Monthly Operating Rept for July 1999 for DC Cook Nuclear Plant,Units 2.With 990812 Ltr
ML17326A086
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 07/31/1999
From: Bakken A, Pratt M, Richardson S
AMERICAN ELECTRIC POWER CO., INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9908240071
Download: ML17326A086 (48)


Text

REGULA'Y INFORMATION.OISTRIBUTI SYSTEM (RIDS)

DOCKET ¹ FACIL:50-316 Donald C. Cook Nuclear Power Plant, Unit 2, Indiana M 05000316 AUTH.PARE, ~ AUTHOR AFFILIATION PRATT,WM. American Electric Power Co., Inc.

RICHARDSON,S.A. American Electric Power Co.', Inc.

BAKKEN,A.C. American Electric Power Co., Inc.

RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Monthly operat'e t for Units .With 990812 ltr.

1999 for DC Cook Nuclear Plant, DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: Monthly Operating Report (per Tech Specs)

NOTES:

RECIPIENT . COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL ,0 STANG,J 1 1 R

INTERNAL: LE CENTER 01 1 1 OC/DBA/PAD 1 1 R W/DRM~/OERAB 1 1 RGN3 1 1 EXTERNAL: LMITCO MARSHALL 1 1 NOAC 1 1 NRC PDR 1 1 D

0 M5$8L$8 'E NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE. 'TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD) ON EXTENSION 415"2083 TOTAL NUMBER OF COPIES REQUIRED: LTTR 8 ENCL 8

American Electric Pjggr Cook Nudear Plant One Cook Place Bridgman, Ml 49106 6t64655901 August 12, 1999 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Document Control Manager:

Pursuant to the requirements of Donald C. Cook Nuclear Plant Unit 2 Technical Specification 6.9.1.8, the attached Monthly Operating Report for July 1999 is submitted.

Sincerely, Site Vice President ACB/bwo Attachment NRC Region III NRC Project Manager NRR NRC Resident Inspector ANI Nuclear Engineering Department INPO Records Center R. C. Godley G. T. Gaffney Canton D. R. Hahn Department of Health S. Hamming Department of Labor G. John B. Lewis McGraw-Hill Companies D. H. Malin T. P. Noonan D. W. Paul Lancaster J. E. Pollock R. P. Powers Regulatory Licensing Manager M. W. Rencheck W. H. Schalk D. G. Turner 990824007i 'ir'ir073%

PDR,,ADQCK,, 050003ib PDR

N.R.C. OPERATING DATA REPOR DOCKET NO. 50- 316 DATE August 2, 1999 COMPLETED BY M. M. Pratt TELEPHONE 616-465-5901 OPERATING STATUS Notes:

1. Unit Name D. C. Cook Unit 2
2. Reporting Period July-99
3. Licensed Thermal Power (MWt) 3411
4. Name Plate Rating (Gross MWe) 1133
5. Design Electrical Rating (Net MWe) 1090
6. Maximum Dependable Capacity (GROSS MWe) 1100
7. Maximum Dependable Capacity (Net MWe) 1060
8. If Changes Occur in Capacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons:
9. Power Level to Which Restricted, If Any (Net MWe):
10. Reasons For Restrictions, If Any:

This Month Year-to-Date Cumulative

11. Hours in Reporting Period 744.0 5832.0 189912.0
12. No. of Hrs. Reactor Was Critical 0.0 0.0 121771.0
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator on Line 0.0 0.0 118153.4
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Gen. (MWH) 0.0 0.0 366007650.4
17. Gross Electrical Energy Gen. (MWH) 0.0 0.0 118584640.0
18. Net Electrical Energy Gen. (MWH) 0.0 0.0 114257779.0
19. Unit Service Factor 0.0 0.0 63.0
20. Unit Availability Factor 0.0 0.0 63.0
21. Unit Capacity Factor (MDC Net) 0.0 0.0 57.4
22. Unit Capacity Factor (DER Net) 0.0 0.0 55.9
23. Unit Forced Outage Rate 100.0 100.0 22.5
24. Shutdowns Scheduled over Next Six Months (Type, Date, and Duration):

None

25. If Shut Down At End of Report Period, Estimated Date of Startup:

A ril2000

26. Units in Test Status (Prior to Commercial Operation):

Forecast Achieved INITIALCRITICALITY INITIALELECTRICITY COMMERCIAL OPERATION

DOCKET NO. 50- 316 UNIT NAME D.C. Cook Unit 2 DATE August 2, 1999 COMPLETED BY M. M. Pratt TELEPHONE 616-465-5901 AVERAGE DAILYPOWER LEVEL (MWe-Net)

July 1999 DAY AVERAGE DAILY DAY AVERAGE DAILY POWER LEVEL POWER LEVEL 7/1/99 7/17/99 7/2/99 7/18/99 7/3/99 7/1 9/99 7/4/99 7/20/99 7/5/99 7/21/99 7/6/99 7/22/99 7/7/99 7/23/99 7/8/99 7/24/99 7/9/99 7/25/99 7/1 0/99 7/26/99 7/11/99 7/27/99 7/1 2/99 7/28/99 7/13/99 7/29/99 7/1 4/99 7/30/99 7/15/99 7/31/99 7/16/99

DOCKET NO. 50- 316 UNIT NAME D.C. Cook Unit 2 DATE August 5, 1999 COMPLETED BY S. A. Richardson TELEPHONE 616-465-5901 PAGE 1 of1 MONTHLYOPERATING ACTIVITIES - July 1999 HIGHLIGHTS The unit entered this reporting period in Mode 5 at 0% RTP.

The unit exited this reporting period with the core offloaded.

There were no challenges to the pressurizer safety valves or power operated relief valves.

Gross electrical generation for the month of July was 0 MWh.

