Category:INSPECTION REPORT
MONTHYEARIR 05000254/20244012024-12-20020 December 2024 Security Baseline Inspection Report 05000254/2024401 and 05000265/2024401 IR 05000254/20240112024-11-13013 November 2024 Biennial Problem Identification and Resolution Inspection Report 05000254/2024011 and 05000265/2024011 IR 05000254/20240032024-11-12012 November 2024 Integrated Inspection Report 05000254/2024003, 05000265/2024003 and 07200053/2024001 IR 05000254/20240102024-10-28028 October 2024 Age Related Degradation Inspection Report 05000254/2024010 and 05000265/2024010 and Notice of Violation IR 05000254/20244022024-09-12012 September 2024 Material Control and Accounting Program Inspection Report 05000254/2024402 and 05000265/2024402 (Public) IR 05000254/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Quad Cities Nuclear Power Station (Report 05000254/2024005; 05000265/2024005) IR 05000254/20240022024-08-12012 August 2024 Integrated Inspection Report 05000254/2024002 and 05000265/2024002 IR 05000254/20243012024-08-0101 August 2024 NRC Initial License Examination Report 05000254/2024301; 05000265/2024301 IR 05000254/20240012024-05-14014 May 2024 Integrated Inspection Report Nos. 05000254/2024001 and 05000265/2024001 IR 05000254/20245012024-04-0505 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000254/2024501 and 05000265/2024501 IR 05000254/20230062024-02-28028 February 2024 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2023006 and 05000265/2023006) IR 05000254/20230042024-02-0505 February 2024 Integrated Inspection Report 05000254/2023004 and 05000265/2023004 IR 05000254/20234032023-12-22022 December 2023 Public- Quad Cities Nuclear Power Station Security Baseline Inspection Report 05000254/2023403 and 05000265/2023403 IR 05000254/20230102023-12-20020 December 2023 Comprehensive Engineering Team Inspection Report 05000254/2023010 and 05000265/2023010 IR 05000254/20230032023-11-0909 November 2023 Integrated Inspection Report 05000254/2023003 and 05000265/2023003 IR 05000254/20230112023-09-20020 September 2023 Safety-Conscious Work Environment Issue of Concern Team Inspection Report 05000254/2023011 and 05000265/2023011 IR 05000254/20230052023-08-25025 August 2023 Updated Inspection Plan and Assessment Follow-Up Letter for Quad Cities Nuclear Power Station (Report 05000254/2023005; 05000265/2023005) IR 05000254/20230022023-08-0808 August 2023 Integrated Inspection Report 05000254/2023002 and 05000265/2023002 IR 05000254/20234012023-06-26026 June 2023 Cyber Security Inspection Report 05000254/2023401 and 05000265/2023401 IR 05000265/20230402023-06-22022 June 2023 Reissue Quad Cities Nuclear Power Station 95001 Supplemental Inspection Supplemental Report 05000265/2023040 and Follow Up Assessment Letter ML23167B1722023-06-16016 June 2023 95001 Supplemental Inspection Report 05000265/2023040 and Follow-Up Assessment Letter IR 05000254/20234022023-05-15015 May 2023 Security Baseline and ISFSI Inspection Reports 05000254/2023402, 05000265/2023402, 07200053/2023401 IR 05000254/20230012023-05-0808 May 2023 Integrated Report 05000254/2023001 and 05000265/2023001 ML23065A2832023-03-0707 March 2023 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000254/2023010 and 05000265/2023010 IR 05000254/20233012023-03-0707 March 2023 NRC Initial License Examination Report 05000254/2023301; 05000265/2023301 IR 05000254/20220062023-03-0101 March 2023 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2022006 and 05000265/2022006) IR 05000254/20220042023-02-10010 February 2023 Integrated Inspection Report 05000254/2022004 and 05000265/2022004 IR 05000254/20220112023-01-0606 January 2023 Triennial Fire Protection Inspection Report 05000254/2022011 and 05000265/2022011 IR 05000254/20220102022-12-13013 December 2022 Phase 4 Post-Approval License Renewal Inspection Report 05000254/2022010 and 05000265/2022010 ML22313A1502022-11-29029 November 2022 EA-22-062 QC ERV Final Action IR 05000254/20224012022-11-22022 November 2022 Security Baseline Inspection Report 05000254/2022401 and 05000265/2022401 IR 05000254/20220132022-11-17017 November 2022 Biennial Problem Identification and Resolution Inspection Report 05000254/2022013 and 05000265/2022013 IR 05000254/20220032022-11-0303 November 2022 Integrated Inspection Report 05000254/2022003 and 05000265/2022003 IR 05000254/20220052022-08-22022 August 2022 Updated Inspection Plan for Quad Cities Nuclear Power Station (Report 05000254/2022005; 05000265/2022005) IR 05000254/20225012022-08-15015 August 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000254/2022501 and 05000265/2022501 IR 05000254/20220022022-08-0909 August 2022 Integrated Inspection Report 05000254/2022002 and 05000265/2022002 IR 05000254/20220902022-08-0808 August 2022 NRC Inspection Report 05000254/2022090 and 05000265/2022090; Preliminary White Finding IR 05000254/20220122022-07-11011 July 2022 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000254/2022012 and 05000265/2022012 IR 05000254/20220012022-05-11011 May 2022 Integrated Inspection Report 05000254/2022001 and 05000265/2022001 IR 05000254/20210062022-03-0202 March 2022 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2021006 and 05000265/2021006) IR 05000254/20210042022-02-0202 February 2022 Integrated Inspection Report 05000254/2021004 and 05000265/2021004 ML22033A1672022-02-0202 February 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000265/2022001 IR 05000254/20214022021-12-0101 December 2021 Security Baseline Inspection Report 05000254/2021402 and 05000265/2021402 IR 05000254/20210102021-11-24024 November 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000254/2021010 and 05000265/2021010 IR 05000254/20210032021-10-28028 October 2021 Integrated Inspection Report 05000254/2021003 and 05000265/2021003 IR 05000254/20214012021-09-0909 September 2021 Security Baseline Inspection Report 05000254/2021401 and 05000265/2021401 IR 05000254/20210052021-09-0101 September 2021 Updated Inspection Plan for Quad Cities Nuclear Power Station (Report 05000254/2021005 and 05000265/2021005) ML21238A3142021-08-26026 August 2021 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000254/2021004; 05000265/2021004 IR 05000254/20213012021-08-23023 August 2021 NRC Initial License Examination Report 05000254/2021301; 05000265/2021301 IR 05000254/20210022021-08-0909 August 2021 Integrated Inspection Report 05000254/2021002 and 05000265/2021002 2024-09-12
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000254/19990171999-09-15015 September 1999 Insp Repts 50-254/99-17 & 50-265/99-17 on 990823-27.No Violations Noted.Major Areas Inspected:Pilot Baseline Insp for Annual Review of Changes to Safety Analysis Rept & Biennial Review Permanent Plant Mod IR 05000254/19990151999-08-25025 August 1999 Insp Repts 50-254/99-15 & 50-265/99-15 on 990816-20.No Violations Noted.Major Areas Inspected:Maint Rule Implementation IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site IR 05000254/19990161999-08-19019 August 1999 Insp Repts 50-254/99-16 & 50-265/99-16 on 990719-22. Violations Noted.Major Areas Inspected:Physical Protection Cornerstone,Including Review of Access Authoization Program & Changes to Security Plan IR 05000254/19990121999-08-13013 August 1999 Insp Repts 50-254/99-12 & 50-265/99-12 on 990628-0716. Violations Noted.Major Areas Inspected:Corrective Action Process Which Included Methods Used for Identification, Cause Investigation & Correction of Quality Related Items IR 05000254/19990111999-08-13013 August 1999 Insp Repts 50-254/99-11 & 50-265/99-11 on 990601-0720.NCVs Noted.Major Areas Inspected:Performance in Initiating Events,Mitigating Sys,Barrier Integrity Cornerstones & Performance Indicator Verification IR 05000254/19990141999-07-30030 July 1999 Insp Repts 50-254/99-14 & 50-265/99-14 on 990713-15.One Violation Noted & Treated as Ncv.Major Areas Inspected: Heat Sink Performance,Which Covers Inspectable Area Under Initiating Events & Mitigation Sys IR 05000254/19990131999-07-29029 July 1999 Insp Repts 50-254/99-13 & 50-265/99-13 on 990628-0702.No Violations Noted.Major Areas Inspected:Public Radiation Safety & Review of Gaseous & Liquid Radiological Effluents & of Radiological Environmental Monitoring Program IR 05000254/19990091999-06-23023 June 1999 Insp Repts 50-254/99-09 & 50-265/99-09 on 990421-0531.