IR 05000254/2021001

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000254/2021001 and 05000265/2021001
ML21116A247
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 04/26/2021
From: Kenneth Riemer
NRC/RGN-III/DRP/B1
To: Rhoades D
Exelon Generation Co, Exelon Nuclear
References
IR 2021001
Download: ML21116A247 (19)


Text

April 26, 2021

SUBJECT:

QUAD CITIES NUCLEAR POWER STATION - INTEGRATED INSPECTION REPORT 05000254/2021001 AND 05000265/2021001

Dear Mr. Rhoades:

On March 31, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Quad Cities Nuclear Power Station. On April 13, 2021, the NRC inspectors discussed the results of this inspection with Mr. K. Ohr, Site Vice President, and other members of your staff.

The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Kenneth R. Riemer, Chief Branch 1 Division of Reactor Projects

Docket Nos. 05000254 and 05000265 License Nos. DPR-29 and DPR-30

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000254 and 05000265

License Numbers:

DPR-29 and DPR-30

Report Numbers:

05000254/2021001 and 05000265/2021001

Enterprise Identifier: I-2021-001-0049

Licensee:

Exelon Generation Company, LLC

Facility:

Quad Cities Nuclear Power Station

Location:

Cordova, IL

Inspection Dates:

January 01, 2021 to March 31, 2021

Inspectors:

J. Cassidy, Senior Health Physicist

C. Hunt, Senior Resident Inspector

C. Mathews, Illinois Emergency Management Agency

J. Park, Reactor Inspector

D. Tesar, Senior Resident Inspector

Approved By:

Kenneth R. Riemer, Chief

Branch 1

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Quad Cities Nuclear Power Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

UNIT 1 The unit began the inspection period at full-rated thermal power. On February 8, 2021, the unit began its end-of-cycle coastdown period. On March 15, 2021, the unit shut down for Refueling Outage (RO) Q1R26. On March 30, 2021, the unit was restarted, and power ascension was ongoing through the end of the inspection period. For all other periods, the unit was at full-rated thermal power with the exception of short-term power reductions for control rod sequence exchanges, testing, and as requested by the transmission system operator.

UNIT 2 The unit began the inspection period at full-rated thermal power, where it remained for the entire inspection period, with the exception of short-term power reductions for control rod sequence exchanges, testing, and as requested by the transmission system operator.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the Coronavirus Disease 2019 (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time, the resident inspectors performed periodic site visits each week; conducted plant status activities as described in IMC 2515, Appendix D, Plant Status; observed risk-significant activities; and completed on-site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or portions of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated on February 3, 2021, the adequacy of site preparations for impending severe cold weather predicted for February 4 to 11, 2021.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1 reactor core isolation cooling during high pressure coolant injection work window on March 2, 2021
(2) Unit 1/2 emergency diesel generator (EDG) during Unit 1 EDG unavailability on March 16, 2021
(3) Unit 1 EDG following a diesel generator cooling water modification on March 17, 2021
(4) Unit 1B low pressure core injection system walkdown on March 24, 2021

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone 11.1.3, Unit 1 reactor building, elevation 554'-0", high pressure coolant injection (HPCI) & HPCI access tunnel and Fire Zone 11.1.4, Unit 2 reactor building, elevation 544'-0", HPCI pump room on January 21, 2021
(2) Fire Zone 8.2.6.A, Unit 1 turbine building, elevation 595'-0", 4kV switchgear & Unit 1 trackway on February 19, 2021
(3) Fire Zone 11.3.4, Unit 2 reactor building, elevation 544'-0", northeast corner room - 2A residual heat removal room on February 25, 2021
(4) Fire Zone 1.1.1.3, Unit 1 reactor building, elevation 623'-0", mezzanine level on March 22, 2021
(5) Fire Zone 8.2.2A, Unit 2 turbine building, elevation 572'-6", control rod drive pumps on March 23, 2021

71111.08G - Inservice Inspection Activities (BWR)

BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding

Activities (IP Section 03.01)

(1) The inspectors verified that the reactor coolant system boundary, reactor vessel internals, risk-significant piping system boundaries, and containment boundary were appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined, and accepted by reviewing the documentation of the following activities from March 22 to March 26, 2021:

03.01.a - Nondestructive Examination and Welding Activities.

