Ro:On 830927,during Sampling Process,Sample Valve on Boron Injection Tank Found Partially Open Allowing Boric Acid Solution to Drain Out.Caused by Personnel Error.Boron Injection Tank Brought Back Into Spec
ML20078G430
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 09/27/1983
From: Will Smith
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
NUDOCS 8310120234
Download: ML20078G430 (1)


Text

.

n

-- C( ,t

,,,,,, INDIANh & MICHIGAN ELECTRIC _ COMPANY DONALD C. COOK NUCLEAR PLANT P.O. Box 458, Bridgman, Michigan 49106 (616) 465-5901 Septanber 27,'1983 Mr. J.G. Keppler, Regional Administrator thited States Nuclear Regulatory Cannission Region III 799 Roosevelt Road Glen Ellyn, IL 60137 Operating License DPR-74 Docket No. 50-316

~

Dear Mr. Keppler:

This is to confirm a report made by our Mr. B.A. Svensson, Assistant Plant Manager, to your Mr. E.R. Swanson, NRC Region III Resident Inspector at the Donald C. Cook Nuclear Plant on Septarber 27, 1983, at 0922 hours0.0107 days <br />0.256 hours <br />0.00152 weeks <br />3.50821e-4 months <br />. At this time Mr. Swanson was advised that resulting in personnel error in a sanpling process, a sanple valve on the Unit 2 Boron Injection Tank was found in the partially open position which allowed a quantity of boric acid solution to drain out of the Boron Injection Tank.

Preliminary investigation indicates that approximately 600 gallons of boric acid solution leaked out via this flow path over an 8.5 hour5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> period ( l.2 gpn flow calculated. Upon discovery of this condition, all necessary actions were perfonned to bring the Boron Injection Tank back into specification.

Tnis incident is being reported due to the possible degradation of the BIT and its ability to supply boric acid to the Reactor Coolant System in the event of a safety injection. We have referred this event to our Corporate Office for a safety evaluation.

As required by Technical Specification 6.9.1.12, a follou.ip report will be sutxnitted within 14 days.

Sincerely, W.G. Smith, .

Plant Manager

/bab cc: John E. Dolan PNSBC M.P. Alexich J.F. Stietzel R.F. Kroeger E.L. Townley H. Brugger Dir., IE (40 copies)

E.R. Swanson/N.E. DuBry, RO:III Dir., MIPC (4 copies)

R.C. Callen, MISC G. Charnoff, Esq.

J.M. Hennigan R.O. Bruggee, EPRI INPO 8310120234 830927 SEP 301983 gDRADOCK05000 ggy g Q