UPDATED INSPECTION PLAN AND ASSESSMENT FOLLOW-UP LETTER FOR QUAD CITIES NUCLEAR POWER STATION (REPORT 05000254/2023005; 05000265/2023005)

Dear David Rhoades:

The enclosed inspection plan lists the inspections scheduled through June 30, 2025, for the Quad Cities Nuclear Power Station. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

August 25, 2023 Please contact me at 630-829-9732 with any questions you have regarding this letter.

Sincerely, Robert Ruiz, Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket Nos. 05000254 and 05000265 License Nos. DPR-29 and DPR-30 Enclosure:

Inspection Plan cc: Distribution via LISTSERV Signed by Ruiz, Robert on 08/25/23