1. volumetric exam (ultrasonic testing (UT)) of Component ID 30C-S25, Category

R-A, Item R1.20-4

2. volumetric exam (UT) of Component ID 1008B-5, Category R-A, Item R1.11-2

3. surface exam (magnetic particle examination (MT)) of Component ID

1025-W-211A, Category C-C, Item C3.20

4. surface exam (MT) of Component ID RPV-THHF, Category B-A, Item B1.40

5. pressure boundary welds 1, 2, 5, and 10 fabricated during replacement of

1-1001-65B HP residual heat removal service water pump discharge elbow under Work Order 5010715

The above UT and MT exam records were selected from the previous outage in Spring 2019 (Q1R25), since there were neither the inservice inspection exams nor the aging management related exams scoped in during this outage (Spring 2021, Q1R26). It is also noted that there were no volumetric or surface exam records with relevant indications from the previous outage that had been accepted for continued service, and hence were not available for the inspector's review.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (3 Samples)

(1) The inspectors observed and evaluated licensed operator performance in the control room during Unit 1 load drop for end-of-cycle rod pattern adjustments and hydraulic control unit L-12 SCRAM outlet adjustment on January 16, 2021.
(2) The inspectors observed and evaluated licensed operator performance in the control room during Unit 1 shutdown/cooldown for RO Q1R26 on March 15, 2021.
(3) The inspectors observed and evaluated licensed operator performance in the control room during the Unit 1 reactor startup and heat up on March 30, 2021.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a licensed operator requalification training simulator as-left scenario on February 4, 2021.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) E-2 certification meeting and risk management for work week January 24, 2021
(2) E-2 certification meeting and risk management for work week March 1, 2021
(3) E-2 certification meeting and risk management for work week March 8, 2021 (4)impact of emergent issue during Unit 1 Q1R26 RO on Unit 2 online risk on March 17, 2021 (5)trip of reserve auxiliary transformer T-12 during RO Q1R26 on March 19, 2021

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Issue Report 4389284, "Time Delay Unit 10A-K45B As-Found Out of Spec"
(2) Issue Report 633276, "Op Eval 2B CREVs [control room emergency ventilation]

Freon Leak"

(3) Issue Report 4396776, "Expanded Scope WO [work order] 4708066-01 1A RHR

[residual heat removal] Room Cooler Inspection"

(4) Issue Report 4403127, "EO ID Bus 13-1 to 23-1 Tie Breaker Lockout Relay Found Tripped"
(5) Operability Evaluation 633936, "Evaluate Impacts of FWCV [feedwater control valve]

1-0220-62A Lost Parts during Q1R26"

(6) Operability Evaluation 633948, "1-0220-1 Maintenance Steam Line Drain Header Stop Valve"

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (4 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1) Work Order 4688647-21, "Temporary Configuration Change for Work Order

===4688647-21 per Engineering Change 332661," on March 11, 2021

(2) Engineering Change 626221, "Unit 1 HPCI SV-8 and SV-12 Replacement," on March 22, 2021
(3) Engineering Change 407242, "U-1 Install 5 Isolation Valves in Safety Related Service Water Piping on Each ECCS [emergency core cooling system] Room Cooler Supply Piping," on March 15, 2021
(4) Engineering Change 625679, "1A and 1B ASD [adjustable speed drive] Upgrade Modification," on March 18, 2021

