MONTHYEARIR 05000254/20244022024-09-12012 September 2024 Material Control and Accounting Program Inspection Report 05000254/2024402 and 05000265/2024402 (Public) IR 05000254/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Quad Cities Nuclear Power Station (Report 05000254/2024005; 05000265/2024005) IR 05000254/20240022024-08-12012 August 2024 Integrated Inspection Report 05000254/2024002 and 05000265/2024002 IR 05000254/20243012024-08-0101 August 2024 NRC Initial License Examination Report 05000254/2024301; 05000265/2024301 IR 05000254/20240012024-05-14014 May 2024 Integrated Inspection Report Nos. 05000254/2024001 and 05000265/2024001 IR 05000254/20245012024-04-0505 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000254/2024501 and 05000265/2024501 IR 05000254/20230062024-02-28028 February 2024 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2023006 and 05000265/2023006) IR 05000254/20230042024-02-0505 February 2024 Integrated Inspection Report 05000254/2023004 and 05000265/2023004 IR 05000254/20234032023-12-22022 December 2023 Public- Quad Cities Nuclear Power Station Security Baseline Inspection Report 05000254/2023403 and 05000265/2023403 IR 05000254/20230102023-12-20020 December 2023 Comprehensive Engineering Team Inspection Report 05000254/2023010 and 05000265/2023010 IR 05000254/20230032023-11-0909 November 2023 Integrated Inspection Report 05000254/2023003 and 05000265/2023003 IR 05000254/20230112023-09-20020 September 2023 Safety-Conscious Work Environment Issue of Concern Team Inspection Report 05000254/2023011 and 05000265/2023011 IR 05000254/20230022023-08-0808 August 2023 Integrated Inspection Report 05000254/2023002 and 05000265/2023002 IR 05000254/20234012023-06-26026 June 2023 Cyber Security Inspection Report 05000254/2023401 and 05000265/2023401 IR 05000265/20230402023-06-22022 June 2023 Reissue Quad Cities Nuclear Power Station 95001 Supplemental Inspection Supplemental Report 05000265/2023040 and Follow Up Assessment Letter ML23167B1722023-06-16016 June 2023 95001 Supplemental Inspection Report 05000265/2023040 and Follow-Up Assessment Letter IR 05000254/20234022023-05-15015 May 2023 Security Baseline and ISFSI Inspection Reports 05000254/2023402, 05000265/2023402, 07200053/2023401 IR 05000254/20230012023-05-0808 May 2023 Integrated Report 05000254/2023001 and 05000265/2023001 IR 05000254/20233012023-03-0707 March 2023 NRC Initial License Examination Report 05000254/2023301; 05000265/2023301 ML23065A2832023-03-0707 March 2023 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000254/2023010 and 05000265/2023010 IR 05000254/20220062023-03-0101 March 2023 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2022006 and 05000265/2022006) IR 05000254/20220042023-02-10010 February 2023 Integrated Inspection Report 05000254/2022004 and 05000265/2022004 IR 05000254/20220112023-01-0606 January 2023 Triennial Fire Protection Inspection Report 05000254/2022011 and 05000265/2022011 IR 05000254/20220102022-12-13013 December 2022 Phase 4 Post-Approval License Renewal Inspection Report 05000254/2022010 and 05000265/2022010 ML22313A1502022-11-29029 November 2022 EA-22-062 QC ERV Final Action IR 05000254/20224012022-11-22022 November 2022 Security Baseline Inspection Report 05000254/2022401 and 05000265/2022401 IR 05000254/20220132022-11-17017 November 2022 Biennial Problem Identification and Resolution Inspection Report 05000254/2022013 and 05000265/2022013 IR 05000254/20220032022-11-0303 November 2022 Integrated Inspection Report 05000254/2022003 and 05000265/2022003 IR 05000254/20220052022-08-22022 August 2022 Updated Inspection Plan for Quad Cities Nuclear Power Station (Report 05000254/2022005; 05000265/2022005) IR 05000254/20225012022-08-15015 August 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000254/2022501 and 05000265/2022501 IR 05000254/20220022022-08-0909 August 2022 Integrated Inspection Report 05000254/2022002 and 05000265/2022002 IR 05000254/20220902022-08-0808 August 2022 NRC Inspection Report 05000254/2022090 and 05000265/2022090; Preliminary White Finding IR 05000254/20220122022-07-11011 July 2022 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000254/2022012 and 05000265/2022012 IR 05000254/20220012022-05-11011 May 2022 Integrated Inspection Report 05000254/2022001 and 05000265/2022001 IR 05000254/20210062022-03-0202 March 2022 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2021006 and 05000265/2021006) IR 05000254/20210042022-02-0202 February 2022 Integrated Inspection Report 05000254/2021004 and 05000265/2021004 ML22033A1672022-02-0202 February 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000265/2022001 IR 05000254/20214022021-12-0101 December 2021 Security Baseline