Other: ML20137L000, ML20206T655, ML20206T679, ML20206T705, ML20206T726, ML20206T748, ML20206T776, ML20206T792, ML20206T817, ML20206T843, ML20206T847, ML20206T875, ML20206T899, ML20206T913, ML20206T921, ML20206T931, ML20206T937, ML20206T949, ML20206T966, ML20206T981, ML20206T986, ML20206U003, ML20212B914, ML20262E700, ML20262E704, NLS8400108, Forwards Second 10-yr Inservice Insp Plan, NLS8600021, Forwards Addenda to Rev 3 to Inservice Insp Program for ASME Class 1,2 & 3 Components, NLS8600248, Forwards Rev 5 to Inservice Testing Program for ASME Class 1,2 & 3 Components, for Second 10-yr Testing Program. General Pump Testing Procedure 3.9 & General Valve Testing Procedure 3.10 Being Revised to Incorporate Rev 1 Changes
|
MONTHYEARML20206T9131978-10-23023 October 1978 Rev 5 to Surveillance Procedure 6.3.16.1, Reactor Equipment Cooling - Pump Operability Test Project stage: Other ML20206T9861981-08-28028 August 1981 Rev 0 to Surveillance Procedure 6.4.1.8, Control Rod Drive Hydraulic Control Unit Accumulator Leakage Test Project stage: Other NLS8400108, Forwards Second 10-yr Inservice Insp Plan1984-04-0303 April 1984 Forwards Second 10-yr Inservice Insp Plan Project stage: Other ML20206U0031984-07-23023 July 1984 Rev 13 to Nuclear Performance Evaluation Procedure 10.9, Control Rod Scram Time Evaluation Project stage: Other ML20100M8071984-11-28028 November 1984 Draft Rev 9 to QA Policy for Calvert Cliffs Nuclear Power Plant Project stage: Draft Other ML20206T9371984-12-0606 December 1984 Rev 10 to Surveillance Procedure 6.3.18.2, Svc Water Motor Operated Valve Operability Test Project stage: Other ML20206T9311984-12-0606 December 1984 Rev 6 to Surveillance Procedure 6.3.18.1, Svc Water Pump Operability Test Project stage: Other ML20206T8751985-01-0303 January 1985 Rev 11 to Surveillance Procedure 6.3.12.2, Diesel Generator Starting Air Compressor Operability Project stage: Other ML20262E7001985-04-25025 April 1985 Flow Diagram:Circulating,Screen Wash & Service Water Systems. Sheet 1 of 5. Actual Rev STATUS:N14 Project stage: Other ML20262E7041985-04-26026 April 1985 Flow Diagram:Circulating,Screen Wash & Service Water Systems. Sheet 2 of 5. Actual Rev STATUS:N07 Project stage: Other ML20206T9661985-05-0202 May 1985 Rev 13 to Surveillance Procedure 6.3.19.1, Standby Gas Treatment Operability Test Project stage: Other ML20129J6611985-07-12012 July 1985 Submits Revised Inservice Testing Relief Requests RV-03 Re Reactor Recirculation Loops a & B Discharge Bypass Valves, Reflecting Current Pipe Configuration & RP-05 Re HPCI Test Method & Updated Request Index Project stage: Request ML20206T7761985-08-18018 August 1985 Rev 11 to Surveillance Procedure 6.3.8.4, Standby Liquid Control Manual Initiation Test Tank to Reactor Vessel Project stage: Other ML20206T8171985-09-13013 September 1985 Rev 12 to Surveillance Procedure 6.3.10.2, Instrument Line Flow Check Valve Test Project stage: Other ML20137L0001985-10-31031 October 1985 Addenda to Rev 3 to Inservice Insp Program for ASME Class 1,2 & 3 Components Project stage: Other ML20206T7481985-11-21021 November 1985 Rev 15 to Surveillance Procedure 6.3.6.1, RCIC Test Mode Surveillance Operation Project stage: Other ML20206T8431985-12-11011 December 1985 Rev 0 to Surveillance Procedure 6.3.10.16, Check Valves in Cooling Sys of Diesel Generators Integrity Verification Project stage: Other ML20206T9211986-01-16016 January 1986 Rev 12 to Surveillance Procedure 6.3.16.2, Reactor Equipment Cooling Motor Operated Valve Operability Test Project stage: Other NLS8600021, Forwards Addenda to Rev 3 to Inservice Insp Program for ASME Class 1,2 & 3 Components1986-01-17017 January 1986 Forwards Addenda to Rev 3 to Inservice Insp Program for ASME Class 1,2 & 3 Components Project stage: Other ML20206T7051986-01-30030 January 1986 Rev 18 to Surveillance Procedure 6.3.4.1, Core Spray Test Mode Surveillance Operation Project stage: Other ML20154A5251986-02-12012 February 1986 Forwards Request for Addl Info Re Inservice Testing Program, Based on Review of 840615,850522 & 0722 