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01)===

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1) QCOS 6600-06, "Diesel Generator Cooling Water Pump Flow Rate Test," following Work Order 5095941 on February 1, 2021 (2)post-maintenance test for Bus 18 to Bus 19 cross-connect breaker on March 17, 2021 (3)post-maintenance test for 1/2 EDG maintenance on March 19, 2021
(4) QCOS 1000-06, "RHR Pump/Loop Operability Test," ('A' loop RHR) on March 26, 2021
(5) QCOS 1000-04, "'B' RHR Service Water Operability," ('B' loop residual heat removal service water) on March 26, 2021
(6) QCOS 1300-01, "Periodic RCIC [reactor core isolation cooling] Pump Operability Test," on March 31, 2021
(7) QCOS 2300-01, "Periodic HPCI Pump Operability Test," on March 31, 2021

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)

(1)

(Partial)

The inspectors evaluated Unit 1 RO Q1R26 activities from March 15, 2021, to the end of the quarter on March 31, 2021. Inspection activities related to the Q1R26 outage continued into the next inspection period.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Unit 1 EDG monthly load run on January 11, 2021
(2) Work Order 05095941-01, "Backflush DG [diesel generator] HX [heat exchanger]

2-6661 'A' & 'B' Cooling Water Annubar FI 2-3941-26," on February 1, 2021

(3) QOS 6500-01, "4 kV Bus 13-1 Undervoltage Functional Test," on March 25, 2021
(4) QCOS 201-08, "Reactor Coolant System Pressure Test," on March 28, 2021

Inservice Testing (IP Section 03.01) (2 Samples)

(1) QCOS 1000-06, "RHR Pump/Loop Operability Test," Revision 64, on January 25, 2021
(2) QCOS 1100-07, "Standby Liquid Control Pump Flow Rate Test," Revision 41, on February 1, 2021

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) QCOS 0100-42, "Containment Penetration Expansion Bellows Local Leak Rate Test," and QCOS 1400-19, "Core Spray Pressure Isolation Valve Seat Leakage Test," on March 19, 2021

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

(1) The inspectors observed activities related to the technical support center during an emergency preparedness drill on February 2, 2021.

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1)technical support center and control room activities during an emergency preparedness drill on February 23,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

The inspectors evaluated instructions to workers including radiation work permits used to access high radiation areas.

(1) The inspectors evaluated instructions to workers including radiation work permits used to access high radiation areas and labeling of radioactive material in containers.

Contamination and Radioactive Material Control (IP Section 03.03) (3 Samples)

The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material.

(1)observed licensee surveys of potentially contaminated material leaving the radiological controlled area (RCA)

(2)observed workers exiting the RCA at Unit 1 during a refueling outage (3)observed work area staging for inspection/repairs of the 'B' contaminated condensate storage tank

Radiological Hazards Control and Work Coverage (IP Section 03.04) (3 Samples)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and observation of radiological work activities with high radiological risk or airborne radioactivity

(1)observed activities associated with Radiological Work Package QC-01-21-00513, "Drywell Control Rod Drive (CRD) Exchange" (2)observed activities associated with Radiological Work Package QC-01-21-00901, "Reactor Disassembly/Reassembly" (3)observed activities associated with Radiological Work Package QC-00-21-00229, "Inspection/Repair on Contaminated Condensate Storage Tanks" High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples)

The inspectors evaluated licensee controls of the following high radiation areas and very high radiation areas:

(1) Unit 1 reactor cavity
(2) Unit 1 drywell
(3) Unit 2 steam tunnel

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)

(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.02 - Occupational ALARA Planning and Controls

Implementation of ALARA and Radiological Work Controls (IP Section 03.03) (3 Samples)

The inspectors reviewed as low as reasonably achievable practices and radiological work controls and reviewed the following activities:

(1)observed activities associated with Radiological Work Package QC-01-21-00513, "Drywell Control Rod Drive (CRD) Exchange" (2)observed activities associated with Radiological Work Package QC-01-21-00901, "Reactor Disassembly/Reassembly" (3)observed activities associated with Radiological Work Package QC-00-21-00229, "Inspection/Repair on Contaminated Condensate Storage Tanks"

Radiation Worker Performance (IP Section 03.04) (1 Sample)

The inspectors evaluated radiation worker and radiation protection technician performance during:

(1)reactor disassembly/reassembly

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Temporary Ventilation Systems (IP Section 03.02) (1 Sample)

The inspectors evaluated the configuration of the following temporary ventilation systems:

(1)temporary HEPA filtration units on the Unit 1 refuel floor

Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees use of respiratory protection devices.

