8
J. REACTOR WATER CLEANUP SYSTEM
- l. Provide a detailed technical justification for not full-stroke exercising check valve RWCU-CV-15 quarterly.
K. RADWASTE SYSTEM
- 1. Review the safety related function of valve RW-M0-93 to determine if it should be included in the IST program and be categorized A.
L. PRIMARY CONTAINMENT
- 1. Review the safety related function of the motor operated bypasses for valves PC-M0-230 and 231 to determine if they should be included in the IST program and be categorized A.
M. ATMOSPHERIC CONTAINMENT ATMOSPHERE DILUTION SYSTEM
- 1. Review the safety related function of the following valves to determine if they should be included in the IST program and be categorized C.
I ACAD-CV-10 ACAD-CV-13 ACAD-CV-16 j ACAD-CV-ll ACAD-CV-14 ACAD-CV-17 ACAD-CV-12 ACAD-CV-15 i
N. CONTROL R00 DRIVE SYSTEM f
i
- 1. It is the NRC staff position that valves CRD-CV-126 and 127 and check valves 114,115 and 138 perform a safety related function and must be included in the IST program and be tested in l
accordance with the requirements of Section XI.
O S
9
- 2. R; view th] saf;ty ralated functi:n of the following valv;s to determine if they should be included in the IST program and be categorized as indicated ,
CRD-CV-19 (C) CRD-CV-21(C)
CRD-CV-13(iA/C)
CRD-CV-15 A/C) CRD-CV-20 (C) CRD-CV-22 (C)
~
- 0. SERVICE WATER SYSTEM
- 1. Provide P&ID 2077 for our review. Any service water valves on this drawing that are required to change position to support emergency diesel generator operation must be included in the IST
[ program and be tested in accordance with Section XI (also see question A.3).
- 2. Provide the test procedure used to verify operability of valves SW-CV-35, 36, 37 and 38. Does this test procedure meet the requirements of IE BULLETIN NO. 83-03 " Check Valve Failures in Raw Water Cooling Systems of Diesel Generators"?
- 3. Are the following valves required to change position to protect the RHR service water booster pumps?
SW-MV-104 SW-MV-97 SW-CV-23 SW-CV-25 l; SW-MV-90 SW-MV-243 SW-CV-24 SW-CV-26 I 4. Review the safety related function of the following valves to
- determine if they should be included in the IST program
! SW-CV-19 SW-CV-21 SW-CV-27 SW-M0-650 SW-CV-20 SW-CV-22 SW-CV-28 SW-M0-651 I SW-M0-89A SW-M0-886 SW-M0-888 SW-CV-10 SW-M0-89B SW-MO-887 SW-MO-889 SW-CV-ll SW-M0-37 SW-M0-ll7 SW-CV-13 SW-CV-12 O
10
P. MISCELLANEOUS SYSTEMS
- 1. Provide the P& ids that show the instrument air and/or service air containment penetrations.
- 2. The NRC staff position is that the torus to drywell vacuum
. breakers perform a safety related function and must be included in the IST program.
- 3. Review the safety related function of the standby gas treatment system valves to determine if they should be included in the IST g
program. These components need not be considered if they are simple air dampers rather than valves.
- 4. Review the* safety related function of the TIP system valves to determine if they should be included in the IST program.
i i
e i
i 6
O
- 2. PUMP TESTING PROGRAM
- 1. Are lubricant levels / pressures observed during pump testing for all pumps in the Cooper IST program? If not, provide the specific technical justifications for not performing this testing.
- 2. . How is the standby liquid control pump flow rate (Q) measured during each inservice test of these pumpsi
- 3. The NRC staff position is that measurement of vibration velocity is an acceptable alternate method to utilize to monitor pump vibration and has established a maximum velocity of 0.314 in/s.
3
! as the Required Action limit. Exceptions to this staff position may be taken on a case by case basis provided that the licensee I can adequately demonstrate that a particular pump historically exceeds this limit.
t
- 4. Does the P.CIC pump perform a safety related function at Cooper j Nuclear Station?
I
!, 5. Do the reactor building closed cooling (REC) pumps perform a
! safety related function (Refer to question A.13)?
\
r
- 6. If pump parameter deviations fall within the Required Action l
j Range of Table IWP-3100-2, the pump shall be declared inoperative regardless of whether it is also required to be declared
- inoperative by the Station Technical Specifications. The IST program is implemented by and is, therefore, a part of the Station Technical Specification. Exceeding an IST program limit requires that the Code mandated corrective actions be followed even if other Technical Specification limits have not been exceeded (Refer to Inservice Testing of Pumps General
. Procedure IV.B.5.C.2).
~
12
,