MONTHYEARIR 05000254/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Quad Cities Nuclear Power Station (Report 05000254/2024005; 05000265/2024005) ML24197A0482024-07-12012 July 2024 Information Request for the Quad Cities Nuclear Station Biennial Problem Identification and Resolution Inspection IR 05000254/20230062024-02-28028 February 2024 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2023006 and 05000265/2023006) ML24053A1192024-02-22022 February 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000265/2024010 and 05000254/2024010 ML23339A1762023-12-0505 December 2023 Notification of NRC Baseline Inspection and Request for Information (05000265/2024001) IR 05000254/20230052023-08-25025 August 2023 Updated Inspection Plan and Assessment Follow-Up Letter for Quad Cities Nuclear Power Station (Report 05000254/2023005; 05000265/2023005) ML23216A0362023-08-0707 August 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI IR 05000254/20220062023-03-0101 March 2023 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2022006 and 05000265/2022006) ML23013A1502023-01-17017 January 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000254/2023002 IR 05000254/20234012023-01-11011 January 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000254/2023401; 05000265/2023401 ML22249A2332022-09-0606 September 2022 Notification of NRC Fire Protection Team Inspection Request for Information Inspection Report 05000254/2022011 05000265/2022011 IR 05000254/20220052022-08-22022 August 2022 Updated Inspection Plan for Quad Cities Nuclear Power Station (Report 05000254/2022005; 05000265/2022005) IR 05000254/20220102022-08-16016 August 2022 Notification of NRC RFI for Post-Approval Site Inspection for License Renewal Phase IV Inspection Report 05000254/2022010 05000265/2022010 ML22178A1362022-06-28028 June 2022 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Quad Cities Station ML22039A1912022-02-0808 February 2022 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests, and Experiments) Baseline Inspection IR 05000254/20210052021-09-0101 September 2021 Updated Inspection Plan for Quad Cities Nuclear Power Station (Report 05000254/2021005 and 05000265/2021005) ML21203A0662021-07-22022 July 2021 Quad Nuclear Power Station - Notification of NRC DBAI (Programs) and Initial Request for Information: Inspection Report 05000254/2021010; 05000265/2021010 IR 05000254/20200062021-03-0404 March 2021 Annual Assessment Letter for Quad Cities Nuclear Power Station Units 1 and 2 (Report 05000254/2020006 and 05000265/2020006) ML21033A5772021-02-0202 February 2021 Notification of Nrc Baseline Inspection and Request for Information; Inspection Report 05000254/2021001 ML20266G3542020-09-22022 September 2020 Notification of NRC Request for Information for Post-Approval Site Inspection for License Renewal-Phase IV; Inspection Report 05000254/2020012; 05000265/2020012 IR 05000254/20200052020-09-0101 September 2020 Updated Inspection Plan for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2020005 and 05000265/2020005) ML20183A2852020-07-0101 July 2020 Request for Information for an NRC Triennial Baseline Bases Assurance Inspection (Team): Inspection Report 05000254/2020011 and 05000265/2020011 ML20162A1302020-06-10010 June 2020 Information Request to Support Upcoming Problem Identification and Resolution Inspection at the Quad Cities Nuclear Power Station IR 05000254/20190062020-03-0303 March 2020 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2019006 and 05000265/2019006) IR 05000254/20190052019-08-28028 August 2019 Updated Inspection Plan for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2019005 and 05000265/2019005) IR 05000254/20180062019-03-0404 March 2019 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2018006 and 05000265/2018006) ML19014A0932019-01-11011 January 2019 Ltr. 01/11/19 Quad Cities Nuclear Power Station, Unit 1 - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000254/2019001; 05000265/2019001 (DRS-J.Neurauter) IR 05000254/20180052018-08-28028 August 2018 Updated Inspection Plan for Quad Cities Nuclear Power Station -Quad Nuclear Power Station, Units 1 and 2 (Report 05000254/2018005 and 05000265/2018005) IR 05000254/20170062018-03-0202 March 2018 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2017006; 05000265/2017006) IR 05000254/20170052017-08-28028 August 2017 Updated Inspection Plan (Inspection Report 05000254/2017005 and 05000265/2017005) IR 05000254/20160062017-03-0101 March 2017 Annual Assessment Letter for Quad Cities Nuclear Station, Units 1 and 2 (Report 05000254/2016006; 05000265/2016006) ML17033A0622017-02-0101 February 2017 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000254/2017001; 