71124.05 - Radiation Monitoring Instrumentation

Calibration and Testing Program (IP Section 03.02) (10 Samples)

The inspectors evaluated the calibration and testing of the following radiation detection instruments:

(1) Canberra ACCUSCAN II
(2) Unit 1 Division II Drywell Radiation Monitor 1-2419-B
(3) Ludlum Model 3030P Serial Number 264768
(4) MGP Model Amp 200 Serial Number 7711-055
(5) MGP Model Telepole Serial Number 6696-101
(6) Eberline Model AMS4 Serial Number 107/107
(7) RADeCO Model H-809 High Volume Air Sampler Serial Number 052
(8) NE Technology Model IPM9 Serial Number I348
(9) Thermo Scientific Model SAM-12 Serial Number 12205
(10) Ludlum Model 177 Serial Number 339058

Effluent Monitoring Calibration and Testing Program Sample (IP Sample 03.03) (2 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1) Unit 1 steam jet air ejector effluent monitor
(2) Unit 1 service water effluent monitor

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 03.01)===

(1) Unit 1 (01/01/2020 - 12/31/2020)
(2) Unit 2 (01/01/2020 - 12/31/2020)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 03.02) (2 Samples)

(1) Unit 1 (01/01/2020 - 12/31/2020)
(2) Unit 2 (01/01/2020 - 12/31/2020)

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 03.03) (2 Samples)

(1) Unit 1 (01/01/2020 - 12/31/2020)
(2) Unit 2 (01/01/2020 - 12/31/2020)

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 13, 2021, the inspectors presented the integrated inspection results to Mr. K. Ohr, Site Vice President, and other members of the licensee staff.
  • On February 11, 2021, the inspectors presented the radiation protection inspection results to Mr. M. Humphrey, Organizational Effectiveness & Regulatory Director, and other members of the licensee staff.
  • On March 19, 2021, the inspectors presented the radiation protection inspection results to Mr. K. Ohr, Site Vice President, and other members of the licensee staff.
  • On March 26, 2021, the inspectors presented the inservice inspection results to Mr. B. Wake, Plant Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