DETAILS 07/13/99 At 0110 hours0.00127 days <br />0.0306 hours <br />1.818783e-4 weeks <br />4.1855e-5 months <br />, completed draining of Reactor Coolant System to 619.5 foot elevation (1.5 feet below reactor vessel head flange elevation) in preparation for reactor vessel head removal and subsequent core off loading support activities.

07/13/99 At 1920 hours0.0222 days <br />0.533 hours <br />0.00317 weeks <br />7.3056e-4 months <br />, the unit entered Mode 6 as first reactor head stud was de-tensioned.

07/15/99 At 1630 hours0.0189 days <br />0.453 hours <br />0.0027 weeks <br />6.20215e-4 months <br />, completed flood up of the refueling cavity to support core off loading.

07/24/99 At 0945 hours0.0109 days <br />0.263 hours <br />0.00156 weeks <br />3.595725e-4 months <br />, last fuel assembly removed from the reactor vessel.

07/27/99 At 1845 hours0.0214 days <br />0.513 hours <br />0.00305 weeks <br />7.020225e-4 months <br />, both Train A and Train B Emergency Diesel Generators declared inoperable for Modes 5 and 6 due to inability to meet design basis. The combustion air intake, combustion exhaust, ventilation intake and ventilation exhaust structures were deemed inadequate in regard to tornado generated missiles.

All time entries are Eastern Standard Time (EST).

DOCKET NO. 50 - 316 UNIT NAME D.C. Cook Unit 2 DATE August 5, 1999 COMPLETED BY S. A-. Richardson TELEPHONE 616-46(-5901 PAGE 1 of1 UNIT SHUTDOWNS AND POWER REDUCTIONS July 1999 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO. DATE TYPE'OURS REASON REACTOR REPORT NO. CODE CODE TO PREVENT RECURRENCE 333 090897 F 162.0 97-003 N/A N/A The unit was shutdown to resolve 97-004 design basis questions discovered during the 97-005 NRC Architect and Engineering (AE) Inspection.

334 ~ 101397 S 582.0 N/A N/A N/A The scheduled refueling outage commenced while the unit has been shutdown to resolve design basis questions discovered during the NRC AE Inspection.

335 010798 F 744.0 N/A N/A N/A The refueling outage was declared complete, but the unit remained shutdown to resolve design basis questions discovered during the NRC AE Inspection.

1 TYPE: 2 REASON: 3 METHOD: 4 SYSTEM: 5 COMPONENT:

F: Forced A: Equipment Failure (Explain) 1: Manual Exhibit G - Instructions Exhibit I: Same Source S: Scheduled B: Maintenance or Test 2: Manual Scram for preparation of data C: Refueling 3: Automatic Scram entry sheets for Licensee D: Regulatory Restriction 4: Other (Explain) Event Report (LER) File E: Operator Training and (NUREG 0161)

License Examination F: Administrative G: Operational Error (Explain)

H: Other (Explain)

~-9/(

z/jg+oob Distri61.txt Distribution Sheet Priority: Normal From: Esperanza Lomosbog Action Recipients: Copies:

J Stang Paper Copy Internal Recipients:

RidsRgn3MailCenter 0 OK RidsResDraaOerab 0 OK RidsOcfoDpbaPab 0 OK RidsManager OK RidsAcrsAcnwMailCenter 0 OK RGN3 Paper Copy RES/DRAA/OERAB 1 Paper Copy OCFO/D Paper Copy CENTER 01 Paper Copy ACRS Paper Copy External Recipients:

NOAC Paper Copy INEEL Marshall Paper Copy Total Copies:

Item: ADAMS Document Library: ML ADAMS"HQNTAD01 ID: 003694622:1

Subject:

Monthly operating report for February 2000 for D. C. Cook Nuclear Plant, Unit 2. With let ter dated 3/13/00.

Body:

ADAMS DISTRIBUTION-NOTIFICATION.

Electronic Recipients can RIGHT CLICK and OPEN the first Attachment to View the Document in ADAMS. The Document may also be viewed by searching for Accession Number ML003694622.

Page 1

Distri61.txt lE24- Monthly Operating Report (per Tech Specs)

Docket: 05000316 Page 2

Indiana Michigan Power Company Cook Nuoiear Pearl Ore Cook Plaoo BodgmarL Ml 49106 6164666961 INIilkiM NICHlaaQN POWM March 13, 2000 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Document Control Manager:

Pursuant to the requirements of Donald C. Cook Nuclear Plant Unit 2 Technical Specification 6.9.1.8, the attached Monthly Operating Report for February 2000 is submitted.

Sincerely, R. C. Godley Regulatory Affairs Director RCG/mbd Attachments ANI Nuclear Engineering Department A. C. Bakken, III G. T. Gaffney Canton D. R. Hahn Department of Health S. Hamming Department of Labor RAF Harris INPO Records Center G. John B. Lewis McGraw-Hill Companies D. H. Malin NRC Project Manager NRR NRC Region III NRC Resident Inspector T. P. Noonan D. W. Paul Lancaster J. E. Pollock R. P. Powers Regulatory Licensing Manager M. W. Rencheck W. H. Schalk AElr~I rrrericn's I'rreg> I'arlncr

RC OPERATING DATA REPORT DOCKET NO. 50- 316 DATE March 6, 2000 COMPLETED BY J. W. Minor TELEPHONE 616-465-5901 OPERATING STATUS Notes:

1. Unit Name D. C. Cook Unit2 2, Reporting Period Feb-2000
3. Licensed Thermal Power (MWt) 3411
4. Name Plate Rating (Gross MWe) 1133
5. Design Electrical Rating (Net MWe) 1090
6. Maximum Dependable Capacity (GROSS MWe) 1100
7. Maximum Dependable Capacity (Net MWe) 1060
8. If Changes Occur in Capacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons:
9. Power Level to Which Restricted, If Any (Net MWe):
10. Reasons For Restrictions, If Any:

