IR 05000424/1993010

From kanterella
Jump to navigation Jump to search
Insp Repts 50-424/93-10 & 50-425/93-10 on 930510-14.No Violations Noted.Major Areas Inspected:Startup Testing & Power Escalation of Unit 1 & Routine Core Performance Surveillance of Unit 2
ML20044G270
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 05/26/1993
From: Burnett P, Peebles T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20044G267 List:
References
50-424-993-10, 50-425-93-10, NUDOCS 9306020254
Download: ML20044G270 (8)


Text

- - _ _ -

. _ _ _ _ _

_

____ _ _ ___________ _ _ - _ _ _ _ _ _ _ _ _ - __________________ - - _

_

  1. ["Dg UNITED STATES

[

'

o,,

WUCLEAR REGULATORY COMMISslON o

REGION ll

$

j 101 MARIETTA siREET,N_W.

  • f ATLANTA, GEORGI A 30323 i

\\

p$

IteportNos.: 50-424/93-10 and 50-425/93-10 i

Licensee:

Georgia Power Company P. O. Box 1295 Birmingham, AL 35201

-

Docket Nos.:

50-424 and 50-425 License Nos.: NPF-68 and NPF-81 Facility Name: Vogtle 1 and 2 Inspection Conducted: May 10-14, 1993 Inspector: _2 orgd (I W W

'P d. BurnetT ~ '

~

Date Signed Approved by:

5 4[f)

T. A.' Peeblss, Chief D6te Signed Operations Branch Division of Reactor Safety SUMMARY Scope:

This routine, announced inspection was conducted in the areas of startup testing and power escalation of Unit I and routine' core performance surveil-lance of Unit 2.

Results:

The records reviewed, supported the conclusion that the tests inspected'were performed with. acceptable methodology and results. The test results identi-fied a failure to correctly predict the integral and differential reactivity-worth of control rods (paragraph 3).

-The new licensed power level of 3565 MWth could not be achieved with a reduced average coolant temperature, but was obtained once the average temperature was increased 1.5 *F (paragraph 4).

The routine surveillance tests of Unit 2 were performed with acceptable frequency and results (paragraph 5).

One previous violation was closed (paragraph 6).

.

No violations or deviations were identified.

9306020254 930526

_

PDR ADDCK 05000424 O

PDR

...., _.

.... _ _....

.

...

--______-

_ _ _ _ _.

.

[

,'

' REPORT DETAILS l.

.

1.

Person:; Contacted Licensee Employees

  • S. A. Bradley, Reactor Engineering Supervisor
  • J. B. Beasley, Assistant General Manager
  • W. L. Burmeister, Manager, Engineering Support
  • S. H. Chestnut, Manager, Technical Support
  • C. L. Christiansen, SAER Supervisor
  • G. R. Frederick, Manager, Maintenance
  • W. C. Gabbard, Nuclear Specialist
  • W. F. Kitchens, Assistant General Manager, Plant Support

,

  • R. L. LeGrand, Operations Manager l
  • A. G. Rickman, Senior Engineer, SAER
  • M. H. Sheibani, Nuclear Safety and Compliance Supervisor
  • W. B. Shipman, General Manager
  • J. E. Swartzwelder, Manager, Outage Planning Other licensee employees contacted included engineers, operators, and office personnel.

Oglethorp Power Company Representative

  • T. P. hozingo NRC Resident inspectors P. A. Balmain, Resident Inspector
  • B. R. Bonser, Senior Resident Inspector

R. D. Starkey, Resident Inspector i

  • Attended the exit interview on May 14, 1993 Acronyms and initialisms used throughout this report are defined in the final paragraph.

2.

Unit 1, Cycle 5 Precritical Activities (72700)

The inspector reviewed the following procedures completed prior to criticality for Unit 1, cycle 5:

a.

88006-C (Revision 5), Rej Drop Time. Measurement, with Rod Drop Test Cart, was performed twice.

Cold rod denps were completed over the period of April 20-21, 1993, to assure that all rods were falling freely; the average time to dashpot entry was 140 seconds. For the-hot rod drops on April 23-24, 1993, all four RCPs were running, and RCS was 2: 551*F throughout the measurements. The average drop time to dashpot entry was 1.56 seconds. The slowest drop time was 1.61 seconds, and the requirements of TS 3/4.1.3.4.a were satisfied.

_ _ _ _ _ _ - _ _ - _ _ _ _

_____._ - _ _____

.-

-.

,-. -

.-

. -.

.

. -.

-.

-

.

_

'l

,

I

'

Report Details

i

'

b.

