ML23167B172
ML23167B172 | |
Person / Time | |
---|---|
Site: | Quad Cities ![]() |
Issue date: | 06/16/2023 |
From: | Robert Ruiz NRC/RGN-III/DORS/RPB1 |
To: | Rhoades D Constellation Energy Generation, Constellation Nuclear |
References | |
IR 2023040 | |
Download: ML23167B172 (1) | |
See also: IR 05000265/2023040
Text
June 16, 2023
David P. Rhoades
Senior Vice President
Constellation Energy Generation, LLC
President and Chief Nuclear Officer (CNO)
Constellation Nuclear
4300 Winfield Road
Warrenville, IL 60555
SUBJECT: QUAD CITIES NUCLEAR POWER STATION - 95001 SUPPLEMENTAL
INSPECTION SUPPLEMENTAL REPORT 05000265/2023040 AND
FOLLOW-UP ASSESSMENT LETTER
Dear David Rhoades:
On May 4, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed a supplemental
inspection using Inspection Procedure 95001, "Supplemental Inspection Response to Action
Matrix Column 2 (Regulatory Response) Inputs, and discussed the results of this inspection
with you and other members of your staff.
The NRC performed this inspection to review your stations actions in response to a White
finding in the Mitigating Systems cornerstone which was documented and finalized in NRC
Inspection Report 05000254/2022090 and 05000265/2022090 respectively. On March 28, 2023,
you informed the NRC that your station was ready for the supplemental inspection.
The NRC determined that your staffs evaluation identified the cause of the White finding.
Specifically, Quad Cities Nuclear Power Station (the licensee) conducted a root cause analysis
and determined that there were two root causes. The first was "Inadequate Human Performance
(HU) behaviors during the planning and execution of the ERV rebuild," and the second was
"The stations Preventive Maintenance (PM) structure does not ensure that all components for
OPCC [Operationally Critical Components] work are tied to PMIDs that facilitate effective OPCC
screening." The licensee determined that there was inadequate level of detail in the procedures
used to rebuild the electromatic relief valve. In addition, the craft failed to stop when unsure and
proceeded in the face of uncertainty. Because the first root cause was associated with human
performance behaviors; however, there was no corrective action to preclude repetition assigned
to this root cause. The second root cause was associated with preventive maintenance
structure which did not identify operationally critical components to ensure an adequate level of
detail in work documents and supervisory oversight. The corrective actions associated with the
causes identified include actions to improve nuclear professionalism behaviors as well as
reviews of maintenance items to ensure they are structured appropriately with the correct
classification to ensure the appropriate levels of detail and oversight.
The inspectors concluded that the licensee had adequately determined the root and contributing
causes and had appropriate actions in place to address the causes identified.
D. Rhoades 2
The NRC determined that completed or planned corrective actions were sufficient to address
the performance issue that led to the White finding previously described. Therefore, the
performance issue will not be considered as an Action Matrix input following the conclusion of
the debrief conducted on May 4, 2023.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public
Inspections, Exemptions, Requests for Withholding.
Sincerely,
Signed by Ruiz, Robert
on 06/16/23
Robert Ruiz, Chief
Reactor Projects Branch 1
Division of Operating Reactor Safety
Docket No. 05000265
License No. DPR-30
Enclosure:
As stated
cc w/ encl: Distribution via LISTSERV
Non-Sensitive Publicly Available
SUNSI Review
Sensitive Non-Publicly Available
OFFICE RIII
NAME RRuiz:mb
DATE 06/16/2023
U.S. NUCLEAR REGULATORY COMMISSION
Inspection Report
Docket Number: 05000265
License Number: DPR-30
Report Number: 05000265/2023040
Enterprise Identifier: I-2023-040-0004
Licensee: Constellation Nuclear
Facility: Quad Cities Nuclear Power Station
Location: Cordova, IL
Inspection Dates: May 01, 2023 to May 04, 2023
Inspectors: C. St. Peters, Senior Resident Inspector
D. Tesar, Senior Resident Inspector
Approved By: Robert Ruiz, Chief
Reactor Projects Branch 1
Division of Operating Reactor Safety
Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees
performance by conducting a 95001 supplemental inspection at Quad Cities Nuclear Power
Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is
the NRCs program for overseeing the safe operation of commercial nuclear power reactors.
Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
Type Issue Number Title Report Section Status
NOV 05000265/2022090-01 02-0203-3B Electromatic 95001 Closed
Relief Valve Failed to
Operate During As-Found
Testing During Refueling
Outage Q2R26
2
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in
effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with
their attached revision histories are located on the public website at http://www.nrc.gov/reading-
rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared
complete when the IP requirements most appropriate to the inspection activity were met
consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection
Program - Operations Phase. The inspectors reviewed selected procedures and records,
observed activities, and interviewed personnel to assess licensee performance and compliance
with Commission rules and regulations, license conditions, site procedures, and standards.
OTHER ACTIVITIES - TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL
95001 - Supplemental Inspection Response to Action Matrix Column 2 (Regulatory Response)
Inputs
The inspectors reviewed and selectively challenged aspects of the licensees problem
identification, causal analysis, and corrective actions in response to the Unit 2, 2-203-3B
electromatic relief valve failure to operate on March 21, 2023, as documented in NRC
Inspection Reports 05000254/2022090 and 05000265/2022090 and Licensee Event
Report (LER) 265/2022-001-00.
Supplemental Inspection Response to Action Matrix Column 2 (Regulatory Response) Inputs
(1 Sample)
(1) SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) reviewed the licensees corrective
actions to address a White finding by performing a supplemental inspection using
Inspection Procedure 95001, Supplemental Inspection Response to Action Matrix
Column 2 Inputs, at Quad Cities, Unit 2 in accordance with the reactor oversight
process.
The inspectors determined that the licensees problem identification, causal analysis,
corrective actions in place, and incident reports (IR) entered into their corrective
action program (CAP) sufficiently addressed the performance issue that led to the
White finding.
INSPECTION RESULTS
Assessment 95001
1. Problem Identification
a. Identification: This issue was self-revealed when the 2-0203-3B electromatic
relief valves (ERV) (3B ERV) failed to operate during as-found surveillance testing
on March 21, 2022.
b. Exposure Time: The licensee determined that the 3B ERV was inoperable from
April 7, 2021 until March 21, 2022.
3
c. Identification Opportunities: The inspectors determined that the licensee had a
missed opportunity to identify this issue when the 2-0203-3D ERV (3D ERV)
experienced binding and failed to operate correctly in March of 2020, shortly after
the original issue with the 3B ERV occurred. The inspectors identified other
potential opportunities to identify the issue as documented in the report.
d. Risk and Compliance: The licensee conducted a risk evaluation and a review of
Technical Specification (TS) impacts of the 3B ERV failure. Their risk evaluation
determined that the failure of the 3B ERV was a maintenance rule functional
failure (MRFF) and was reportable under Title 10 of the Code of Federal
Regulations (10 CFR) 50.73(a)(2)(i)(B) - Any operation or condition which was
prohibited by the plants Technical Specifications. The licensees risk evaluation
determined a slightly elevated change in core damage frequency (delta CDF).
The NRC also conducted a risk evaluation (utilizing the Standardized Plant
Analysis Risk (SPAR) Model) accounting for the ERV failure over the exposure
time and determined that the delta CDF was consistent with a White finding of low
to moderate safety significance.
NRC Assessment:
The inspectors determined that the licensee had completed the risk evaluation as
required. The difference in the outcome between the licensee risk evaluation and
the NRC evaluation was due to differences in the models used as well as the
exposure time (12 months) used by the NRC in the SPAR model. The licensees
corrective actions were based upon the NRC determination of White, low to
moderate safety significance. Therefore, the inspectors determined that the
actions taken and/or planned adequately addressed the safety significance of the
issue.