05000265/2017001 IR 05000254/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Quad Cities Nuclear Power Station Units 1 and 2 (Report 05000254/2016005 and 05000265/2016005) ML16175A3552016-06-23023 June 2016 Information Request to Support Upcoming Problem Identification and Resolution Inspection at the Quad Cities Nuclear Power Station IR 05000254/20150062016-03-0202 March 2016 Annual Assessment Letter for Quad Cities Nuclear Power Stations, Units 1 and 2 (Inspection Report 05000254/2015006 and 05000265/2015006) IR 05000254/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2015005; 05000265/2015005) IR 05000254/20140012015-03-0404 March 2015 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2014001; 05000265/2014001) ML14245A3582014-09-0202 September 2014 Mid-Cycle Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 IR 05000254/20130012014-03-0404 March 2014 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2013001; 05000265/2013001) ML14049A4382014-02-14014 February 2014 Inspection Report Plan for 05000254-14-003 & 05000265-14-003 ML13246A2242013-09-0303 September 2013 2013 Quad Cities Nuclear Power Station Mid-Cycle Letter Combined IR 05000254/20120012013-03-0404 March 2013 Annual Assessment Letter for Quad Cities Nuclear Power Station, Unit 1 and 2 (Reports 05000254/2012001 and 05000265/2012001) ML13023A3582013-01-23023 January 2013 Ltr. 01/23/13 Quad Cities ISI, Unit 1, Request for Information ML12249A4102012-09-0404 September 2012 Mid-Cycle Assessment Letter for Quad Cities Nuclear Power Station, Unit 1 and 2 IR 05000254/20110062011-09-0101 September 2011 Mid-Cycle Letter for Quad Cities Nuclear Power Station, Units 1 and 2; 05000254/2011-006; 05000265/2011-006 IR 05000254/20110012011-03-0404 March 2011 Annual Assessment Letter for Quad Cities Nuclear Power Station (Report 05000254-11-001 and 05000265-11-001) ML1024400782010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Quad Cities Nuclear Power Station ML1006104912010-03-0303 March 2010 EOC Annual Assessment Letter, Inspection/Activity Plan ML0924403202009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan IR 05000254/20090012009-03-0404 March 2009 Annual Assessment Letter - Quad Cities Nuclear Power Station, Units 1 and 2 (05000254/2009001; 05000265/2009001) 2024-08-28
[Table view] Category:Letter
MONTHYEARIR 05000254/20240112024-11-13013 November 2024 Biennial Problem Identification and Resolution Inspection Report 05000254/2024011 and 05000265/2024011 IR 05000254/20240032024-11-12012 November 2024 Integrated Inspection Report 05000254/2024003, 05000265/2024003 and 07200053/2024001 ML24317A1432024-11-0404 November 2024 Constellation Energy Generation, LLC, 2024 Annual Report - Guarantees of Payment of Deferred Premiums RS-24-101, License Amendment Request for One-Time Extension of Standby Gas Treatment System Technical Specifications Completion Time to Support Piping Repair2024-11-0404 November 2024 License Amendment Request for One-Time Extension of Standby Gas Treatment System Technical Specifications Completion Time to Support Piping Repair RS-24-126, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in Accordance with 10 CFR 2.390(b)(4)2024-10-31031 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in Accordance with 10 CFR 2.390(b)(4) 05000265/LER-2024-002-01, Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure2024-10-30030 October 2024 Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure SVP-24-065, Offsite Dose Calculation Manual (ODCM) Section 12.2.2 Radioactive Gaseous Effluent Monitoring Instrumentation Report Main Chimney High Range Noble Gas Monitor2024-10-29029 October 2024 Offsite Dose Calculation Manual (ODCM) Section 12.2.2 Radioactive Gaseous Effluent Monitoring Instrumentation Report Main Chimney High Range Noble Gas Monitor IR 05000254/20240102024-10-28028 October 2024 Age Related Degradation Inspection Report 05000254/2024010 and 05000265/2024010 and Notice of Violation RS-24-080, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in .2024-10-16016 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in . RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests SVP-24-059, Correction to Registration of Use of Casks to Store Spent Fuel2024-10-0404 October 2024 Correction to Registration of Use of Casks to Store Spent Fuel ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24247A1642024-09-30030 September 2024 Alternative Request RP-01 IR 05000254/20244022024-09-12012 September 2024 Material Control and Accounting Program Inspection Report 05000254/2024402 and 05000265/2024402 (Public) SVP-24-054, Deviation from BWR Vessel and Internals Project (BWRVIP) Guidelines - Inspection of Top Guide Rim Welds2024-09-11011 September 2024 Deviation from BWR Vessel and Internals Project (BWRVIP) Guidelines - Inspection of Top Guide Rim Welds ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000254/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Quad Cities Nuclear Power Station (Report 05000254/2024005; 05000265/2024005) RS-24-078, Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval2024-08-20020 August 2024 Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval ML24183A1082024-08-0808 August 2024 – Issuance of Amendment Nos. 302 and 298 Adoption of Tstf-505, Provide Risk Informed Extended Completion Times – RITSTF Initiative 4b SVP-24-049, Owners Activity Report Submittal Sixth 10-Year Interval 2024 Refueling Outage Activities2024-08-0707 August 2024 Owners Activity Report Submittal Sixth 10-Year Interval 2024 Refueling Outage Activities IR 05000254/20243012024-08-0101 August 2024 NRC Initial License Examination Report 05000254/2024301; 05000265/2024301 SVP-24-048, Registration of Use of Casks to Store Spent Fuel2024-07-31031 July 2024 Registration of Use of Casks to Store Spent Fuel 05000265/LER-2024-002, Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure2024-07-22022 July 2024 Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions SVP-24-041, Regulatory Commitment Change Summary Report2024-07-0505 July 2024 Regulatory Commitment Change Summary Report SVP-24-043, Registration of Use of Casks to Store Spent Fuel2024-07-0505 July 2024 Registration of Use of Casks to Store Spent Fuel ML24162A0982024-07-0303 July 2024 – Issuance of Amendment Nos. 301 and 297 Adoption of 10 CFR 50.69 Risk Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors SVP-24-040, Registration of Use of Casks to Store Spent Fuel2024-06-25025 June 2024 Registration of Use of Casks to Store Spent Fuel RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations SVP-24-039, Ile Post Exam Package Letter2024-06-12012 June 2024 Ile Post Exam Package Letter RS-24-053, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed2024-06-0606 June 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed ML24110A0492024-05-28028 May 2024 Audit Report Related to the TSTF-505 and 10 CFR 50.59 Amendments ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24141A2102024-05-20020 May 2024 Operator Licensing Examination Approval - Quad Cities Nuclear Power Station, May 2024 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report IR 05000254/20240012024-05-14014 May 2024 Integrated Inspection Report Nos. 05000254/2024001 and 05000265/2024001 RS-24-042, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-05-10010 May 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion 05000265/LER-2024-001, Automatic Actuation of Reactor Protection System During Scram Discharge Volume Leak Rate Testing2024-05-10010 May 2024 Automatic Actuation of Reactor Protection System During Scram Discharge Volume Leak Rate Testing SVP-24-034, Annual Radiological Environmental Operating Report2024-05-10010 May 2024 Annual Radiological Environmental Operating Report RS-24-046, 10 CFR 50.46 Annual Report2024-05-0606 May 2024 10 CFR 50.46 Annual Report ML24109A0662024-05-0202 May 2024 – Relief Request I5R-26, Revision 0 RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests SVP-24-028, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2024-04-26026 April 2024 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report SVP-24-029, Radioactive Effluent Release Report for 20232024-04-26026 April 2024 Radioactive Effluent Release Report for 2023 ML24114A1712024-04-23023 April 2024 State of Illinois (IEMA-OHS) Comment Quad Cities HI-STORM Exemption Environmental Assessment SVP-24-024, Corrected Radioactive Effluent Release Report for 20222024-04-0505 April 2024 Corrected Radioactive Effluent Release Report for 2022 IR 05000254/20245012024-04-0505 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000254/2024501 and 05000265/2024501 RS-24-032, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-04-0505 April 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report 2024-09-04
[Table view] |
Text
March 1, 2023
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 (REPORT 05000254/2022006 AND 05000265/2022006)
Dear David Rhodes:
The NRC has completed its end-of-cycle performance assessment of the Quad Cities Nuclear Power Station, Units 1 and 2, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2022, through December 31, 2022. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.
The NRC determined the performance at Quad Cities Nuclear Power Station, Unit 1, during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green).