88018-C (Revision 5), NIS Alignment for Refueling, was used to calculate preliminary, conservative IRNI and PRNI trip setpoints for

-.

the beginning-of-cycle use until measured calibration data became (

available during power escalation.

For each ion chamber, full power.

!

currents, obtained during the last calibration of the previous cycle,

,

were adjusted by the ratio of predicted power in adjacent fuel assemblies for the current cycle, to assembly powers measured when the i

chamber currents were recorded.

For the Unit 2, cycle 3 startup, this j

method did not yield conservative results for the IRNIs.

For this i

startup, the fuel assembly locations selected for use in the ratio' and

!

the aesembly weighting factors were changed.

Conservative results l

were obtrined.

!

c.

88003-C (Revision 2), Shutdown Margin by Minimum Bank Height, was

-

completed prior to rod withdrawal, using data from the NDR. The

'

requirements of TS 4.1.1.1.1.d (COLR) were satisfied.

.

.

i 3.

Unit 2. Cycle 3 Initial Criticality and Low-Power Tests (72700, 61708,

.;

61710)

.l t

88002-C (Revision 5), Reload Low Power Physics Testing, was performed i

during the period April 21 to April 26, 1993. Activities accomplished

!

under this procedur e included initial criticality for the cycle, AR0 Cs

!

determination, ITC-MIC measurement, and control rod worth measurements. A

good feature of the approach to criticality included careful checkout of

!

^

the SRNis using a reliability factor test (analogous to the chi-squared test) to assure proper functioning of those instrument channels. The test

was performed successfully for both channels prior to withdrawing control i

banks for ICRR mcasurements and prior to beginning dilution to l

criticality.

The two SRNis compared closely in ICRR throughout the

approach to criticality.

t

,

I The procedure records indicate that initial criticality for cycle 5 was achieved in a well controlled manner.

Subsequently the ARO C was (

s determined to be 1901 ppm B, which was in good agreement with the

predicted C of 1891 ppm B.

j a

,

..

The DRC was checked out usin;,

"lly generated exponential signals simulating bot.h positive and e reactivity inputs.

Later the

'i

'

,

dynamic test, using reactor ger..cated periods was performed using only

positive reactivities.

In all cases, measured and predicted reactivities

-:

agreed acceptably.

J The ITC was measured at ARO for a 3*F cooldown followed by a 3.5'F heatup.

l The corresponding ITCs were 3.3 and 2.8 pcm/*F. Agreement within 1 pcm/*F

!

indicates good control of the variables of the measurement, _ regardless 'of l

the relatively small temperature changes used in the measurements. The resulting HTC was 5.02 pcm/*F, which was acceptably less than the TS.

,

3.1.1.1 (COLR) limit of 7 pcm/*F. Common practice is to use temperature i

changes of at least 4*F.

With the measured MTC approaching the TS limit,

'

i

!

l f

f'

t

'~'

" ~ ' '

-

  • ' - '

- - - - - ' ^ ^ ^ - -

.

.

..-

-. -_-.

.-.

-

..

.

.-.

-

i

!

t

. Report Details

.

!

'

the greater temperature change would increase the resolution of the

-!

measurement and the confidence that the TS limit was satisfied. The

,

current measurements are not in question, but future measurements, with

[

noisier chart records for analysis might be questioned.

Shutdown bank B, the calculated highest reactivity worth control. rod bank, was designated the reference bank, and its reactivity worth was measured

'

.i

'

during boron dilution. The worth of each of the remaining control rod

.

banks was determined using the rod swap technique with the reference bank.

!

The results for all banks are given below.

j Reactivity worth (ncm)

{

i Bank Predicted Measured Difference (%)

i control A 357 360.6

+1.0 t

control B 696 607.3-12.7

!

,

'

control C 775 744.7-3.9

,

control D 484 507.7

+4.9 shutdown A 287 278.6-2.9 shutdown B(REF)

892 780.0-12.6 l

shutdown C 409 384.9-5.9

!

shutdown D 406 380.9-6.2 I

shutdown E 436 391.4-10.2 l

'

TOTAL 4742 4436.1

- 6'. 5 -

The review criterion for the reference bank worth and total bank worth was l

10% of prediction. For the remaining rod banks the criterion was the larger of 115% or 1100 pcm of prediction. The result of the reference

,

bank measurement did not satisfy the review criterion.

l l

The inspector independently analyzed the reactivity traces for the

!

reference bank worth measurement using a mechanically different means of j

determining reactivity increments from that used by the' licensee. The

!

integral worth obtained from that analysis was 776 pcm, whicn.

accept-l able agreement for the method used. The measured and predicted differen-l tial reactivity curves are significantly different, as can be seen from

!

the figure below.