Assessment 95001
2. Causal Analysis
a. Methodology: The licensee initially conducted an equipment causal analysis,
then subsequently conducted a root cause analysis to determine the root and
contributing causes of the event. Analytical tools implemented included event and
causal factors, cause and effects analysis, and TapRoot methodologies. In
addition, interviews and anonymous surveys were used to solicit information from
plant staff. The inspectors review concluded that the root cause analysis was the
appropriate level of evaluation and that the methodologies implemented were
appropriate.
b. Level of Detail: In general, the inspectors determined that the causal evaluation
was conducted with an appropriate level of detail commensurate with the safety
significance of the issue. Inspectors identified additional potential opportunities as
discussed within this report. The results of the licensees evaluation were clearly
documented in the report with root and contributing causes identified and what
actions were put in place to correct each of the causes.
c. Operating Experience: The licensee adequately identified and addressed
operating experience associated with the failure of the 2-0203-3B ERV. Other
events considered during this analysis included, but were not limited to:
4
Quad Cities, "2-0203-3D Electromatic Relief Valve did not Operate"
(2020)(IR478917)
Quad Cities, "Electromatic Relief Valve Failed to Stroke"
Quad Cities, "Inadequate Maintenance Risk Assessment" (incident reports
(IR) 4506936)
Quad Cities, "Carousel Lift Over Spent Fuel Pool" (IR 4442806)
Quad Cities, "Forced Normal Reactor Shutdown due to Failure of
Bearings/Bushings and Plunger in Main Steam Relief Valve"
(2006)(IR 219321)
Dresden, "Electromatic Relief Valve Actuator Failed to Actuate During
Surveillance"
Oyster Creek, "EMRV Failed to Open When Operated from the MCR"
Waterford, "Automatic Reactor Trip Occurred While Attempting to Synchronize
a Second Motor Generator Set"
There were some similarities in many of these events, however, the licensee
determined that the issue was not operating experience (OE) preventable due to
differences in the failure mechanism, differences in the equipment, or lack of detail
associated with the previous industry event. The inspectors determined that the
licensee had reasonably considered OE with one potential opportunity when
considering the ERV failure to operate identified in 2020. As identified below, the
licensee entered this potential missed opportunity into their corrective action
program (CAP).
d. Extent of Condition and Cause: The inspectors reviewed the extent of condition
and the extent of cause conducted by the licensee. The inspectors did not identify
any issues associated with the extent of condition review but did question the
scope of the extent of cause. The extent of cause was determined to apply to the
three maintenance groups and the planners as they were the ones who utilized
the engineering change request (ECR) process; therefore, the corrective actions
were restricted to these groups. The inspectors questioned whether engineering
should also be included in this population, as the engineers also initiate and
disposition ECRs as well. This issue was entered into the CAP as IR 04675488,
NRC ID 95001: Formal Engineering Training for ECR Process."
e. Safety Culture: The inspectors reviewed the safety culture evaluation that was
conducted for the root cause and performed an independent assessment by
interviewing plant personnel. These interviews revealed that some plant personnel
believed there is an over emphasis placed on production at the station. One
example shared with inspectors demonstrated that, while senior station leadership
discussed appropriate nuclear safety culture behaviors during plant meetings and
pre-job briefs, they appeared to reward achieving success (i.e., job completion)
regardless of contrary behaviors that were exhibited to achieve that goal. Licensee
staff further stated that supervisory presence in the field was less than ideal, which
results in decreased opportunity for supervisors to set and reinforce standards and
appropriate behaviors.
Although the production-focused mentality was not discussed in the root cause
evaluation associated with the 3B ERV failure, at the time of the 95001 inspection,
the licensee was conducting an additional root cause evaluation associated with
5
CAP 4669057, "Loss of U1 Reactor Vessel System Inventory through CRD
System Vent Valves, which identified the same production-focused mentality that
was raised to the inspectors. This second root cause evaluation has since been
completed and incorporates actions to address the safety culture aspects
identified during the 95001 inspection. Actions to address the mindset of being
overly focused on production are being taken in Root Cause 4669057
documented in corrective actions CA 4669057-51 and CA 4669057-56, both
assigned to the plant manager.
NRC Assessment:
The licensee causal evaluation determined the following root and contributing
causes:
Root Cause 1: Inadequate human performance (HU) behaviors were evident
during the planning and execution of the ERV rebuild.
Root Cause 2: The stations preventive maintenance (PM) structure does not
ensure that all components for OPCC work are tied to PMIDs that facilitate
effective OPCC screening.
