IR 05000424/1990007

From kanterella
Jump to navigation Jump to search
Insp Repts 50-424/90-07 & 50-425/90-07 on 900312-16.No Violations or Deviations Noted.Major Areas Inspected: Inservice Insp (ISI) & Review of ISI Program Implementing Procedures & Unit 1 ISI Plan for Current Outage
ML20042E521
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 03/22/1990
From: Blake J, Newsome R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20042E520 List:
References
50-424-90-07, 50-424-90-7, 50-425-90-07, 50-425-90-7, NUDOCS 9004230521
Download: ML20042E521 (10)


Text

.- _

.

,

'*

UNIT E3 STATES

[pt 882g,q%"

NUCLEAR REOULATORY COMMISslON i

,

CE! ION il

8O*

b 101 MARIETTA STREET N.W.

D

'f ATLANTA, CEORGI A 30323 l

%,..... p

(

Report Nos.: 50-424/90-07 and 50-425/90-07 l

Licensee: Georgia Power Company j

P.O. Box 1295

,

Birmingham, AL 35201 l

.

DotLct Nos.: 50-424 and 50-425 License Nos.:

NPF-68 and NPF-81

,

facility Name: Vogtle 1 and 2

,

l Inspection Conducted: March 12 thru 16,1990 Inspectors:

ud/ dd.

3-> /- 90 u_tae>we -

R. W. Newsome (

Date Signed

3,daz/9d Approved [Y mc ee m J. J. Blake, Chief Fate Signed Materials and Processes Section

'

Engineering Branch

Division of Reactor Safety SUMMARY

!

i i

Scope

This routine, unannounced inspection was conducted on site in the area of Inservice Inspection (ISI) ard included a review of the ISI program implementing procedures and the Unit 1 ISI plan for this outage; reviews of i

nondestructive examination (NDE) procedures; observations of in-progress NDE

examinations; independent examination verifications; reviews of NDE personnel

cualifications; reviews of NDE equipment calibration and material certification

!

cocumentation; and, a review of completed NDE examination data, j

Results

In the areas inspected, violations or deviations were not identified.

,

This inspection indicated that ISI nondestructive examinations were being (

conducted adequately.

Also, documentation of examination results, personnel

,

.

qualifications, and material certification records were adequate.

"

,

i

.

9004230521 9oo42o gDR ADOCK 05o00424 PDC

,

.i

,

.

-

,

i

.

!

,

i

!

!

REPORT DETAILS

!

1.

Persons Contacted l

Licensee Employees

!

i

  • J. Aufdenkampe, Manager. Technical Support

!

  • H. Beacher, Senior Plant Engineer

!

  • G. Bockhold, General Manager
  • M. Horton, Manager, Engineering Support

~

  • D. Hudson, Senior Plant Engineer i
  • W. Kitchens, Assistant General Manager, Operations

.

'

  • G. McCarley, Supervisor, Independent Safety Engineering droup
  • A. Mosbaugh, Assistant General Manager, Support

.

  • R. Odem Supervisor, Plant Engineering

!

"

  • J. Swartzwelder, Manager, Operations
  • J. Williams, Supervisor, Plant Engineering i

t Other licensee employcas contacted during this inspection included engineers, security force members, technicians, and administrative personnel.

>

t Other Organizations

'

e

.

Southern Company Services

  • J. Churchwell, Senior Engineer i
  • R. Keck, ISI Project Coordinator l

NRC Resident inspector

,

  • D. Starkey, Resident Inspector
  • Attended exit interview t

2.

Inservice Inspection

[

The inspector reviewed documents and records and observed activities, as

-

indicated below, to determine whether ISI was being conducted in

'

accordance with applicable procedures, regulatory; requirements, and licensee commitments. The applicable code for ISI is the American Society of Mechanical Engineers Boiler and Pressure Vessel. (ASME BAPV) Code,-

Section XI,1983 edition with addenda through Summer 1983.

Westinghouse Electric Corporation (W) had the responsibility for the eddy current (EC)

examination of steam generator (SG) tubing 6nd utilized automated

"

evaluation equipment for the primary data evaluation and a variety of NDE laboratory personnel to conduct the secondary, manual.. data nyaluations, a

Westinghouse also had the responsibility for the automated ultrasonic

~

,

i

+

F

...