It appears that much of the difference in integral j

worth is the result of over predicting the worth of the bank in the lower-l half of the core.

The large, non-conservative error in the prediction is

'

currently being reviewed by Westinghouse, and the licensee expects a j

formal report on and evaluation of the error in the near future. The

licensee stated that the results of the report by Westinghouse would be j

incorporated into the startup report.

Shutdown margin is not an issue j

this early in core life.

j All predicted values discussed in this paragraph were obtained from the NDR.

q l

l J

---

_

..

.

..

!

i L

!

I Report Details

{

.

.

VOGTLE 1, Cycle 5 i

.

Reference Bank 7-

<~

- W asu d 6-I

's

- Predicted

,/

y 5-

/

'x

/

\\

y 4-

'

y j

N t

li l

'x'

3-i

's

/

\\

E

!

\\

f

/

\\

i g

/

\\

'

,

/

/

\\

1- /

\\

!

O !.

,,]

,,,,

,i

,.

,

,

,,.

.

0.0 60.0 120.0 180.0 240.0 Steps Wrthdrawn

r The measured curve in the figure is from the inspector's analysis of the DRC data.

Because of software limitations, a smoothed result is shown

'

rather than the measured points.

The licensee does not determine a measured DBW for comparison with the predicted DBW. This omission is not consistent with ANSI /ANS-19.6-1985,

Reload Startup Physics Tests for Pressurized Water Reactors, Table A-1.

The necessary data are available from the reference bank reactivity worth measurement.

Using the available data, the inspector calculated a DBW of-7.6 pcm/ ppm, which is within 110% of the predicted value.

4.

Power Escalation Testing (72700, 61702, 61705)

,

Initial power escalation-and testing, for Unit 1, cycle 5, was controlled and scheduled by 88019-C (Revision 3), Power Ascensicn after Refueling.

This procedure also controlled the readjustment of the PRNI high flux trip high setpoint.

The trips were increased to 70% prior to increasing to the l

50% power plateau and to 95% prior to increasing power ta 80%. The normal 109% trips were not established until testing at the 80% power plateau was completed. This conservative management of the high flux trip high setpoint is considered a good practice. All power percentages are in-

.

,

_.

_ _ _ _

_. _

_

.-.

_ _. _. _

_

_ _ _. _

_

-.

_

,

-

.f

!

t

Report Details

l

!

I terms of the new licensed RTP of 3565 MWth. The inspector reviewed the

following completed terts:

l t

a.

88014-C (Revision 6), Reactor Coolant System Flow Measurement, was

!

performed on May 1, 1993, at 95% RTP.

The flow was determined from

equating heat balances across the primary and secondary systems, and

the results are dependent upon reliable measurement of the temperature

!

rise through the reactor vessel. Neglecting the uncertainties created

.

by hotleg streaming, the results were acceptable.

The greatest hotleg

!

temperature differences observed during this test were about 5'F, l

which is less than the differences observed at similar facilities.

b.

88075-C (Revision 5), Precision Heat Balance, was completed on May 1,

!

1993.

The procedure contains no acceptance criteria, but a step in

!

the procedure requires that a work request for recalibration be issued-i if the feedwater flows measured on the plant flow meters are not

,

within the span 0 to +2.5% of the precision instruments. This i

approach assures that the major contributor to the plant calorimetric l

is conservative, but does not fully confirm the conservatism of the

.

plant calorimetric, which is used to calibrate the PRNIs. The

'

licensee agree 0 to revise the procedure to confirm that the plant calorimetric calculation is conservative relative to the precision I

heat balance.

i q

c.

88007-2 (Revision 3), Limiting Hot Channel Factor Determination, was

performed at nominal power levels of 30, 50, 80, 95% RTP, during power

!

escalation for cycle 5.

The limits on Fa and Fg were satisfied in e

o all cases for both the LOPAR and VANTAGE-5 fuel assemblies.

j

'

d.

88023-C (Revision 7), One-Point Incore/Excore Detector Calibration,

-

was performed at nominal power levels of 30, 50, 80, and 95% RTP

<

during cycle 5 power escalation.

l At the time the one-point correlation was developed, only incore -

)

,

excore detector relationships obtained near full power (3411 MWth)

!

were used in the analysis. Use of relationships obtained at lower i

-

power levels was found to increase the uncertainty of the correlation.

!

The inspector questioned the use of that correlation at the increased

,

)

power level of 3565 MWth. The licensee's informal evaluation was that

.

,

with no change in the materials between the core and the excore

{

detectors and with little change in T,vo the original one-point i

correlation was still valid.

l

!

.

The intent of this procedure was to obtain the new RTP (3565 MWth)

.j with a Tava of 583.5 *F.