Inspection Report 05000254/2021402 and 05000265/2021402 IR 05000254/20210102021-11-24024 November 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000254/2021010 and 05000265/2021010 IR 05000254/20210032021-10-28028 October 2021 Integrated Inspection Report 05000254/2021003 and 05000265/2021003 IR 05000254/20214012021-09-0909 September 2021 Security Baseline Inspection Report 05000254/2021401 and 05000265/2021401 IR 05000254/20210052021-09-0101 September 2021 Updated Inspection Plan for Quad Cities Nuclear Power Station (Report 05000254/2021005 and 05000265/2021005) ML21238A3142021-08-26026 August 2021 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000254/2021004; 05000265/2021004 IR 05000254/20213012021-08-23023 August 2021 NRC Initial License Examination Report 05000254/2021301; 05000265/2021301 IR 05000254/20210022021-08-0909 August 2021 Integrated Inspection Report 05000254/2021002 and 05000265/2021002 IR 05000254/20214032021-06-28028 June 2021 Quad Nuclear Power Station - Material Control and Accounting Program Inspection Report 05000254/2021403 and 05000265/2021403 IR 05000254/20210012021-04-26026 April 2021 Integrated Inspection Report 05000254/2021001 and 05000265/2021001 IR 05000254/20200062021-03-0404 March 2021 Annual Assessment Letter for Quad Cities Nuclear Power Station Units 1 and 2 (Report 05000254/2020006 and 05000265/2020006) IR 05000254/20200042021-02-0404 February 2021 Integrated Inspection Report 05000254/2020004 and 05000265/2020004 IR 05000254/20204022021-01-11011 January 2021 Security Baseline Inspection Report 05000254/2020402 and 05000265/2020402 2024-09-12
[Table view] Category:Letter
MONTHYEARRS-24-080, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in .2024-10-16016 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in . RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests SVP-24-059, Correction to Registration of Use of Casks to Store Spent Fuel2024-10-0404 October 2024 Correction to Registration of Use of Casks to Store Spent Fuel ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24247A1642024-09-30030 September 2024 Alternative Request RP-01 IR 05000254/20244022024-09-12012 September 2024 Material Control and Accounting Program Inspection Report 05000254/2024402 and 05000265/2024402 (Public) SVP-24-054, Deviation from BWR Vessel and Internals Project (BWRVIP) Guidelines - Inspection of Top Guide Rim Welds2024-09-11011 September 2024 Deviation from BWR Vessel and Internals Project (BWRVIP) Guidelines - Inspection of Top Guide Rim Welds ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000254/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Quad Cities Nuclear Power Station (Report 05000254/2024005; 05000265/2024005) RS-24-078, Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval2024-08-20020 August 2024 Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval ML24183A1082024-08-0808 August 2024 – Issuance of Amendment Nos. 302 and 298 Adoption of Tstf-505, Provide Risk Informed Extended Completion Times – RITSTF Initiative 4b SVP-24-049, Owners Activity Report Submittal Sixth 10-Year Interval 2024 Refueling Outage Activities2024-08-0707 August 2024 Owners Activity Report Submittal Sixth 10-Year Interval 2024 Refueling Outage Activities IR 05000254/20243012024-08-0101 August 2024 NRC Initial License Examination Report 05000254/2024301; 05000265/2024301 SVP-24-048, Registration of Use of Casks to Store Spent Fuel2024-07-31031 July 2024 Registration of Use of Casks to Store Spent Fuel SVP-24-046, Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure2024-07-22022 July 2024 Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions SVP-24-041, Regulatory Commitment Change Summary Report2024-07-0505 July 2024 Regulatory Commitment Change Summary Report SVP-24-043, Registration of Use of Casks to Store Spent Fuel2024-07-0505 July 2024 Registration of Use of Casks to Store Spent Fuel ML24162A0982024-07-0303 July 2024 – Issuance of Amendment Nos. 301 and 297 Adoption of 10 CFR 50.69 Risk Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors SVP-24-040, Registration of Use of Casks to Store Spent Fuel2024-06-25025 June 2024 Registration of Use of Casks to Store Spent Fuel RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations SVP-24-039, Ile Post Exam Package Letter2024-06-12012 June 2024 Ile Post Exam Package Letter RS-24-053, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed2024-06-0606 June 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed ML24110A0492024-05-28028 May 2024 Audit Report Related to the TSTF-505 and 10 CFR 50.59 Amendments ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24141A2102024-05-20020 May 2024 Operator Licensing Examination Approval - Quad Cities Nuclear Power Station, May 2024 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report IR 05000254/20240012024-05-14014 May 2024 Integrated Inspection Report Nos. 05000254/2024001 and 05000265/2024001 SVP-24-034, Annual Radiological Environmental Operating Report2024-05-10010 May 2024 Annual Radiological Environmental Operating Report RS-24-042, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-05-10010 May 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion SVP-24-031, Automatic Actuation of Reactor Protection System During Scram Discharge Volume Leak Rate Testing2024-05-10010 May 2024 Automatic Actuation of Reactor Protection System During Scram Discharge Volume Leak Rate Testing RS-24-046, 10 CFR 50.46 Annual Report2024-05-0606 May 2024 10 CFR 50.46 Annual Report ML24109A0662024-05-0202 May 2024 – Relief Request I5R-26, Revision 0 RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests SVP-24-029, Radioactive Effluent Release Report for 20232024-04-26026 April 2024 Radioactive Effluent Release Report for 2023 SVP-24-028, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2024-04-26026 April 2024 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report ML24114A1712024-04-23023 April 2024 State of Illinois (IEMA-OHS) Comment Quad Cities HI-STORM Exemption Environmental Assessment IR 05000254/20245012024-04-0505 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000254/2024501 and 05000265/2024501 RS-24-032, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-04-0505 April 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion SVP-24-024, Corrected Radioactive Effluent Release Report for 20222024-04-0505 April 2024 Corrected Radioactive Effluent Release Report for 2022 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report SVP-24-023, Ile Outline Submittal Letter2024-03-29029 March 2024 Ile Outline Submittal Letter RS-24-019, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Completion Times TSTF2024-03-19019 March 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Completion Times TSTF ML23340A1552024-03-15015 March 2024 – Issuance of Amendment Nos. 299 and 295 Adoption of TSTF-564, Safety Limit MCPR RS-24-020, Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Quad Cities Nuclear Power Station - Holtec MPC-68MCBS2024-03-15015 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Quad Cities Nuclear Power Station - Holtec MPC-68MCBS SVP-24-018, Ile Proposed Exam Submittal Letter2024-03-13013 March 2024 Ile Proposed Exam Submittal Letter RS-24-015, Submittal of RP-01 Relief Request Associated with the Sixth Inservice Testing Interval2024-02-29029 February 2024 Submittal of RP-01 Relief Request Associated with the Sixth Inservice Testing Interval IR 05000254/20230062024-02-28028 February 2024 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2023006 and 05000265/2023006) ML24053A1192024-02-22022 February 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000265/2024010 and 05000254/2024010 2024-09-04
[Table view] |
Text
December 1, 2021
SUBJECT:
QUAD CITIES NUCLEAR POWER STATION - SECURITY BASELINE INSPECTION REPORT 05000254/2021402 AND 05000265/2021402
Dear Mr. Rhoades:
On November 8, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Quad Cities Nuclear Power Station and discussed the results of this inspection with Ms. Danielle Fuson, Director of Organizational Performance and Regulatory and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Signed by Orth, Steven on 12/01/21 Steven K. Orth, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 05000254 and 05000265 License Nos. DPR-29 and DPR-30
Enclosure:
As stated
Inspection Report
Docket Numbers: 05000254 and 05000265 License Numbers: DPR-29 and DPR-30 Report Numbers: 05000254/2021402 and 05000265/2021402 Enterprise Identifier: I-2021-402-0058 Licensee: Exelon Generation Company, LLC Facility: Quad Cities Nuclear Power Station Location: Cordova, IL Inspection Dates: October 18, 2021 to November 08, 2021 Inspector: G. Bonano, Physical Security Inspector Approved By: Steven K. Orth, Chief Plant Support Branch Division of Reactor Safety Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Quad Cities Nuclear Power Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.
Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.
SAFEGUARDS
71130.04 - Equipment Performance, Testing, and Maintenance
The inspector evaluated the security equipment testing and maintenance program through completion of the following procedure elements. In addition, the completion of these elements combined with the completion of elements documented in report 05000254/2020402 and
===05000265/2020402, dated January 11, 2021, constitute one complete sample.