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000254/19990061999-05-14014 May 1999 Insp Repts 50-254/99-06 & 50-265/99-06 on 990307-0420.Three Violations Noted & Being Treated as non-cited Violations. Major Areas Insptected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000254/19990081999-05-11011 May 1999 Insp Repts 50-254/99-08 & 50-265/99-08 on 990419-23.No Violations Noted.Major Areas Inspected:Adequacy of Licensee Programs,Procedures,Training & Supporting Documentation IR 05000254/19990031999-04-0909 April 1999 Insp Repts 50-254/99-03 & 50-265/99-03 on 990308-12.No Violations Noted.Major Areas Inspected:Maint & Engineering IR 05000254/19990011999-04-0101 April 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990121-0306. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19990071999-03-31031 March 1999 Radiation Protection Insp Repts 50-254/99-07 & 50-265/99-07 on 990309-12.No Violations Noted.Major Areas Inspected:Solid Radwaste Processing & Control Program & Radioactive Matls Shipping Program IR 05000254/19980211999-03-0505 March 1999 Insp Repts 50-254/98-21 & 50-265/98-21 on 981112-1218. Violation Noted:Major Areas Inspected:Isi Activities at Plant During Refueling Outage 15 IR 05000254/19990041999-02-26026 February 1999 Insp Repts 50-254/99-04 & 50-265/99-04 on 990201-05.No Violations Noted.Major Areas Inspected:Emergency Prepardeness Program as Aspect of Plant Support IR 05000254/19990021999-02-25025 February 1999 Insp Repts 50-254/99-02 & 50-265/99-02 on 990125-29.No Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Program Included Water Chemistry Control, Instrument Quality Control & internal-lab Comparison IR 05000254/19980241999-01-14014 January 1999 Partially Withheld Security Insp Repts 50-254/98-24 & 50-265/98-24.Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Quad Cities Facility.Details Withheld (Ref 10CFR2.790) IR 05000254/19980201998-12-28028 December 1998 Insp Repts 50-254/98-20 & 50-265/98-20 on 981014-1201.No Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000254/19980221998-12-28028 December 1998 Insp Repts 50-254/98-22 & 50-265/98-22 on 981130-1204.No Violations Noted.Major Areas Inspected:Radiation Protection Staff Preparation for Q1R15 Refueling Outage,Including Review of ALARA Planning & Work Plan Integration IR 05000254/19980191998-12-18018 December 1998 Insp Repts 50-254/98-19 & 50-265/98-19 on 981019-1106. Violations Noted.Major Areas Inspected:Effectiveness of Engineering & Technical Support Provided to Plant in Performance of Routine & Reactive Site Activities IR 05000254/19980171998-11-0505 November 1998 Insp Repts 50-254/98-17 & 50-265/98-17 on 980902-1014.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19980181998-10-15015 October 1998 Partially Withheld Insp Repts 50-254/98-18 & 50-265/98-18 on 980914-18 (Ref 10CFR73.71).No Violations Identified.Major Areas Inspected:Review of Plant Support Activities,Security Activities Re Onsite Personnel Access & Communications IR 05000254/19980131998-09-22022 September 1998 Insp Repts 50-254/98-13 & 50-265/98-13 on 980716-0901.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980141998-09-17017 September 1998 Insp Repts 50-254/98-14 & 50-265/98-14 on 980825-28.No Violations Noted.Major Areas Inspected:Evaluation of Licensee Performance During Plant Biennial Exercise of Emergency Plan IR 05000254/19980161998-09-0404 September 1998 Insp Repts 50-254/98-16 & 50-265/98-16 on 980810-14.No Violations Noted.Major Areas Inspected:Radiation Protection Program Included External & Internal Exposure Control,Whole Body Counting & Contamination & Survey Monitoring Program IR 05000254/19980151998-07-31031 July 1998 Insp Repts 50-254/98-15 & 50-265/98-15 on 980721-24.No Violations Noted.Major Areas Inspected:Aspects of Licensee Corrective Actions & Engineering Involvement in Corrective Actions Process IR 05000254/19980111998-07-0202 July 1998 Insp Repts 50-254/98-11 & 50-265/98-11 on 980504-22. Violations Noted.Major Areas Inspected:Quad Cities Safe Shutdown Analysis & Supporting Procedures IR 05000254/19980081998-05-11011 May 1998 Insp Repts 50-254/98-08 & 50-265/98-08 on 980407-09 & 14-17. No Violations Noted.Major Areas Inspected:Maint,Quality Assurance & Engineering IR 05000254/19982011998-05-0606 May 1998 Insp Repts 50-254/98-201 & 50-265/98-201 on 980216-0327.No Violations Noted.Major Areas Inspected:Evaluation of Capability of Selected Sys to Perform Safety Functions Required by Design Bases IR 05000254/19980101998-05-0606 May 1998 Insp Repts 50-254/98-10 & 50-265/98-10 on 980413-17.No Violations Noted.Major Areas Inspected:Liquid & Gaseous Effluent Programs,Annual Effluent Rept,Continuous Air & Area Radiation Monitors IR 05000254/19980051998-04-23023 April 1998 Insp Repts 50-254/98-05 & 50-265/98-05 on 980216-0326. Violations Noted.Major Areas Inspected:Engineering,Including Allowances for Development of Emergency & Immediate Mods ML20217G3401998-04-23023 April 1998 Insp Repts 50-254/98-04 & 50-265/98-04 on 980211-0331. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support IR 05000254/19980071998-04-22022 April 1998 Insp Repts 50-254/98-07 & 50-265/98-07 on 980330-0403.No Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Plant,Adequacy of Security Procedures & Event Logs ML20216C2601998-03-0606 March 1998 Insp Repts 50-254/97-28 & 50-265/97-28 on 971224-980210. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000254/19970221998-02-13013 February 1998 Insp Repts 50-254/97-22 & 50-265/97-22 on 971027-1121. Violations Noted.Major Areas Inspected:Hpci Sys Operational Performance for Operations,Maintenance & Engineering IR 05000254/19980021998-02-0505 February 1998 Insp Repts 50-254/98-02 & 50-265/98-02 on 980112-16. Violations Noted.Major Areas Inspected:Review of ALARA Planning,Radiation Work Permits & Observations of Radworker Performance IR 05000254/19970261998-01-21021 January 1998 Insp Repts 50-254/97-26 & 50-265/97-26 on 971103-1223. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19970241998-01-13013 January 1998 Insp Repts 50-254/97-24 & 50-265/97-24 on 971124-1202.No Violations Noted.Major Areas Inspected:Licensed RO & SRO Requalification Training Programs ML20197F5741997-12-23023 December 1997 Insp Repts 50-254/97-27 & 50-265/97-27 on 971103-07 & 1204. Violations Noted.Major Areas Inspected:Maint & Engineering IR 05000254/19970141997-12-16016 December 1997 Insp Repts 50-254/97-14 & 50-265/97-14 on 970729-0922.NOV & Deviations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support Re Troubleshooting Resulting in Discovery of Long Standing Problem W/Fire Pump IR 05000254/19970251997-12-0909 December 1997 Insp Repts 50-254/97-25 & 50-265/97-25 on 971103-07.No Violations Noted.Major Areas Inspected:Respiratory Protection Plan,Source Term Reduction Efforts & Follow Up on Several Open Items IR 05000254/19970211997-12-0909 December 1997 Insp Repts 50-254/97-21 & 50-265/97-21 on 970923-1103.No Violations Noted.Major Areas Inspected:Operation,Maint, Engineering & Plant Support IR 05000254/19970191997-11-18018 November 1997 Insp Repts 50-254/97-19 & 50-265/97-19 on 971006-10.No Violations Noted.Major Areas Inspected:Ep Program IR 05000254/19970181997-11-10010 November 1997 Insp Repts 50-254/97-18 & 50-265/97-18 on 970922-25. Violations Noted.Major Areas Inspected:Maintenance & Engineering IR 05000254/19970161997-11-0505 November 1997 Insp Repts 50-254/97-16 & 50-265/97-16 on 970825-29. Violations Noted.Major Areas Inspected:Fire Protection Program & Several App R Issues IR 05000254/19970201997-10-25025 October 1997 Insp Repts 50-254/97-20 & 50-265/97-20 on 970929-1002.No Violations Noted.Major Areas Inspected:Quality of Security Related Audits,Reviewed Effectiveness of Mgt Controls & Verified Performance of Protected Area Control Activities IR 05000254/19970151997-09-0303 September 1997 Insp Repts 50-254/97-15 & 50-265/97-15 on 970811-14.No Violations Noted.Major Areas Inspected:Station Chemistry & REMP IR 05000254/19970121997-07-31031 July 1997 Insp Repts 50-254/97-12 & 50-265/97-12 on 970707-16.No Violations Noted.Major Areas Inspected:Review of Plant Support Activities Re Physical Protection of Facility & Corrective Actions to Security Issues IR 05000254/19970081997-07-11011 July 1997 Insp Repts 50-254/97-08 & 50-265/97-08 on 970506-0616. Violations Noted.Major Areas Inspected:Operations,Maint & Surveillance,Engineering & Plant Support 1999-09-15
