Category:INSPECTION REPORT
MONTHYEARIR 05000254/19990011999-10-0707 October 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990721-0908.No Violations Noted.Major Areas Inspected:Initiating Events, Mitigating Sys & Barrier Integrity IR 05000254/19990171999-09-15015 September 1999 Insp Repts 50-254/99-17 & 50-265/99-17 on 990823-27.No Violations Noted.Major Areas Inspected:Pilot Baseline Insp for Annual Review of Changes to Safety Analysis Rept & Biennial Review Permanent Plant Mod IR 05000254/19990161999-09-0909 September 1999 Errata to Insp Repts 50-254/99-16 & 50-265/99-16 Conducted on 990819.Administrative Error Was Corrected on Page 8 of Subj Rept.One Open Item Was Deleted & re-numbering of Two Other Items Were Identified IR 05000254/19990151999-08-25025 August 1999 Insp Repts 50-254/99-15 & 50-265/99-15 on 990816-20.No Violations Noted.Major Areas Inspected:Maint Rule Implementation IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site ML20211D2031999-08-19019 August 1999 Insp Repts 50-254/99-16 & 50-265/99-16 on 990719-22. Violations Noted.Major Areas Inspected:Physical Protection Cornerstone,Including Review of Access Authoization Program & Changes to Security Plan IR 05000254/19990121999-08-13013 August 1999 Insp Repts 50-254/99-12 & 50-265/99-12 on 990628-0716. Violations Noted.Major Areas Inspected:Corrective Action Process Which Included Methods Used for Identification, Cause Investigation & Correction of Quality Related Items IR 05000254/19990111999-08-13013 August 1999 Insp Repts 50-254/99-11 & 50-265/99-11 on 990601-0720.NCVs Noted.Major Areas Inspected:Performance in Initiating Events,Mitigating Sys,Barrier Integrity Cornerstones & Performance Indicator Verification IR 05000254/19990141999-07-30030 July 1999 Insp Repts 50-254/99-14 & 50-265/99-14 on 990713-15.One Violation Noted & Treated as Ncv.Major Areas Inspected: Heat Sink Performance,Which Covers Inspectable Area Under Initiating Events & Mitigation Sys IR 05000254/19990131999-07-29029 July 1999 Insp Repts 50-254/99-13 & 50-265/99-13 on 990628-0702.No Violations Noted.Major Areas Inspected:Public Radiation Safety & Review of Gaseous & Liquid Radiological Effluents & of Radiological Environmental Monitoring Program IR 05000254/19990091999-06-23023 June 1999 Insp Repts 50-254/99-09 & 50-265/99-09 on 990421-0531.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000254/19990061999-05-14014 May 1999 Insp Repts 50-254/99-06 & 50-265/99-06 on 990307-0420.Three Violations Noted & Being Treated as non-cited Violations. Major Areas Insptected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000254/19990081999-05-11011 May 1999 Insp Repts 50-254/99-08 & 50-265/99-08 on 990419-23.No Violations Noted.Major Areas Inspected:Adequacy of Licensee Programs,Procedures,Training & Supporting Documentation IR 05000254/19990031999-04-0909 April 1999 Insp Repts 50-254/99-03 & 50-265/99-03 on 990308-12.No Violations Noted.Major Areas Inspected:Maint & Engineering ML20205J2951999-04-0101 April 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990121-0306. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19990071999-03-31031 March 1999 Radiation Protection Insp Repts 50-254/99-07 & 50-265/99-07 on 990309-12.No Violations Noted.Major Areas Inspected:Solid Radwaste Processing & Control Program & Radioactive Matls Shipping Program IR 05000254/19980211999-03-0505 March 1999 Insp Repts 50-254/98-21 & 50-265/98-21 on 981112-1218. Violation Noted:Major Areas Inspected:Isi Activities at Plant During Refueling Outage 15 IR 05000254/19990041999-02-26026 February 1999 Insp Repts 50-254/99-04 & 50-265/99-04 on 990201-05.No Violations Noted.Major Areas Inspected:Emergency Prepardeness Program as Aspect of Plant Support IR 05000254/19990021999-02-25025 February 1999 Insp Repts 50-254/99-02 & 50-265/99-02 on 990125-29.No Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Program Included Water Chemistry Control, Instrument Quality Control & internal-lab Comparison ML20199E9431999-01-14014 January 1999 Partially Withheld Security Insp Repts 50-254/98-24 & 50-265/98-24.Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Quad Cities Facility.Details Withheld (Ref 10CFR2.790) IR 05000254/19980201998-12-28028 December 1998 Insp Repts 50-254/98-20 & 50-265/98-20 on 981014-1201.No Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000254/19980221998-12-28028 December 1998 Insp Repts 50-254/98-22 & 50-265/98-22 on 981130-1204.No Violations Noted.Major Areas Inspected:Radiation Protection Staff Preparation for Q1R15 Refueling Outage,Including Review of ALARA Planning & Work Plan Integration IR 05000254/19980191998-12-18018 December 1998 Insp Repts 50-254/98-19 & 50-265/98-19 on 981019-1106. Violations Noted.Major Areas Inspected:Effectiveness of Engineering & Technical Support Provided to Plant in Performance of Routine & Reactive Site Activities IR 05000254/19980171998-11-0505 November 1998 Insp Repts 50-254/98-17 & 50-265/98-17 on 980902-1014.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19980181998-10-15015 October 1998 Partially Withheld Insp Repts 50-254/98-18 & 50-265/98-18 on 980914-18 (Ref 10CFR73.71).No Violations Identified.Major Areas Inspected:Review of Plant Support Activities,Security Activities Re Onsite Personnel Access & Communications IR 05000254/19980131998-09-22022 September 1998 Insp Repts 50-254/98-13 & 50-265/98-13 on 980716-0901.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980141998-09-17017 September 1998 Insp Repts 50-254/98-14 & 50-265/98-14 on 980825-28.No Violations Noted.Major Areas Inspected:Evaluation of Licensee Performance During Plant Biennial Exercise of Emergency Plan IR 05000254/19980161998-09-0404 September 1998 Insp Repts 50-254/98-16 & 50-265/98-16 on 980810-14.No Violations Noted.Major Areas Inspected:Radiation Protection Program Included External & Internal Exposure Control,Whole Body Counting & Contamination & Survey Monitoring Program IR 05000254/19980121998-08-11011 August 1998 Insp Repts 50-254/98-12 & 50-265/98-12 on 980529-0716. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000254/19980151998-07-31031 July 1998 Insp Repts 50-254/98-15 & 50-265/98-15 on 980721-24.No Violations Noted.Major Areas Inspected:Aspects of Licensee Corrective Actions & Engineering Involvement in Corrective Actions Process IR 05000254/19980111998-07-0202 July 1998 Insp Repts 50-254/98-11 & 50-265/98-11 on 980504-22. Violations Noted.Major Areas Inspected:Quad Cities Safe Shutdown Analysis & Supporting Procedures IR 05000254/19980091998-07-0202 July 1998 Insp Repts 50-254/98-09 & 50-265/98-09 on 980401-0529. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980081998-05-11011 May 1998 Insp Repts 50-254/98-08 & 50-265/98-08 on 980407-09 & 14-17. No Violations Noted.Major Areas Inspected:Maint,Quality Assurance & Engineering IR 05000254/19982011998-05-0606 May 1998 Insp Repts 50-254/98-201 & 50-265/98-201 on 980216-0327.No Violations Noted.Major Areas Inspected:Evaluation of Capability of Selected Sys to Perform Safety Functions Required by Design Bases IR 05000254/19980101998-05-0606 May 1998 Insp Repts 50-254/98-10 & 50-265/98-10 on 980413-17.No Violations Noted.Major Areas Inspected:Liquid & Gaseous Effluent Programs,Annual Effluent Rept,Continuous Air & Area Radiation Monitors ML20217G3401998-04-23023 April 1998 Insp Repts 50-254/98-04 & 50-265/98-04 on 980211-0331. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support ML20217G2481998-04-23023 April 1998 Insp Repts 50-254/98-05 & 50-265/98-05 on 980216-0326. Violations Noted.Major Areas Inspected:Engineering,Including Allowances for Development of Emergency & Immediate Mods IR 05000254/19980071998-04-22022 April 1998 Insp Repts 50-254/98-07 & 50-265/98-07 on 980330-0403.No Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Plant,Adequacy of Security Procedures & Event Logs ML20216C2601998-03-0606 March 1998 Insp Repts 50-254/97-28 & 50-265/97-28 on 971224-980210. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering ML20202G3071998-02-13013 February 1998 Insp Repts 50-254/97-22 & 50-265/97-22 on 971027-1121. Violations Noted.Major Areas Inspected:Hpci Sys Operational Performance for Operations,Maintenance & Engineering ML20202B0501998-02-0505 February 1998 Insp Repts 50-254/98-02 & 50-265/98-02 on 980112-16. Violations Noted.Major Areas Inspected:Review of ALARA Planning,Radiation Work Permits & Observations of Radworker Performance ML20198T5071998-01-21021 January 1998 Insp Repts 50-254/97-26 & 50-265/97-26 on 971103-1223. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19970241998-01-13013 January 1998 Insp Repts 50-254/97-24 & 50-265/97-24 on 971124-1202.No Violations Noted.Major Areas Inspected:Licensed RO & SRO Requalification Training Programs ML20197F5741997-12-23023 December 1997 Insp Repts 50-254/97-27 & 50-265/97-27 on 971103-07 & 1204. Violations Noted.Major Areas Inspected:Maint & Engineering ML20197B2641997-12-16016 December 1997 Insp Repts 50-254/97-14 & 50-265/97-14 on 970729-0922.NOV & Deviations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support Re Troubleshooting Resulting in Discovery of Long Standing Problem W/Fire Pump IR 05000254/19970251997-12-0909 December 1997 Insp Repts 50-254/97-25 & 50-265/97-25 on 971103-07.No Violations Noted.Major Areas Inspected:Respiratory Protection Plan,Source Term Reduction Efforts & Follow Up on Several Open Items IR 05000254/19970211997-12-0909 December 1997 Insp Repts 50-254/97-21 & 50-265/97-21 on 970923-1103.No Violations Noted.Major Areas Inspected:Operation,Maint, Engineering & Plant Support IR 05000254/19970191997-11-18018 November 1997 Insp Repts 50-254/97-19 & 50-265/97-19 on 971006-10.No Violations Noted.Major Areas Inspected:Ep Program IR 05000254/19970181997-11-10010 November 1997 Insp Repts 50-254/97-18 & 50-265/97-18 on 970922-25. Violations Noted.Major Areas Inspected:Maintenance & Engineering IR 05000254/19970161997-11-0505 November 1997 Insp Repts 50-254/97-16 & 50-265/97-16 on 970825-29. Violations Noted.Major Areas Inspected:Fire Protection Program & Several App R Issues 1999-09-09