This Month Year-to-Date Cumulative

11. Hours in Reporting Period 696.0 1440.0 194730.0
12. No. of Hrs. Reactor Was Critical 0.0 0.0 121771.0
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator on Line 0.0 0.0 118153.4
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Gen. (MWH) 0.0 0.0 366007650.4
17. Gross Electrical Energy Gen. (MWH) 0.0 0.0 118584640.0
18. Net Electrical Energy Gen. (MWH) 0.0 0.0 114257779.0
19. Unit Service Factor 0.0 0.0 61.4
20. Unit Availability Factor 0.0 0.0 61.4
21. Unit Capacity Factor (MDC Net) 0.0 0.0 55.9
22. Unit Capacity Factor (DER Net) 0.0 0.0 54.5
23. Unit Forced Outage Rate 100.0 100.0 24.7
24. Shutdowns Scheduled over Next Six Months (Type, Date, and Duration):

None

25. If Shut Down At End of Report Period, Estimated Date of Startup:

April 2000

26. Units in Test Status (Prior to Commercial Operation):

Forecast Achieved

. INITIALCRITICALITY INITIALELECTRICITY COMMERCIALOPERATION

DOCKET NO. 50 - 316 UNIT NAME D.C. Cook Unit 2 DATE March 6, 2000 COMPLETED BY J. W. Minor TELEP MONE 616-465-5901 AVERAGE DAILYPOWER LEVEL (MWe-Net) .

February 2000 DAY AVERAGE DAILY DAY AVERAGE DAILY POWER LEVEL POWER LEVEL 2/1/2000 0 2/17/2000 2/2/2000 0 2/1 8/2000 2/3/2000 0 2/19/2000 2/4/2000 0 2/20/2000 2/5/2000 0 2/21/2000 2/6/2000 0' 2/22/2000 2/7/2000 2/23/2000 2/8/2000 0 2/24/2000 2/9/2000 0 2/25/2000 2/1 0/2000 0 2/26/2000 2/1 1/2000 0 2/2?/2000 2/12/2000 0 2/28/2000 2/13/2000 0 2/29/2000 2/14/2000 0 2/1 5/2000 0 2/16/2000 0

DOCKET NO. 50 - 316 UNIT NAME D.C. Cook Unit'2 DATE March 6, 2000 COMPLETED BY MB Depuydt TELEPHONE 616465-5901 PAGE 1 of1 UNIT SHUTDOWNS AND POWER REDUCTIONS February 2000 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO. DATE TYPE" HOURS REASON> REACTOR3 REPORT NO. CODE4 CODE5 TO PREVENT RECURRENCE 335 010798 F 696.0 N/A N/A N/A The unit remained shutdown to resolve design basis questions identified during the NRC Architect and Engineering (AE)

Inspection.

1 TYPE: 2 REASON: 3 METHOD: 4 SYSTEM: 5 COMPONENT:

F: Forced A: Equipment Failure (Explain) 1: Manual Exhibit G - Instructions Exhibit I: Same Source S: Scheduled B: Maintenance or Test 2: Manual Scram for preparation of data C: Refueling 3: Automatic Scram entry sheets for Licensee D: Regulatory Restriction 4: Other (Explain) Event Report (LER) File E: Operator Training and (NUREG 0161)

License Examination F: Administrative G: Operational Error (Explain)

H: Other (Explain)

\

Distri80.txt

~u/mls Distribution Sheet Priority: Normal From: Patricia Exum Action Recipients: Copies:

Internal Recipients:

RidsRgn3 MailCenter 1 Paper Copy RidsResDraaOerab 0 OK RidsManager OK RidsAcrsAcnwMailCenter 0 OK RGN3 1 Paper Copy RES/DRAA/OERAB 1 Paper Copy OCFOIDPBA Paper Copy

<FILE CENTER 01 Paper Copy ACRS 1 Paper Copy External Recipients:

NOAC Paper Copy INEEL Marshall Paper Copy Total Copies:

Item: ADAMS Document Library: ML ADAMS"HQNTAD01 ID: 003685747:1

Subject:

Forward monthly operating report for January 2000, regarding Donald C. Cook Nuclear Plant unit 2 technical specification 6.9.1.8.

Body:

ADAMS DISTRIBUTION NOTIFICATION.

Electronic Recipients can RIGHT CLICK and OPEN the first Attachment to View the Document in ADAMS. The Document may also be viewed by searching for Accession Number ML003685747.

Page 1

Distri80.txt lE24 - Monthly Operating Report (per Tech Specs)

Page 2

One Cook Pbce Ml 49106 616465961 R

INQIANA NICHIGQN PQWM February 11, 2000 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Document Control Manager:

Pursuant to the requirements of Donald C. Cook Nuclear Plant Unit 2 Technical Specification 6.9.1.8, the attached Monthly Operating Report for January 2000 is submitted.