The NRC determined the performance at the Quad Cities Nuclear Power Station, Unit 2, during the most recent quarter was within the Regulatory Response Column, the second highest performance column of the NRCs Reactor Oversight Process (ROP) Action Matrix. This conclusion was based on a single inspection finding having low-to-moderate safety significance (i.e., White) in the Mitigating Systems Cornerstone originating in the third quarter of 2022 (ML22313A150), and all PIs within the expected range (i.e., Green).
Therefore, in addition to ROP baseline inspections, the NRC plans to conduct a supplemental inspection in accordance with Inspection Procedure 95001, Supplemental Inspection Response to Action Matrix Column 2 (Regulatory Response) Inputs. This inspection procedure is conducted to provide assurance that the root cause and contributing cause of risk significant performance issues are understood, the extent of condition and the extent of cause are identified, and the corrective actions are sufficient to prevent recurrence. This inspection will be scheduled when you notify the NRC of your readiness.
D. Rhoades
The enclosed inspection plan lists the inspections scheduled through December 31, 2024.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In response to the COVID-19 public health emergency (PHE), the NRC adjusted inspection plans and schedules to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. While the PHE continues, overall conditions throughout the country support performance of our inspection and oversight activities returning to normal onsite presence by our resident and region-based inspectors and completion of nominal baseline inspection samples. We continue to monitor site-specific conditions and, as discussed in our November 2, 2021, memo, Implementation of Inspection Programs Following Re-Entry from the Public Health Emergency for the Reactor Safety Program (ML21295A302), it may be necessary to alter how and when we perform our inspection and oversight activities as we balance the importance of protecting the health and safety of our staff with the need to conduct effective oversight that supports the NRCs critical safety mission.
For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.
Beginning on January 1, 2023, the engineering inspection frequency will transition from a triennial (3-year) to a quadrennial (4-year) cycle. The new engineering inspection program will consist of a Comprehensive Engineering Team Inspection (CETI)1 and three Focused Engineering Inspections (FEIs) that will be performed in each quadrennial cycle. For the cycle beginning in 2023, the FEIs will be: Fire Protection Team Inspection, Commercial Grade Dedication and an engineering inspection that reviews age-related degradation and management2.
1 Aspects of the Design Basis Assurance Inspection (DBAI), Evaluations of Changes, Tests, & Experiments, and Heat Sink inspections will be included in the new CETI inspection. Previously scheduled Evaluation of Changes, Tests, & Experiments and Heat Sink inspections have been cancelled and removed from attached Report 22.
2 The Age-Related Degradation procedure is publicly, and the NRC plans to implement the first inspection of this type beginning in July 2023.
D. Rhoades
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Mr. Robert Ruiz at 630-829-9732 with any questions you have regarding this letter.
Sincerely,
/RA/
Julio F. Lara, Director Division of Operating Reactor Safety
Docket Nos. 05000254, 05000265, and 07200053 License Nos. DPR-29 and DPR-30
Enclosure:
Inspection Plan
cc: Distribution via LISTSERV
D. Rhoades
Letter to David P. Rhoades from Julio F. Lara dates March 1, 2023.
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 (REPORT 05000254/2022006 AND 05000265/2022006)
DISTRIBUTION:
Jessie Quichocho Marc Ferdas Paul Zurawski RidsNrrDorlLpl3 RidsNrrPMQuadCities Resource RidsNrrDroIrib Resource John Giessner Mohammed Shuaibi Diana Betancourt-Roldan Allan Barker R3-DORS ROPassessment.Resource@nrc.gov
ADAMS Accession Number: ML23054A143 Publicly Available Non-Publicly Available Sensitive Non-Sensitive OFFICE RIII
RIII
RIII
NAME NShah:mb RRuiz JLara
DATE 02/23/2023 02/24/2023 02/24/2023
OFFICIAL RECORD COPY
Site Inspection Activity Plan 07200053 - Quad Cities (ISFSI)
01/01/2023 - 12/31/2024 Unit Start End Activity CAC Title Staff Count ISFSI Security Inspection
4/24/2023 4/28/2023 IP 81311 001006 Physical Security Requirements for Independent Spent Fuel Storage Installations ISFSI Cask Loading Inspection