Contributing Cause 1: The solenoid actuator rebuild procedure did not contain
adequate procedure guidance or acceptance criteria for correction of upper guide
bracket warping or installation of plunger well plastic guides.
Contributing Cause 2: Lack of communication between electrical
maintenance (EM) first line supervisors (FLS), EM technicians, and EM planners
regarding incorporation of ECR into the work package.
Contributing Cause 3: EM supervisors failed to provide effective oversight of
work affecting quality of safety-related components.
Based upon discussions with licensee staff, there is evidence of a prevailing
mindset which overemphasizes production over the demonstration of nuclear
safety culture behaviors at the station. Personnel also expressed that there is a
lack of supervisors in the field setting and reinforcing high standards and
appropriate behaviors.
While not addressed in the root cause evaluation for the failure of the 3B ERV, as
mentioned above, this was identified by the licensee in Root Cause 4669057
Loss of U1 Reactor Vessel System Inventory through CRD System Vent Valves,
which was ongoing for a subsequent issue. Actions to correct the condition are
being taken in that root cause.
The inspectors identified additional questions in the following areas:
The inspectors questioned whether it would be appropriate to incorporate
design/dimensional clearance checks into the actuator rebuild procedure to
eliminate the possibility of binding. The revisions which had already been
incorporated into the applicable procedures focused on the proper orientation
of the guides. Although this was a contributing cause (Contributing Cause 1)
due to the lack of symmetry in the construction of the guides, it may not
completely address the issue when considering the manufacturing tolerances
of the various components. The licensee entered this into their CAP as
6
The inspectors questioned the actions taken by plant maintenance personnel
utilizing Action Verbs used in the actuator rebuild procedures. Based upon
questions from the inspectors, it was determined that Constellation does not
have a corporate procedure, nor does Quad Cities have a site-specific
procedure in which action verbs are defined. This may have contributed to a
maintenance technician taking inappropriate action based upon the individual's
understanding of what the action verb in the procedure was specifying (verify
vs. ensure). This issue was entered into the licensees CAP as IR 4675200.
The inspectors provided the above feedback to the licensee. All items identified by the
inspectors have been entered into the licensee's CAP. Overall, the inspectors
determined that the causes identified, corrective actions taken by the licensee, and
with the additional items identified by the inspectors, were appropriate for the safety
significance of the issue. The inspectors noted that although the production-focused
mindset at the station was missing from the initial causal evaluation, it was identified
in the subsequent root cause analysis with actions included to correct the condition.
Based upon the initial causal evaluations and the actions from the subsequent root
cause, the inspectors determined that the licensee response was appropriate for the
safety significance of the white finding.
Assessment 95001
3. Corrective Actions
a. Corrective Actions to Preclude Repetition: The inspectors concluded that
corrective actions planned or taken to preclude repetition of the Quad Cities White
performance issue were appropriate, timely, and commensurate with the safety
significance of the issue.
(1) Completed
The corrective actions to preclude repetition have not yet been completed.
(2) Planned
(a) Root Cause #2 for this event was The stations Preventive Maintenance
(PM) structure does not ensure that all components for Operational Critical
Component (OPCC) work are tied to PMIDs that facilitate OPCC
screening. Specifically, the Preventive Maintenance Identification
number (PMID) for ERV actuator rebuild was a standalone PMID which
was not coded as OPCC work. The actuator install was a different PMID
which was screened and coded as OPCC work. The significance being
that OPCC work has additional oversight and reviews performed to ensure
the appropriate quality of work for operationally significant components.
The corrective action to preclude repetition (CAPR) for root cause #2 is to
review PMIDs for critical components which are not appropriately flagged
and either tie them to a parent PMID or to tie them appropriately ensuring
that they are screened and coded properly. (These reviews are being
tracked via separate Action Item Tracking (ACIT) actions for each
department.) The site is tracking this CAPR under action request (AR)
assignment numbers 4539936-33 and 4539936-34, with a due date of
August 10, 2023. The action items tied to the CAPR are to review a list of
7
work item PMIDs for critical components with no Equipment Identification
number (EPN) tagged and add PMID to respective parent PMID via
Preventive Maintenance Modification Request (PMMR), or to generate a
PMMR to tie an EPN with no parent PMID.