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000254/20244012024-12-20020 December 2024 Security Baseline Inspection Report 05000254/2024401 and 05000265/2024401 IR 05000254/20240112024-11-13013 November 2024 Biennial Problem Identification and Resolution Inspection Report 05000254/2024011 and 05000265/2024011 IR 05000254/20240032024-11-12012 November 2024 Integrated Inspection Report 05000254/2024003, 05000265/2024003 and 07200053/2024001 IR 05000254/20240102024-10-28028 October 2024 Age Related Degradation Inspection Report 05000254/2024010 and 05000265/2024010 and Notice of Violation IR 05000254/20244022024-09-12012 September 2024 Material Control and Accounting Program Inspection Report 05000254/2024402 and 05000265/2024402 (Public) IR 05000254/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Quad Cities Nuclear Power Station (Report 05000254/2024005; 05000265/2024005) IR 05000254/20240022024-08-12012 August 2024 Integrated Inspection Report 05000254/2024002 and 05000265/2024002 IR 05000254/20243012024-08-0101 August 2024 NRC Initial License Examination Report 05000254/2024301; 05000265/2024301 IR 05000254/20240012024-05-14014 May 2024 Integrated Inspection Report Nos. 05000254/2024001 and 05000265/2024001 IR 05000254/20245012024-04-0505 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000254/2024501 and 05000265/2024501 IR 05000254/20230062024-02-28028 February 2024 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2023006 and 05000265/2023006) IR 05000254/20230042024-02-0505 February 2024 Integrated Inspection Report 05000254/2023004 and 05000265/2023004 IR 05000254/20234032023-12-22022 December 2023 Public- Quad Cities Nuclear Power Station Security Baseline Inspection Report 05000254/2023403 and 05000265/2023403 IR 05000254/20230102023-12-20020 December 2023 Comprehensive Engineering Team Inspection Report 05000254/2023010 and 05000265/2023010 IR 05000254/20230032023-11-0909 November 2023 Integrated Inspection Report 05000254/2023003 and 05000265/2023003 IR 05000254/20230112023-09-20020 September 2023 Safety-Conscious Work Environment Issue of Concern Team Inspection Report 05000254/2023011 and 05000265/2023011 IR 05000254/20230052023-08-25025 August 2023 Updated Inspection Plan and Assessment Follow-Up Letter for Quad Cities Nuclear Power Station (Report 05000254/2023005; 05000265/2023005) IR 05000254/20230022023-08-0808 August 2023 Integrated Inspection Report 05000254/2023002 and 05000265/2023002 IR 05000254/20234012023-06-26026 June 2023 Cyber Security Inspection Report 05000254/2023401 and 05000265/2023401 IR 05000265/20230402023-06-22022 June 2023 Reissue Quad Cities Nuclear Power Station 95001 Supplemental Inspection Supplemental Report 05000265/2023040 and Follow Up Assessment Letter ML23167B1722023-06-16016 June 2023 95001 Supplemental Inspection Report 05000265/2023040 and Follow-Up Assessment Letter IR 05000254/20234022023-05-15015 May 2023 Security Baseline and ISFSI Inspection Reports 05000254/2023402, 05000265/2023402, 07200053/2023401 IR 05000254/20230012023-05-0808 May 2023 Integrated Report 05000254/2023001 and 05000265/2023001 ML23065A2832023-03-0707 March 2023 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000254/2023010 and 05000265/2023010 IR 05000254/20233012023-03-0707 March 2023 NRC Initial License Examination Report 05000254/2023301; 05000265/2023301 IR 05000254/20220062023-03-0101 March 2023 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2022006 and 05000265/2022006) IR 05000254/20220042023-02-10010 February 2023 Integrated Inspection Report 05000254/2022004 and 05000265/2022004 IR 05000254/20220112023-01-0606 January 2023 Triennial Fire Protection Inspection Report 05000254/2022011 and 05000265/2022011 IR 05000254/20220102022-12-13013 December 2022 Phase 4 Post-Approval License Renewal Inspection Report 05000254/2022010 and 05000265/2022010 ML22313A1502022-11-29029 November 2022 EA-22-062 QC ERV Final Action IR 05000254/20224012022-11-22022 November 2022 Security Baseline Inspection Report 05000254/2022401 and 05000265/2022401 IR 05000254/20220132022-11-17017 November 2022 Biennial Problem Identification and Resolution Inspection Report 05000254/2022013 and 05000265/2022013 IR 05000254/20220032022-11-0303 November 2022 Integrated Inspection Report 05000254/2022003 and 05000265/2022003 IR 05000254/20220052022-08-22022 August 2022 Updated Inspection Plan for Quad Cities Nuclear Power Station (Report 05000254/2022005; 05000265/2022005) IR 05000254/20225012022-08-15015 August 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000254/2022501 and 05000265/2022501 IR 05000254/20220022022-08-0909 August 2022 Integrated Inspection Report 05000254/2022002 and 05000265/2022002 IR 05000254/20220902022-08-0808 August 2022 NRC Inspection Report 05000254/2022090 and 05000265/2022090; Preliminary White Finding IR 05000254/20220122022-07-11011 July 2022 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000254/2022012 and 05000265/2022012 IR 05000254/20220012022-05-11011 May 2022 Integrated Inspection Report 05000254/2022001 and 05000265/2022001 IR 05000254/20210062022-03-0202 March 2022 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2021006 and 05000265/2021006) IR 05000254/20210042022-02-0202 February 2022 Integrated Inspection Report 05000254/2021004 and 05000265/2021004 ML22033A1672022-02-0202 February 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000265/2022001 IR 05000254/20214022021-12-0101 December 2021 Security Baseline Inspection Report 05000254/2021402 and 05000265/2021402 IR 05000254/20210102021-11-24024 November 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000254/2021010 and 05000265/2021010 IR 05000254/20210032021-10-28028 October 2021 Integrated Inspection Report 05000254/2021003 and 05000265/2021003 IR 05000254/20214012021-09-0909 September 2021 Security Baseline Inspection Report 05000254/2021401 and 05000265/2021401 IR 05000254/20210052021-09-0101 September 2021 Updated Inspection Plan for Quad Cities Nuclear Power Station (Report 05000254/2021005 and 05000265/2021005) ML21238A3142021-08-26026 August 2021 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000254/2021004; 05000265/2021004 IR 05000254/20213012021-08-23023 August 2021 NRC Initial License Examination Report 05000254/2021301; 05000265/2021301 IR 05000254/20210022021-08-0909 August 2021 Integrated Inspection Report 05000254/2021002 and 05000265/2021002 2024-09-12
[Table view] Category:UTILITY