--

_

,

!

'

-

-

.

!

i

examination of the reactor vessel welds examined during this outage and (

utilized the demonic Data Recording and Processing System (UDRPS) to

'

accomplish thm euminations.

Southern Company Services (SCS) has the-responsibility for the remainder of the ISI examination activities and is

}

utilizing SCS and Lambert, MacGill, Thomas, Inc. (LMT) personnel to

'

conduct the examinations.

Examinations were conducted by SCS and LMT personnel during this inspection! however, just prior to this inspection, the reactor vessel ultrasonic examinations and the eddy current examinations of the steam generator tubing had been completed.

The NRC inspector reviewed the preliminary-results reports for both the completed reactor vessel examinations and the steam generator tubing examinations and reviewed quality assurance documentation relative to the procedures, personnel qualifications, and equipment used to conduct both the completed and on going NDE examinations.

a.

ISIProgramReview, Units 1and2(73051)

The inspector reviewed the following documents relating to the ISI program to determine whether the plan had been approved by the licensee and to assure that procedures and plans.had been established (written, reviewed, approved and issued) to control and accomplish the following applicable activities:

organizational structure including qualifications, training, responsibilities, and duties of personnel responsible for ISI; audits including procedures, frequency, and qualif1 cation of personnel; general Quality Assurance requirements. Including examination reports, deviations from previously established program, material certifications, and identification of components to be covered; work and inspection procedures; control of processes including suitably controlled work conditions, special methods, and use of qualified personnel; l

corrective action; document control; control of examination equipment; quality records including documentation of indications-and NDE findings, review of documentation, provisions to assure l

1egibility and retrievability, and corrective action; scope of the inspection including description of areas to be examined.. examination category, method of inspection, extent of examinations, and justifi-cation for any exception; definition of inspection interval and extent of examination; qualification of NDE personnel; and, controls of generation, approval, custody, storage and maintenance of NDE.

records.

ISI Dutage Plan Second Refueling Outage (Period 1/ Interval 1)

-

with Dev. 001

.

.

.

.

_.

i

.

.

,

.

.

SCS/ Inspection, Testing, and Engineering Policy and Procedures

.

-

'

Manual, Revision 1 Sect on Title i

2-2 R-0 Examination And Testing Plan 2-6 R-0 Final Reports

'

3-1 R-0 On-Site Data Review

3-2 R-0 On-Site Data Control

.

3-4 R-0 Indication Notification t

AUX-H/F/V-300(R-4)

Procedure (Written Practice) for i

with Dev. 001 Qualification and Certification of

Nondestructive Examination Personnel

'

AUX-V-308(R-1)

Preservice And Inservice Handling And-

-

.

Care Of Calibration Blocks Under SCS l

Control b.

ReviewofNDEProcedures, Units 1and2(73052)

!

(1) The inspector reviewed the procedures listed below to determine

!

whether these procedures were consistent with regulatory requirements and licensee commitments. The procedures were also reviewed in the areas of procedure approval, requirements for

!

qualification of NDE personnel, and compilation of required records; and, if applicable, division of responsibility between

.

the licensee and contractor personnel if contractor. personnel are involved in the ISI effort.

<

GAE-ISI-153(RO)

General Requirements For The Ultrasonic

-

'

Examination Of The Reactor Pressure Vessel Using UDRPS GAE-ISI-154(RO)

Ultrasonic Examination Requirements For'

-

Outlet Nozzles And Piping Welds From

)

The Nozzle Bores Using UDRPS

.

UT-V-407(RI)

Manual Ultrasonic Examination Of

-

full-Penetration Welds (.15" to.S")

+

.

PT-V-605(R1)

Color Contrast, Solvent-Removable

-

Liquid Penetrant Examination Procedure

!

M1-V-505(RI)

Dry Powder Magnetic Particle t

-

Examination: Yoke Method 85052-0(RI)

Visual Examination Of Component

-

<

Supports And Hangers

!

h

._

\\

-

.

.