Sincerely,

/&pc+

R. C. Godley Regulatory Affairs Director RCG/mbd Attachments ANI Nuclear Engineering Department A. C. Bakken, III G. T. Gaffney Canton D. R. Hahn Department of Health S. Hamming Department of Labor RAF Harris INPO Records Center G. John B. Lewis McGraw-Hill Companies D. H. Malin NRC Project Manager NRR NRC Region III NRC Resident Inspector T. P. Noonan D. W. Paul Lancaster J. E. Pollock R. P. Powers Regulatory Licensing Manager M. W. Rencheck W. H. Schalk

NRC OPERATING DATA REPORT DOCKET NO. 50 - 316 DATE February 4, 2000 COMPLETED BY J. W. Minor TELEPHONE 616465-5901 OPERATING STATUS Notes:

1. Unit Name D. C. Cook Unit 2
2. Reporting Period Jan-2000
3. Licensed Thermal Power (MWt) 3411
4. Name Plate Rating (Gross MWe) 1133
5. Design Electrical Rating (Net MWe) 1090
6. Maximum Dependable Capacity (GROSS MWe) 1100
7. Maximum Dependable Capacity (Net MWe) 1060
8. If Changes Occur in Capacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons:
9. Power Level to Which Restricted, If Any (Net MWe):
10. Reasons For Restrictions, If Any:

This Month Year-to-Date Cumulative

11. Hours in Reporting Period 744.0 744.0 194034.0
12. No. of Hrs. Reactor Was Critical 0.0 0.0 121771.0
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator on Line 0.0 0.0 118153.4
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Gen. (MWH) 0.0 0.0 366007650.4
17. Gross Electrical Energy Gen. (MWH) 0.0 0.0 118584640.0
18. Net Electrical Energy Gen. (MWH) 0.0 0.0 114257779.0
19. Unit Service Factor 0.0 0.0 61.6
20. Unit Availability Factor .0.0 0.0 61.6
21. Unit Capacity Factor (MDC Net) 0.0 0.0 56.1
22. Unit Capacity Factor (DER Net) 0.0 0.0 54.7
23. Unit Forced Outage Rate 100.0 100.0 24.4
24. Shutdowns Scheduled over Next Six Months (Type, Date, and Duration):

None

25. If Shut Down At End of Report Period, Estimated Date of Startup:

A ril 2000

26. Units in Test Status (Prior to Commercial Operation):

Forecast Achieved INITIALCRITICALITY INITIALELECTRICITY COMMERCIAL OPERATION

DOCKET NO. 50- 316 UNIT NAME D.C. Cook Unit 2 DATE February 4, 2000 COMPLETED BY J. W. Minor TELEPHONE 616465-5901 AVERAGE DAILYPOWER LEVEL (INWe-Net)

January 2000 DAY AVERAGE DAILY DAY AVERAGE DAILY POWER LEVEL POWER LEVEL 1/1/2000 0 1/17/2000 1/2/2000 0 1/1 8/2000 1/3/2000 0 1/1 9/2000 1/4/2000 0 1/20/2000 1/5/2000 0 1/21/2000 1/6/2000 0 1/22/2000 1/7/2000 0 1/23/2000 1/8/2000 0 1/24/2000 1/9/2000 0 1/25/2000 1/10/2000 0 1/26/2000 1/11/2000 0 1/27/2000 1/12/2000 0 1/28/2000 1/1 3/2000 0 1/29/2000 1/14/2000 0 1/30/2000 1/15/2000 0 1/31/2000 1/1 6/2000 0

DOCKET NO. 50 - 316 UNlT NAME D.C. Cook Unit 2 DATE February 8, 2000 COMPLETED BY MB Depuydt TELEPHONE 616-465-5901 PAGE 1 of1 UNIT SHUTDOWNS AND POWER REDUCTIONS January 2000 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO. DATE TYPE'OURS - REASON REACTOR REPORT NO. CODE CODE TO PREVENT RECURRENCE 335 010798 F 744.0 N/A N/A N/A The unit remained shutdown to resolve design basis questions identified during the NRC Architect and Engineering (AE)

Inspection.

1 TYPE: 2 REASON: 3 METHOD: 4 SYSTEM: 5 COMPONENT:

F: Forced A: Equipment Failure (Explain) 1: Manual Exhibit G - Instructions Exhibit I: Same Source S: Scheduled B: Maintenance or Test 2: Manual Scram for preparation of data C: Refueling 3: Automatic Scram entry sheets for Licensee D: Regulatory Restriction 4: Other (Explain) Event Report (LER) File E: Operator Training and (NUREG 0161)

License Examination F: Administrative G: Operational Error (Explain)

H: Other (Explain)

Distri28.txt Distribution Sheet Priority: Normal From: Andy Hoy Action Recipients: Copies:

J Stang 1 Paper Copy Internal Recipients:

RGN3. Paper Copy RES/DRAA/OERAB Paper Copy 0 FO/'DP13 Paper Copy FILE CENTER 01 Paper Copy CR Paper Copy External Recipients:

NOAC Paper Copy INEEL Marshall Paper Copy Total Copies:

Item: ADAMS Document Library: ML ADAMS"HQNTAD01 ID: 003677045

Subject:

Monthly operating report for December, 1999 for D C Cook, Unit 2. With letter dated January 14, 2000.

Body:

ADAMS DISTRIBUTION NOTIFICATION.

Electronic Recipients can RIGHT CLICK and OPEN the first Attachment to View the Document in ADAMS. The Document may also be viewed by searching f or Accession Number ML003677045.

IE24 Monthly Operating Report (per Tech Specs)

Docket: 05000316 Page 1

~ ~ ~

One Cook Race Mynen Mi 49106 616466961 INlklM NICHIGQN JPQUPM January 14, 2000 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Document Control Manager:

Pursuant to the requirements of Donald C. Cook Nuclear Plant Unit 2 Technical Specification 6.9.1.8, the attached Monthly Operating Report for December 1999 is submitted.