Ltrs Describing Second 10-yr Inservice Testing Program.Response Requested within 45 Days Project stage: RAI ML20206T8471986-03-0606 March 1986 Rev 17 to Surveillance Procedure 6.3.12.1, Diesel Generator Operability Test Project stage: Other ML20206T9491986-03-0606 March 1986 Rev 15 to Surveillance Procedure 6.3.18.3, Svc Water Surveillance Operation Project stage: Other ML20206T7261986-03-13013 March 1986 Rev 21 to Surveillance Procedure 6.3.5.1, RHR Test Mode Surveillance Operation Project stage: Other ML20206T9811986-04-24024 April 1986 Rev 17 to Surveillance Procedure 6.3.20.1, RHR Svc Water Booster Pump Flow Test & Valve Operability Test Project stage: Other ML20211A1361986-04-28028 April 1986 Trip Rept of 860415-16 Site Visit for Pump & Valve Inservice Testing Program Working Meeting Re Questions Resulting from Program Review.List of Attendees,Questions Serving as Agenda for Meeting & Responses to Questions Encl Project stage: Meeting ML20211A0891986-05-30030 May 1986 Forwards Contractor Summary of 860412 & 16 Meetings at Facility Re to Recipient Requesting Addl Info on Second 10-yr Inservice Testing Program.Correction Made on Page 2 of Summary Project stage: Meeting ML20206T8991986-06-0505 June 1986 Rev 3 to Surveillance Procedure 6.3.12.8, Diesel Generator Fuel Oil Transfer Pump Flow Test Project stage: Other ML20206T7921986-06-0505 June 1986 Rev 1 to Surveillance Procedure 6.3.9.1, MSIV Accumulator Functional Test Project stage: Other ML20206T6551986-06-12012 June 1986 Rev 13 to Surveillance Procedure 6.3.2.1, Automatic Depressurization Sys Manual Valve Actuation Project stage: Other ML20206T6791986-06-12012 June 1986 Rev 23 to Surveillance Procedure 6.3.3.1, HPCI Test Mode Surveillance Operation Project stage: Other ML20206T6381986-06-30030 June 1986 Forwards Response to W Long 860212 Request for Addl Info Re Inservice Testing Program & 860415-16 Meetings Re Open Items.Surveillance Procedures,Including Procedure 6.3.2.1, Also Encl Project stage: Meeting NLS8600248, Forwards Rev 5 to Inservice Testing Program for ASME Class 1,2 & 3 Components, for Second 10-yr Testing Program. General Pump Testing Procedure 3.9 & General Valve Testing Procedure 3.10 Being Revised to Incorporate Rev 1 Changes1986-07-30030 July 1986 Forwards Rev 5 to Inservice Testing Program for ASME Class 1,2 & 3 Components, for Second 10-yr Testing Program. General Pump Testing Procedure 3.9 & General Valve Testing Procedure 3.10 Being Revised to Incorporate Rev 1 Changes Project stage: Other ML20212B9141986-07-31031 July 1986 Vols I & II of Rev 5 to Inservice Testing Program for ASME Class 1,2 & 3 Components, for Second 10-yr Testing Program Project stage: Other ML20148C9481988-01-13013 January 1988 Forwards Safety Evaluation of Util Second 10-yr Inservice Testing Program Submitted w/860730 Ltr.Certain Relief Requests Denied Where Proposed Alternative Testing Unacceptable.Technical Evaluation Rept Also Encl Project stage: Approval ML20151H8461988-04-13013 April 1988 Forwards Response to Anomalies Identified in NRC 880113 SER Re Facility Inservice Testing Program.Reactor Equipment Pumps Will Be Tested in Accordance W/Section Xi.Util Evaluating Need for Any Relief Request in Performing Test Project stage: Request ML20151L3111988-07-29029 July 1988 Forwards Revised & New Relief Requests & Program Corrections to Second 10 Yr Inservice Testing Program.Addl Review of Program Identified Need for Further Changes to Program Including Rev of Existing Relief Requests Project stage: Request 1986-01-16
[Table View] |
Text
,
s COOPER NUCLEAR STATION OPERATIONS MANUAL SURVEILLANCE PROCEDURE 6.3.16.1 REC - PITMP OPERABILITY TEST I.
PURPOSE To provide a detailed instruction for station personnel to perform a pump operability test of the reactor equipment cooling system.
II.
DISCUSSION The pumpreesting is performed to provide assurance of reliability of pump requirements listed in Technical Specifications Section 3.12.B.
III.
REFERENCE MATERIAL A.
SAR.
1.
Volume IV, Section 10, Subsection 6.0.
2.
Amendment 14, Pages 14.4.1 thru 8.
B.