6/24/2024 6/28/2024 IP 60855 001001 Operation Of An ISFSI Prepared on 2/22/2023 11:18:05 AM 1 of 3
Site Inspection Activity Plan Quad Cities 01/01/2023 - 12/31/2024 Unit Start End Activity CAC Title Staff Count Quad Cities January 2023 Initial License Exam
1,2 1/1/2023 1/7/2023 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1,2 1/29/2023 2/4/2023 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)
1,2 2/5/2023 2/10/2023 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)
Corporate Security Baseline Inspection
1,2 1/23/2023 1/27/2023 IP 71130.08 000740 Fitness For Duty Program Security Baseline Inspection
1,2 2/27/2023 3/3/2023 IP 71130.02 000734 Access Control 1,2 2/27/2023 3/3/2023 IP 71130.08 000740 Fitness For Duty Program 1,2 3/20/2023 3/24/2023 IP 71130.07 000739 Security Training 1,2 4/24/2023 4/28/2023 IP 71130.09 001656 Security Plan Changes 1,2 4/24/2023 4/28/2023 IP 71151 001338 Performance Indicator Verification 1,2 4/24/2023 4/28/2023 IP 81311 000831 Physical Security Requirements for Independent Spent Fuel Storage Installations Inservice Inspection Unit 1
1 3/27/2023 4/7/2023 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
Radiation Protection Baseline Inspection
1,2 4/3/2023 4/7/2023 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls Cyber Security Inspection
1,2 5/15/2023 5/19/2023 IP 71130.10 000741 Cybersecurity Radiation Protection Baseline Inspection
1,2 6/5/2023 6/9/2023 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2 6/5/2023 6/9/2023 IP 71124.04 000728 Occupational Dose Assessment Security Baseline Inspection
1,2 9/5/2023 9/8/2023 IP 71130.14 000743 Review of Power Reactor Target Sets Emergency Preparedness Baseline Inspection / Performance Indicator Verification
1,2 9/25/2023 9/29/2023 IP 71114.02 000717 Alert and Notification System Testing 1,2 9/25/2023 9/29/2023 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1,2 9/25/2023 9/29/2023 IP 71114.05 000720 Maintenance of Emergency Preparedness 1,2 9/25/2023 9/29/2023 IP 71151 001397 Performance Indicator Verification Comprehensive Engineering Team Inspection
1,2 10/16/2023 11/3/2023 IP 71111.21M 000713 Comprehensive Engineering Team Inspection Quad Cities Biennial Requalification Program Inspection
Prepared on 2/22/2023 11:18:05 AM 2 of 3
Site Inspection Activity Plan 1,2 11/13/2023 11/19/2023 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Radiation Protection Baseline Inspection
1,2 11/13/2023 11/17/2023 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Corporate Security Baseline Inspection
1,2 1/22/2024 1/26/2024 IP 71130.01 000733 Access Authorization Emergency Preparedness Exercise Inspection / Performance Indicator Verification
1,2 2/26/2024 3/1/2024 IP 71114.07 000722 Exercise Evaluation - Hostile Action (HA) Event 1,2 2/26/2024 3/1/2024 IP 71151 001397 Performance Indicator Verification Security Baseline Inspection
1,2 2/26/2024 3/1/2024 IP 71130.01 000733 Access Authorization 1,2 2/26/2024 3/1/2024 IP 71130.02 000734 Access Control 1,2 2/26/2024 3/1/2024 IP 71130.09 001656 Security Plan Changes 1,2 2/26/2024 3/1/2024 IP 71151 001338 Performance Indicator Verification 1,2 4/1/2024 4/5/2024 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance Inservice Inspection Unit 2
2 3/18/2024 3/29/2024 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
Radiation Protection Baseline Inspection
1,2 3/18/2024 3/22/2024 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 3/18/2024 3/22/2024 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation Quad Cities May 2024 Initial License Exam
1,2 4/21/2024 4/27/2024 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1,2 5/26/2024 6/1/2024 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)
1,2 6/2/2024 6/7/2024 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)
Radiation Protection Baseline Inspection
1,2 6/24/2024 6/28/2024 IP 71124.07 000731 Radiological Environmental Monitoring Program Functional Engineering Inspection - Aging of SSCs
1,2 8/5/2024 8/23/2024 IP 71111.21N.04 001832 Age-Related Degradation Biennial Problem Identification and Resolution Inspection
1,2 9/9/2024 9/27/2024 IP 71152B 000747 Problem Identification and Resolution Force-on-Force Planning and Exercises - QUAD
1,2 10/7/2024 10/11/2024 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1,2 10/28/2024 11/1/2024 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Radiation Protection Baseline Inspection
1,2 11/4/2024 11/8/2024 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Prepared on 2/22/2023 11:18:05 AM 3 of 3