However, the turbine control valves were

'

!.

full open at 95% RTP.

Testing under this procedure was terminated at step 8.6.8.7.

Operation continued under procedure 1200-C.

Rescaling to a RTP T,vc of 586.4 'F and further testing were performed under the control of T-

l l

,

._

_ -,..

.

-

_

__.. _ _

_

_

___. _. _

_._

. _.

,

!

!

f Report Details

1

!

r TS-93-02 (Revision 0). During this inspection, the unit was operating i

stably at 3565 MWth and T,vc at 586.4 'F.

5.

Unit 2 Core Performance Surveillance Activities (61702, 61705)

j

~f The inspector reviewed the following Unit 2 surveillance procedures j

<

completed during the current operating cycle._

j a.

88013-C (Revision 2), Overall Core Reactivity Balance, has been i

performed with at least 31-EFPD frequency throughout the cycle. The

_:

reactivity differences have ranged from -567 to +85 pcm, with no

!

obvious trend toward the i 1000 pcm limit.

!

F b.

88016-C (Revision 0), Determination of RCS Delta T Power at~100% Rated i

!

Thermal Power, ~was first issued on February 25, 1992. The

.

The surveillance performed is required by TS 4.3.1.1 every 18 months.

.

licensee has opted to perform the surveillance quarterly in response

to observed changes in radial power shape with burnup and concomitant I

changes in indicated hot leg temperatures because of hotleg streaming.

r The Delta T meters are rescaled when they differ from the heat balance

l by 1% or more. This is a good practice and initiative.

~!

c.

88007-1 (Revision 1), Limiting Hot Channel Factor Determination,-has been performed with 31-EFPD frequency throughout the current cycle.

}

The limits on Fo and F, were satisfied in all cases for both.the j

LOPAR and VANTAGE-5 fuel assemblies.

-}

.

!

d.

88023-C (Revision 4), One-Point IncordExcore Detector Calibration,

!

,

has been performed at 31-EFPD intervals during the current cycle.

Recalibrations were performed on two occasions in response to the.

l surveillance observations.

A good feature of reactor engineering surveillance activities' is that the parameters discussed above and others are routinely trended for both units.

j

,

6.

Followup of Violation (92702)

!

(Closed) VIO 50-424 and 50-425/92-17-01:

Step 6.1.4 in the 88xxx-x and 87xxx-x series of procedures violates requirements for review of temporary changes to procedures.

-I The licensee acknowledged the violation in their letter of-September 2, t

1992. Their corrective action began on August 27,1992, with the issuance l

of a memorandum to the staff instructing them not to use step 6.1.4.

,

Subsequently, all procedures were revised to remove the step. All

procedures reviewed during this inspection were acceptable, and there was j

no evidence of unapproved changes to procedures in the documentation

!

reviewed.

l t

!

'!

'

.-

-

-

-

.

-

.

-

.

...

.

.

.

..

. -... _

.

- - -....- -

._.

_

?

!

!

L Re' port Details

f

-

-i 7.

Exit Interview l

The inspection scope and findings were summarized on May 14, 1993, with

!

those persons identified in paragraph I above. The inspector described t

the areas inspected and discussed in detail the inspection-findings.

,

Proprietary materials were provided to and reviewed by the inspector ~

!

-during this inspection, but are not incorporated into this report. The i

licensee stated that they did not consider the material in the figure above to be proprietary.

j 8. ' Acronyms and Initialisms Used in This Report

't ANSI American Standards Institute

}

!

ANS American Nuclear Society ARO all rods out i

C, boron' concentration in the RCS

}

COLR Core Operating Limits Report

DBW differential boron (reactivity) worth

!

DRC digital reactivity computer

>

'

EFPD effective full power days F

heat flux hot channel factor o

fog enthalpy rise hot channel factor

,

HZP hot zero power

!

ICRR inverse countrate ratio i

'

IRNI intermediate range nuclear instrument ITC isothermal temperature coefficient MTC

'noderator temperature coefficient

'

MWD /MTU megawatt days per metric tonne of uranium

NDR WCAP-I3607, The Nuclear Design Report for Vogtle Electric

Generating Plant Unit I, Cycle. 5.

j NIS nuclear instrument system i

pcm percent millirho (reactivity)

ppm B parts per million boron j

PRNI power range nuclear instrument RCP reactor coolant pump RCS reactor coolant Ustem

RTP rated thermal power l

SAER Safety Audit and Engineering Review

'

T average Coolant temperature in the reactor vessel AVG SRNI source range nuclear instrument

e TS Technical Specifications j

'i i

!

.

?

I

]

l l

.i

.-

_

-.

--