MONTHYEARIR 05000254/19900141990-10-0404 October 1990 Insp Repts 50-254/90-14 & 50-265/90-14 on 900805-0915. Violations Noted.Major Areas Inspected:Ler Review,Regional Request,Followup on TMI Action Items,Operational Safety Verification,Esf Sys & Monthly Maint Observations IR 05000254/19900121990-08-22022 August 1990 Safety Insp Repts 50-254/90-12 & 50-265/90-12 on 900617- 0804.No Violations Noted.Two Unresolved Items Noted.Major Areas Inspected:Licensee Action on Previously Identified Items,Ler Review,Regional Requests & Testing of Mods IR 05000254/19900101990-08-14014 August 1990 Insp Repts 50-254/90-10 & 50-265/90-10 on 900605-0802. Violations Noted.Major Areas Inspected:Allegation That 1/2 Emergency Diesel Generator Cooling Pump Could Not Fulfill Cooling of Diesel & ECCS Room Coolers IR 05000254/19900111990-07-13013 July 1990 Insp Repts 50-254/90-11 & 50-265/90-11 on 900611-14.No Violations or Deviations Noted.Major Areas Inspected: Licensee Radwaste Mgt Program,Including Solid,Liquid & Gaseous Wastes & Audits & Assessments IR 05000254/19900081990-07-11011 July 1990 Insp Repts 50-254/90-08 & 50-265/90-08 on 900429-0616.No Violations Noted.Major Areas Inspected:Licensee Action on Previously Identified Items,Ler Review,Operational Safety Verification & Monthly Maint Observation IR 05000254/19890241990-06-15015 June 1990 Insp Repts 50-254/89-24 & 50-265/89-24 on 891030-900518. Violations Noted.Major Areas Inspected:Local Leak Rate Test Program,Containment Integrated Leak Rate Test Procedure & Review of Licensee Actions on Previous Insp Findings IR 05000254/19900061990-05-15015 May 1990 Insp Repts 50-254/90-06 & 50-265/90-06 on 900318-0428. Violations Noted.Major Areas Inspected:Plant Operations,Esf Sys,Radiological Controls,Maint & Surveillance,Emergency Preparedness,Security & Engineering/Technical Support IR 05000237/19900141990-04-20020 April 1990 Insp Repts 50-456/90-11,50-457/90-14,50-454/90-13, 50-455/90-12,50-237/90-14,50-249/90-13,50-373/90-07, 50-374/90-08,50-254/90-07,50-265/90-07,50-295/90-10 & 50-304/90-11 on 900220-0404.No Violations Noted IR 05000254/19900051990-04-10010 April 1990 Insp Repts 50-254/90-05 & 50-265/90-04 on 900326-30.No Violations Noted.Weaknesses Re Testing of New Whole Body Counter Noted.Major Areas Inspected:Operational Radiation Protection Program,Including External Exposure Controls IR 05000254/19900021990-04-0404 April 1990 Safety Insp Repts 50-254/90-02 & 50-265/90-02 on 900128- 0317.Violation Noted.Major Areas Inspected:Licensee Actions on Previous Items,Plant Operations,Radiological Controls, Maint/Surveillance,Emergency Preparedness & Security IR 05000265/19900051990-03-30030 March 1990 Safety Insp Rept 50-265/90-05 on 900220-0322.No Violations or Deviations Noted.Major Areas Inspected:Inservice Insp Activities,Including Review of Program,Procedures,Work Activities & Insp Data IR 05000254/19900041990-03-23023 March 1990 Insp Repts 50-254/90-04 & 50-265/90-03 on 900312-16.No Violation Noted.Major Areas Inspected:Mgt Support,Security Program Plans & Audits,Protected & Vital Area Physical Barriers & Detection & Assessment Aids IR 05000254/19890281990-02-13013 February 1990 Safety Insp Repts 50-254/89-28 & 50-265/89-28 on 891217-900127.No Violations Noted.Major Areas Inspected: Licensee Actions on Previous Items,Plant Operations, Radiological Controls,Maint Surveillance & Security IR 05000254/19890251990-01-0909 January 1990 Insp Repts 50-254/89-25 & 50-265/89-25 on 891030-1214. Violations Noted.Major Areas Inspected:Mods & Design Changes Implemented During Unit 1 Outage & Recent Request from Temporary Waiver of Compliance from Tech Specs IR 05000254/19890261990-01-0505 January 1990 Safety Insp Repts 50-254/89-26 & 50-265/89-26 on 891105- 1216.Violations Noted.Major Areas Inspected:Plant Operations,Radiological Controls,Allegations,Emergency Preparedness,Security & Engineering/Technical Support IR 05000254/19890271990-01-0505 January 1990 Insp Rept 50-254/89-27 on 891215.No Violations Noted.Major Areas Inspected:Review of Adequacy of Licensee Analysis of Reactor Feedwater Transient on Min Critical Power Ratio Safety Limit & Determination of Cause of Turbine Trip IR 05000254/19890221989-11-30030 November 1989 Insp Repts 50-254/89-22 & 50-265/89-22 on 890924-1104. Violations Noted.Major Areas Inspected:Plant Operations, Radiological Controls,Maint/Surveillance,Emergency Preparedness,Security & Engineering/Technical Support IR 05000254/19890171989-11-28028 November 1989 Insp Repts 50-254/89-17 & 50-265/89-17 on 890918-22,1002-06 & 18.Violations Noted.Major Areas Inspected:Maint,Support of Maint & Related Mgt Activities IR 05000254/19890231989-11-22022 November 1989 Insp Repts 50-254/89-23 & 50-265/89-23 on 891016-20 & 1115. Violations Noted.Major Areas Inspected:Implementation of Licensee Fire Protection Program,Including Followup of Licensee Actions on Previous Insp Findings IR 05000254/19890211989-11-16016 November 1989 Safety Insp Repts 50-254/89-21 & 50-265/89-21 on 890926, 1002-04 & 12-13 & 1102.No Violations or Deviations Noted. Major Areas Inspected:Inservice Insp Activities,Including Review of Programs,Procedures & Work Activities IR 05000254/19890201989-10-0606 October 1989 Insp Repts 50-254/89-20 & 50-265/89-20 on 890820-0923. Violations Noted.Major Areas Inspected:Licensee Actions on Previous Items,Plant Operations,Radiological Controls, Emergency Preparedness,Security & Maint/Surveillance IR 05000254/19890161989-08-28028 August 1989 Insp Repts 50-254/89-16 & 50-265/89-16 on 890625-0819. Violations Noted.Major Areas Inspected:Plant Operations, Radiological Controls,Maint/Surveillance,Safety Assessment/ Quality Verification,Emergency Preparedness & Security IR 05000254/19890181989-08-24024 August 1989 Physical Security Insp Repts 50-254/89-18 & 50-265/89-18 on 890814-18.No Violations Noted.Major Areas Inspected:Mgt Support,Security Program Plans,Audits,Protected & Vital Area Physical Barriers & Detection & Assessment Aids IR 05000237/19880201989-08-0404 August 1989 Insp Repts 50-237/88-20,50-254/88-22,50-295/88-17, 50-373/88-23,50-454/88-15,50-456/88-24,50-457/88-24, 50-455/88-14,50-249/88-21,50-374/88-22,50-265/88-22 & 50-304/88-17 on 880816-890802.No Violations Noted IR 05000254/19890121989-07-17017 July 1989 Insp Repts 50-254/89-12 & 50-265/89-12 on 890514-0624.One licensee-identified Violation & Two Unresolved Items Noted. Major Areas Inspected:Licensee Actions on Previous Items, Plant Operations,Emergency Preparedness & Security ML20246C3471989-06-29029 June 1989 Safety Insp Repts 50-254/89-13 & 50-265/89-13 on 890522-0608.No Violations,Deviations or Open Items Noted. Major Areas Inspected:Maint & Inservice Testing of Pumps & Valves,Including Actions in Response to NRC Bulletin 85-003 IR 05000254/19890151989-06-28028 June 1989 Insp Repts 50-254/89-15 & 50-265/89-15 on 890619-21.No Violations Noted.Major Areas Inspected:Radwaste Mgt Program, Including Solid,Liquid & Gaseous Radwastes,Audits & Assessments & Unplanned Liquid Radwaste Release IR 05000254/19890141989-06-27027 June 1989 Insp Repts 50-254/89-14 & 50-265/89-14 on 890605-09.No Violations or Deviations Noted.Major Areas Inspected: Implementation of NRC Bulletin 88-010 Requirements Re molded-case Circuit Breakers IR 05000237/19880211989-06-0808 June 1989 Safety Insp Repts 50-237/88-21,50-249/88-22,50-254/88-23 & 50-265/88-23 on 890824-25,890124-25 & 890522-23.No Violations or Deviations Noted.Major Areas Inspected:Util Action & Previously Identified Noncompliances IR 05000254/19890101989-05-22022 May 1989 Insp Repts 50-254/89-10 & 50-265/89-10 on 890402-0513.No Violations Noted.Major Areas Inspected:Plant Operations, Radiological Controls,Maint/Surveillance,Emergency Preparedness,Security & Engineering/Technical Support IR 05000237/19890141989-05-10010 May 1989 Insp Repts 50-237/89-14,50-249/89-13,50-254/89-11, 50-265/89-11,50-295/89-14,50-304/89-14,50-373/89-11, 50-374/89-11,50-454/89-12,50-455/89-14,50-456/89-13 & 50-457/89-13 Re Emergency Preparedness Programs IR 05000254/19890071989-04-17017 April 1989 Insp Repts 50-254/89-07 & 50-265/89-07 on 890404-06.No Violations Noted.Major Areas Inspected:Annual Emergency Preparedness Exercise Involving Six NRC Representatives IR 05000254/19890041989-04-13013 April 1989 Insp Repts 50-254/89-04 & 50-265/89-04 on 890205-0401.No Violations Noted.Major Areas Inspected:Plant Operations, Radiological Controls,Maint/Surveillance,Emergency Preparedness & Security IR 05000254/19890061989-03-0707 March 1989 Insp Repts 50-254/89-06 & 50-265/89-06 on 890214-17.No Violations Noted.One Potential Contamination Control Weakness Noted.Major Areas Inspected:Radiation Protection Program,Including Organization & Mgt Controls & ALARA IR 05000254/19890051989-02-27027 February 1989 Insp Repts 50-254/89-05 & 50-265/89-05 on 890206-10.No Violations Noted.Major Areas Inspected:Chemistry Program, Including Procedures,Organization & Training & Radiological Environ Monitoring Program & Qc/Qa Program in Lab IR 05000254/19880201988-10-13013 October 1988 Insp Repts 50-254/88-20 & 50-265/88-20 on 880807-0930.No Violations or Deviations Noted.Major Areas Inspected: Operations,Maint,Surveillance,Ler Review,Routine Repts, Temporary Instructions,Radiation Control & Info Notices IR 05000254/19880211988-10-0505 October 1988 Insp Repts 50-254/88-21 & 50-265/88-21 on 