OP-AA-108-111-

1001

Severe Weather and Natural Disaster Guidelines

QCOP 0010-02

Required Cold Weather Routines

71111.04

Corrective Action

Documents

IR 4238058

EO ID: Steam Leak on RCIC Drain Pot LS Drain Valve

04/10/2019

Procedures

QCOP 6600-04

Diesel Generator 1/2 Preparation for Standby Operation

QCOS 1300-11

RCIC Valve Position Verification

71111.05

Fire Plans

FZ 1.1.1.3

Unit 1 RB 623'-0" Elev. Mezzanine Level

07/2012

FZ 11.3.4

Unit 2 RB 544'-0" Elevation NE Corner Room - 2A RHR

Room

07/2009

FZ 8.2.2.A

Unit 2 TB 572'-6" Elevation CRD Pumps

10/2013

FZ 8.2.6.A

Unit 1 TB 595'-0" TB 595'-0" Elev. 4KV Switchgear & U-1

Trackway

03/2018

71111.08G Corrective Action

Documents

IR 4232329

Foreign Material Lost in RPV

03/23/2019

IR 4233819

Q1R25 FW Check Valve 1-0220-62A VT-3 Exam As-Found

Condition

03/28/2019

IR 4234666

OLL 1-0220-62A Bonnet Bolting Missed Surface Exam

03/30/2019

IR 4235215

PSU Q1R25 VT-1 of Bolting for Valve 1-1301-41 Bypassed

04/01/2019

IR 4235562

Required Exam for 1-8799-214 Not Performed in Q1R25

04/02/2019

IR 4239633

Q1R25 Trend IR - Required Bolting Exams Not Performed

04/15/2019

IR 4245286

VT3 of Support M-994D-22 During Q1R26

05/01/2019

IR 4256252

Q1R25 MSIV 1-0203-1B Bonnet Nut Installed W/O MT & VT-

Exam

06/12/2019

IR 4410615

B CCST Tank NDE Results

03/22/2021

Engineering

Changes

EC 627753

Evaluation of Foreign Material Lost from GEH Core Spray

Inspection Tool in Unit 1 Reactor Vessel in Q1R25

04/09/2019

EC 628503

Evaluation of the Waiver of R-4411 MT/VT-1 Exam

Requirements for a Class I Bonnet Nut on 1-0203-1B MSIV

(Q1R25)

Miscellaneous18-115

ASME Section XI Repair/Replacement Plan

06/20/2019

20-003

ASME Section XI Repair/Replacement Plan

08/24/2020

CPS

Procedure Qualification Record (PQR)