Sincerely, R. C. Godley Regulatory Affairs D ctor RCG/mbd Attachments ANI Nuclear Engineering Department A. C. Bakken, III G. T. Gaffney- Canton D. R. Hahn Department of Health S. Hamming Department of Labor INPO Records Center G. John B. Lewis McGraw-Hill Companies D. H. Maiin NRC Project Manager NRR NRC Region III NRC Resident Inspector T. P. Noonan D. W. Paul Lancaster J. E. Pollock R. P. Powers Regulatory Licensing Manager M. W. Rencheck W. H. Schalk D. G. Turner

DOCKET NO. 50 - 316 DATE January 5, 2000 COMPLETED BY J. W. Minor TELEPHONE 616-465-5901 OPERATING STATUS Notes:

1. Unit Name D. C. Cook Unit2
2. Reporting Period Dec-99
3. Licensed Thermal Power (MWt) 3411
4. Name Plate Rating (Gross MWe) 1133
5. Design Electrical Rating (Net MWe) 1090
6. Maximum Dependable Capacity (GROSS MWe) 1100
7. Maximum Dependable Capacity (Net MWe) 1060
8. If Changes Occur in Capacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons:
9. Power Level to Which Restricted, If Any (Net MWe):
10. Reasons For Restrictions, If Any:

This Month Year-to-Date Cumulative

11. Hours in Reporting Period 744.0 8760.0 193290.0
12. No. of Hrs. Reactor Was Critical 0.0 0.0 121771.0
13. Reactor Reserve Shutdown Hours 0.0 0.0 . 0.0
14. Hours Generator on Line 0.0 0.0 118153.4
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Gen. (MWH) 0.0 0.0 366007650.4
17. Gross Electrical Energy Gen. (MWH) 0.0 0.0 118584640.0
18. Net Electrical Energy Gen. (MWH) 0.0 0.0 114257779.0
19. Unit Service Factor 0.0 0.0 61.8
20. Unit Availability Factor 0.0 0.0 61.8
21. Unit Capacity Factor (MDC Net) 0.0 0.0 56.3
22. Unit Capacity Factor (DER Net) 0.0 0.0 54.9
23. Unit Forced Outage Rate 100.0 100.0 24.0
24. Shutdowns Scheduled over Next Six Months (Type, Date, and Duration):

None

25. If Shut Down At End of Report Period, Estimated Date of Startup:

April 2000

26. Units in Test Status (Prior to Commercial Operation):

Forecast Achieved INITIALCRITICALITY INITIALELECTRICITY COMMERCIALOPERATION

DOCKET NO. 50- 316 UNIT NAME D.C. Cook Unit 2 DATE January 5, 2000 COMPLETED BY J. W. Minor TELEPHONE 616-465-5901

. AVERAGE DAILYPOWER LEVEL (MWe-Net)

December 1999 DAY AVERAGE DAILY DAY AVERAGE DAILY POWER LEVEL POWER LEVEL 12/1/99 12/17/99 12/2/99 12/18/99 12/3/99 12/19/99 12/4/99 12/20/99 12/5/99 12/21/99 12/6/99 12/22/99 12/7/99 12/23/99 12/8/99 12/24/99 12/9/99 12/25/99 12/10/99 12/26/99 12/11/99 12/27/99 12/12/99 12/28/99 12/13/99 12/29/99 12/14/99 12/30/99 12/15/99 12/31/99 12/16/99

DOCKET NO. 50- 316 UNIT NAME D.C. Cook Unit 2 DATE January 9, 2000 COMPLETED BY MB Depuydt TELEPHONE 616-465-5901 PAGE 1 of1 UNIT SHUTDOWNS AND POWER REDUCTIONS December 1999 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO. DATE TYPE'OURS REASON2 REACTOR3 REPORT NO. CODEi CODE TO PREVENT RECURRENCE 333 090897 F 162.0

  • 97-003 N/A N/A The unit was shutdown to resolve 97-004 design basis questions disc'overed during 97-005 the NRC Architect and Engineering (AE)

Inspection.

334 101397 S 582.0

  • N/A N/A N/A The scheduled refueling outage commenced while the unit has been shutdown to resolve design basis questions discovered during =.

the NRC AE Inspection.

335 010798 F 744.0 N/A N/A N/A The unit remained shutdown to resolve design basis questions identified during the NRC Architect and Engineering (AE)

Inspection.

Historical values included for consistency with CNP Unit 1

~EK: RJRE&SQH: 3JdJHHQD: ~YGIEh1:

F: Forced A: Equipment Failure (Explain) 1: Manual Exhibit G - Instructions Exhibit I: Same Source S: Scheduled B: Maintenance or Test 2: Manual Scram for preparation of data C: Refueling 3: Automatic Scram entry sheets for Licensee D: Regulatory Restriction 4: Other (Explain) Event Report (LER) File E: Operator Training and (NUREG 0161)

License Examination F: Administrative G: Operational Error (Explain)

H: Other (Explain)

1 1

T

i/lHj~o Distri47.txt Distribution Sheet Priority: Normal From: Esperanza Lomosbog Action Recipients: Copies:

J Stang 1 Not Found Internal Recipients:

RGN 3 1 Not Found RES/DRAA/OERAB 1 Not Found OCFO/DPB 1 Not Found CENTER 0 1 Not Found

-1 Not Found External Recipients:

NOAC Not Found INEEL Marshall Not Found Total Copies:

Item: ADAMS Document Library: ML ADAMS"HQNTAD01 ID: 003678905

Subject:

Monthly operating report for December 1999 for DE C. Cook Nuclear Plan t, Unit 2. With letter dated 1/14/00.

Body:

Docket: 05000316, Notes: N/A Page 1

Indiana hlichigan Power Company Cocktkdear Aant One Cock Race Mynan.ha 49106 616466690>

Z INDIANA MICHIGAN POWER January 14, 2000 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Document Control Manager:

Pursuant to the requirements of Donald C. Cook Nuclear Plant Unit2 Technical Specification 6.9.1.8, the attached Monthly Operating Report for December 1999 is submitted.