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000254/19990011999-10-0707 October 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990721-0908.No Violations Noted.Major Areas Inspected:Initiating Events, Mitigating Sys & Barrier Integrity IR 05000254/19990171999-09-15015 September 1999 Insp Repts 50-254/99-17 & 50-265/99-17 on 990823-27.No Violations Noted.Major Areas Inspected:Pilot Baseline Insp for Annual Review of Changes to Safety Analysis Rept & Biennial Review Permanent Plant Mod IR 05000254/19990161999-09-0909 September 1999 Errata to Insp Repts 50-254/99-16 & 50-265/99-16 Conducted on 990819.Administrative Error Was Corrected on Page 8 of Subj Rept.One Open Item Was Deleted & re-numbering of Two Other Items Were Identified IR 05000254/19990151999-08-25025 August 1999 Insp Repts 50-254/99-15 & 50-265/99-15 on 990816-20.No Violations Noted.Major Areas Inspected:Maint Rule Implementation IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site ML20211D2031999-08-19019 August 1999 Insp Repts 50-254/99-16 & 50-265/99-16 on 990719-22. Violations Noted.Major Areas Inspected:Physical Protection Cornerstone,Including Review of Access Authoization Program & Changes to Security Plan IR 05000254/19990121999-08-13013 August 1999 Insp Repts 50-254/99-12 & 50-265/99-12 on 990628-0716. Violations Noted.Major Areas Inspected:Corrective Action Process Which Included Methods Used for Identification, Cause Investigation & Correction of Quality Related Items IR 05000254/19990111999-08-13013 August 1999 Insp Repts 50-254/99-11 & 50-265/99-11 on 990601-0720.NCVs Noted.Major Areas Inspected:Performance in Initiating Events,Mitigating Sys,Barrier Integrity Cornerstones & Performance Indicator Verification IR 05000254/19990141999-07-30030 July 1999 Insp Repts 50-254/99-14 & 50-265/99-14 on 990713-15.One Violation Noted & Treated as Ncv.Major Areas Inspected: Heat Sink Performance,Which Covers Inspectable Area Under Initiating Events & Mitigation Sys IR 05000254/19990131999-07-29029 July 1999 Insp Repts 50-254/99-13 & 50-265/99-13 on 990628-0702.No Violations Noted.Major Areas Inspected:Public Radiation Safety & Review of Gaseous & Liquid Radiological Effluents & of Radiological Environmental Monitoring Program IR 05000254/19990091999-06-23023 June 1999 Insp Repts 50-254/99-09 & 50-265/99-09 on 990421-0531.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000254/19990061999-05-14014 May 1999 Insp Repts 50-254/99-06 & 50-265/99-06 on 990307-0420.Three Violations Noted & Being Treated as non-cited Violations. Major Areas Insptected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000254/19990081999-05-11011 May 1999 Insp Repts 50-254/99-08 & 50-265/99-08 on 990419-23.No Violations Noted.Major Areas Inspected:Adequacy of Licensee Programs,Procedures,Training & Supporting Documentation IR 05000254/19990031999-04-0909 April 1999 Insp Repts 50-254/99-03 & 50-265/99-03 on 990308-12.No Violations Noted.Major Areas Inspected:Maint & Engineering ML20205J2951999-04-0101 April 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990121-0306. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19990071999-03-31031 March 1999 Radiation Protection Insp Repts 50-254/99-07 & 50-265/99-07 on 990309-12.No Violations Noted.Major Areas Inspected:Solid Radwaste Processing & Control Program & Radioactive Matls Shipping Program IR 05000254/19980211999-03-0505 March 1999 Insp Repts 50-254/98-21 & 50-265/98-21 on 981112-1218. Violation Noted:Major Areas Inspected:Isi Activities at Plant During Refueling Outage 15 IR 05000254/19990041999-02-26026 February 1999 Insp Repts 50-254/99-04 & 50-265/99-04 on 990201-05.No Violations Noted.Major Areas Inspected:Emergency Prepardeness Program as Aspect of Plant Support IR 05000254/19990021999-02-25025 February 1999 Insp Repts 50-254/99-02 & 50-265/99-02 on 990125-29.No Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Program Included Water Chemistry Control, Instrument Quality Control & internal-lab Comparison ML20199E9431999-01-14014 January 1999 Partially Withheld Security Insp Repts 50-254/98-24 & 50-265/98-24.Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Quad Cities Facility.Details Withheld (Ref 10CFR2.790) IR 05000254/19980201998-12-28028 December 1998 Insp Repts 50-254/98-20 & 50-265/98-20 on 981014-1201.No Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000254/19980221998-12-28028 December 1998 Insp Repts 50-254/98-22 & 50-265/98-22 on 981130-1204.No Violations Noted.Major Areas Inspected:Radiation Protection Staff Preparation for Q1R15 Refueling Outage,Including Review of ALARA Planning & Work Plan Integration IR 05000254/19980191998-12-18018 December 1998 Insp Repts 50-254/98-19 & 50-265/98-19 on 981019-1106. Violations Noted.Major Areas Inspected:Effectiveness of Engineering & Technical Support Provided to Plant in Performance of Routine & Reactive Site Activities IR 05000254/19980171998-11-0505 November 1998 Insp Repts 50-254/98-17 & 50-265/98-17 on 980902-1014.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19980181998-10-15015 October 1998 Partially Withheld Insp Repts 50-254/98-18 & 50-265/98-18 on 980914-18 (Ref 10CFR73.71).No Violations Identified.Major Areas Inspected:Review of Plant Support Activities,Security Activities Re Onsite Personnel Access & Communications IR 05000254/19980131998-09-22022 September 1998 Insp Repts 50-254/98-13 & 50-265/98-13 on 980716-0901.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980141998-09-17017 September 1998 Insp Repts 50-254/98-14 & 50-265/98-14 on 980825-28.No Violations Noted.Major Areas Inspected:Evaluation of Licensee Performance During Plant Biennial Exercise of Emergency Plan IR 05000254/19980161998-09-0404 September 1998 Insp Repts 50-254/98-16 & 50-265/98-16 on 980810-14.No Violations Noted.Major Areas Inspected:Radiation Protection Program Included External & Internal Exposure Control,Whole Body Counting & Contamination & Survey Monitoring Program IR 05000254/19980121998-08-11011 August 1998 Insp Repts 50-254/98-12 & 50-265/98-12 on 980529-0716. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000254/19980151998-07-31031 July 1998 Insp Repts 50-254/98-15 & 50-265/98-15 on 980721-24.No Violations Noted.Major Areas Inspected:Aspects of Licensee Corrective Actions & Engineering Involvement in Corrective Actions Process IR 05000254/19980111998-07-0202 July 1998 Insp Repts 50-254/98-11 & 50-265/98-11 on 980504-22. Violations Noted.Major Areas Inspected:Quad Cities Safe Shutdown Analysis & Supporting Procedures IR 05000254/19980091998-07-0202 July 1998 Insp Repts 50-254/98-09 & 50-265/98-09 on 980401-0529. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980081998-05-11011 May 1998 Insp Repts 50-254/98-08 & 50-265/98-08 on 980407-09 & 14-17. No Violations Noted.Major Areas Inspected:Maint,Quality Assurance & Engineering IR 05000254/19982011998-05-0606 May 1998 Insp Repts 50-254/98-201 & 50-265/98-201 on 980216-0327.No Violations Noted.Major Areas Inspected:Evaluation of Capability of Selected Sys to Perform Safety Functions Required by Design Bases IR 05000254/19980101998-05-0606 May 1998 Insp Repts 50-254/98-10 & 50-265/98-10 on 980413-17.No Violations Noted.Major Areas Inspected:Liquid & Gaseous Effluent Programs,Annual Effluent Rept,Continuous Air & Area Radiation Monitors ML20217G3401998-04-23023 April 1998 Insp Repts 50-254/98-04 & 50-265/98-04 on 980211-0331. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support ML20217G2481998-04-23023 April 1998 Insp Repts 50-254/98-05 & 50-265/98-05 on 980216-0326. Violations Noted.Major Areas Inspected:Engineering,Including Allowances for Development of Emergency & Immediate Mods IR 05000254/19980071998-04-22022 April 1998 Insp Repts 50-254/98-07 & 50-265/98-07 on 980330-0403.No Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Plant,Adequacy of Security Procedures & Event Logs ML20216C2601998-03-0606 March 1998 Insp Repts 50-254/97-28 & 50-265/97-28 on 971224-980210. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering ML20202G3071998-02-13013 February 1998 Insp Repts 50-254/97-22 & 50-265/97-22 on 971027-1121. Violations Noted.Major Areas Inspected:Hpci Sys Operational Performance for Operations,Maintenance & Engineering ML20202B0501998-02-0505 February 1998 Insp Repts 50-254/98-02 & 50-265/98-02 on 980112-16. Violations Noted.Major Areas Inspected:Review of ALARA Planning,Radiation Work Permits & Observations of Radworker Performance ML20198T5071998-01-21021 January 1998 Insp Repts 50-254/97-26 & 50-265/97-26 on 971103-1223. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19970241998-01-13013 January 1998 Insp Repts 50-254/97-24 & 50-265/97-24 on 971124-1202.No Violations Noted.Major Areas Inspected:Licensed RO & SRO Requalification Training Programs ML20197F5741997-12-23023 December 1997 Insp Repts 50-254/97-27 & 50-265/97-27 on 971103-07 & 1204. Violations Noted.Major Areas Inspected:Maint & Engineering ML20197B2641997-12-16016 December 1997 Insp Repts 50-254/97-14 & 50-265/97-14 on 970729-0922.NOV & Deviations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support Re Troubleshooting Resulting in Discovery of Long Standing Problem W/Fire Pump IR 05000254/19970251997-12-0909 December 1997 Insp Repts 50-254/97-25 & 50-265/97-25 on 971103-07.No Violations Noted.Major Areas Inspected:Respiratory Protection Plan,Source Term Reduction Efforts & Follow Up on Several Open Items IR 05000254/19970211997-12-0909 December 1997 Insp Repts 50-254/97-21 & 50-265/97-21 on 970923-1103.No Violations Noted.Major Areas Inspected:Operation,Maint, Engineering & Plant Support IR 05000254/19970191997-11-18018 November 1997 Insp Repts 50-254/97-19 & 50-265/97-19 on 971006-10.No Violations Noted.Major Areas Inspected:Ep Program IR 05000254/19970181997-11-10010 November 1997 Insp Repts 50-254/97-18 & 50-265/97-18 on 970922-25. Violations Noted.Major Areas Inspected:Maintenance & Engineering IR 05000254/19970161997-11-0505 November 1997 Insp Repts 50-254/97-16 & 50-265/97-16 on 970825-29. Violations Noted.Major Areas Inspected:Fire Protection Program & Several App R Issues 1999-09-09