04/19/2001

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

209.05F001

NDE Reports

20-MT-006

Magnetic Particle Examination Data Sheet

2/28/2020

20-MT-008

Magnetic Particle Examination Data Sheet

2/28/2020

20-PT-013

Liquid Penetrant Examination Data Sheet

2/28/2020

20-PT-014

Liquid Penetrant Examination Data Sheet

2/28/2020

20-VT-001

VT-1 Visual Examination NDE Report

2/28/2020

Q1R25-MT-003

Magnetic Particle Examination

03/24/2019

Q1R25-MT-004

Magnetic Particle Examination

03/26/2019

Q1R25-MT-005

Magnetic Particle Examination

03/26/2019

Q1R25-UT-003

UT Calibration/Examination

03/24/2019

Q1R25-UT-014

UT Calibration/Examination

03/23/2019

Procedures

CC-AA-501-1011

Preheat, Interpass Temperature and Postweld Heat

Treatment of Welds

ER-AA-334-044

Eddy Current Surface Examinations

ER-AA-335-002

Liquid Penetrant (PT) Examination

ER-AA-335-003

Magnetic Particle (MT) Examination

and 9

ER-AA-335-004

Ultrasonic (UT) Measurement of Material Thickness and

Interfering Conditions

ER-AA-335-016

VT-3 Visual Examination of Component Supports,

Attachments, and Interiors of Reactor Vessels

GEH-PDI-UT-1

PDI Generic Procedure for the Ultrasonic Examination of

Ferritic Welds

PDI-UT-1

Table 1

PDI-UT-1

Table 2

03/10/2020

WPS 1-1-GTSM-

PWHT

ASME Welding Procedure Specification Record

Work Orders

WO 4899216

CRD 34-23 Drive Mechanism Leakage

04/18/2019

WO 5010715

MM 1B RHRSW Discharge Piping Leak

03/03/2020

71111.13

Corrective Action

Documents

IR 4276940

PRA Review Question, HRE Guidance for SW Strainers

09/05/2019

IR 4406805

Temporary Structure Placed on FLEX Haul Path

03/05/2021

IR 4410299

Trip of Reserve Aux Transformer T-12 During Q1R26

03/19/2021

Procedures

OP-QC-107-1001

Quad Cities Risk Management Guidelines

QCOS 0050-02

Flex Haul Path Inspection

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.15

Corrective Action

Documents

IR 4389289

Time Delay Unit 10A-K45B As Found Out of Spec

2/09/2021

IR 4396776

Expanded Scope w/o 4708066-01, 1A RHR Room Cooler

Inspection

01/19/2021

IR 4397447

4.0 Critique 1A RHR Room Cooler Inspection

01/20/2021

IR 4397726

EOC for IR 4396776 - 1A RHR Room Cooler HX Inspection

01/19/2021

IR 4403127

EO ID Bus 13-1 to 23-1 Tie Breaker Lockout Fly Found

Tripped

2/18/2021

Engineering

Changes

EC 633276

Op Eval EC 'B' CREVS Freon Leak

EC 633936

Evaluate Impacts of FW CV 1-0220-62A Lost Parts During

Q1R26

000

EC 633948

1-0220-1 Main Steam Line Drain Header Stop Valve

000

Work Orders

WO 4708066

1A RHR Corner Room Cooler

01/19/2021

71111.18

Corrective Action

Documents

IR 4410056

APS - Handle of Valve Installed Contacts a 3/4" Line

03/19/2021

IR 4411723

Liquid Penetrant Inspection Indications on New Rigid

Support

03/26/2021

IR 4411796

Q1R26 Pin Hole Leak on DGCW Line Downstream of

1-399-885

03/26/2021

Engineering

Changes

EC 332661

Temporary Support for the Diesel Generator Cooling Water

(DGCW) System While the Reactor Feed Pump Motors are

Being Moved

EC 407242

U-1 Install 5 Isolation Valves in SR Service Water Piping on

Each ECCS Room Cooler Supply Piping

EC 626221

Unit 1 HPCI SV-8 and SV-12 Replacement

Procedures

CC-AA-112

Temporary Configuration Changes

QCOP 0202-51

ASD Testing in Open Loop Test Mode

71111.19

Corrective Action

Documents

IR 4399543

U2 EDGCWP Initial Test Conditions Not Established

2/01/2021

IR 504920

Aborted QCOS 6600-06 for U1 EDG

06/29/2006

Procedures

QCOP 6600-05

Shared Unit Diesel Generator Start Up

QCOS 1000-04

RHR Service Water Pump Operability Test

QCOS 1000-06

RHR Pump/Loop Operability Test

QCOS 1300-01

Periodic RCIC Pump Operability Test

QCOS 2300-01

Periodic HPCI Pump Operability Test

QCOS 6600-06

Diesel Generator Cooling Water Pump Flow Rate Test

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.20

Engineering

Changes

EC 633340

Q1R26 Decay Heat and Related Calculations

Miscellaneous

Safety Evaluation

Report

Control of Heavy Loads

06/27/1983

Technical

Evaluation Report

Control of Heavy Loads

06/27/1983

Procedures

MA-AA-716-022

Control of Heavy Loads Program

MA-QC-756-600

Reactor Disassembly

OU-QC-104

Shutdown Safety Management Program Quad Cities Annex

QCMM 5800-04

Reactor Building Overhead Crane Reactor Cavity

Maintenance Support Tools Transport

QCMM 5800-05

Reactor Building Overhead Crane Utilization

QCOP 1000-44

Alternate Decay Heat Removal

71111.22

Procedures

QCOP 0100-01

Local Leak Rate Test Make-up Flow Rate Method

QCOS 0100-42

Containment Penetration Expansion Bellows Local Leak

Rate Test

Work Orders

WO 4614054

OP As Found Seat Leakage Test MO 1-1402-25A

03/17/2021

WO 4911057

QOS 6500-01, 4 KV Undervoltage Functional Test

WO 4938159

OP Perform Testable Double Ply Bellows (LLRT)

03/23/2021

WO 5090622

QCOS 1000-6 'A' RHR Pump Flow Rate Group A Test (IST)

WO 5092243

QCOS 1100-7 'A' SBLC Pump Flow Rate Group B Test

WO 5095941

Backflush DG HX 2-6661 A&B Cooling Water Annubar FE

2-3941-42

2/01/2021

WO 5108653

QCOS 6600-41 U1 DG Monthly Load Test

01/10/2021

71114.06

Corrective Action

Documents

IR 4410803

1st Quarter ERO Drill Performance

03/22/2021

71124.01

ALARA Plans

QC-00-21-00229

Inspection / Repair on CCST Tanks

03/15/2021

QC-01-21-00513

DW Control Rod Drive (CRD) Exchange

QC-01-21-00901

FF RX Disassembly/Reassembly Activities

Corrective Action

Documents

Resulting from

Inspection

IR 4409652

RWP's Lack Info

03/17/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Procedures

NISP-RP-010

Radiological Job Coverage

RP-AA-401-1002

Radiological Risk Management

Radiation Work

Permits (RWPs)