Sincerely, R. C. Godley Regulatory Affairs D ctor RCG/mbd Attachments ANI Nuclear Engineering Department A. C. Bakken, III G. T. Gaffney Canton D. R. Hahn Department of Health S. Hamming Department of Labor INPO Records Center G. John B. Lewis McGraw-Hill Companies D. H. Malin NRC Project Manager NRR NRC Region III NRC Resident Inspector T. P. Noonan D. W. Paul- Lancaster J. E. Pollock R. P. Powers Regulatory Licensing Manager M. W. Rencheck W. H. Schalk D. G. Turner

NRC OPERATING DATA REPORT DOCKET NO. 50- 316 DATE January 5, 2000 COMPLETED BY J. W. Minor TELEPHONE 616465-5901 OPERATING STATUS Notes:

1. Unit Name D. C. Cook Unit2
2. Reporting Period Dec-99
3. Licensed Thermal Power (MWt) 3411
4. Name Plate Rating (Gross MWe) 1133
5. Design Electrical Rating (Net MWe) 1090
6. Maximum Dependable Capacity (GROSS MWe) 1100
7. Maximum Dependable Capacity (Net MWe) 1060
8. If Changes Occur in Capacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons:
9. Power Level to Which Restricted, If Any (Net MWe):
10. Reasons For Restrictions, If Any:

This Month Year-to-Date Cumulative

11. Hours in Reporting Period 744.0 8760.0 193290.0
12. No. of Hrs. Reactor Was Critical 0.0 0.0 121771.0
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator on Line 0.0 0.0 118153.4
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Gen. (MWH) 0.0 0.0 366007650.4
17. Gross Electrical Energy Gen. (MWH) 0.0 0.0 118584640.0
18. Net Electrical Energy Gen. (MWH) 0.0 0.0 114257779.0
19. Unit Service Factor 0.0 0.0 61.8
20. Unit Availability Factor 0.0 0.0 61.8
21. Unit Capacity Factor (MDC Net) 0.0 0.0 56.3
22. Unit Capacity Factor (DER Net) 0.0 0.0 54.9
23. Unit Forced Outage Rate 100.0 100.0 24.0
24. Shutdowns Scheduled over Next Six Months (Type, Date, and Duration):

None

25. If Shut Down At End of Report Period, Estimated Date of Startup:

April 2000

26. Units in Test Status (Prior to Commercial Operation):

Forecast Achieved INITIALCRITICALITY INITIALELECTRICITY COMMERCIALOPERATION

DOCKET NO. 50-316 UNIT NAME D.C. Cook Unit 2 DATE January 5, 2000 COMPLETED BY J. W. Minor TELEPHONE 616465-5901 AVERAGE DAILYPOWER LEVEL (MWe-Net)

December 1999 DAY AVERAGE DAILY DAY AVERAGE DAILY POWER LEVEL POWER LEVEL 12/1/99 12/17/99 0 12/2/99 12/18/99 0

. 12/3/99 12/19/99 0 12/4/99 12/20/99 0 12/5/99 12/21/99 0 12/6/99 12/22/99 0 12/7/99 12/23/99 0 12/8/99 12/24/99 0 12/9/99 12/25/99 0 12/10/99 12/26/99 0 12/11/99 12/27/99 0 12/12/99 12/28/99 0 12/13/99 12/29/99 0 12/14/99 12/30/99 0 12/15/99 12/31/99 0 12/16/99

DOCKET NO. 50- 316 UNIT NAME D.C. Cook Unit 2 DATE January 9, 2000 COMPLETED BY MB Depuydt TELEPHONE 616-465-5901 PAGE 1 of 1 UNIT SHUTDOWNS AND POWER REDUCTIONS December 1999 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO. DATE TYPE~ HOURS REASONS REACTORs REPORT NO CODEi CODEs TO PREVENT RECURRENCE 333 090897 F 162.0 97-003 N/A N/A The unit was shutdown to resolve 97-004 design basis questions discovered during 97-005 the NRC Architect and Engineering (AE)

Inspection.

'82.0 334 101397 S N/A N/A N/A The scheduled refueling outage commenced while the unit has been shutdown to resolve design basis questions discovered during the NRC AE Inspection.

335 010798 F 744.0 N/A N/A NIA The unit remained shutdown to resolve design basis questions identified during the NRC Architect and Engineering (AE)

Inspection.

Historical values included for consistency with CNP Unit 1 i3ZEE: 2JREEGQH: XJBEEHQD: ~YSIEM:

F: Forced A; Equipment Failure (Explain) 1: Manual Exhibit G - Instructions Exhibit I: Same Source S: Scheduled B: Maintenance or Test 2: Manual Scram for preparation of data C: Refueling 3: Automatic Scram entry sheets for Licensee D: Regulatory Restriction 4: Other (Explain) Event Report (LER) File E: Operator Training and {NUREG 0161)

License Examination F: Administrative G: Operational Error {Explain)

H: Other (Explain)

'i 1 Distri27.txt Distribution Sheet Priority: Normal From: Elaine Walker Action Recipients: Copies:

J Stang Not Found Internal Recipients:

RGN 3 Not Found RES/DRAA/OERAB Not Found OC/DB 1 Not Found E CENTER 01 Not Found ACRS Not Found External Recipients:

NRC PDR Not Found NOAC Not Found INEEL Marshall Not Found Total Copies:

Item: ADAMS Document Library: ML ADAMS"HQNTAD01 ID: 993500238

Subject:

Monthly operating report for November 1999 for D. C. Cook Nuclear Plant, Unit 2. With 9 91208 letter.

