ML20078B919

From kanterella
Revision as of 02:36, 25 April 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Informs of Schedule Change for Initial Fuel Loading.Fuel Load Target Date Revised from 831201 to 840215 Based on Recent Reviews of Const Progress.Addl Work Required to Complete Piping Supports & Modify Ventilation Ductwork
ML20078B919
Person / Time
Site: Byron Constellation icon.png
Issue date: 09/23/1983
From: Reed C
COMMONWEALTH EDISON CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
7362N, NUDOCS 8309270320
Download: ML20078B919 (1)


Text

- _- . - - .- - - . - - - - - . -

' Commonwealth Edison O One Fest National Plaza. Chicago, liknois C Address R: ply to: Post Office Box 767 Chicago, filinois 60690 i

September 23, 1983 i

Mr. Harold R..Denton, Director Of fice of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555

Subject:

Byron Generating Station Units 1 and 2 Fuel Load Date NRC Docket Nos. 50-454 and 50-455

Dear Mr. Denton:

This is to inform you of a change to our schedule for initial fuel loading at Byron Unit 1. Based on recent reviews of construction progress we are revising the target date for fuel load from December 1, 1983 to February 15, 1984. Unanticipated additional work required to complete piping supports and to modify sections of ventilation ductwork has caused us to revise our schedule.

We are making every ef fort to accelerate the Byron 1 fuel i

load schedule but there are also contingencies which could cause further delay. I will continue to keep you advised of changes in our schedules for these units.

I Very ruly yours, A_m Cordell Reed

} Vice-President l

l TRT/1m l

l 7362N pl l

b 9309270320 830923 i PDR ADOCK 05000454 A PDR s -

y e'a-,.v .7--,-m-r ~c,------,---~ , . - - - -,- - y.. r,----,r.-e-,, - . .,, wee,- -w.e rw gmt-,--ee r-~~,- **--we- +-,te- ev e