Equipment Performance, Testing, and Maintenance ===
- (1) Tier I: 02.02 b - h; 02.03 c; 02.04 b, c, f, g; 02.05 b - d; 02.06 b; 02.08 e Tier II: 02.09 a; 02.10 a; 02.11 a, b; 02.12 a Tier III: None
71130.07 - Security Training
The inspector evaluated the security training program through completion of the following
procedure elements: Security Training
Main article: IP 71130.07
- (1) Tier I: All Requirements Tier II: 02.05 a - d; 02.07 a; 02.09 a Tier III: 02.11 a; 02.12 a, b; 02.13 b, c
71130.09 - Security Plan Changes
Review Security Plan Changes (IP Section 02.01) (1 Sample)
The inspector evaluated the security plan changes through completion of the following procedure elements:
- (1) Since the last NRC inspection of this program area, Security Plan Revision(s) 16 to 17 were implemented based on your determination, in accordance with Title 10 of the Code of Federal Regulations (CFR), Part 50.54(p)(2), that the changes resulted in no decrease in safeguards effectiveness of the security plan, and that the revised security plan changed continues to meet the requirements of 10 CFR 73.55(b). The inspector conducted a review of the security plan changes to evaluate for potential decrease in safeguards effectiveness of the security plan. However, this review does not constitute formal NRC approval of the changes. Therefore, these changes remain subject to future NRC inspection in their entirety.
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspector verified no proprietary information was retained or documented in this report.
On November 8, 2021, the inspector presented the security baseline inspection results to Ms. Danielle Fuson, Director of Organizational Performance and Regulatory and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
71130.04 Corrective Action AR 04418307 Vehicle Key Control 04/22/2021
Documents
Miscellaneous SC-JA-0016 Security Equipment Tamper Test 12
SY-QC-101-1003- Weekly Test Checklist for Performance of Security System January -
F-05 Tests October
21
Procedures SY-AA-101-122 Testing Security Equipment 23
SY-AA-101-122- Performance of Access Control Device and Portal Tests 0
103
SY-AA-101-122- Performance of Special Purpose Detector, Communication, 0
104 Lighting, and Biometrics Threshold Tests
SY-AA-150-1010 FIREARMS PRACTICE RANGE MAINTENANCE 1
SY-AA-150-103 FIREARMS MAINTENANCE, TESTING, AND 2
ACCOUNTABILITY
71130.07 Corrective Action AR 04456127 NRC Range Observation 10/27/2021
Documents
Resulting from
Inspection
Miscellaneous Armed Responder - Individual Qualification Records 2020 - 2021
Response Team Leader - Individual Qualification Records 2020 - 2021
The National Rifle Association of America
Training Instructor Certificates - 5 Personnel (Trainers)
QC Tactical Course 2021 0
LMS Component Completion Report 11/04/2021
HR-AA-07-110 Armed MSO Medical Examination Records (11 Personnel 17
Records)
SY-AA-150-105- Quad Cities Physical Fitness Test (PFT) 0
F-11
Procedures SY-AA-101-145 Security Standards of Conduct 16
SY-AA-150-1007 EXELON NUCLEAR SECURITY ADVERSARY FORCE 2
SY-AA-150-1008 FIREARM TRAINING SIMULATOR (FATS) 1
SY-AA-150-1009 FIREARMS PRACTICE RANGE MANAGEMENT 1
Inspection Type Designation Description or Title Revision or
Procedure Date
SY-AA-150-101 EXELON NUCLEAR SECURITY TRAINING 2
SY-AA-150-104 EXELON NUCLEAR SECURITY OJT PROGRAM 1
SY-AA-150-105 EXELON NUCLEAR SECURITY PHYSICAL FITNESS TEST 1
DEVELOPMENT, APPROVAL AND CONDUCT
Self-Assessments NOSA-QDC-20- Security Programs Audit Report - 02/05/2020
(AR 4308330) January 21 to January 31, 2020
NOSA-QDC-21- Security Programs Audit Report - 03/10/2021
(AR January 19 to March 5, 2021
04394294)
71130.09 Miscellaneous Quad Cities Station Site Security Plan, Safeguards 17
Contingency Plan, Training and
Qualification Plan, and Independent Spent Fuel Storage
Installation Program
Procedures SY-AA-500-126 Duties and Responsibilities of the Exelon Nuclear Security 20
Organization
6