,

.

i t

84001-C(RO)

Inspection Of Component Supports And

-

Engineering Evaluation

.

MRS 2.4.2 GPC-1 (RO) Digital Multi-Frequency Eddy Current i

-

Inspection Of Preservice And Inservice

Heat Exchanger Tubing DAT-GYD-001(R3)

Data Analysis Guidelines

[

-

All procedures listed above have been reviewed during previous

,

NRC inspections.

Only current revisions were reviewed during

,

this inspection.

>

(2) The inspector reviewed the Ultrasonic procedures to ascertain had been reviewed and approved in accordance with whether they's established QA procedures. The procedures were the licensee also reviewed for technical adequacy and conformance with ASME,Section V. Article 5 and other licensee commitments / requirements'

f in the following areas:

type of apparatus used; extent of coverage of weldment; calibration requirements; search units; beam angles; DAC curves; reference level for monitoring discontinuities; method for demonstrating penetration; limits e

for evaluating and recording indications; recording significant indications; and, acceptance limits.

(3) The inspector reviewed the 1.1 quid Penetrant procedure to ascertain whethe" it had been reviewed and approved in accordance with the licensee's established QA procedures.

The procedure was also reviewed for technical adequacy and confonnance with ASME,Section V, Article 6, and other licensee commitments / requirements in the following areas:

specified method; penetrant material identification; penetrant materials analyzed for sulfur; penetrant materials. analyzed for total halogens; surface temperature; acceptable pre-examination

!

surface conditioning; method used for pre-examination surface cleaning; surface drying time prior to penetrant application;

,

i method of penetrant application; penetrant dwell time; method used for. excess penetrant removal; surface drying prior to developer application, if applicable; type of developer;

,

l examination technique; evaluation techniques;. and, procedure

requalification.

)

t L

(4) The inspector. reviewed the Magnetic Particle procedure to ascertain whether it had been reviewed and approved in

,

accordance with the licensee's establishd QA procedurcs. The

'

procedure was reviewed for technical adequacy-and for conformance with the ASME Code Section V, Article 7, and other licensee consnitments/ requirements in the following areas:

examination methods; contrast of Sy sewder particle color with background; surface temperature; suspemion medium and surface

,

temperature requirement for wet particles; viewing conditions; E

k

..

. - - _.

.

-

-

..

-

. _ _

. _.

.

'

-

.

-

1 examination overlap and directions; pole or prod spacing; current or lifting power (yoke); and, icceptance criteria.

l

.

(5) The inspector reviewed the Visual examination procedures to

!

determine whether they contained sufficient instructions to I

assure that the following parameters were. specified and controlled within the limits permitted by the applicable code, j

standard, or any other specification requirement:

method -

i direct visual, remote visual or translucent visual; epplication

- hydrostatic testing, fabrication procedure, visual examination

.

of welds, leak testing, etc.; how visual examination is to be performed; type. of surface-condition available; method or implement used for surface preparation, if any; whether direct

-

or remote viewing is used; sequence of performing examination, when applicable; data to be tabulated, if any; acceptance criteria is specified and. consistent with the applicable code

,

section or controlling specification;- and, report form comple-

.

tion.

(6) The inspector reviewed the Eddy Current procedures for technical'

,

content relative to:

multichannel examination unit,

,

multichannel examination indication equipment is specified,

~

examination sensitivity, method of examination, method of.

calibration and calibration sequence, and acceptance criteria.

',

All procedures reviewed appeared to contain the necessary elements -

for conducting the specific examination.

'

c.

ObservationofWorkandWorkActivities, Unit 1(73N)

The inspector observed work activities, reviewos certification records of NDE equipment and materials, and reviewed NDE personnel qualifications for personnel that had been utilized during the required ISI examinations during this outage.

The observitions and

-

reviews conducted by the inspector are documented below.

!

(1) The. inspector observed calibration activities and the in-process ultrasonic (UT) examinations being conducted on. 4 pressurizer safety and relief valve circumferential. piping welds and 2 steam generator number 3 auxiliary feedwater circumferential-piping welds.