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000254/19990011999-10-0707 October 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990721-0908.No Violations Noted.Major Areas Inspected:Initiating Events, Mitigating Sys & Barrier Integrity IR 05000254/19990171999-09-15015 September 1999 Insp Repts 50-254/99-17 & 50-265/99-17 on 990823-27.No Violations Noted.Major Areas Inspected:Pilot Baseline Insp for Annual Review of Changes to Safety Analysis Rept & Biennial Review Permanent Plant Mod IR 05000254/19990161999-09-0909 September 1999 Errata to Insp Repts 50-254/99-16 & 50-265/99-16 Conducted on 990819.Administrative Error Was Corrected on Page 8 of Subj Rept.One Open Item Was Deleted & re-numbering of Two Other Items Were Identified IR 05000254/19990151999-08-25025 August 1999 Insp Repts 50-254/99-15 & 50-265/99-15 on 990816-20.No Violations Noted.Major Areas Inspected:Maint Rule Implementation IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site ML20211D2031999-08-19019 August 1999 Insp Repts 50-254/99-16 & 50-265/99-16 on 990719-22. Violations Noted.Major Areas Inspected:Physical Protection Cornerstone,Including Review of Access Authoization Program & Changes to Security Plan IR 05000254/19990121999-08-13013 August 1999 Insp Repts 50-254/99-12 & 50-265/99-12 on 990628-0716. Violations Noted.Major Areas Inspected:Corrective Action Process Which Included Methods Used for Identification, Cause Investigation & Correction of Quality Related Items IR 05000254/19990111999-08-13013 August 1999 Insp Repts 50-254/99-11 & 50-265/99-11 on 990601-0720.NCVs Noted.Major Areas Inspected:Performance in Initiating Events,Mitigating Sys,Barrier Integrity Cornerstones & Performance Indicator Verification IR 05000254/19990141999-07-30030 July 1999 Insp Repts 50-254/99-14 & 50-265/99-14 on 990713-15.One Violation Noted & Treated as Ncv.Major Areas Inspected: Heat Sink Performance,Which Covers Inspectable Area Under Initiating Events & Mitigation Sys IR 05000254/19990131999-07-29029 July 1999 Insp Repts 50-254/99-13 & 50-265/99-13 on 990628-0702.No Violations Noted.Major Areas Inspected:Public Radiation Safety & Review of Gaseous & Liquid Radiological Effluents & of Radiological Environmental Monitoring Program IR 05000254/19990091999-06-23023 June 1999 Insp Repts 50-254/99-09 & 50-265/99-09 on 990421-0531.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000254/19990061999-05-14014 May 1999 Insp Repts 50-254/99-06 & 50-265/99-06 on 990307-0420.Three Violations Noted & Being Treated as non-cited Violations. Major Areas Insptected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000254/19990081999-05-11011 May 1999 Insp Repts 50-254/99-08 & 50-265/99-08 on 990419-23.No Violations Noted.Major Areas Inspected:Adequacy of Licensee Programs,Procedures,Training & Supporting Documentation IR 05000254/19990031999-04-0909 April 1999 Insp Repts 50-254/99-03 & 50-265/99-03 on 990308-12.No Violations Noted.Major Areas Inspected:Maint & Engineering ML20205J2951999-04-0101 April 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990121-0306. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19990071999-03-31031 March 1999 Radiation Protection Insp Repts 50-254/99-07 & 50-265/99-07 on 990309-12.No Violations Noted.Major Areas Inspected:Solid Radwaste Processing & Control Program & Radioactive Matls Shipping Program IR 05000254/19980211999-03-0505 March 1999 Insp Repts 50-254/98-21 & 50-265/98-21 on 981112-1218. Violation Noted:Major Areas Inspected:Isi Activities at Plant During Refueling Outage 15 IR 05000254/19990041999-02-26026 February 1999 Insp Repts 50-254/99-04 & 50-265/99-04 on 990201-05.No Violations Noted.Major Areas Inspected:Emergency Prepardeness Program as Aspect of Plant Support IR 05000254/19990021999-02-25025 February 1999 Insp Repts 50-254/99-02 & 50-265/99-02 on 990125-29.No Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Program Included Water Chemistry Control, Instrument Quality Control & internal-lab Comparison ML20199E9431999-01-14014 January 1999 Partially Withheld Security Insp Repts 50-254/98-24 & 50-265/98-24.Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Quad Cities Facility.Details Withheld (Ref 10CFR2.790) IR 05000254/19980201998-12-28028 December 1998 Insp Repts 50-254/98-20 & 50-265/98-20 on 981014-1201.No Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000254/19980221998-12-28028 December 1998 Insp Repts 50-254/98-22 & 50-265/98-22 on 981130-1204.No Violations Noted.Major Areas Inspected:Radiation Protection Staff Preparation for Q1R15 Refueling Outage,Including Review of ALARA Planning & Work Plan Integration IR 05000254/19980191998-12-18018 December 1998 Insp Repts 50-254/98-19 & 50-265/98-19 on 981019-1106. Violations Noted.Major Areas Inspected:Effectiveness of Engineering & Technical Support Provided to Plant in Performance of Routine & Reactive Site Activities IR 05000254/19980171998-11-0505 November 1998 Insp Repts 50-254/98-17 & 50-265/98-17 on 980902-1014.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19980181998-10-15015 October 1998 Partially Withheld Insp Repts 50-254/98-18 & 50-265/98-18 on 980914-18 (Ref 10CFR73.71).No Violations Identified.Major Areas Inspected:Review of Plant Support Activities,Security Activities Re Onsite Personnel Access & Communications IR 05000254/19980131998-09-22022 September 1998 Insp Repts 50-254/98-13 & 50-265/98-13 on 980716-0901.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980141998-09-17017 September 1998 Insp Repts 50-254/98-14 & 50-265/98-14 on 980825-28.No Violations Noted.Major Areas Inspected:Evaluation of Licensee Performance During Plant Biennial Exercise of Emergency Plan IR 05000254/19980161998-09-0404 September 1998 Insp Repts 50-254/98-16 & 50-265/98-16 on 980810-14.No Violations Noted.Major Areas Inspected:Radiation Protection Program Included External & Internal Exposure Control,Whole Body Counting & Contamination & Survey Monitoring Program IR 05000254/19980121998-08-11011 August 1998 Insp Repts 50-254/98-12 & 50-265/98-12 on 980529-0716. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000254/19980151998-07-31031 July 1998 Insp Repts 50-254/98-15 & 50-265/98-15 on 980721-24.No Violations Noted.Major Areas Inspected:Aspects of Licensee Corrective Actions & Engineering Involvement in Corrective Actions Process IR 05000254/19980111998-07-0202 July 1998 Insp Repts 50-254/98-11 & 50-265/98-11 on 980504-22. Violations Noted.Major Areas Inspected:Quad Cities Safe Shutdown Analysis & Supporting Procedures IR 05000254/19980091998-07-0202 July 1998 Insp Repts 50-254/98-09 & 50-265/98-09 on 980401-0529. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980081998-05-11011 May 1998 Insp Repts 50-254/98-08 & 50-265/98-08 on 980407-09 & 14-17. No Violations Noted.Major Areas Inspected:Maint,Quality Assurance & Engineering IR 05000254/19982011998-05-0606 May 1998 Insp Repts 50-254/98-201 & 50-265/98-201 on 980216-0327.No Violations Noted.Major Areas Inspected:Evaluation of Capability of Selected Sys to Perform Safety Functions Required by Design Bases IR 05000254/19980101998-05-0606 May 1998 Insp Repts 50-254/98-10 & 50-265/98-10 on 980413-17.No Violations Noted.Major Areas Inspected:Liquid & Gaseous Effluent Programs,Annual Effluent Rept,Continuous Air & Area Radiation Monitors ML20217G3401998-04-23023 April 1998 Insp Repts 50-254/98-04 & 50-265/98-04 on 980211-0331. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support ML20217G2481998-04-23023 April 1998 Insp Repts 50-254/98-05 & 50-265/98-05 on 980216-0326. Violations Noted.Major Areas Inspected:Engineering,Including Allowances for Development of Emergency & Immediate Mods IR 05000254/19980071998-04-22022 April 1998 Insp Repts 50-254/98-07 & 50-265/98-07 on 980330-0403.No Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Plant,Adequacy of Security Procedures & Event Logs ML20216C2601998-03-0606 March 1998 Insp Repts 50-254/97-28 & 50-265/97-28 on 971224-980210. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering ML20202G3071998-02-13013 February 1998 Insp Repts 50-254/97-22 & 50-265/97-22 on 971027-1121. Violations Noted.Major Areas Inspected:Hpci Sys Operational Performance for Operations,Maintenance & Engineering ML20202B0501998-02-0505 February 1998 Insp Repts 50-254/98-02 & 50-265/98-02 on 980112-16. Violations Noted.Major Areas Inspected:Review of ALARA Planning,Radiation Work Permits & Observations of Radworker Performance ML20198T5071998-01-21021 January 1998 Insp Repts 50-254/97-26 & 50-265/97-26 on 971103-1223. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19970241998-01-13013 January 1998 Insp Repts 50-254/97-24 & 50-265/97-24 on 971124-1202.No Violations Noted.Major Areas Inspected:Licensed RO & SRO Requalification Training Programs ML20197F5741997-12-23023 December 1997 Insp Repts 50-254/97-27 & 50-265/97-27 on 971103-07 & 1204. Violations Noted.Major Areas Inspected:Maint & Engineering ML20197B2641997-12-16016 December 1997 Insp Repts 50-254/97-14 & 50-265/97-14 on 970729-0922.NOV & Deviations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support Re Troubleshooting Resulting in Discovery of Long Standing Problem W/Fire Pump IR 05000254/19970251997-12-0909 December 1997 Insp Repts 50-254/97-25 & 50-265/97-25 on 971103-07.No Violations Noted.Major Areas Inspected:Respiratory Protection Plan,Source Term Reduction Efforts & Follow Up on Several Open Items IR 05000254/19970211997-12-0909 December 1997 Insp Repts 50-254/97-21 & 50-265/97-21 on 970923-1103.No Violations Noted.Major Areas Inspected:Operation,Maint, Engineering & Plant Support IR 05000254/19970191997-11-18018 November 1997 Insp Repts 50-254/97-19 & 50-265/97-19 on 971006-10.No Violations Noted.Major Areas Inspected:Ep Program IR 05000254/19970181997-11-10010 November 1997 Insp Repts 50-254/97-18 & 50-265/97-18 on 970922-25. Violations Noted.Major Areas Inspected:Maintenance & Engineering IR 05000254/19970161997-11-0505 November 1997 Insp Repts 50-254/97-16 & 50-265/97-16 on 970825-29. Violations Noted.Major Areas Inspected:Fire Protection Program & Several App R Issues 1999-09-09
[Table view] Category:UTILITY
