1 1

(

Nebraska Public Power District NebraMs Energy Leader NLS990086 August 10,1999 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001 Gentlemen:

Subject:

Organization Changes Cooper Nuclear Station, NRC Docket 50-298, DPR-46 Nebraska Public Power District requests that the following changes be made to the distribution on Nuclear Regulatory Commission correspondence. Original correspondence should be addressed to Mr. J. H. Swailes, Vice President of Nuclear Energy, P.O. Box 98, Brownville, Nebraska 68321. The following changes should be made to the carbon copy addressees:

Mr. G. R. Horn, Sr. Vice President of Energy Supply, 141415th Street, Columbus, Nebraska 68601 replaces Mr. J. H. Swailes.

Should you have any questions concerning this matter, please contact me.

Sincerely, L. i ew Nuclear Licensing & Safety Manager

/nr cc: Regional Administrator USNRC - Region IV Senior Project Manager USNRC - NRR Project Directorate IV-1 Senior Resident Inspector }f USNRC 9908130055 990810 PDR ADOCK 05000298 H PDR O

Cooper Nudear Station Po. Box 98/Brownville NE 68321-0098 l Telephone: (402) 825-38H / Fax: (402) 825-5211 httpf/www nppd com

e 1

y ATTACHMENT 3 LIST OF.NRC COMMITMENTS i

Correspondence No: NLS990086 The following table identifies those actions committed to by the District in

,this document. Any other actions discussed in the submittal represent l intended or planned actions by the District. They are described to the NRC for the NRC's information and are not regulatory commitments. Please notify the Licensing Manager at Cooper Nuclear Station of any questions regarding l this document or any associated regulatory commitments.

l COMMITTED DATE COMMITMENT OR OUTAGE None 1

i l PROCEDURE NUMBER 0.42 l REVISION NUMBER 1.2 l PAGE 8 OF 10 l j 1