An effectiveness review associated with this CAPR is to be completed by
October 27, 2023. The site will conduct a pre-outage (Q2R27)
self-assessment of OPCC screening to determine if all pre-outage and
outage PMIDs for critical components have been screened for potential
OPCC work.
The inspectors determined that implementation of this CAPR was timely
based upon the number of items to be reviewed, as well as completion
time prior to subsequent outages. The timeliness of these actions is related
to the resources needed to complete each item. The action items that feed
into the CAPR have varying due dates reflective of the different work
groups involved. The inspectors determined that the corrective actions
planned or implemented adequately addressed the root and contributing
causes.
When complete, the NRC plans to inspect and assess the planned
corrective action to preclude repetition as identified in ARs 4539936-33
and 4539936-34, which are scheduled for completion on August 10, 2023.
b. Other Corrective Actions:
(1) Completed
(a) The site had already completed some corrective actions prior to the root
cause report being finalized, including corrective actions from the previous
CAP evaluation (CAPE) as well as interim actions from the CAP
associated with the root cause. Those corrective actions included marking
up procedures QCEM 0200-13 and QCEMS 0250-13 to include improved
upper guide bracket installation, inspection, and alignment criteria, as well
as implementing purchase requirements ensuring new plungers meet the
vendor specifications for Cat ID 1441792. These corrective actions were
completed in AR 4330737.
Completed corrective actions related to root cause 1 included submitting
training requests for development of nuclear professionalism training for
delivery to all site personnel and development of targeted training for ERV
rebuilds for electrical maintenance personnel. Due to root cause 1 being
HU related, the site performed a risk assessment and determined no
CAPRs were required. However, the nuclear professionalism training is
intended to address the human performance behaviors for all site
personnel, with additional targeted training for the specific groups involved.
The action to develop the training has been completed although actual
delivery of the training has not yet been completed.
Another completed corrective action was maintenance managers
reinforcing with supervisors and planners their specific roles and
8
responsibilities in implementing the ECR process. This action addressed
contributing cause 2.
To address contributing cause 3, actions were taken to develop a matrix
for review of completed work packages to ensure proper closure
(IRs written, feedback provided). Included in the matrix is a supervisory
peer check and manager review for a period of 2 years.
(2) Planned
(a) The root cause for this event was determined to be inadequate HU
behaviors. No corrective action to preclude repetition (CAPR) was created
for root cause 1 in accordance with licensee procedure PI-AA-125-1001,
Root Cause Analysis Manual, and in alignment with human performance-
based root cause precedent (2443241-04 and 2646772-11), based upon
the following:
i. The root cause is human performance based.
ii. INPO Good Practice 07-006, Human Performance Tools for Managers
and Supervisors, states that there are no reliable corrective actions
that can absolutely prevent recurrence of human error.
iii. Due to the inherent risk of human fallibility, future error cannot be
totally eliminated.
iv. Actions are assigned to strengthen and reinforce the set of tools that
manager, supervisors, and individual contributors can use to help
minimize the frequency and severity of events triggered by active
errors.
v. Effectiveness review is assigned to review results from the corrective
action plan.
As discussed in the section above, training requests were made to deliver nuclear
professionalism training to site personnel to address root cause 1. The site has staggered
completion dates for this training to be delivered to all site personnel to include those already
hired and with consideration for future hires. The site is also tracking a training evaluation
effectiveness review following the initial rollout of the training with a due date of
November 30, 2023.
Additional corrective actions are planned to address root cause 2. One CA is to ensure each
task for ERV actuator rebuild is included as a pre-outage support activity under the outage
work for the actuator installation to ensure correct OPCC screening. Ensuring both the ERV
and the actuator are denoted as critical components along with flagging the respective tasks
for additional OPCC reviews is also planned.
NRC Assessment:
The inspectors determined that the licensees proposed corrective actions were
adequate to address the cause and that these actions are scheduled for completion
by August 10, 2023.