Body:

PDR ADOCK 05000316 R Docket: 05000316, Notes: N/A Page 1

indiana Michigan Power Company Cook Nudeas Hant onecooa~

BMymn, Ml461 06 616 465 5901 Ni INQlkftM NlCHIGQN POMFJR December 8, 1999 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Document Control Manager:

Pursuant to the requirements of Donald C. Cook Nuclear Plant Unit 2 Technical Specification 6.9.1.8, the attached Monthly Operating Report for November 1999 is submitted.

Sincerely, Pm) UQ R. C. Godley Regulatory Affairs Director RCG/mbd Attachments ANI Nuclear Engineering Department A. C. Bakken, III G. T. Gaffney Canton D. R. Hahn Department of Health S. Hamming Department of Labor INPO Records Center G. John B. Lewis McGraw-Hill Companies D. H. Malin NRC Project Manager NRR NRC Region III NRC Resident Inspector T. P. Noonan D. W. Paul Lancaster J. E. Pollock R. P. Powers Regulatory Licensing Manager M. W. Rencheck W. H. Schalk D. G. Turner

~ O~

pg)(D~L, Q.5QQ DB/4 AEI': America's Eneigl'nrlner

NRC OPERATING DATA REPORT DOCKET NO. 50 - 316 DATE December 3, 1999 COMPLETED BY J. W. Minor TELEPHONE 616-465-5901 OPERATING STATUS Notes:

1. Unit Name D. C. Cook Unit2
2. Reporting Period Nov-99
3. Licensed Thermal Power (MWt) 3411
4. Name Plate Rating (Gross MWe) 1133
5. Design Electrical Rating (Net MWe) 1090
6. Maximum Dependable Capacity (GROSS MWe) 1100
7. Maximum Dependable Capacity (Net MWe) 1060
8. If Changes Occur in Capacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons:

'. Power Level to Which Restricted, IfAny (Net MWe):

10. Reasons For Restrictions, IfAny:

This Month Year-to-Date Cumulative

11. Hours in Reporting Period 720.0 8016.0 192546.0
12. No. of Hrs. Reactor Was Critical 0.0 0.0 121771.0 ~
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator on Line 0.0 0.0 118153.4
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Gen. (MWH) 0.0 0.0 366007650.4
17. Gross Electrical Energy Gen. (MWH) 0.0 0.0 118584640.0
18. Net Electrical Energy Gen. (MWH) 0.0 0.0 114257779.0
19. Unit Service Factor 0.0 0.0 62.1
20. Unit Availability Factor 0.0 0.0 62.1
21. Unit Capacity Factor (MDC Net) 0.0 0.0 56.6
22. Unit Capacity Factor (DER Net) 0.0 0.0 55.1
23. Unit Forced Outage Rate 100.0 100.0 23.6
24. Shutdowns Scheduled over Next Six Months (Type, Date, and Duration):

None

25. If Shut Down At End of Report Period, Estimated Date of Startup:

April 2000

26. Units in Test Status (Prior to Commercial Operation):

Forecast Achieved INITIALCRITICALITY INITIALELECTRICITY COMMERCIALOPERATION

I, DOCKET NO. 50 - 316 UNIT NAME D.C. Cook Unit 2 DATE December 3, 1999 COMPLETED BY J. W. Minor TELEPHONE 616-465-5901 AVERAGE DAILYPOWER LEVEL (MWe-Net)

November 1999 DAY AVERAGE DAILY DAY AVERAGE DAILY POWER LEVEL POWER LEVEL 11/1/99 0 11/17/99 11/2/99 0 11/18/99 11/3/99 0 11/19/99 11/4/99 0 11/20/99 11/5/99 0 11/21/99 11/6/99 0 11/22/99 11/7/99 0 11/23/99 11/8/99 0 11/24/99 11/9/99 0 11/25/99 11/10/99 0 11/26/99 11/11/99 0 11/27/99 11/12/99 ,0 11/28/99 11/13/99 0 11/29/99 11/14/99 0 11/30/99 11/15/99 0 11/16/99 0

DOCKET NO. 50- 316 UNIT NAME D.C. Cook Unit 2 DATE December 6, 1999 COMPLETED BY S. Cherba TELEPHONE 616-465-5901 PAGE 1 of1 UNIT SHUTDOWNS AND POWER REDUCTIONS November 1999 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION O. DATE TYPE'OURS REASON2 REACTOR3 REPORT NO. CODEi CODE5 TO PREVENT RECURRENCE 333 090897 F 162.0 97-003 N/A N/A The unit was shutdown to resolve 97-004 design basis questions discovered during 97-005 the NRC Architect and Engineering (AE)

Inspection.

334 101397 S 582.0 N/A N/A N/A The scheduled refueling outage commenced while the unit has been shutdown to resolve design basis questions discovered during the NRC AE Inspection.

335 010798 F 720.0 N/A N/A N/A The unit remained shutdown to resolve design basis questions identified during the NRC Architect and Engineering (AE)

Inspection.

1 TYPE: 2 REASON: 3 METHOD: 4 SYSTEM: 5 COMPONENT:

F: Forced A: Equipment Failure (Explain) 1: Manual Exhibit G - Instructions Exhibit I: Same Source S: Scheduled B: Maintenance or Test 2: Manual Scram for preparation of data C: Refueling 3: Automatic Scram entry sheets for Licensee D: Regulatory Restriction 4: Other (Explain) Event Report (LER) File E: Operator Training and (NUREG 0161)

License Examination F: Administrative G: Operational Error (Explain)

H: Other (Explain)

Cp Distri21.txt Distribution Sheet Priority: Normal From: Stefanie Fountain Action Recipients: Copies:

J Stang Not Found Internal Recipients:

RGN 3. Not Found RES/DRAA/OERAB 1 Not Found OC/DB IPAD LE ACRS G~f g ~ 1 Not Found Not Found Not Found External Recipients:

NRC PDR Not Found NOAC Not Found INEEL Marshall Not Found Total Copies:

Item: ADAMS Document Library: ML ADAMS"HQNTAD01 ID: 993250002

Subject:

Monthly Operating Report for October 1999 for D. C. Cook Nuclear Plant, Unit 2.With No vember 9, 1999 Letter.