QC-01-21-00513

DW Control Rod Drive (CRD) Exchange

QC-01-21-00901

FF RX Disassembly/Reassembly Activities

71124.02

Procedures

RP-AA-403

Administration of the Radiation Work Permit Program

71124.03

Miscellaneous

QC-01-21-00513

TEDE-ALARA Evaluation Screening Worksheet

01/21/2021

QC-01-21-00901

TEDE-ALARA Evaluation Screening Worksheet

03/08/2021

Procedures

NISP-RP-008

Use and Control of HEPA Filtration and Vacuum Equipment

71124.05

Calibration

Records

Calibration of the ACCUSCAN II WBC System at the Quad

Cities Nuclear Generating Station

07/21/2020

26942

00162776-01. TS, DI

V. II, Drywell Radiation Monitor

Cal/Func Test, WS124031M

2/10/2019

Certificate

0011217699

MGP Amp200 Serial Number 7711-055

03/10/2020

Certificate

0011225896

Ludlum Model 177 Serial Number 339058

2/25/2020

Certificate

0011238650

Certificate of Calibration Ludlum 3030P Serial Number

264768

06/05/2020

Certificate

0011242092

Certificate of Calibration RAD-PRO 5 Serial Number

20110702019

05/19/2020

Certificate

0011244672

Eberline Model AMS4 Serial Number 107/107

05/15/2020

Certificate

0011244710

MGP Telepole Serial Number 6696-101

05/29/2020

RADeCO Serial

Number 052

RADeCO Model H-809 High Volume Air Sampler

05/12/2020

RP-AA-700-1210

IPM Calibration Data Sheet Monitor I348

03/14/2021

RP-AA-700-1239

SAM-12 Calibration Data Sheet Serial Number 12205

2/10/2020

WO 4882857

Unit 1 Steam Jet Air Ejector Off-GAs Logarithmic Radiation

Monitor Calibration and Functional Test

08/18/2020

WO 4935387

Service Water Monitor Calibration

01/13/2021

Corrective Action

Certificate

Ludlum 3/43-92 Serial Number 282993/PR314732

07/16/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

  1. 0011237071

IR 4354654

MCR Received 902-3 G-16, Fuel Pool Channel A Hi

Radiation

07/04/2020

IR 4374473

Drywell CAM Detector Sensitive to Light

10/05/2020

IR 4374922

Unit 2 Reactor Building Stack Monitor Low Sample Flow

10/07/2020

IR 4375070

Follow up to IR 4374922

10/07/2020

IR 4391080

Quarterly Lists of QC Results and Plots

2/18/2020

IR 4395624

Conservative Setpoint Used for Radwaste Effluent Monitor

01/13/2021

Miscellaneous

Quality Control Charts for ACCUSCAN II Second Quarter

20

2/16/2020

CY-QC-130-404

Unit 1 Steam Jet Air Ejector Setpoint Calculation

2/22/2020

QDC-19-003

Unconditional Release Detection Thresholds and Dose

Consequences

Procedures

RP-AA-700

Controls for Radiation Protection Instrumentation

RP-AA-700-1210

Operation and Calibration of IPM Whole Body Frisking

Monitor

RP-AA-700-1216

Calibration of H-Vol Air Samplers

RP-AA-700-1239

Operation and Calibration of the Model SAM-12 Small

Articles Monitor

Self-Assessments IR 4201130

Exelon Power Labs RP Instruments (EPL)

2/31/2019

71151

Miscellaneous

Quad Cities 1 Quarterly Performance Indicators

Quad Cities 2 Quarterly Performance Indicators

QC Unit 1 Power History Report

QC Unit 2 Power History Report