MONTHYEARIR 05000254/19900141990-10-0404 October 1990 Insp Repts 50-254/90-14 & 50-265/90-14 on 900805-0915. Violations Noted.Major Areas Inspected:Ler Review,Regional Request,Followup on TMI Action Items,Operational Safety Verification,Esf Sys & Monthly Maint Observations IR 05000254/19900101990-08-14014 August 1990 Insp Repts 50-254/90-10 & 50-265/90-10 on 900605-0802. Violations Noted.Major Areas Inspected:Allegation That 1/2 Emergency Diesel Generator Cooling Pump Could Not Fulfill Cooling of Diesel & ECCS Room Coolers IR 05000254/19900111990-07-13013 July 1990 Insp Repts 50-254/90-11 & 50-265/90-11 on 900611-14.No Violations or Deviations Noted.Major Areas Inspected: Licensee Radwaste Mgt Program,Including Solid,Liquid & Gaseous Wastes & Audits & Assessments IR 05000254/19890161989-08-28028 August 1989 Insp Repts 50-254/89-16 & 50-265/89-16 on 890625-0819. Violations Noted.Major Areas Inspected:Plant Operations, Radiological Controls,Maint/Surveillance,Safety Assessment/ Quality Verification,Emergency Preparedness & Security IR 05000254/19890181989-08-24024 August 1989 Physical Security Insp Repts 50-254/89-18 & 50-265/89-18 on 890814-18.No Violations Noted.Major Areas Inspected:Mgt Support,Security Program Plans,Audits,Protected & Vital Area Physical Barriers & Detection & Assessment Aids IR 05000254/19890121989-07-17017 July 1989 Insp Repts 50-254/89-12 & 50-265/89-12 on 890514-0624.One licensee-identified Violation & Two Unresolved Items Noted. Major Areas Inspected:Licensee Actions on Previous Items, Plant Operations,Emergency Preparedness & Security ML20246C3471989-06-29029 June 1989 Safety Insp Repts 50-254/89-13 & 50-265/89-13 on 890522-0608.No Violations,Deviations or Open Items Noted. Major Areas Inspected:Maint & Inservice Testing of Pumps & Valves,Including Actions in Response to NRC Bulletin 85-003 IR 05000254/19890151989-06-28028 June 1989 Insp Repts 50-254/89-15 & 50-265/89-15 on 890619-21.No Violations Noted.Major Areas Inspected:Radwaste Mgt Program, Including Solid,Liquid & Gaseous Radwastes,Audits & Assessments & Unplanned Liquid Radwaste Release IR 05000254/19890141989-06-27027 June 1989 Insp Repts 50-254/89-14 & 50-265/89-14 on 890605-09.No Violations or Deviations Noted.Major Areas Inspected: Implementation of NRC Bulletin 88-010 Requirements Re molded-case Circuit Breakers IR 05000254/19890101989-05-22022 May 1989 Insp Repts 50-254/89-10 & 50-265/89-10 on 890402-0513.No Violations Noted.Major Areas Inspected:Plant Operations, Radiological Controls,Maint/Surveillance,Emergency Preparedness,Security & Engineering/Technical Support IR 05000254/19890041989-04-13013 April 1989 Insp Repts 50-254/89-04 & 50-265/89-04 on 890205-0401.No Violations Noted.Major Areas Inspected:Plant Operations, Radiological Controls,Maint/Surveillance,Emergency Preparedness & Security IR 05000254/19890061989-03-0707 March 1989 Insp Repts 50-254/89-06 & 50-265/89-06 on 890214-17.No Violations Noted.One Potential Contamination Control Weakness Noted.Major Areas Inspected:Radiation Protection Program,Including Organization & Mgt Controls & ALARA IR 05000254/19890051989-02-27027 February 1989 Insp Repts 50-254/89-05 & 50-265/89-05 on 890206-10.No Violations Noted.Major Areas Inspected:Chemistry Program, Including Procedures,Organization & Training & Radiological Environ Monitoring Program & Qc/Qa Program in Lab IR 05000254/19880201988-10-13013 October 1988 Insp Repts 50-254/88-20 & 50-265/88-20 on 880807-0930.No Violations or Deviations Noted.Major Areas Inspected: Operations,Maint,Surveillance,Ler Review,Routine Repts, Temporary Instructions,Radiation Control & Info Notices IR 05000254/19880211988-10-0505 October 1988 Insp Repts 50-254/88-21 & 50-265/88-21 on 880222-0901. Violations Noted.Major Areas Inspected:Compliance W/App R to 10CFR50 & Review of Fire Protection Program Requirements IR 05000254/19880191988-09-22022 September 1988 Insp Repts 50-254/88-19 & 50-265/88-19 on 880830-0902.No Violations Noted.Weakness & Four Open Items Identified.Major Areas Inspected:Annual Exercise IR 05000254/19880251988-09-20020 September 1988 Insp Repts 50-254/88-25 & 50-265/88-26 on 880908-14.No Violations Noted.Major Areas Inspected:Licensee Written Practice for Nondestructive Exam Pertaining to 25% Rule Described in SNT-TC-1A ML20154L9461988-09-14014 September 1988 Insp Rept 50-265/88-24 on 880826.No Violations Noted. Major Areas Inspected:Weakness Identified in Verification of Component Operability as Documented in Insp Repts 50-254/88-15 & 50-265/88-15 ML20154L7701988-09-14014 September 1988 Corrected Pages 13 & 14 to Insp Repts 50-254/88-15 & 50-265/88-15 IR 05000254/19882001988-09-0707 September 1988 Emergency Operating Procedures Insp Rept 50-254/88-200 on 880613-30.Inadequacies & Deficiencies Noted.Major Areas Inspected:Determination If Procedures Technically Correct & Whether Procedures Could Be Carried Out & Performed IR 05000254/19880181988-07-29029 July 1988 Partially Withheld Physical Security Insp Repts 50-254/88-18 & 50-265/88-18 on 880718-21 (Ref 10CFR73.21).Noncompliances Noted.Major Areas Inspected:Security Plan & Implementing Procedures & Mgt Effectiveness IR 05000254/19880171988-07-14014 July 1988 Insp Repts 50-254/88-17 & 50-265/88-17 on 880706-07.No Violations Noted.Major Areas Inspected:Emergency Preparedness Program Areas,Including Actions on Previously Identified Items & Initiatives to Improve Program IR 05000254/19880161988-07-0101 July 1988 Insp Repts 50-254/88-16 & 50-265/88-16 on 880607-15. Violations Noted.Major Areas Inspected:Containment Integrated Leak Rate Test Procedure,Performance & Results, Local Leak Rate Test Results & LER Followup IR 05000254/19880121988-06-28028 June 1988 Insp Repts 50-254/88-12 & 50-265/88-06 on 880310-0411-12,18, 21,26-29 & 05-10,17-18 & 0601 & 20.No Violations Noted.Major Areas Inspected:Inservice Insp Activities,Including Review of Programs 73051,Procedures 73052 & Observation of Work ML20195H1591988-06-21021 June 1988 Insp Repts 50-254/88-11 & 50-265/88-12 on 880422-0601. Violations Noted.Major Areas Inspected:Maint Activities & Followup on Previous Identified Insp Items Using Selected Portions of Listed Insp Modules IR 05000254/19880131988-06-15015 June 1988 Insp Repts 50-254/88-13 & 50-265/88-13 on 880510-20. Violation Noted.Major Areas Inspected:Radwaste Mgt & Radiation Protection Programs During Refueling & Maint Outage Including Organization & Mgt Controls IR 05000254/19880091988-06-0707 June 1988 Insp Repts 50-254/88-09 & 50-265/88-10 on 880403-0604.No Violations Noted.Major Areas Inspected:Operations,Maint, Surveillance,Ler Review,Routine Repts,Temporary Instructions & Administrative Controls Affecting Quality IR 05000254/19880101988-06-0606 June 1988 Insp Repts 50-254/88-10 & 50-265/88-11 on 880418-29.No Violations Noted.Major Areas inspected:safety-related Piping Weldments,Components & Supports Selected from Plant Mod Packages & Inservice Insp Plan IR 05000254/19880071988-05-0404 May 1988 Errata to Insp Repts 50-254/88-07 & 50-265/88-08 ML20151Z6211988-04-28028 April 1988 Insp Repts 50-254/88-07 & 50-265/88-08 on 880328-0407.No Violations Noted.Major Areas Inspected:Hpci/Rcic History & Mgt Activities,Root Cause Determination & Corrective Action & Maint Activities Re HPCI & RCIC IR 05000254/19880881988-04-27027 April 1988 Insp Repts 50-254/88-88 & 50-265/88-09 on 880404-08.No Violations Noted.Major Areas Inspected:Qa & Confirmatory Measurements for in-plant Radiochemical Analyses & Verification of TLD Collocation IR 05000254/19880041988-04-12012 April 1988 Insp Repts 50-254/88-04 & 50-265/88-04 on 880207-0402. Violations Noted.Major Areas Inspected:Operations,Maint, Surveillance,Ler Review,Routine Repts,Temporary Instructions & Administrative Controls Affecting Quality IR 05000254/19880061988-03-31031 March 1988 Insp Repts 50-254/88-06 & 50-265/88-07 on 880315-17.No Violations Noted.Major Areas Inspected:Licensee Actions on Previously Identified Items,Emergency Plan Activations, Review of Licensee Initiatives to Improve Program IR 05000254/19870331988-02-24024 February 1988 Insp Repts 50-254/87-33 & 50-265/87-33 on 871206-880206. Violations & Deviations Noted.Major Areas Inspected: Operations,Maint & Surveillance,Ler Review,Routine Repts & Administrative Controls Affecting Radiation Control IR 05000254/19880031988-02-0404 February 1988 Partially Withheld Physical Security Insp Repts 50-254/88-03 50-265/88-03 on 880111-14 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Mgt Effectiveness Security Program Audits,Records & Repts IR 05000254/19880021988-01-27027 January 1988 Insp Repts 50-254/88-02 & 50-265/88-02 on 880105-07.No Violations or Deviations Noted.Major Areas Inspected:Items Identified in Nov 1987 Insp & Initial Review of Licensee Initiatives to Improve Emergency Preparedness Program IR 05000254/19870241987-12-29029 December 1987 Insp Repts 50-254/87-24 & 50-265/87-24 on 870913-1208.No Violations or Deviations Noted.Major Areas Inspected: Containment Integrated Leak Rate Test (Cilrt) Procedure, Cilrt Performance Witnessing & Cilrt Results IR 05000254/19870201987-12-21021 December 1987 Safety Insp Rept 50-254/87-20 on 870901-1209.No Violations Noted.Major Areas Inspected:Inservice Insp Activities, Including Review of Programs,Procedures,Observation of Work Activities,Data Review & IE Bulletin Evaluation IR 05000254/19870301987-12-17017 December 1987 Insp Repts 50-254/87-30 & 50-265/87-30 on 871026-1105.One Violation Noted.Major Areas Inspected:Licensee Action on Previous Insp Findings,Implementation of QA Program in Areas of Design Changes & Mod & Maint IR 05000254/19870271987-12-16016 December 1987 Insp Repts 50-254/87-27 & 50-265/87-27 on 871001-1205.No Violations Noted.Major Areas Inspected:Maint,Operations, Surveillance,Ler Review,Routine Repts & Administrative Controls Affecting Quality & Radiation Control IR 05000254/19870321987-12-0404 December 1987 Insp Repts 50-254/87-32 & 50-265/87-32 on 871102-06.No Violations or Deviations Noted.Major Areas Inspected: Chemistry Program,Including Procedures,Organization & Training & Qa/Qc Program in Lab IR 05000254/19870311987-12-0101 December 1987 Insp Repts 50-254/87-31 & 50-265/87-31 on 871102-06. Violations Noted.Major Areas Inspected:Emergency Plan Activations,Operational Status of Emergency Preparedness Program & Emergency