Body:

PDR ADOCK 05000316 R Docket: 05000316, Notes: N/A Page 1

r' One Ca%Place Ndgnan.ul 49106 6t6456901

'S INQlAN8l g

MfCNICRQM PQYi/M November 9, 1999 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Document Control Manager:

Pursuant to the requirements of Donald C. Cook Nuclear Plant Unit 2 Technical Specification 6.9.1.8, the attached Monthly Operating Report for October 1999 is submitted.

Sincerely, R. C. Godley Regulatory Affairs Director RCG/mbd Attachment NRC Region III NRC Project Manager- NRR NRC Resident Inspector ANI Nuclear Engineering Department INPO Records Center A. C. Bakken, III G. T. Gaffney-Canton D. R. Hahn Department of Health S. Hamming Department of Labor G. John B. Lewis McGraw-Hill Companies D. H. Malin T. P. Noonan D. W. Paul Lancaster J. E. Pollock R. P. Powers Regulatory Licensing Manager M. W. Rencheck W. H. Schalk D. G. Turner g~Q hi4 I~

AEP:~I irierlcn's Eaerg> Inrlner

NRC OPERATING DATA REPORT DOCKET NO. 50- 316 DATE November 4, 1999 COMPLETED BY J. W. Minor TELEPHONE 616-465-5901 OPERATING STATUS Notes:

1. Unit Name D. C. Cook Unit2
2. Reporting Period Oct-99
3. Licensed Thermal Power (MWt) 3411
4. Name Plate Rating (Gross MWe) 1133
5. Design Electrical Rating (Net MWe) 1090
6. Maximum Dependable Capacity (GROSS MWe) 1100
7. Maximum Dependable Capacity (Net MWe) 1060
8. If Changes Occur in Capacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons:
9. Power Level to Which Restricted, If Any (Net MWe):
10. Reasons For Restrictions, If Any:

This Month Year-to-Date Cumulative

11. Hours in Reporting Period 744.0 7320.0 191850.0
12. No. of Hrs. Reactor Was Critical 0.0 0.0 121771.0
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator on Line 0.0 0.0 118153.4
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Gen. (MWH) 0.0 0.0 366007650.4
17. Gross Electrical Energy Gen. (MWH) 0.0 0.0 118584640.0
18. Net Electrical Energy Gen. (MWH) 0.0 0.0 114257779.0
19. Unit Service Factor 0.0 0.0 62.3
20. Unit Availability Factor 0.0 0.0 62.3
21. Unit Capacity Factor (MDC Net) 0.0 0.0 56.8
22. Unit Capacity Factor (DER Net) 0.0 0.0 55.3
23. Unit Forced Outage Rate 100.0 100.0 23.3
24. Shutdowns Scheduled over Next Six Months (Type, Date, and Duration):

None

25. If Shut Down At End of Report Period, Estimated Date of Startup:

April 2000

26. Units in Test Status (Prior to Commercial Operation):

Forecast Achieved INITIALCRITICALITY INITIALELECTRICITY COMMERCIALOPERATION

DOCKET NO. 50- 316 UNIT NAME D.C. Cook Unit 2 DATE November 4, 1999 COMPLETED BY J. W. Minor TELEPHONE 616-465-5901 AVERAGE DAILYPOWER LEVEL (MWe-Net)

October 1999 DAY AVERAGE DAILY DAY AVERAGE DAILY POWER LEVEL POWER LEVEL 10/1/99 10/17/99 0 10/2/99 10/18/99 0 10/3/99 10/19/99 0 10/4/99 10/20/99 0 10/5/99 10/21/99 0 10/6/99 10/22/99 0 10/7/99 10/23/99 0 10/8/99 10/24/99 0 10/9/99 10/25/99 0 10/10/99 10/26/99 0 10/11/99 10/27/99 0 10/12/99 10/28/99 0 10/13/99 10/29/99 0 10/14/99 10/30/99 0 10/15/99 10/31/99 0 10/16/99

L DOCKET NO. 50- $18 UNIT NAME D.C. Cook Unit 2 DATE November 5, 1999 COMPLETED BY S. A. Richardson TELEPHONE 616465-5901 PAGE 1 of1 UNIT SHUTDOWNS AND POWER REDUCTIONS October 1999 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO. DATE TYPE" HOURS REASON> REACTOR> REPORT NO. CODE4 CODE5 TO PREVENT RECURRENCE 333 090897 F 162.0 97-003 N/A N/A The unit was shutdown to resolve 97-004 design basis questions discovered during 97-005 the NRC Architect and Engineering (AE)

Inspection.

334 101397 S 582.0 N/A N/A N/A The scheduled refueling outage commenced while the unit has been shutdown to resolve design basis questions discovered during the NRC AE Inspection.

335 010798 F 744.0 N/A N/A N/A The unit remained shutdown to resolve design basis questions identified during the

. NRC Architect and Engineering (AE)

Inspection.

1 TYPE: 2 REASON: 3 METHOD: 4 SYSTEM: 5 COMPONENT:

F: Forced A: Equipment Failure (Explain) 1: Manual Exliibit G - Instructions Exhibit I: Same Source S: Scheduled B: Maintenance or Test 2: Manual Scram for preparation of data C: Refueling 3: Automatic Scram entry sheets for Licensee D: Regulatory Restriction 4: Other (Explain) Event Report (LER) File E: Operator Training and (NUREG 0161)

License Examination F: Administrative G: Operational Error (Explain)

H: Other (Explain)