These observations were compared with the applicable procedures and the ASME B&PV Code in the following areas:

availability of and compliance with approved NDE procedures; use of knowledgeable NDE personnel; use of NDE personnel qualified to the proper level; type of apparatus used; calibration

requirements; search units; beam angles; DAC curves; reference level for monitoring discontinuities; method of demonstrating penetration; extent of weld / component examination coverage;

'

limits of evaluating and recording indications; recording significant indications; and, acceptance limits.

i e

-

-.

....,,-

-. -

,

-,

-.. --

-, -..

.

.

.

,

The inspector conducted en independent ultrasonic verification examination, using SCS equipment, on portions of. 3 of the pressurizer safety and relief valve welds previously observed being examined.

These examinations were conducted in order to evaluate the technical adequacy of the ultrasonic examination i

procedure being used by the licensee and to assess the validity

'

of the information being reported by the ultrasonic examiners, j

The verification ultrasonic examinations conducted by the inspector indicated that the procedure being used to conduct the i

examinations' is adequate and the verification examination l

results compared favorably with the information being reported

-

by the ultrasonic examiners.

The following ~ listed ultrasonic equipment and materials certification records were reviewed:

Ultrasonic Instruments Manufacturer /Model Serial No.

,

Sonic /MK I 14494E KK/USK-7B 31451-1021 KB/USIP-12 29321-1082 The inspector reviewed spectrum analysis data for the ultrasonic transducers listed below:

Serial No.

Size Frequency

'

C26682 1.0" 2.25 MHz F18232

.75" 2.25 MHz 031328

.375" 2.25 MHz 125391 1.0" 2.25 MHz 125388 1.0" 2.25 MHz Ultrasonic Couplant Batch Numbers 8767 and 8982 Ultrasonic Calibration Bic:h ISI-D-404A, ISI-D-304A.

131-D-307A, ISI-D-319A, and ISI-D-315A (2) The inspector observed. the in process liquid-penetrant (PT)

examinations of 2 circumferential piping-welds. One weld was a 4" safety injection system weld, weld number. 3 on sketch 151-11201-29. and the other was a 2" main loop crossover drain line weld, weld number 1 on sketch ISI-11201-031.

In addition-to the 2 welds = above, the-inspector observed the in process examination of an integral attachment weld to a 6" safety injection' system pipe.

This attachment weld was designated as weld number 27 on sketch SIS-11204-039. These observations were-

,

.

,

.

compared with the applicable procedure and the ASME B&PV Code in the following areas:

specified method, penetrant materials identified; penetrant materials analyzed for halogens and sulfur; acceptable pre-examination surface; surface temperature; surface drying time prior to penetrant application; method of penetrant application; penetrant dwell time; method used.for excess penetrant removal; surface drying prior to developing, if applicable; type of developer; examination technique; evaluation technique; and, reporting of examination results.

The NRC inspector re-evaluated the main coolant-loop crossover drain line weld and the integral attachment weld following the PT examiners evaluation of the welds but prior to the developer being removed from the weld surfaces. These re-evaluations were conducted in order to determine if the evaluations performed by the PT examiner was.in accordance with the applicable procedure acceptance criteria and to determine if the examination results were being reported as required.

The re-evaluations conducted by the NRC inspector indicated that the proper evaluation was made by the PT examiners and that the examination results were being reported as required.

The inspector's review of the below listed liquid penetrant-materials certification records indicated that the sulfur and halogen content of the material was within acceptable content limits.

Materials Batch Number Liquid Penetrant 87A045 Cleaner / Remover 89L01P, 89E04K Developer 88H043 (3) The inspector observed the in-process magnetic particle (MT)

examinations of 3 steam generator number 4 auxiliary feedwater circumferential welds, numbers 40, 41, and 42.

These

- !

observations were compared with the applicable procedures and the Code in the following areas: examination methods; contrast of dry powder particle color with background; surface temperature; suspension medium for wet particles,.if applicable; viewing conditions; examination overlap (and directions; pole or prod spacing; current or lifting power yoke);_and acceptance criteria.

During the examination of weld 40, two exial direction linear indications, one approximately 3"

long and the other i

approximately 7" long in the pipe spool piece adjacent to the weld, were detected by the examiners.