Detection & Classification IR 05000254/19870251987-11-23023 November 1987 Insp Repts 50-254/87-25 & 50-265/87-25 on 870922-1105. Violations Noted.Major Areas Inspected:Licensee Implementation of Generic Ltr 85-06 Re ATWS Mitigation Sys (25020) & Onsite Followup Events IR 05000254/19870211987-11-16016 November 1987 Special Allegation Insp Repts 50-254/87-21 & 50-265/87-21 on 870831-1029.No Violations Noted.Major Areas Inspected:Review of Allegation That Security Force Members Required to Work Excessive Overtime Hours ML20236Q4481987-11-0404 November 1987 Safety Insp Repts 50-254/87-29 & 50-265/87-29 on 871019-21. No Violations or Deviations Noted.Major Areas Inspected: Implementation of Conditions of 861114 Amend 1 to Confirmatory Action Ltr CAL-RIII-86-07 IR 05000254/19870191987-10-15015 October 1987 Insp Repts 50-254/87-19 & 50-265/87-19 on 870802-1003. Violations Noted.Major Areas Inspected:Operations,Maint, Surveillance,Ler Review,Routine Repts,Training,Radiation Control,Outages & Administrative Controls Affecting Quality ML20235W4321987-10-13013 October 1987 Insp Repts 50-254/87-26 & 50-265/87-26 on 870921-25.No Violations or Deviations Noted.Major Areas Inspected: Radwaste Mgt & Radiation Protection Programs During Refueling & Maint Outage & Response to Selected IE Notices IR 05000254/19870221987-09-11011 September 1987 Mgt Meeting Summary Repts 50-254/87-22 & 50-265/87-22 on 870908.Major Areas Discussed:Training Program Effectiveness ML20238A2241987-08-31031 August 1987 Safety Insp Repts 50-254/87-11 & 50-265/87-11 on 870608-0728.Violations Noted.Major Areas Inspected:Environ Qualification of Electric Equipment within Scope of 10CFR50.49 IR 05000254/19870131987-08-25025 August 1987 Insp Repts 50-254/87-13 & 50-265/87-13 on 870607-0801. Violations Noted.Major Areas Inspected:Operations,Maint, Surveillance,Ler Review,Routine Repts,Training,Bulletins, Generic Ltrs,Radiation Control,Outages & Licensee Meetings 1990-08-14
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000254/19990011999-10-0707 October 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990721-0908.No Violations Noted.Major Areas Inspected:Initiating Events, Mitigating Sys & Barrier Integrity IR 05000254/19990171999-09-15015 September 1999 Insp Repts 50-254/99-17 & 50-265/99-17 on 990823-27.No Violations Noted.Major Areas Inspected:Pilot Baseline Insp for Annual Review of Changes to Safety Analysis Rept & Biennial Review Permanent Plant Mod IR 05000254/19990161999-09-0909 September 1999 Errata to Insp Repts 50-254/99-16 & 50-265/99-16 Conducted on 990819.Administrative Error Was Corrected on Page 8 of Subj Rept.One Open Item Was Deleted & re-numbering of Two Other Items Were Identified IR 05000254/19990151999-08-25025 August 1999 Insp Repts 50-254/99-15 & 50-265/99-15 on 990816-20.No Violations Noted.Major Areas Inspected:Maint Rule Implementation IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site ML20211D2031999-08-19019 August 1999 Insp Repts 50-254/99-16 & 50-265/99-16 on 990719-22. Violations Noted.Major Areas Inspected:Physical Protection Cornerstone,Including Review of Access Authoization Program & Changes to Security Plan IR 05000254/19990121999-08-13013 August 1999 Insp Repts 50-254/99-12 & 50-265/99-12 on 990628-0716. Violations Noted.Major Areas Inspected:Corrective Action Process Which Included Methods Used for Identification, Cause Investigation & Correction of Quality Related Items IR 05000254/19990111999-08-13013 August 1999 Insp Repts 50-254/99-11 & 50-265/99-11 on 990601-0720.NCVs Noted.Major Areas Inspected:Performance in Initiating Events,Mitigating Sys,Barrier Integrity Cornerstones & Performance Indicator Verification IR 05000254/19990141999-07-30030 July 1999 Insp Repts 50-254/99-14 & 50-265/99-14 on 990713-15.One Violation Noted & Treated as Ncv.Major Areas Inspected: Heat Sink Performance,Which Covers Inspectable Area Under Initiating Events & Mitigation Sys IR 05000254/19990131999-07-29029 July 1999 Insp Repts 50-254/99-13 & 50-265/99-13 on 990628-0702.No Violations Noted.Major Areas Inspected:Public Radiation Safety & Review of Gaseous & Liquid Radiological Effluents & of Radiological Environmental Monitoring Program IR 05000254/19990091999-06-23023 June 1999 Insp Repts 50-254/99-09 & 50-265/99-09 on 990421-0531.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000254/19990061999-05-14014 May 1999 Insp Repts 50-254/99-06 & 50-265/99-06 on 990307-0420.Three Violations Noted & Being Treated as non-cited Violations. Major Areas Insptected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000254/19990081999-05-11011 May 1999 Insp Repts 50-254/99-08 & 50-265/99-08 on 990419-23.No Violations Noted.Major Areas Inspected:Adequacy of Licensee Programs,Procedures,Training & Supporting Documentation IR 05000254/19990031999-04-0909 April 1999 Insp Repts 50-254/99-03 & 50-265/99-03 on 990308-12.No Violations Noted.Major Areas Inspected:Maint & Engineering ML20205J2951999-04-0101 April 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990121-0306. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19990071999-03-31031 March 1999 Radiation Protection Insp Repts 50-254/99-07 & 50-265/99-07 on 990309-12.No Violations Noted.Major Areas Inspected:Solid Radwaste Processing & Control Program & Radioactive Matls Shipping Program IR 05000254/19980211999-03-0505 March 1999 Insp Repts 50-254/98-21 & 50-265/98-21 on 981112-1218. Violation Noted:Major Areas Inspected:Isi Activities at Plant During Refueling Outage 15 ML20207G1771999-03-0505 March 1999 Notice of Violation from Insp on 99112-1218.Violation Noted:Licensee Had Not Included in Revised ISI Program,Basis for Determination That Code Required Exam Was Impractical For,Unit 2 Reactor Pressure Vessel Nozzle Weld Nsb IR 05000254/19990041999-02-26026 February 1999 Insp Repts 50-254/99-04 & 50-265/99-04 on 990201-05.No Violations Noted.Major Areas Inspected:Emergency Prepardeness Program as Aspect of Plant Support IR 05000254/19990021999-02-25025 February 1999 Insp Repts 50-254/99-02 & 50-265/99-02 on 990125-29.No Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Program Included Water Chemistry Control, Instrument Quality Control & internal-lab Comparison ML20199E9431999-01-14014 January 1999 Partially Withheld Security Insp Repts 50-254/98-24 & 50-265/98-24.Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Quad Cities Facility.Details Withheld (Ref 10CFR2.790) IR 05000254/19980201998-12-28028 December 1998 Insp Repts 50-254/98-20 & 50-265/98-20 on 981014-1201.No Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000254/19980221998-12-28028 December 1998 Insp Repts 50-254/98-22 & 50-265/98-22 on 981130-1204.No Violations Noted.Major Areas Inspected:Radiation Protection Staff Preparation for Q1R15 Refueling Outage,Including Review of ALARA Planning & Work Plan Integration ML20198G2901998-12-18018 December 1998 Notice of Violations from Insp on 981019-1106.Violations Noted:As of 980327,performance of Listed Test Procedures Did Not Demonstrate Equipment Could Perform Satisfactorily Under Design Conditions IR 05000254/19980191998-12-18018 December 1998 Insp Repts 50-254/98-19 & 50-265/98-19 on 981019-1106. Violations Noted.Major Areas Inspected:Effectiveness of Engineering & Technical Support Provided to Plant in Performance of Routine & Reactive Site Activities IR 05000254/19980171998-11-0505 November 1998 Insp Repts 50-254/98-17 & 50-265/98-17 on 980902-1014.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19980181998-10-15015 October 1998 Partially Withheld Insp Repts 50-254/98-18 & 50-265/98-18 on 980914-18 (Ref 10CFR73.71).No Violations Identified.Major Areas Inspected:Review of Plant Support Activities,Security Activities Re Onsite Personnel Access & Communications IR 05000254/19980131998-09-22022 September 1998 Insp Repts 50-254/98-13 & 50-265/98-13 on 980716-0901.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980141998-09-17017 September 1998 Insp Repts 50-254/98-14 & 50-265/98-14 on 980825-28.No Violations Noted.Major Areas Inspected:Evaluation of Licensee Performance During Plant Biennial Exercise of Emergency Plan ML20154G4301998-09-11011 September 1998 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $88,000.Violation Noted:As of 970926,licensee Failed to Provide Alternate Shutdown Capability for Some Fire Areas of Facility Containing Safe Shutdown Equipment ML20195D1951998-09-0808 September 1998 EN-98-057B:on 980911,notice of Proposed Imposition of Civil Penalty in Amount of $88,000 Issued to Licensee.Action Based on One Severity Level II Problem Involving Very Significant Inadequacies in Comm Ed Capability to Shut Down IR 05000254/19980161998-09-0404 September 1998 Insp Repts 50-254/98-16 & 50-265/98-16 on 980810-14.No Violations Noted.Major Areas Inspected:Radiation Protection Program Included External & Internal Exposure Control,Whole Body Counting & Contamination & Survey Monitoring Program IR 05000254/19980121998-08-11011 August 1998 Insp Repts 50-254/98-12 & 50-265/98-12 on 980529-0716. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support ML20237D6671998-08-11011 August 1998 Notice of Violation from Insp on 980529-0716.Violation Noted:On 980622,while Performing Quad Cities Operating Surveillance Procedure 6600-01,rev 24,operator Failed to Position Throttle Air Box Drain Valve One Turn ML20195D2341998-08-11011 August 1998 EN-98-057:on 980814,notice of Proposed Imposition of Civil Penalty in Amount of $143,000 Issued to Licensee.Action Based on One Severity Level II Problem & One Severity Level III Violation IR 05000254/19980151998-07-31031 July 1998 Insp Repts 50-254/98-15 & 50-265/98-15 on 980721-24.No Violations Noted.Major Areas Inspected:Aspects of Licensee Corrective Actions & Engineering Involvement in Corrective Actions Process IR 05000254/19980111998-07-0202 July 1998 Insp Repts 50-254/98-11 & 50-265/98-11 on 980504-22. Violations Noted.Major Areas Inspected:Quad Cities Safe Shutdown Analysis & Supporting Procedures ML20236M0831998-07-0202 July 1998 Notice of Violation from Insp on 980401-0529.Violation Noted:On 980501,Interim Procedure 98-0035 Was Not Implemented When Change Was Made to Personnel Out-of Svc Number 98-512 Which Was Not Reviewed & Approved IR 05000254/19980091998-07-0202 July 1998 Insp Repts 50-254/98-09 & 50-265/98-09 on 980401-0529. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20237E7051998-06-0505 June 1998 EN-98-043:informs Commission That Staff Intends to Exercise Enforcement Discretion Per Section VI.B.6 of Enforcement Policy & Not Issue NOV to Util for Failure to Provide Complete & Accurate Info to NRC ML20248L7951998-06-0505 June 1998 Notice of Violation from Investigation on 970530.Violations Noted:Licensee Provided to Commission on 960825,operability Determination Checklist.Info Inaccurate Because Supporting Calculations Showed FICs to Be Excess of 1.0 ML20247P4551998-05-15015 May 1998 Notice of Violation from Insp on 971014-980415.Violation Noted:On 971215,inspector Identified That Licensee Failed to Provide Training of Personnel Performing Activities Affecting Quality IR 05000254/19980081998-05-11011 May 1998 Insp Repts 50-254/98-08 & 50-265/98-08 on 980407-09 & 14-17. No Violations Noted.Major Areas Inspected:Maint,Quality Assurance & Engineering IR 05000254/19980101998-05-0606 May 1998 Insp Repts 50-254/98-10 & 50-265/98-10 on 980413-17.No Violations Noted.Major Areas Inspected:Liquid & Gaseous Effluent Programs,Annual Effluent Rept,Continuous Air & Area Radiation Monitors IR 05000254/19982011998-05-0606 May 1998 Insp Repts 50-254/98-201 & 50-265/98-201 on 980216-0327.No Violations Noted.Major Areas Inspected:Evaluation of Capability of Selected Sys to Perform Safety Functions Required by Design Bases ML20217G2341998-04-23023 April 1998 Notice of Violation from Insp on 980216-0326.Violation Noted:Between 971006 & 10,work Package 970104149-03 Replaced 2A Recirculation Loop Sample Pci Valve AO-2-0220-44,activity Affecting Quality,Prepared & Installed Prior to 971014 ML20217G2481998-04-23023 April 1998 Insp Repts 50-254/98-05 & 50-265/98-05 on 980216-0326. Violations Noted.Major Areas Inspected:Engineering,Including Allowances for Development of Emergency & Immediate Mods ML20217G3101998-04-23023 April 1998 Notice of Violations from Insp on 980211-0331.Violations Noted:On 980314,non-licensed Operators Performing Plant Operating Procedure 6600-7,rev 6,attachment H,Failed to Charge Breaker Closing Spring for Unit 2 ML20217G3401998-04-23023 April 1998 Insp Repts 50-254/98-04 & 50-265/98-04 on 980211-0331. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support IR 05000254/19980071998-04-22022 April 1998 Insp Repts 50-254/98-07 & 50-265/98-07 on 980330-0403.No Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Plant,Adequacy of Security Procedures & Event Logs 1999-09-09
[Table view] |
Text
__ _ - _ -
U.S. NUCLEAR REGULATORY COMMISSION
REGION III
Reports No. 50-254/89016(DRP); 50-265/89016(DRP)
Docket lios. 50-254; 50-265 Licenses No. DPR-29; DPR-30 Licensee: Commonwealth Edison Company i Post Office Box 767 I Chicago, IL 60690 Facility Name: Quad Cities Nuclear Power Station, Units 1 and 2 Inspection At: Quad Cities Site, Cordova, IL Inspection Conducted: June 25 through August 19, 1989 Inspectors: R. L. Higgins D. E. Jones R. M. Lerch M. Parker A. Dunlop J. M. Shine R. Bocanegra T. M. Ross F. J. Witt Approved By:
/fA.bDwf R. M. Lerch, Acting Chief f-2f-E7 Reactor Projects Section 1B Date Inspection Summary Inspection on June 25 through August 19, 1989 (Reports No. 50-254/89016(DRP);
50-265/69016(DRP))
Areas Inspected: Routine, unannounced safety inspection by the resident, regional and Nuclear Reactor Regulation (NRR) inspectors of plant operations, radiological controls, maintenance / surveillance, licensee action on previous items, emergency preparedness, security, engineering / technical support and safety assessment / quality verificatio Results: During the inspection period one previously-identified unresolved item was determined to be a violation of NRC requirements (see attached Notice of Violation), and one new unresolved item was identified (see paragraph 8 of this report).
8909060200 89082s
$DR ADOCK 05000254 FDC
_ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ __ .__ __ _ _ _ . - _ _ _ _ _ ___ _]
- - _ _ - __
___ ___-_
_
..
' 'i l DETAILS Personnel Contacted
- G. Spedl, Production' Superintendent
- R. Robey, Technical. Superintendent
- L. Petrie, Assistant Superintendent of Maintenance
- D. Gibson, Regulatory Assurance Supervisor l- *J. Wethington, Quality Assurance Supervisor l *T. Barber, Regulatory Assurance
- Denotes those,present at the exit interview on August 21, 198 The inspectors also contacted and interviewed other licensee and contractor personnel during the course of this inspectio . Action on Previous Items (92702)
~ (Closed) Unresolved Item / Violation.254/89012-02; 265/89012-02: *
Installation of Improper Check Valves. This item was reviewed -
and corrective actions described in paragraph 5.b(2) of Inspection . -
Report 254/89012(DRP); 265/89012(DRP). .
As documented in the cover letter and enclosed Notice, this unresolved item was determined to be a Severity Level IV violatio All corrective actions have been completed, therefore no response was required. This item is considered close (Closed) Violation 254/89012-01; 265/89012-01: Loss of Secondary Containment. This item was licensee-identified and all corrective actions to prevent a recurrence have been completed. This item is considered close . Plant Operations Operational Safety Verification (71707)
The inspectors, through direct observation, discussions with licensee personnel, and review of applicable records and togs, examined _ plant operations. The inspectors verified that all a activities were accomplished in a timely manner using approved procedures and drawings and were inspected / reviewed as applicable; and that procedures, procedure revisions and routine reports were in accordance with Technical Specifications, regulatory guides, and industry codes or standards. Additionally, the inspectors verified that approvals were obtained prior to initiating any work; activities were accomplished by qualified personne); the limiting conditions.for operation were met during normal operation and while components or systems were removed from service; functional testing and/or calibrations were performed prior to returning components or systems to service; and independent verification of equipment lineup and review of test results were accomplished. Also verified were
_ _ _ _ _ _ _ - _ _ - - _ _ - _ _ - - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ - _ . _ _ _ _ _ _ _ _ _ _ _
_ _ _ - - -_ - - _ - -
.
i
.
quality control records for being properly maintained and reviewed, and parts, materials and equipment for proper certification, calibration, storage, and maintenance as applicable. The inspectors l
-
conducted frequent tours of plant facilities to search for the
existence of adverse plant conditions such as equipment malfunctions, I potential fire hazards, radiological hazards, fluid leaks, excessive vibrations, and personnel errors. The inspectors' review ensured these issues were addressed in a timely manner with sufficient and proper corrective actions and reviewed by appropriate management personne During the inspection period a detailed plant tour was performed by the Branch Chief, Section Chiefs and Senior Resident Inspectors of the Region III Division of Reactor Projects Branch 1, by three of the Licensing Project Managers of Project Directorate III-2 of the Office of Nuclear Reactor Regulation, and by the Region III coordinator in the Office of the Executive Director for Operation ho significant safety discrepancies were found, but numerous minor deficiencies were noted., These were provided to the Senior Resident Inspector, who then presented them to licensee management. The licensee has instituted corrective actions to rectify these deficiencie b. Engineered Safety Features System Walkdown (71710)
During plant tours of Units 1 and 2, the inspectors walked down some of the accessible portions of the High Pressure Coolant Injection (HPCI), Reactor Core Isolation Cooling (RCIC), Core Spray (CS),
Residual Heat Ramoval (RHR), RHR Service Water, Standby Liquid Control (SLC) Systems, and Standby Gas Treatment (SGT) Systems. The inspectors also walked down the Emergency Diesel Generators (EDG)
and the Station Batteries. No violations or deviations were note c. Summary of Operations Unit 1 Unit 1 operated normally at the maximum power which fuel depletion would sustain (an operating status termed "coastdown"), or at reduced power in order to perform surveillance testing or respond to load dispatcher orders, until the reactor scrammed on June 29, 1989 due to a turbine trip caused by a spurious main condenser low vacuum
>-
signal (refer to paragraph 3.d.(1) of this report). Following maintenance work including replacement of the 1B recirculation pump seal, the reactor restarted on July 2, 1989, but shut down to repair a steam leak on a balance-of-plant component (refer to paragraph 3.d.(2) of this report). The reactor restarted on July 4, 1989, and oaerated normally at power in a coastdown status until July 7, 1989, w1en high down-river temperature limits established by the Illinois Environmental Protection Agency (EPA) restricted the reactor's power level (refer to paragraph 3.d.(3) of this report). The reactor power restrictions were removed on July 14, 1989, and the reactor operated in a coast down status for the remainder of the inspection perio _ _ - _ _
_ _ . _ _ - - _ _ _ - _ _ _ _ _ _ _ -
4
Unit 2 i
Unit 2 operated normally at full power, on Economic Generation Control (EGC), or at reduced power in order to perforu surveillance
- testing or respond to load dispatcher orders, until July 7, 1989, I
when high down-river temperature limits established by the Illinois EPA restricted the reactor's power level (refer to paragraph 3.d.(3)
of'this report). The reactor power restrictions were removed on July 14, 1989, and the reactor resumed normal power operation On July 19, 1989, problems with the Core Monitorinq Code (CMC)
computer used to generate reactor power and critical heat flux limits malfunctioned (refer to paragraph 3.d.(4) of this report).