880222-0901. Violations Noted.Major Areas Inspected:Compliance W/App R to 10CFR50 & Review of Fire Protection Program Requirements IR 05000254/19880191988-09-22022 September 1988 Insp Repts 50-254/88-19 & 50-265/88-19 on 880830-0902.No Violations Noted.Weakness & Four Open Items Identified.Major Areas Inspected:Annual Exercise IR 05000254/19880251988-09-20020 September 1988 Insp Repts 50-254/88-25 & 50-265/88-26 on 880908-14.No Violations Noted.Major Areas Inspected:Licensee Written Practice for Nondestructive Exam Pertaining to 25% Rule Described in SNT-TC-1A ML20154L7701988-09-14014 September 1988 Corrected Pages 13 & 14 to Insp Repts 50-254/88-15 & 50-265/88-15 ML20154L9461988-09-14014 September 1988 Insp Rept 50-265/88-24 on 880826.No Violations Noted. Major Areas Inspected:Weakness Identified in Verification of Component Operability as Documented in Insp Repts 50-254/88-15 & 50-265/88-15 IR 05000254/19882001988-09-0707 September 1988 Emergency Operating Procedures Insp Rept 50-254/88-200 on 880613-30.Inadequacies & Deficiencies Noted.Major Areas Inspected:Determination If Procedures Technically Correct & Whether Procedures Could Be Carried Out & Performed IR 05000254/19880151988-08-23023 August 1988 Insp Repts 50-254/88-15 & 50-265/88-15 on 880605-0806.No Violations Noted.Major Areas Inspected:Resident Insp of Operations,Maint,Surveillance,Ler Review,Routine Repts, Temporary Instructions & Radiation Control IR 05000254/19880181988-07-29029 July 1988 Partially Withheld Physical Security Insp Repts 50-254/88-18 & 50-265/88-18 on 880718-21 (Ref 10CFR73.21).Noncompliances Noted.Major Areas Inspected:Security Plan & Implementing Procedures & Mgt Effectiveness IR 05000254/19880171988-07-14014 July 1988 Insp Repts 50-254/88-17 & 50-265/88-17 on 880706-07.No Violations Noted.Major Areas Inspected:Emergency Preparedness Program Areas,Including Actions on Previously Identified Items & Initiatives to Improve Program IR 05000254/19880161988-07-0101 July 1988 Insp Repts 50-254/88-16 & 50-265/88-16 on 880607-15. Violations Noted.Major Areas Inspected:Containment Integrated Leak Rate Test Procedure,Performance & Results, Local Leak Rate Test Results & LER Followup IR 05000254/19880121988-06-28028 June 1988 Insp Repts 50-254/88-12 & 50-265/88-06 on 880310-0411-12,18, 21,26-29 & 05-10,17-18 & 0601 & 20.No Violations Noted.Major Areas Inspected:Inservice Insp Activities,Including Review of Programs 73051,Procedures 73052 & Observation of Work IR 05000237/19880141988-06-28028 June 1988 Insp Repts 50-237/88-14,50-249/88-15,50-254/88-14 & 50-265/88-14 on 880525-0616.No Violations or Deviations Noted.Major Areas Inspected:Action on Previously Identified Noncompliances & LERs IR 05000254/19880111988-06-21021 June 1988 Insp Repts 50-254/88-11 & 50-265/88-12 on 880422-0601. Violations Noted.Major Areas Inspected:Maint Activities & Followup on Previous Identified Insp Items Using Selected Portions of Listed Insp Modules IR 05000254/19880131988-06-15015 June 1988 Insp Repts 50-254/88-13 & 50-265/88-13 on 880510-20. Violation Noted.Major Areas Inspected:Radwaste Mgt & Radiation Protection Programs During Refueling & Maint Outage Including Organization & Mgt Controls 1990-08-22
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000254/19990171999-09-15015 September 1999 Insp Repts 50-254/99-17 & 50-265/99-17 on 990823-27.No Violations Noted.Major Areas Inspected:Pilot Baseline Insp for Annual Review of Changes to Safety Analysis Rept & Biennial Review Permanent Plant Mod IR 05000254/19990151999-08-25025 August 1999 Insp Repts 50-254/99-15 & 50-265/99-15 on 990816-20.No Violations Noted.Major Areas Inspected:Maint Rule Implementation IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site IR 05000254/19990161999-08-19019 August 1999 Insp Repts 50-254/99-16 & 50-265/99-16 on 990719-22. Violations Noted.Major Areas Inspected:Physical Protection Cornerstone,Including Review of Access Authoization Program & Changes to Security Plan IR 05000254/19990121999-08-13013 August 1999 Insp Repts 50-254/99-12 & 50-265/99-12 on 990628-0716. Violations Noted.Major Areas Inspected:Corrective Action Process Which Included Methods Used for Identification, Cause Investigation & Correction of Quality Related Items IR 05000254/19990111999-08-13013 August 1999 Insp Repts 50-254/99-11 & 50-265/99-11 on 990601-0720.NCVs Noted.Major Areas Inspected:Performance in Initiating Events,Mitigating Sys,Barrier Integrity Cornerstones & Performance Indicator Verification IR 05000254/19990141999-07-30030 July 1999 Insp Repts 50-254/99-14 & 50-265/99-14 on 990713-15.One Violation Noted & Treated as Ncv.Major Areas Inspected: Heat Sink Performance,Which Covers Inspectable Area Under Initiating Events & Mitigation Sys IR 05000254/19990131999-07-29029 July 1999 Insp Repts 50-254/99-13 & 50-265/99-13 on 990628-0702.No Violations Noted.Major Areas Inspected:Public Radiation Safety & Review of Gaseous & Liquid Radiological Effluents & of Radiological Environmental Monitoring Program IR 05000254/19990091999-06-23023 June 1999 Insp Repts 50-254/99-09 & 50-265/99-09 on 990421-0531.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000254/19990061999-05-14014 May 1999 Insp Repts 50-254/99-06 & 50-265/99-06 on 990307-0420.Three Violations Noted & Being Treated as non-cited Violations. Major Areas Insptected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000254/19990081999-05-11011 May 1999 Insp Repts 50-254/99-08 & 50-265/99-08 on 990419-23.No Violations Noted.Major Areas Inspected:Adequacy of Licensee Programs,Procedures,Training & Supporting Documentation IR 05000254/19990031999-04-0909 April 1999 Insp Repts 50-254/99-03 & 50-265/99-03 on 990308-12.No Violations Noted.Major Areas Inspected:Maint & Engineering IR 05000254/19990011999-04-0101 April 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990121-0306. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19990071999-03-31031 March 1999 Radiation Protection Insp Repts 50-254/99-07 & 50-265/99-07 on 990309-12.No Violations Noted.Major Areas Inspected:Solid Radwaste Processing & Control Program & Radioactive Matls Shipping Program ML20207G1771999-03-0505 March 1999 Notice of Violation from Insp on 99112-1218.Violation Noted:Licensee Had Not Included in Revised ISI Program,Basis for Determination That Code Required Exam Was Impractical For,Unit 2 Reactor Pressure Vessel Nozzle Weld Nsb IR 05000254/19980211999-03-0505 March 1999 Insp Repts 50-254/98-21 & 50-265/98-21 on 981112-1218. Violation Noted:Major Areas Inspected:Isi Activities at Plant During Refueling Outage 15 IR 05000254/19990041999-02-26026 February 1999 Insp Repts 50-254/99-04 & 50-265/99-04 on 990201-05.No Violations Noted.Major Areas Inspected:Emergency Prepardeness Program as Aspect of Plant Support IR 05000254/19990021999-02-25025 February 1999 Insp Repts 50-254/99-02 & 50-265/99-02 on 990125-29.No Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Program Included Water Chemistry Control, Instrument Quality Control & internal-lab Comparison IR 05000254/19980241999-01-14014 January 1999 Partially Withheld Security Insp Repts 50-254/98-24 & 50-265/98-24.Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Quad Cities Facility.Details Withheld (Ref 10CFR2.790) IR 05000254/19980201998-12-28028 December 1998 Insp Repts 50-254/98-20 & 50-265/98-20 on 981014-1201.No Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000254/19980221998-12-28028 December 1998 Insp Repts 50-254/98-22 & 50-265/98-22 on 981130-1204.No Violations Noted.Major Areas Inspected:Radiation Protection Staff Preparation for Q1R15 Refueling Outage,Including Review of ALARA Planning & Work Plan Integration ML20198G2901998-12-18018 December 1998 Notice of Violations from Insp on 981019-1106.Violations Noted:As of 980327,performance of Listed Test Procedures Did Not Demonstrate Equipment Could Perform Satisfactorily Under Design Conditions IR 05000254/19980191998-12-18018 December 1998 Insp Repts 50-254/98-19 & 50-265/98-19 on 981019-1106. Violations Noted.Major Areas Inspected:Effectiveness of Engineering & Technical Support Provided to Plant in Performance of Routine & Reactive Site Activities IR 05000254/19980171998-11-0505 November 1998 Insp Repts 50-254/98-17 & 50-265/98-17 on 980902-1014.