Flow Diagrams.
1.
B & R Dwg. 2029; Demineralized Water System.
2.
B & R Dwg. 2031, Sht. 1; RBCCW System.
1 3.
B & R Dwg. 2031, Sht. 2; RBCCW System.
4.
B & R Dwg. 2031, Sht. 3; RECCW System.
C.
Vendor Manuals.
1.
Fairbanks Morse, 68-63-6; RBCCW System Pump and Motor.
D.
Electrical Diagrams.
1.
B & R Dwg. 3006; Auxiliary One Line Diagram.
2.
B & R Dwg. 3007; Auxiliary One Line Diagram.
3.
B & R Dwg. 3010; Vital One Line Diagram.
4.
B & R Dwg. 3037; Control Elernentary Diagram.
5.
B & R Dwg. 3045; Control Elementary-Diagram.
IV.
PREREQUISITES A.
Obtain permission and signature from the Shif t Supervisor before starting the test.
8607080252 860630 PDR ADOCK 05000298 p
PDR Revised By/Date Reviewed By/Date Approved By/Date Rev.
Procedure Page 1
R. Brungardt 10/6/78 H. Williams 10/18/7f
/t 5
6.3.16.1 Of 3 Pages
/0-23 79
h B.
Coordinate testing with the Control Ro,m Operator.
C.
REC System operable.
V.
LIMITATIONS A.
Surveillance Requirements - Technical Specifications Section 4.12.B.1.a.
Pump Operability Testing - once per month.
B.
Administrative Limits.
1.
All discrepancies shall be recorded in the Shif t Supervisor's log.
2.
Data Sheet 6.3.16.1 attached shall be used to record the test, and filed as part of the station records.
3.
All testing shall be coordinated with the Control Roou Operator.
VI.
PRECAUTIONS A.
Observe normal operating requirements.
VII. TEST EQUIPMENT None required..
VIII'.
PROCEDURE Note: Two or three pumps are normally in service.
A.
Perform Test as Follows:
+ 4-3,;3 1.
Obtain permission and signatare from Shift Supervisor before starting the test.
2.
Establish communication between Operator locally at REC pumps and Control Room vertical board M.
3.
Note and record REC system pressure as indicated on REC-PI-452, VBD-M.
4.
Record REC pumps presently in service.
5.
Start an idle pump by turning control switch on VBD-H to " start".
Creen "stop" light goes out and red " start" light turns on.
a.
b.
Note REC pressure increases on REC-PI-452.
c Procedure Number. 6.3.16.1 Date n _ y: ~ k
' Revision 5
Page 2 of 3
-Pages
b D
6.
Secure one REC pump originally in service by turning control switch to "stop".
Red " start" light goes out and green "stop" light turns on.
a.
b.
Note REC pressure on REC-PI-452 returns to approximately initial recorded pressure.
7.
Repeat Steps 5 and 6 for remaining REC pumps originally idle.
8.
Locally at pumps, visually check pumps for normal operation i.e. normal noise and vibration level, idle pumps not rotating backwards.
9.
Restore the pump configuration as existing operating requirements dictate.
Refer to Operating Procedure 2.2.65.
10.
Notify the Shift Supervisor that the test is completed.
IX.
ATTACIIMENTS A.
N.A.
B.
Data Sheet 6.3.16.1, Rev. 5; Pump Operability Test Data.
i Procedure Number 6.3.16.1 Date
.'??'N Revision 5
Page,_3,of 3
Pages
COOP _ER NUCLEAR _ STATION _0PERATION_S_ MANUAL e
ATTACIDIENT "B" SURVEILLANCE PROCEDURE 6.3.16.1 REC - PUMP OPERABILITY TEST DATA CHECK PROCEDURE A l B i C lD A.
1.
Permission obtained to perform test 2.
Communications established between locally and VBD-M.
3.
Record reading of REC-PI-452, VBD-M.
psig 4.
REC pumps in service.
5.
Start one REC pump originally idle.
Creen "stop" light off and red " start" light on.
a.
b.
Note REC pressure increases on REC-PI-452.
6.
Secure one REC pump originally in service.
Red " start" light off and green "stop" light on.
a.
b.
Note REC pressure returns to approximately initial pressure.
7.
Steps 5 and 6 repeated for all originally idle pumps.
8.
Perform local visual checks on pumps for normal operation:
9.
Restore pumps as required by operating conditions.
10.
Notify Shif t Supervisor test complete.
Discrepancies:
Operator
/
Date Shif t Supervisor
/
Permission to Start Date i
Shif t Supervisor
/
Test Complete & Reviewed Date 4
Shift Supervisor
/
NCR Written if Required Date MRR(s) Number if Required Reviewed By
/
Date Procedure Number 6.3.16.1 Date
' :' '4
' 'i Revision 5
Page 1 of 1