The reactor was maintained at a constant power level of 80% (650 MWe) until the malfunction was repaired on July 25, 1989. The reactor operated normally at power throughout the rest of the inspection perio d. Onsite Followup of Events at Operating Power Reactors (93702)
(1) Reactor Scram At 10:39 PM CDT on June 29, 1989, with Unit 1 at 100% power, the Unit 1 turbine tripped causing a reactor scram. Post scram actions were normal, except for a group 1 isolation (MSIV closure) which caused reactor pressure to rise resulting in an electromatic relief valve opening momentaril The group I isolation occurred because main steam header pressure dropped below the isolation setpoint pressur Immediately after the scram the licensee reset the group 1 isolation and placed the reactor in cold shutdow The cause of the June 29th turbine trip was determined to be a loose connection on the wire to the vacuum indicator 119it PS.105B on'the 901-7 panel. This loose connection would occasionally make and break electrical contact, generating a voltage spike on the vacuum indicator wire, which would in turn generate a voltage spike in the low vacuum turbine trip circuit, causing a turbine trip and reactor scram. It is suspected that this problem also caused the Unit 1 turbine trip and reactor scram which occurred on December 5, 1988. (Refer to paragraph 3.e.(1) of inspection report 50-254/88028(DRP)
and 50-265/88029(DRP)).
During the unplanned outage the licensee tightened the loose connection to PS 105B, replaced the malfunctioning seal on the 1B reactor recirculation pump, repaired the 1B reactor recirculation pump suction valve and performed other maintenance r ' vitie _ _ _ _ _ _ - - _ _ _ - - _ .
3, J
.
(2) Reactor Shutdown and Startup At 12:30 PM CDT on July 3, 1989, with Unit 1 at 25% power in the process of raising power following a reactor startup, the licensee discovered a steam leak on the 1A moisture separator drain tank vent line to the 1A moisture separator in the low pressure heater bay. The licensee shutdown the reactor at 10:17 PM on July 3, 1989, and entered cold shutdown at 3:50 AM on July 4, 198 During the unalanned maintenance outage the licensee repaired the steam leac on the moisture separator drain tank vent line, repacked the RCIC inboard steam supply valve and performed other minor maintenance in the drywell. At 3:49 PM CDT on July 4, 1989, the licensee began control rod withdrawal to restart Unit 1. Reactor criticality was achieved at 6:16 PM on July 4, 1989, and the main generator was synchronized to the electrical grid on July 5, 1989.,
(3) Summer Dronht Operational Restrictions Quad Cities must abide by several environmental limits imposed by the Illinois EPA concerning the effect which circulating water discharging into the Mississippi River has on river temperature. These limits are: (1) the maximum differential between up-river and down-river temperatures is not permitted to exceed 5 degrees F; (2) the maximum down-river temperature is limited to vabes which vary according to the month of the year (for the months of July and August this temperature limit is 86 degrees F), and down-river temperature is prohibited from exceeding these values for more than a total of 87 hours0.00101 days <br />0.0242 hours <br />1.438492e-4 weeks <br />3.31035e-5 months <br /> and 36 minutes in any 12 month period; (3) the down-rive. temperature is prohibited from ever exceeding the monthly temperature limit by more than 3 degrees F (for the months of July and August this temperature limit is 66 degrees F, never to exceed 89 degrees).
Because of drought conditions which existed during 1988, Quad Cities had only 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> remaining during the month of July '
before the time limit would be exceeded. On July 7, 1989, down-river temperature exceeded the limit for the first time in 1969. The limit was exceeded again on July 8, 9 and 10, 1989, as well. At 5:15 PM CDT on July 10, 1989, Qued Cities exceeded !
the 87 hour0.00101 days <br />0.0242 hours <br />1.438492e-4 weeks <br />3.31035e-5 months <br /> 36 minute time limit. The licensee immediately ;
reduced power on both units to 30% (250 MWe), and limited power i to this 30% value through July 13. 1989, when the Illinois EPA I granted Quad Cities an additional 100 hours0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br /> during which the !
time-dependent temperature limit could be exceeded. This l additional time, plus cooler weather, permitted Quad Cities to !
resume normal operations on July 14, 198 l
(4) Core Monitoring Code Abnormality l
At 8:00 PM on July 19, 1989, with Unit 2 at 100% power, the reactor core thermal limits of MFLPD (maximum fraction of 5 l
____a
_ _ = _ . ___ . _ _ _ . - - - _- __ - - _ _ _ _ _ _
Qy .
W '
w ,
p,>
- a p.* *
h
- line y power density), MAPLHGR-(maximum fraction of linear heat generation rate) and MCPR (minimum critical power ratio) a '
D L calculated by the process computer were determined to be in ,
l- violation of-their limiting values. The licensee'promptly commenced a power reduction to 80% power.: Comparison with the-core thermal limits which were calculated 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> previousl .and found to be within. limits, and the knowledge that no plant-
.. transients, power changes, or rod shuffles had occurred, caused-the licensee to question the validity of the core thermal
'
- limits which were calculated to. exceed their limiting values.
p The. licensee continued power operation of Unit '.by holding p power constant at 80% and obtaining core thermal limits from B corporate headquarters'and from. General Electric. The thermal L
'
limits so obtained were within their' limiting value :
The abnormality in the core thermal limit calculation was determined to be due to a factor of ten error in a xenon l constant for type'4 fuel in the core monitoring code. This problem was-insignificant at low fuel exposure but became more significant later in~ core life. The error was corrected, and Unit ~2 was returned to permal operaticn wit'h core thermal 111mits provided by the plant process computer on July 25, 198 (5) Loss of Service Air Compressor-On July 19, 1989, with both units operating at power, the
'2A service air compressor had to be shutdown because'it was spurting oil. The 1A service hir. compressor was out of service for maintenance. With only the 1B' service air-compressor'
operating, service air pressure began to decrease. Since the service air system was supplying the instrument air system,-
instrument air pressure'also began to' decrease. The cperating crew took action to minimize the use of service and instrument air, thereby arresting the pressure decrease, restoring service air and instrument air pressure, and preventing the possible shutdown of both units. The 1A service air compressor was subsequently returned to service and the service air;and instrument air systems returned-to normal operatio ,
(6) Degraded Reactor Recirculation Pump 2A Seal On August 10, 1989, operaticrs personnel noticed that the seal cavity pressure for the 2A reactor recirculation pump had increased from its normal value of approximately 500 psig at full power to 600 psig, indicating a degraded inner seal. The licensee promptly instituted a temporary procedure to monitor and rccord seal cavity pressure plus several other related parameters every four hours (this is the same temporary procedure as is described in paragraph 3.d.(10) in inspection report 254/89012; 265/89012). Seal degradation has been 0- gradual, and at the end of-the inspection period the seal cavity pressure has increased to 700 psig. The licensee intends to shutdown in the latter part of August to replace the degraded sea _ - - _ _ _ _ _ _ _ _ - _ _ _ - _ - - - _ _ _ - _ - _ _ - _ _ _ _- .
,.
,
4... Radiological Controls (71707)
The licensee continued to demonstrate noteworthy performance in the area'of radiological controls. Unanticipated maintenance activities including the replacement of the IB reactor recirculation pump seal were performed in the Unit 1 drywell wid no associated personnel contaminations. Personnel exposure was less than budgeted despite unant'cipated maintenance activities in the drywell and otner potentially high radiation areas. Several more personnel contaminations than budgeted occurred in the latter part of July, but only one personnel contamination occurred in the August portion of the reporting perio During the inspection perlod the inspectors monitored the radiological survey of the low pressure heater bay and the transfer of resin from the Unit 2 phase separator to the Unit 1 phase separator. The licensee's performance, and the attention showed by management to further reduce personnel contaminations and exposure, is indicative of strong licensee support for the ALARA progra No violations or deriations were note . Maintenance / Surveillance Monthly Maintenance Observation (62703)
Station maintenance activities of safety-related and nonsafety-related systems and components listed below were observed / reviewed to ascertain that they were conducted in accordance with approved procedures, regulatory guides and industry codes or standards and in conformance with Technical Specification The following items were considered during this review: the limiting conditions for operation were met while compor.ents or systems were removed from service; approvals were obtained prior to initiating the work; activities were accomplished using approved procedures and were inspected as applicable. Additional items reviewed included verification that functional testing and/or calibrations were performed prior to returning components or systems to service; quality control records were maintained; and activities were accomplished by qualified personnel. Also, the inspectors verified that parts and materials used were properly certified; radiological controls were implemented; ar.d fire prevention procedures were followed. Work requests were reviewed to determine the status of outstanding jobs and to assure that priority is assigned to the maintenance of safety related equipment which may affect system performanc Portions of the following activities were observed / reviewed:
(1) Unit 2 Control Rod Drive Hydraulic Control Unit (54-27) Scram Inlet and Outlet Valves Overhaul and Inspectio (2) Unit 2 Control Rod Drive Hydraulic Control Unit (54-27) Ball Check Yalve Inspection / Replacemen __ _ _ - - _ _ _ _ _ - _ - - _ _ _
- _ _ - _-.
'
..
6
<
(3) Unit 2A Service Air Compressor Overhau (4) Unit 1C Reactor Feed Pump Auxiliary 011 Pump Maintenanc (5) Unit 1A. Moisture Separator Drain Tank Elbow Repai No violations or deviations were note b.- Monthly Surveillance Observation (61726)
The inspectors observed surveillance testing required tv the Technical Specification and verified that testing was performed .
in accordance with adequate procedures, that test instrumer.tation i was calibrated, and that limiting conditions for operatior were met. Additionally, the inspectors observed / verified the removal and restoration of the affected components, and that test results conformed with Technical Specifications and procedure requirement Also. the inspectors verified that the results were reviewed by personnel other than the individual directing the test and that any deficiencies identified during the testing were properly reviewed and resolved by appropriate menagement personne Portions of the following activities were observed / reviewe i (1) Unit 2 Core Flux Mapping Using the Traveling Incore Prob ;
(2) Local Leak Rate Test of the Unit 1 Personnel Hatc I (3) Unit 2 High Reactor Vessel. Pressure Scram Surveillanc I (4) Unit 2 High Drywell Pressure Scram Surveillanc (5) 1/2 B Standby Gas Treatment System Torque Switch Testin (6) Calibration checks of steam tunnel temperature s tector . Emergency Preparedness (71707)
During the inspection period the inspectors irspected the Quad Cities Technical Support Center (TSC) and the Emergelcy Operations Facility (EOF).
No violations or deviations were note l Security (71707) '
During the inspection period the inspectors toured the plant and the Central Alarm Station to assure that security programs were being properly implemented. The inspectors verified that security barriers were in place, security doors were operable, the security force was alert, personnel correctly displayed their identification badges and visitor access was being properly controlled. No violations or deviations were note l 8 )
_______ - _____ ______ - _-
- - . _ _- _
- - _ _ - _ _ - _ . . - _ _ -
,
.. ,
,,
j .- ,
Y C .. .
.
E :a- ' Loss of Security Electrical Power
- At 8:48 AM CDT on June 28, 1989, electrical power was lost to the security computers, security television cameras, security alarms,
.
and' central and secondary' alarm station consoles. The-licensee immediately initiated. compensatory me,asures, began to search for the- .!
cause of the loss of electrical power, and took action to restore l
% : electrical power to the' security equipment.: At 9:32 AM the NRC' '
7 ~ Emergency Operations Center was notified, and at 10:04 AM electrical-power was restored to the. security equipment.