Final disposition of these indications had not been determined at the conclusion of this inspection.

i

!

I

_

-_

_

_ __

_ _ _ _

._..

.

f

.*

'

.

!

The inspector conducted MT verification examinations, using SCS

!

equipment, on portions of 2 of the welds previously observed l

being examined.

These examinations were conducted in order to evaluate the technical adequacy of the examination procedure

'

being used by the licensee to perform examinations and to assess l

the validity of the information being reported by the MT

!

examiners.

,

The information reported by the NT examiners compared favorably

!

with the verification examinations.

'

'

The inspector reviewed documentation indicating that a 10 pound lift test had been performed on magnetic particle alternating

current (AC) yokes 445 and 2363.

The certification record for

"

'

the lift test plate that was used to conduct the tests, SCS-112, was reviewed to confirm the weight of the test plate.

A review of the magnetic particle material certification record

'

for batch number 87A035 indicated the particles met the applicable specifications requirements.

,

(4) Certification records for EC calibration standards ISI-D-806A i

and ISI-D-806D were reviewed for material type, correct-

'

fabrication, and artificial flaw location and size.

(5) The inspector reviewed personnel qualification documentation for

,

10 UT examiners, 2 pi examiners, 2 MT examiners,-2 VT examiners,

6 EC.

These personnel qualifications were reviewed in the

,

following areas:

employer's name; person certified; activity

!

qualified to perform; current period of certification; signature of employer's designated representative; basis used -for

.

certification; and, annual. visual acuity, color vision examination, and periodic recertification.

e d.

Data Review and Evaluation, Unit 1(73755)

{

v (1) Records of completed ISI nondestructive examinations for 28 UT

<

examinations,. including the reactor vessel preliminary examination results, and-27' PT,18 MT, and 17 VT examinations were selected and reviewed to ascertain whether: themethod(s),

technique, and extent of the examination complied with the ISI plan and applicable NDE procedures; findings were properly recorded and evaluated by qualified personnel; progransnatic deviations were recorded as required; p(ersonnelinstruments}.

calibration blocks, and NDE materials penetrants, couplants

'

were designated.

i (2) The inspector reviewed the, preliminary EC data analysis results and a sampie of associated completed records for over 400 SG

' ?

tubes, ar iroximately 100 tubes from each of - four Steam

,

Generators.

The reviews were compared with the applicable

<

.f

.

-

--

-

-

.

. -..

...

se

.

.o,

.

O

procedures and the ASME B&PV Code in the following areas: the multichannel eddy current examination equipment has been identified; material permeability has' been recorded; method of examination has been recorded; and, results are consistent with acceptance criteria.

All of the examination reports reviewed appeared to contain the required examination information including disposition of indications, if any.

A random sample of current examination results were compared with historical examination results.

No major discrepancies were noted during the comparison.

In the areas inspected, violations or deviations were not identified.

3.

Exit Interview-The inspection scope and results were summarized.on March 16, 1990, with those persons indicated in paragraph 1.

The inspector described the areas ins pected and discussed in detail the inspection results. listed below.

Altlough reviewed during this inspection, proprietary information is not contained in this report.

Dissenting coninents were not received from the licensee.

4.

Acronyms and Initialisms AC Alternating Current

-

ASME American Society of Mechanical Engineers

-

B&PV Boiler and Pressure Vessel

-

DAC Distance Amplitude Curve

-

Dev.

Deviation

-

EC Eddy Currer.t

-

ISI Inservice Inspection

-

KB Krautkramer/Branson

-

KK Krautkramer

-

LMT Lambert, MacGill, Thomas, Inc.

-

HT Magnetic Particle

-

MHz Megahertz

-

NDE Nondestructive Examination

-

No.

Number

-

NRC Nuclear Regulatory Commission

-

PT Liquid Penetrant

-

QA Quality Assurance

-

R Revision

-

SCS Southern Company Services

-

SG Steam Generator

-

UDRPS -

Ultrasonic Data Recording and Processing System UT Ultrasonic

-

VT Visual

-

Westinghouse Electric Inc.

- l

}{

-

'