The inspectors determined that overall, the licensees problem identification, causal
analysis, corrective actions taken, corrective actions planned, and IRs entered into
their CAP sufficiently addressed the performance issue that led to the White finding
9
and met the objectives of the IP. While the site does not have a formal completion
plan for the CAPR (Root Cause 2), it is being tracked under AR 4539936. The
inspectors discussed with the licensee the potential for the action items associated
with the CAPR to be resolved with no action taken, which could result in a CAPR with
no actions to correct the significant condition adverse to quality (SCAQ). The licensee
identified in procedure, PI-AA-125, Corrective Action Program Revision 8, that if a
CAPRs scope is changed, which would be the case if no actions were to be taken,
then it is subject to review by MRC and the root cause qualified investigator or
responsible manager. The inspectors identified several potential gaps which the
licensee has entered into their CAP to evaluate and take actions as deemed
necessary. The potential gaps identified include those mentioned previously as well
as the following:
a. IR 4675473 ERV rebuild procedure level of use evaluation - The procedure
utilized to perform the rebuild of the safety-related ERV actuators is reference
use. Inspectors questioned why this would not be a Continuous Use procedure.
The licensee response was that it met the criteria for being a reference use
procedure. Inspectors pointed out that it also appeared to meet the criteria for a
continuous use procedure which would be more limiting and provide additional
controls. The inspectors also pointed out the significant impacts from performing
the work incorrectly (White finding). The licensee initiated the above issue
resolution to evaluate the condition and revise the procedure level of use as
deemed necessary.
b. IR 4675449 NRC ID 95001: ECR Process Gap - The inspectors identified a
potential gap in the ECR process where there is no procedural requirement to tie
a generated ECR to the product needing to be changed. In the example
associated with this event, an ECR was processed and approved, but never
incorporated into the work documents. Relying solely on individuals to
communicate that an ECR was initiated and where it is in the process appears to
be a human performance error trap. The licensee entered this into their CAP as
indicated above.
c. IR 4675446 NRC ID 95001: Incomplete Documentation of Work - the inspectors
identified that Work Order (WO) 4804706-01 indicated that work was performed
on the ERV actuator. However, this was not documented in the work package as
required by attachment 2, and the maintenance procedures. This failure to
document work minimizes the effectiveness of the work package closeout reviews
and downstream work management processes. The licensee entered this issue
into their CAP as indicated above.
d. IR 4675254 NRC ID 95001: Missed Rework Investigation for WO 4768996,
inspectors identified that in March of 2020 when the 3D ERV failed to operate, the
licensee missed a potential opportunity to learn from the event by failing to
recognize that the process required a rework investigation when the 3D failed to
stroke. The licensee performed troubleshooting and additional maintenance on
the 3D ERV valve. This event occurred on the same day as the rework on the 3B
ERV. In both instances, a rework investigation could have provided additional
insights into the issue. The licensee entered this issue into their CAP as indicated
above.
10
e. IR 4675273 NRC ID 95001: WO Missing Key Steps/Critical Steps, the
inspectors determined that the Licensee failed to follow their process and missed
additional potential opportunities to prevent or mitigate the event when they failed
to identify key/critical steps within their work documents. Even though the
licensee failed to identify this work as OPCC work, their process would still
require them to identify key/critical steps in the work instructions, that if performed
incorrectly could have direct consequences and impact the operability of the
component. During their review of the work documents, the inspectors identified
that there were no key/critical steps identified. The licensee entered this issue into
their CAP as indicated above.
Assessment 95001
4. Conclusion:
Inspectors reviewed the licensees corrective actions to address a White finding by
performing a supplemental inspection utilizing Inspection Procedure 95001,
Supplemental Inspection Response to Action Matrix Column 2 Inputs, at Quad
Cities, Unit 2 in accordance with the reactor oversight process.
During the inspection, inspectors identified 4 potential additional issues of concern
associated with 10 CFR 50, Appendix B, Criterion V; however, these were further
examples similar to, and associated with, those already captured in the White finding
and notice of violation (NOV) documented in NRC Inspection
Report 05000254/2022091 and 05000265/2022091. Therefore, it was determined that
no additional inspection was required to further assess those examples as they were
already covered by the existing documented NOV.