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19980181998-10-15015 October 1998 Partially Withheld Insp Repts 50-254/98-18 & 50-265/98-18 on 980914-18 (Ref 10CFR73.71).No Violations Identified.Major Areas Inspected:Review of Plant Support Activities,Security Activities Re Onsite Personnel Access & Communications IR 05000254/19980131998-09-22022 September 1998 Insp Repts 50-254/98-13 & 50-265/98-13 on 980716-0901.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980141998-09-17017 September 1998 Insp Repts 50-254/98-14 & 50-265/98-14 on 980825-28.No Violations Noted.Major Areas Inspected:Evaluation of Licensee Performance During Plant Biennial Exercise of Emergency Plan ML20154G4301998-09-11011 September 1998 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $88,000.Violation Noted:As of 970926,licensee Failed to Provide Alternate Shutdown Capability for Some Fire Areas of Facility Containing Safe Shutdown Equipment ML20195D1951998-09-0808 September 1998 EN-98-057B:on 980911,notice of Proposed Imposition of Civil Penalty in Amount of $88,000 Issued to Licensee.Action Based on One Severity Level II Problem Involving Very Significant Inadequacies in Comm Ed Capability to Shut Down IR 05000254/19980161998-09-0404 September 1998 Insp Repts 50-254/98-16 & 50-265/98-16 on 980810-14.No Violations Noted.Major Areas Inspected:Radiation Protection Program Included External & Internal Exposure Control,Whole Body Counting & Contamination & Survey Monitoring Program ML20195D2341998-08-11011 August 1998 EN-98-057:on 980814,notice of Proposed Imposition of Civil Penalty in Amount of $143,000 Issued to Licensee.Action Based on One Severity Level II Problem & One Severity Level III Violation ML20237D6671998-08-11011 August 1998 Notice of Violation from Insp on 980529-0716.Violation Noted:On 980622,while Performing Quad Cities Operating Surveillance Procedure 6600-01,rev 24,operator Failed to Position Throttle Air Box Drain Valve One Turn IR 05000254/19980151998-07-31031 July 1998 Insp Repts 50-254/98-15 & 50-265/98-15 on 980721-24.No Violations Noted.Major Areas Inspected:Aspects of Licensee Corrective Actions & Engineering Involvement in Corrective Actions Process ML20236M0831998-07-0202 July 1998 Notice of Violation from Insp on 980401-0529.Violation Noted:On 980501,Interim Procedure 98-0035 Was Not Implemented When Change Was Made to Personnel Out-of Svc Number 98-512 Which Was Not Reviewed & Approved IR 05000254/19980111998-07-0202 July 1998 Insp Repts 50-254/98-11 & 50-265/98-11 on 980504-22. Violations Noted.Major Areas Inspected:Quad Cities Safe Shutdown Analysis & Supporting Procedures ML20237E7051998-06-0505 June 1998 EN-98-043:informs Commission That Staff Intends to Exercise Enforcement Discretion Per Section VI.B.6 of Enforcement Policy & Not Issue NOV to Util for Failure to Provide Complete & Accurate Info to NRC ML20248L7951998-06-0505 June 1998 Notice of Violation from Investigation on 970530.Violations Noted:Licensee Provided to Commission on 960825,operability Determination Checklist.Info Inaccurate Because Supporting Calculations Showed FICs to Be Excess of 1.0 ML20247P4551998-05-15015 May 1998 Notice of Violation from Insp on 971014-980415.Violation Noted:On 971215,inspector Identified That Licensee Failed to Provide Training of Personnel Performing Activities Affecting Quality IR 05000254/19980081998-05-11011 May 1998 Insp Repts 50-254/98-08 & 50-265/98-08 on 980407-09 & 14-17. No Violations Noted.Major Areas Inspected:Maint,Quality Assurance & Engineering IR 05000254/19982011998-05-0606 May 1998 Insp Repts 50-254/98-201 & 50-265/98-201 on 980216-0327.No Violations Noted.Major Areas Inspected:Evaluation of Capability of Selected Sys to Perform Safety Functions Required by Design Bases IR 05000254/19980101998-05-0606 May 1998 Insp Repts 50-254/98-10 & 50-265/98-10 on 980413-17.No Violations Noted.Major Areas Inspected:Liquid & Gaseous Effluent Programs,Annual Effluent Rept,Continuous Air & Area Radiation Monitors IR 05000254/19980051998-04-23023 April 1998 Insp Repts 50-254/98-05 & 50-265/98-05 on 980216-0326. Violations Noted.Major Areas Inspected:Engineering,Including Allowances for Development of Emergency & Immediate Mods ML20217G3401998-04-23023 April 1998 Insp Repts 50-254/98-04 & 50-265/98-04 on 980211-0331. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support ML20217G2341998-04-23023 April 1998 Notice of Violation from Insp on 980216-0326.Violation Noted:Between 971006 & 10,work Package 970104149-03 Replaced 2A Recirculation Loop Sample Pci Valve AO-2-0220-44,activity Affecting Quality,Prepared & Installed Prior to 971014 ML20217G3101998-04-23023 April 1998 Notice of Violations from Insp on 980211-0331.Violations Noted:On 980314,non-licensed Operators Performing Plant Operating Procedure 6600-7,rev 6,attachment H,Failed to Charge Breaker Closing Spring for Unit 2 IR 05000254/19980071998-04-22022 April 1998 Insp Repts 50-254/98-07 & 50-265/98-07 on 980330-0403.No Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Plant,Adequacy of Security Procedures & Event Logs IR 05000254/19983031998-04-13013 April 1998 Exam Repts 50-254/98-303OL & 50-265/98-303OL on 980316-20. Exam Results:All Three Applicants Passed All Portions of Respective Exams ML20217D9661998-03-0909 March 1998 EN-98-010:informs That NOV & Proposed Imposition of Civil Penalty in Amount of $330,000 Will Be Issued on or About 980312 to Comm Ed.Action Based on Two Severity Level III Problems Consisting of Violations ML20216C2531998-03-0606 March 1998 Notice of Violation from Insp on 971224-980210.Violation Noted:From 971216-20,both Standby Gas Treatment Subsystems Inoperable & Unit 1 Remained in Mode 1 & Not Placed in Hot Shutdown Condition within 12 H ML20216C2601998-03-0606 March 1998 Insp Repts 50-254/97-28 & 50-265/97-28 on 971224-980210. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering 1999-09-15
[Table view] |
Text
7, q a
,q
+
s.
> >
,p pE
N n
,, %
b'
3
.-
.
\\ '4 s
->
_*
?
-
s+
s
~
.
is
'
) f &,
4-
- ~g
.
s
%
\\f }
f:.
'
'
s y
jU. S. NUCLEAR REGULATORY COMMISSION
,
+
x
.,
'
'
(,,
!
,
,
REGION III
q g
[g}
y
,
.
t
)
'
Report No. 50-254/6;-18(DPRP);'50-265/82-20(DPRP)
, f
-
-
,
t e.
.
$
s, 4 J
Docket No. 50-254; 50-265 License No. DPR-29; b?R-30
'
',
.
'
Licensee: Commedwea'th Edison Company
..
Post pffice Box 767
.
Chicago,IL 60690
,
.g
.
Facility Name: Qdad-CitiesNuclearPowerS:iation, Units {&2,
,1
.
':
,
,
.
,y
%
+
Inspection At: Qu'ad-Cities Site, Cordova,'IL s
ftt Li I
i
'
Inspection Conducted: September 8,1982, through October 22,3982 S
,
i f
SS.54.0lzm /n D(
l O's Inspectors:
N. J. Chrissotimos x.
ll I9-@ A l'
'
h, {lf1hhNf t:
S. G. DuPont
//di-C.A,
'
)
.
f$, tff,g 3,.
,j
,
.
Approved By:
R. D. Walker, Chief
//- /7-@
',
'
Reactor Projects Section 2C
,
h t
.
e t,,
.
i ',
i.
4 s,
'
,
f/,. \\ *N \\
'
'
'Q Inspection Summary
'
s.
i
'
x
,
g Inspection on September 8, 1982, thro _u.ght Octoher 22, 1982 (Report Nos.
/ 1A
? I
'
50-254/82-18(DPRP); 50-265/82-20(DPRP)
%
LicenseeActionso.n[ Previous *InlspectionFindings; Inspdc\\tiEn,~,
\\'{
I Areas Inspected:
During Longterm Shutdown; Maincenance 'syefueling; Surveillance - Refueling; Refueling Activities; Training; T,echnt. cal Assistance to the Office r>f Nucle tr
s Reactor Regulation; Followup on,significant Event; High Density Fue) Racks;
'
Significant Event During Fuehithndlird,; Vessel Internal Inspectio n; Reactor Scram; Feedwater Sparger Modification; Licensee Event Reports Followud; Inspector Observation of Lu.'ensee's Corrective Actions; and Irdependent Inspection Effort. The inspectiod involved a total of 281 irdpector-hours
,
on site by two NRC inspectors' including 32 inspectce-hours ons.itf during
'
', 1 O
off-shifts.
-
Results: No items of noncomplianc,e were identified.
'
,
f
\\
s
-
>
.
,1
,
\\
/
}
.
,
..
,
'
- (
_i
%
l
-
i
,
s
.
8212030197 821119 M-
'.
<
PDR ADOCK 05000254
'
l}
,
O PDR
'
l c\\
,
,
,
,,
a
_
-m
,/
.
i
,
J DETAILS
.
s we
i' U 1.
Persons > Contacted
?
j -
- N. dalivianakis, Superintendent
.