'
The cause of the loss of electrical power to-the security equipment l l was the opening of the wrong circuit breaker while tagging out the '!
l
'
security diesel generator. When the breaker was reshut, electrical- ,
j power was restore l
\ Security Drill l l On July 15, 1989, the Senior Resident. Inspector monitored the
- . performance of a security drill involving a simulated attack of the plant and occupation of'several plant buildings by security personnel playing the parts of terrorists. The drill. involved-the participation of local law enforcement agencies and included u-simulated fires, hostages and casualtie ;
8 . -- ' Engineering / Technical Support 'RHR Service Water Pump Discharge Pipino Modification (37828) !
During the inspection period the inspectors monitored the installation of the replacement piping for,the 2B RHR service water q discharge pipe. The only problem noted was the apparent inadequate support of compressed gas cylinders. . Several compressed gas-l cylinders were found to be held in their upright position by wire, .
I while several others at other plant locations were found to be held u l- in their upright position by rope. Both the rope and wire method !
of. supporting compressed gas cylinders appear to violate the rules for the control of compressed gas cylinders stated in the Flammable l- and Combustible Material Control procedure QAP 1700-1. These I
apparent deficiencies were brought to the licensee's attention and i correcte Feedwater Hydrogen Addition
'
During the inspection perind the inspectors monitored the l installation and modification testing of the feedwater hydrogen '
,
addition system. The results of an inspection of the feedwater
!
hydrogen addition system which was performed in May 1989 by NRC
!
headquarters personnel were published during the inspection perio The NRC headquarters personnel determined that the feedwater hydrogen addition system complied with the applicable Electric Power Research Institute guideline L_-__-__________
g _
..
- - - - - -
,
- - --
y F yp .
'
> ,
.. ,
l 9 [ H
,
~ Neutron Radioassay Testing of the Unit 1<High 1 Density Fuel Racks >
The Licensing Project Manager for Quad Cities (an inspector fro 'i-NRC headquarters) monitored a portion of the neutron radioassay test of the. Unit 1.high-density fuel. racks (HDFRs) which was performed by~the National Nuclea_r Corporation to determine the extend of Boraflex' degradation and gap growth ~.
-Neutron ~ attenuation tests (both the Standard and Special Test Methods) of the Boraflex-lining in Unit-1 HDFRs, as observed, was aerformed in a deliberate and controlled manner by experienced and knowledgeable personnel. .Compliante with-the unique test
' procedure instructions and radiological controls was deemed-acceptable. The overa11' testing evolution was. accomplished consistent with previous licensee commitments. ' Appropriate Precautions were-taken!(i.e. redistribution of spent fuel in
,
adjacent discharge racks) at the onset to preclude any potential-inadvertent criticality problems considering' introduction of ' Californium neutron source into the spent fuel pi The licensee is working in conjunction with the Electric Power Research Institute (EPRI) to develop an industry data base on-
~
performance of Boraflex in HDFRs. _ Based upon the results of the
- analyzed test data gathered by the licensee and EPRI, gap grov:th
.versus exposure will be trended and evaluated to determine the validity of the " Gap Growth Nodel" as a bounding assumption for the spent fuel pit criticality analyses. This will allow.for-continued verification of Technical Specification 5.5.B ( less'than .95 Keff) compliance and reassessment of the surveillance-program testing intervals (presently conducted after each refuelina cycle).- The aforementioned results and data will be completed in' ;
several months. =The NRC' plans to review this information with the licensee at that time. ' ~
d.- Requalification Training During the inspection period the inspectors monitored two separate qualification training exercises: a simulated fire in the cable spreading room on June 29, 1989, and a simulated plant shutdown from outside the control room vn July 11, 1989. Both training exercises were realistic, well-controlled by licensee training personnel, and beneficial for the participant Configuration Control During the course of the inspection the inspectors noted several deficiencies in plant' drawings and several mislabeled valve Until the extent and safety significance of these deficiencies is determined, these deficiencies will be treated as an unresolved item (254/89016-01(DRP); 265/89016-01(DRP)).
_ __ _______:_____ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _
, , - _ _ - - . __
.
.'~ %
lQ ,
.,. { S') y
" :9.: Safety Assessment / Quality Verification a. ' Evaluation of Licensee Quality Assurance Program Implementation U (35502)
Dur:ng the inspection period the' Senior Resident Inspector observed quality assurance personnel inspecting portions of the 28 RHR service water pump discharge piping modification,'and attended the
'
exit meeting for;the industrial hygiene audit performed by the Quality Assurance staff.
'
iThe quality assurance inspectors were conscientious and,the audits were thorough and detaile s 4 In-Office Review of Written Reports of Nonroutine Events at Power Reactcr Facilities (90712) and Onsite Followup of Written Reports of-Nonroutine Events at Power Reactor Facilities) (92700)
During-the' inspection period the resident inspectors reviewed
.
incidents such as scrams, ESF actuations and component failures which occurred at other plants. .The resident inspectors informed the licensee of the details of all events which potentially had'
applicability to components or activities at Quad Cities.
t '
LER Review (1) (Closed) LER 254/87006 Revision 01: Unit 1.HPCI Inoperable Due to Loose Solenoid Soldered Connectio This revision updates a previous LER by documenting the completion of the long term corrective actions taken to ensure-that similar events are avoided. This item is considered close (2) (0 pen).LER 254/87017, Revision 00: High Pressure Coolant Injection System Inoperable due to Invalid System Isolation from Failed Differential Pressure Switc Licensee corrective ac.lons for this event are partially complete. This LER will remain open until the supplemental report is issue (3)- (Closed) LER 254/87025 Revision 00: Control Room Habitability Design Basis Assumption Error Results in Exceeding Allowable Filter Efficienc This item was discussed in Inspection Report 254/87033(DRP).
Tracking of this item has been assumed by Region based-inspectors under 254/87025-L2. This intem is close (4) (0 pen) LER 265/89003 Revision 00: Loss of Secondary Containment Integrit _ _ _ - _ _ _ . _ - _ - _ _ _ _a
_ _
_ ,_
y
'
-
, ?
This event is discussed in paragraph 3.d.(6) of Inspection
. Report 254/89012 and 265/8901 It will remain open pending revision of Q0A 6900-2, Loss of Unit One 125 VDC Supply, and Q0A 6900-4, Loss of Unit Two 125 VDC Supply, in accordance with the corrective actions stated in the LE (5) (0 pen) 254/89004 Revision 00: Manual Reactor Scram Due to Relief Valve 1-203-3D Stuck Ope This event is discussed in paragraph 3.d.(7) of Inspection Report 254/89010. This item will remain open pending the revision of the Electromatic Relief Valve (ERV) Disassembly, Inspection, Repair and Reassembly procedure, QMMP 203-22, to include a check off step to verify that the drain orifice in the dire retainer of the main valve is clear. It will also remain open until the licensee receives the report from Dresser Industries and addresses all additional actions which Dresser recommends be implemented to enhance the reliability of the j ERVs and pilot valve (6) (Closed) LER 254/89006 Revision 00: Recirculation Pump Tri This is a voluntary LER which covers an event discussed in paragraph 3.d.(9) of inspection report 254/89012 and 265/8901 All corrective actions are complete. This item is considered clcse (7) (Closed) LER 254/89007 Revision 00: lA Refuel Floor Radiation Monitor Spiked hig i This event is discussad in p,.ragraph 4.c. of Inspection Report '
254/89012 and 265/89012. All corrective actions have been completed. This item is considered close (8) (Closed) LER 254/89008 Revision 00: Inability of Pressure Valve 1-1601-23 to Fail Saf l This event is discussed in paragraph 5.b.(2) of Inspection Report 254/89012 and 265/89012. It will remain open pending revision of QOS 1600-15, Pressure Suppression System ,
Power-0perated Valve Quarterly Fail-Safe Test, to test for both slow and fast loss of instrument ai l l (9) (0 pen) LER 254/89009 Revision 00: Unmonitored Release of Laundry Water to the Discharge Bay.
l This event is discussed in paragraph 4.b. of Inspection Report 1 254/89012 and 265/89012. It will remain open pending the l replacement of the skid drain line piping now in use with I piping designed for acidic / caustic application (10) (Closed) LER 254/89010 Revision 00: Reactor Scram Due to a Loose Wire on the Condenser Low Vacuum Pressure Switch Indicating Lam ;
i
l l
)
________________A
( :;y '.
r.'
hs ..
~ ,. h
"' '
iThis event is discussed in paragra n 3.c. of'this repor '
.All.short term corrective actions lave been completed, and La1171ong-term corrective actions are being tracked by the
'
l11censee's-Nuclear Tracking System. This item is considered-l close '(11)'(Open) LER 254/89011 Revision 00: Unit 1 Diesel Generator Fire-Protection System Operabl During surveillance testing of the Unit 1 diesel generator on July.7, 1989,'the normal vent supply. damper was found open when it should have been closed. The cause was determined to be a:
pipe plug which had been left in the exhaust port of the' dampe solenoid valve. 1The damper ~had been'. inoperable since July 14 1988, when the solenoid valve had been replaced and no operability test had been conducted. The plug was removed, the-system was tested satisfactorily and returned to service on July 8, 198 This' item will remain open pending the' completion of the corrective actions listed in the LE (12) (Closed) LER 265/87009, Revision 00: Scram Caused by Turbine /
Generator Load Mismatch Due to a Main Transformer "C" Phase Faul The licensee corrective actions reviewed by the resident-inspector appeared adequate. This item is close Evaluation of Licensee Self-Assessment Capability (40500)
-(1)~'On-Site Review Committee During the inspection period.the Senior Resident Inspector ..
attended an On-Site Review Committee meeting on the' loss of I security electrical power (refer to paragraph 7.a of this
.eport). The committee was properly staffed, adequately l addressed the relevant issues, and demonstrated adequate concern for reactor safet (2) Licensee Self-Assessment During the inspection period the Senior Resident Inspector attended the exit meeting conducted by the licensee's operations self-assessment team. The assessment appeared thorough.and detailed, and the assessment team's findings l were communicated in a professional manne No violations or deviations were note ,
!
. . . i L' -
-
.I
_
- _ _ _ _ _ _ _ _ - _ _ - _ _ - _ _ _ _ _
.o
.
.
,. .- -
10. Management Meetings - Entrance and Exit Interviews (30703)
The inspectors met with licensee representatives (denoted in Paragraph 1)
throughout the inspection period and at the conclusion of the inspection on August 21, 1989, and summarized the scope and findings of the inspection activitie The inspectors also discussed the likely informational content of the inspection report with regard to documents or processes reviewed by the ins)ectors during the inspection. The licensee did not identify any suci documents / processes as proprietary.
l-L 14
{