Other: ML20005E175, ML20043D315, ML20065P534, ML20079H345, ML20091B776, ML20094J061, ML20094J331, ML20147E720, ML20151A331, ML20151L355, ML20154A938, ML20155A488, ML20236F308, ML20245B123, ML20245J248
|
MONTHYEARML20236F3081987-10-21021 October 1987 Ack Receipt of Util Transmitting Proposed Amend to Plant Physical Security Plan,In Response to Miscellaneous Amends & Search Requirements.Comments on Physical Security Changes Encl.Response Requested within 30 Days Project stage: Other ML20147E7201988-01-14014 January 1988 Forwards Rev 22 to Security Plan.All Amend Items Will Be Implemented Upon Receipt of NRC Approval Notification W/ Listed Exceptions.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20151L3551988-04-18018 April 1988 Forwards Rev 23 to Security Plan.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20154A9381988-05-11011 May 1988 Forwards Rev 24 of Security Plan for Plant.Rept Withheld (Ref 10CFR73.21) Project stage: Other ML20151A3311988-07-14014 July 1988 Forwards Rev 25 to Security Plan.Encl Withhled (Ref 10CFR73.21) Project stage: Other ML20155A4881988-09-26026 September 1988 Forwards Rev 26 to Security Plan.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20245J2481989-04-25025 April 1989 Forwards Rev 27 to Security Plan.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20245B1231989-06-20020 June 1989 Forwards Rev 28 to Plant Security Plan.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20005E1751989-12-22022 December 1989 Forwards Rev 29 to Security Plan.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20043D3151990-06-0101 June 1990 Forwards Rev 30 to Security Plan.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20065P5341990-10-30030 October 1990 Forwards Rev 31 to Security Plan,Adding 10CFR26 to App B Section.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20091B7761991-07-17017 July 1991 Forwards Rev 32 to Security Plan,Reflecting Current chain-of Command for Security Mgt Organization,Type of Weapons Onsite & Change to Shotgun Qualification Requirements.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20079H3451991-09-27027 September 1991 Forwards Rev 33 to Security Plan,Per 10CFR50.4.Plan Withheld (Ref 10CFR73.21) Project stage: Other ML20094J3311995-11-0606 November 1995 Requests Exemption from Certain Requirements of 10CFR73.55, Requirements for Physical Protection of Licensed Activities in NPR Against Radiological Sabotage for Plant.Encl Withheld Project stage: Other ML20094J0611995-11-0606 November 1995 Forwards Three Copies of Rev 44 of Plant Security Plan.Encl Withheld Project stage: Other 1989-12-22
[Table View] |
Similar Documents at Byron |
|---|
|
Text
-
c.
7 N Commonwealth Edison
^l
/., 72 West Adams Street, ChicaQo, Illinois
\\bv'/ Address Reply to: Post Othee Box 767 Chicago, Illinois 60690 0767
,.p.p December 22, 1989 h
-1 U.S. Nuclear: Regulatory Commission i
g ATTN: Document Control Desk Washington,'D.C.
20555
Subject:
Byron Nuclear Power Stations Units 1 and 2 Byron Station Security Plan NRC Decket Nos. 50-454 & 50-455 TAC Nos. 65282/65283 Enclosed are the original and three (3) copies of Revision 29 of the Byron Nuclear Power Station. Security Plan. This revision reflects administrative changes in the management structure at the station.
Pursuant to 10CFR 50.4, the signed original and three copies of the security plan revisions _are being provided to your office. A copy of this letter and'two copies of the security plan revisions are being sent to Region III.
We have concluded that these changes do not decrease the safeguards effectiveness of the plan. These enclosures contain Safeguards Information which must be protected from public disclosure pursuant to 10CFR 73.21.
I Sincerely, i
/
l 1
Thomas J. K ach j
Nuclear Licensing Manager i
cc: A. B. Davis (w/two encls.)
THE ENCLOSURE CONTAINS SAFEGUARDS INFORMATION Uoon separation, this once is decontrolled f
PDR..ADOCK0500kDC, k