T.#TAmlyn, Assistant Superintendent for Operations q.,y D. Bdx, Assistant Superintendent Maintenance L. Gerner, Assistant Superintendent for Administration
- J. H 11 man, Quality Assurance, Operations
- G. Tietz, Technical Staff Supervisor The inspector also interviewed several other licensee employees, including shift engineers and foremen, reactor operators, technical staff personnel and' quality control personnel.
>
- Denotes those present at the exit interview on October 22, 1982.
2.
Licea ee Action on Previous Inspection Findings
/
c (Closed) Noncompliance (50-254/82-08-01): Failure to Perform Required Tescing. Prior to Declaring System Operability. The inspector verified j
\\
that the actions described in the licensee's response letter of August 18,
'
1982 have been accomplished. The inspector has no further concerns.
i (Closed) Noncompliance (50-254/82-08-02): Failure to Take Immediate
' Actions Required by Technical Specifications. The inspector has reviewed the actions described in the licensee's reponse letter of August 18, 1982 and has no further concerns.
t j
?
,1/ *
(Closed) Noncompliance (50-254/82-08-03): Failure to Maintain Systems l*
Installed to Prevent or Mitigate the Consequences of Flooding the Con-
densate Pump Room. The inspector verified that the actions described
.'y, in the licensee's response letter dated August 18, 1982 have been accomp-
'
lished. The inspector has no further concerns.
3.
Inspection During Longterm Shutdown The inspector observed control room operations to verify the licenriee's
'
'
/ adherence to the Technical Specifications and approved procedures during the conths of September and October 1982. The inspector verified that p\\
the required surveillance tests were accomplished. The inspector also reviewed tagout records and ensured that the applicable containment integrity requirements were met.
Tours of accessible areas were con-ducted to make independent assessments of plant and equipment conditions in accordance with regulatory requirements. The inspector observed the implementation of radiation controls and plant housekeeping, including
,
'
control of potential fire hazards. The inspector also verified the implementation of the licensee's jumper / bypass system, physical security plan, and radioactive waste system controls.
%
>
No items of noncompliance or deviations were identified.
,
,
---
-
- -. - -
.
O 4.
Maintenance - Refueling The inspector verified maintenance procedures include administrative approvals for removing and returning systems to service, hold points for inspection / audit and signoff by Quality Assurance (QA) or other licensee personnel, provisions for operational testing following main-tenance, provisions for special authorization and fire watch respons-ibilities for activities involving welding, open flame, and other ignition sources, provisions for review of material certifications, provisions for assuring Limiting Condition for Operation (LCO) require-ments were met during repair, provisions for housekeeping during and following maintenance, and responsibilities for reporting defects to management.
The inspector observed the maintenance activities listed below and verified work was accomplished by qualified personnel in accordance with approved procedures.
Unit 1 WR 20874 1D RHR Service Water Pump Vent Line Repair (LER R0 82-21/03L)
WR 20960 1/2 A SBGT System Profilter Replacement WR 20967 CRD Scram Discharge Valve Maintenance WR 21181 1/2 Diesel Generator Fuel Filter Replacement WR 21240 1B RHR Heat Exchanger Bypass Valve Replacement WR 21258 1/2A SBGT Heater Thermostat Replacement WR 21615 HPCI Room Cooler Leak Repair WR 21632 Back-up Scram Solenoid Maintenance WR 21634 24vDC Battery Cell Testing WR 21638 Core Spray Check Valve Maintenance No items of noncompliance or deviations were identified.
5.
Surveillance - Refueling The inspector observed the station battery surveillance testing on Unit 1 to verify that the tests were covered by properly approved procedures, that the procedures used were consistent with regulatory requirements, licensee commitments, and administrative controls, that minimum crew requirements were met, test prerequisites were completed, special test equipment was calibrated and in service, and required data was recorded for final review and analysis, that the qualifications of personnel conducting the test were adequate, and that the test results were adequate.
No items of noncompliance or deviations were identified.
6.
Eefueling Activities The inspector verified that prior to handling fuel in the core, all surveillance testing required by Technical Specifications and the 11-censee's approved procedures had been completed including required
J
.
.
periodic testing on refueling related equipment. During the months of September and October, 1982, the inspector toured the Unit I reactor building to verify that containment integrity and good housekeeping practices were maintained in refueling areas. The inspector also verified thet the licensco's staffing during refac11ng operations was in accordance with Technical Specifications.
No items of noncompliance or deviations were identified.
7.
Training The inspector examined the licensee's overall training and retraining activities for non-licensed employees and general training for licensed employees to verify that the programs were in conformance with the Technical Specifications and Quality Assurance program requirements.
a.
Program Changes The licensee recently impicmented a computerized training status system. The system presently is limited to recall of an individual's total training record from 1982 forward. Training records prior to 1982 are being tracked manually and will not be incorporated into the system.
Following discussions with the inspector, the licensee will examine system capability for possible use as a scheduling tool for recurring training.
b.
Records The inspector reviewed the training records of ten non-licersed personnel from the mechanical, instrumentation, electrical, and administrative departments. All personnel folders reviewed con-tained records for employee background, on-site, and off-site training. Training courses appeared to be relevant to the job classifications of the personnel reviewed. The inspector also reviewed records of required repetitive training in the areas of annual radiation protection, security, and fire protection training to verify compliance with approved procedures.
The inspector reviewed records of several licensee and contractor female employees for training in prenatal radiation exposure. All licensee and contractor employees had signed acknowledgement sheets in their training record folders indicating annual training had been received by means of video tape, written information, and per-sonal response to questions pertaining to prenatal radiation exposure.
c.
Training Observation The inspector attended the general nuclear training course which covers radiation protection, security, fire fighting, QA, respira-tory protection, and basic nuc1 car science topics.
The course lasted for approximately 3.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />. A 20 question multiple choice exam was administered on completion and required a 70 per cent
J
.
.
passing score. Changes in the program over the past year were highlighted, and NUREG 8.13 information was discussed separately with the female attendee.
The inspector discussed similar presentations of other faci.'. ties with respect to possible modifications of the program. The in-structor discussed planned changes to the program with the inspector, which will include visual aids.
No items of noncompliance or deviations were identified.
8.
Technical Assistance to NRR On September 20, 1982, Messrs. Matthew Chiramal of the Office of Analysis and Evaluation of Operational Data (AEOD) and Roby Bevan of the Operating Reactors Branch, Office of Nuclear Reactor Regulation (NRR), visited the Quad-Cities site. Their purpose was to discuss and gather additional technical information concerning the circumstances surrounding the June 22, 1982 event.
(IE Report 254-82-10/265-82-11, paragraph 14)
9.
Followup on Significant Event On June 22, 1982, the licensee experienced a loss of offsite power event as a result of attempting to remove reserve auxiliary trans-former 22 (TR 22) from service for repair.
Following the event, the licensee committed to notify the NRC prior to removing TR 22 from service while the unit was operating. After many discussions, the Office of Nuclear Reactor Regulation determined that the licensee could perform the desired maintenance with the unit operating, provided that TR 12 (Unit 1 auxiliary transformer) and all three diesels were operable.
On the weekend of October 8, 1982, Unit 2 was shutdown for scheduled routine maintenance, (Unit I has been in refuel since September 6, 1982) and the licensee decided to perform maintenance on TR 22.
Power was supplied to essential equipment by operating both Unit 2 and shared diesel generators in conjunction with feeding TR 12 to Unit 2.
This electrical arrangement and maintenance on TR 22 was accomplished without any difficulties.
The licensee's conservative approach to performing this maintenance while the unit was down is indicative of good nuclear safety judgement.
No items of noncompliance or deviations were identified.
10.
High Density Fuel Racks During a tour, the inspector observed bubbles rising from the newly installed high density fuel storage racks located in the Unit 1 spent fuel pool.
l l
J
,
.
O The inspector questioned the licensee concerning the identification of the bubbles and the mechanism of generation. The licensee examined and identified the bubbles as mainly hydrogen, oxygen and some nitrogen.
Additional information was made available to the licensee in a report from Brand Industrial Service. It was determined that some generation of gas is a normally expected occurring byproduct of boraflex (boraflex is the material utilized for neutron absorbtion in high density fuel racks) in both an ionizing field as well as radiolytic decomposition of water. Brand Industrial Service had determined that the majority of gas generated by boraflex is nitrogen and oxygen while radiolytic decomposition of water forms hydrogen and oxygen. Further studies concluded that the gas generation rate would decrease approximately 50 per cent every few hours until after 100 hours0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br /> when the rate would be less than 0.09 per cent.
Additionally, the licensee installed a boraflex sample adjacent to a fuel bundle to gather further information on boraflex. The test revealed no degradation.
The licensee has developed a surveillance program for testing neutron attenuation, material hardness and other physical properties of boraflex for the expected lifetime of the high density fuel storage racks. The licensee is also continuing analysis of the bubbles.
No items of noncompliance or deviations were identified.
11.
Significant Event During Fuel Handling While attempting to lift a fuel assembly out of the core during normal refueling operations on September 16, 1982, it was found that the assembly had become attached to its fuel support piece and the two components could not be separated. The support piece is normally positioned by guide pins on the lower core plate and supports four assemblies.