The inspectors determined that the licensees problem identification, causal analysis,
corrective actions in place, and the IRs entered into their CAP sufficiently addressed
the performance issues that were identified. The inspectors determined that the
inspection objectives as listed in IP 95001 were met, and that the corrective actions
taken and planned adequately addressed the White finding and associated NOV.
Therefore, in accordance with IMC 0305, this action matrix input will be CLOSED and
no longer considered.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On May 4, 2023, the inspectors presented the 95001 supplemental inspection results to
Drew Griffith, Plant Manager, and other members of the licensee staff.
11
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
95001 Corrective Action CAPE 4330737 ERV 2-0203-3D Did Not Actuate 04/24/2020
Documents CAPE 4486294 ERV 2-0203-3B Relief Valve Failed to Actuate 04/18/2022
RCR 04669057 Loss of U1 Reactor Vessel System Inventory through CRD 05/24/2023
System Vent Valves
RCR 4539936 Quad Cities Unit 2 3B ERV Failure Event 01/31/2023
Engineering QDC-76517 Failure Analysis of: 3B Electromatic Relief Valve Solenoid 1
Evaluations Actuator
Procedures CC-AA-101 ENGINEERING CHANGE REQUESTS (ER) 7
HU-AA-101 HUMAN PERFORMANCE TOOLS AND VERIFICATION 14
PRACTICES
HU-AA-104-101 PROCEDURE USE AND ADHERENCE 7
MA-AA-1000- KEY STEP PROCESS 0
1001
MA-AA-716-003 TOOL POUCH / MINOR MAINTENANCE 13
MA-AA-716-010- OPERATIONAL CRITICAL COMPONENT WORK (OPCCW) 9
1015 PROCESS
PI-AA-125 CORRECTIVE ACTION PROGRAM (CAP) PROCEDURE 8
PI-AA-125-1003 ROOT CAUSE ANALYSIS MANUAL 6
QCEM 0200-13 DRESSER ELECTROMATIC SOLENOID ACTUATOR 0
REBUILD INSTRUCTIONS
QCEM 0200-13 DRESSER ELECTROMATIC SOLENOID ACTUATOR 10
REBUILD INSTRUCTIONS
QCEM 0200-13 DRESSER ELECTROMATIC SOLENOID ACTUATOR 11
REBUILD INSTRUCTIONS
QCEM 0200-13 DRESSER ELECTROMATIC SOLENOID ACTUATOR 12
REBUILD INSTRUCTIONS
QCEM 0200-13 DRESSER ELECTROMATIC SOLENOID ACTUATOR 13
REBUILD INSTRUCTIONS
QCEMS 0250-13 DRESSER ELECTROMATIC SOLENOID ACTUATOR 30
INSTALLATION, REPLACEMENT, INSPECTION, AND EQ
SURVEILLANCE
QCEMS 0250-13 DRESSER ELECTROMATIC SOLENOID ACTUATOR 31
12
Inspection Type Designation Description or Title Revision or
Procedure Date
INSTALLATION, REPLACEMENT, INSPECTION, AND EQ
SURVEILLANCE
QCEMS 0250-13 DRESSER ELECTROMATIC SOLENOID ACTUATOR 32
INSTALLATION, REPLACEMENT, INSPECTION, AND EQ
SURVEILLANCE
QCEMS 0250-13 DRESSER ELECTROMATIC SOLENOID ACTUATOR 33
INSTALLATION, REPLACEMENT, INSPECTION, AND EQ
SURVEILLANCE
Work Orders QCEMS 0250-13 DRESSER ELECTROMATIC SOLENOID ACTUATOR 03/01/2020
INSTALLATION, REPLACEMENT, INSPECTION, AND EQ
SURVEILLANCE
WO 04804706 INSPECT/REPAIR SPARE ERV ACTUATORS 03/20/2020
PREOUTAGE (EQ)
WO 04912065 INSPECT AND REPAIR SPARE ERV ACTUATORS PRE- 03/02/2021
OUTAGE (EQ)
WO 4766980 Stroke ERV 2-203-3D 3 Times at Beginning of Refuel 03/24/2020
Outages
WO 4800206 Dresser Electromatic Solenoid Actuator Insp (EQ) 01/17/2020
13