The three other assemblies that rest on this piece had already been removed. Once out of the core, the licensee transferred both the assembly and the attached support piece to the Spent Fuel Pool via the refueling trolly grapple.
Because of the attached support, the assembly could not be removed to the pool through normal methods.
The inspector witnessed the transfer of the fuel assembly from the vessel to the fuel pool. The transfer was accomplished in accordance with an approved temporary procedure and all possible precautions were taken to prevent an accidental dropping of the assembly. The inspector also observed that additional radiological precautions were taken while using the trolly grapple, which is not the normal method of transfer.
.
The General Electric Company is currently evaluating methods on how to I
separate the support piece from the fuel assembly. An analysis of the failure mechanism will be performed to determine possible generic concerns.
i No items of noncompliance or deviations were identified.
t
,
)
-
.
.
12.
Vessel Internal Inspections The inspector witnessed the remote visual inspection of Unit I core spray spargers and jet pump beam bolts. The one mill wire calibration of the video camera was also witnessed. The inspections were conducted in accordance with approved procedures and requirements.
No items of ncacompliance or deviations were identified.
13.
Reactor Scrams Unit 2 On October 17, 1982, the unit scrammed from 90 per cent power due to high Average Power Range Monitor (APRM) limits. The cause was deter-mined to be the condensate demineralizer effluent regulating valves acting irregular in conjunction with a feedwater regulating valve drifting open. This caused a 100 per cent condensate demineralizer bypass valve to open and a standby condensate pump to automatically start. The excessive amount of cooler water now injecting into the reactor vessel caused the high APRM scram.
The licensee determined that the master controller for the effluent regulating valves was receiving incorrect signals from the local stations and proceeded to balance the system. The licensee has not been able to duplicate the problem experienced on the feeduater regulating valve and is still continuing to monitor its operation.
The inspector determined the status of the reactor and safety systems by discussions with licensee personnel and review of documentation.
i No items of noncompliance or deviations were identified.
14.
Feedwater Sparger Modification The licensee is replacing the interference-fit design feedwater spar ers with General Electric recommended triple-sleeve design spargers. The triple-sleeve design will substantially reduce bypass leakage flow.
Previous designs caused high differential metal temperatures which re-sulted in fatigue and crack initiation of the nozzles. This temperature differential occurred whenever feedwater heaters were not in use as during startups and shutdowns. The triple-sleeve design reduces bypass flow by utilizing two piston-ring seals, an interference fit and three I
concentric thermal sleeves.
During preparation for sparger work, three items were lost inside the vessel: a section of rope, a wrench, and a lens cover from a submersible light. The inspector verified that the items were listed in the tools lost log and that the licensee will recover or conduct a loose parts analysis of the items prior to startup. The inspector
!
has no further concerns in this area.
J No items of noncompliance or deviations were identified.
J
T
.
.
15.
Licensee Event Reports Followup
,
Through direct observations, discussions with licensee personnel, and review of records, the following event reports were reviewed to determine that reportability requirements were fulfilled, immediate corrective action was accomplished, and corrective action to prevent recurrence had been accomplished in accordance with technical specifications.
Unit 1 R0 82-12/01T, dated June 22, 1982, the 1/2 diesel generator tripped during a reactor scram. The circumstances concerning R0 82-12/01T are documented in Inspection Reports 50-254/82-10(DPRP) and 50-265/82-11 (DPRP), Paragraph 14.
R0 82-13/03L, dated June 21, 1982, the diesel generator cooling water pump became airbound during surveillance. Concerning R0 82-13/03L, the pump became airbound after the suction line of 'A' RHR service water loop was drained and refilled for installation of a modification on June 20, 1982.
The system was air loaded because the line was open for installation of new piping (LER R0 81-24, IE Reports 50-254/82-03(DPRP)
and 50-265/82-03(DPRP), Paragraph 7).
The general maintenance procedure did not have a precaution that specifically ensured the system would be completely vented. Ecwever, it is questionable that the precaution would have been effective because of the amount of air loading. The evolution was a unique, one-time modification to replace existing piping and the system was not designed to be airloaded in this manner. Thus, venting may not have prevented the airbounding of the pump. As corrective action, the licensee has added a precaution to the general maintenance procedure requiring venting. The actions taken by the licensee were adequate, and the inspector has no further concerns in this area.
R0 82-15/03L, dated June 28, 1982, the 1/2 A diesel fire pump was taken out of service for preventive maintenance. Concerning RO 82-15/03L, during overhaul of the fire pump, the 1/2 B diesel fire pump and a 3160 gpm portable diesel pump were available for fire protection as required.
R0 82-17/03L, dated July 13, 1982, while taking the inboard core spray injection valve (1-1402-25B) out of service for inspection, the valve failed to open. Concerning R0 82-17/03L, the failure was caused by water leaking through the valve packing gland. This damaged the rotor and brake of the valve operator motor which prevented the valve from opening. The valve was taken out of service in the open position and the 24B valve was positioned closed.
If an automatic core spray injec-tion was required, the logic would not be inhibited. Final corrective action is to replace the valve packing gland and repair the valve operator during the current refueling outage.
R0 82-23/03L, dated August 24, 1982, the 1A RHR service water pump removed from service for preventive maintenance on the RHR room cooler isolation valve.
3
.
.
R0 82-24/03L, dated August 26, 1982, the 1D RHR service water pump removed from service for preventive maintenance on the RHR room cooler isolation valve.
Concerning RO's 82-23/03L and 82-24/03L, the RHR service water pumps were taken out of service to perform minor preventive maintenance on the associated room cooler' isolation valve packings. Both pump outages were limited to within one day. The inspector has no further concerns.
RO 82-26/03L, dated September 6, 1982, the flange seal gasket failed the load leak rate. test (LLRT). Concerning R0 82-26/03L, the seal gasket will be replaced during the current refuel outage and a second LLRT will be performed following the repair.
RO 82-29/01T, dated September 16, 1982, cracks in the heat affected zone of the reactor water cleanup system piping discovered by ultrasonic testing. Concerning R0 82-29, the licensee will replace the reactor water cleanup piping with low carbon stainless pipe and fittings. The repair program committed to by the licensee requires the new pipe to be ASME SA-312, Grade TP 304 stainless with carbon content less than 0.035 per cent or TP 304L with the same physical properties of TP 304.
The completed program will be reviewed by a Regional specialist and documented in inspection reports 50-254/82-19 and 50-265/82-22(DPRP).
R0 82-30/03L, dated September 5, 1982, ID RHR service water pump packing failed during surveillance.
RO 82-31/03L, dated September 5, 1982, the RCIC system was taken out of service to perform a scheduled turbine overspeed surveillance.
R0 82-32/03L, dated September 5, 1982, the HPCI system was taken out of service to perform a scheduled turbine overspeed surveillance.
Unit 2 RO 82-11/01T, dated July 15, 1982, the LPCI inboard injection valve failed to open during surveillance.
R0 82-14/03L, dated August 2, 1982, RHR service water pump outboard gland and packing nut found off during operation. Concerning R0 82-14/03L, an equipment attendant, while performing his observation rounds, found the gland and packing nut off of the 2C RHR service water pump. The pump could have performed its intended function, but continued operation in this condition may have led to excessive gland and packing leakage.
The pump was repacked as preventive maintenance and returned to service on the same day. This occurrence is still under review by the licensee and a supplemental report will be submitted when the cause has been determined.
RO 82-15/03L, dated August 4, 1982, a small leak developed in the diesel generator flexible fuel line.
J
~
.
e R0 82-16/03L, dated July 29, 1982, the 2B RHR service water pump was removed from service to adjust the pump seal packing.
No items of noncompliance or deviations were identified.
16.
Inspector Observation of Licensee's Corrective Actions As a result of recurring problems with RHR service water pump packing leaks, the licensee has initiated a program to resolve the problem.
A modification being considered involves sealing the bearings. This would eliminate the need to tig*aten packings during installation _which has caused failures. Another action being considered involves installing mechanical seals to eliminate leakage through the packing. Both actions are currently being pursued to determine the optimum solution. The in-spector considers licensee actions to be appropriate.
No items of noncompliance or deviations were identified.
17.
Independent Inspection Effort While reviewing NUREG/CR-2000 (Licensee Event Report Compilation, August, 1982), the inspector noticed that a Licensee Event Report (LER 82-39) from Duane Arnold may be applicable to Quad-Cities.
The report described a diesel generator failing to start due to a rusty air start solenoid. The corrective action was to add solenoid inspections to the diesel annual inspection.
The inspector discussed the applicability of this event with the licensee. Although the licensee had not experienced any failures of this nature, they previously had some minor moisture problems and modified the piping to eliminate them. Additionally, the licensee will add the solenoid to its inspection program.
No items of noncompliance or deviations were identified.
18.
Exit Interview The inspector met with licensee representatives (denoted in Paragraph 1)
on October 22, 1981, and at the conclusion of the inspection and summar-ized the scope and findings of the inspection activities.
a